Page 2: Power Point Presentation

Terrific Table-Top Tips for a Crisis Management Exercise

kpmg

Page 3: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 3

kpmg

Welcome to Today’s Meeting

Our Objectives Today . . .

Your Tips and Best Practices:

ParticipantsSuppliesLogisticsScenarioConducting the ExercisePost Exercise

Sample Task List

Demo

Page 4: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 4

kpmg

Relation of Planning & Execution

“Normal” TimelineUnplanned Event

(something bad happens)

Crisis Management Plans

Disaster Recovery Plans

Business Continuity Plans

CM Plans “trigger” Disaster Recovery Plans and

Business Continuity Plans

BC Plans continue until

“normal” operations resumed

DR and CM Plans “stop” upon successful completion

Page 5: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 5

kpmg

Sample Task List:

Page 6: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 6

kpmg

Interactive Mock . . . For Practitioners by PractitionersSimplistic Exercise:

Learning Tool

Interaction is the Key

BC versus DR

Legend Symbols

Action

Information

Incoming Call

Time Out

Ready?

I

A

Page 7: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 7

kpmg

Scenario INews FlashApril 28, Wednesday, 7:45 a.m.

The local TV stations and newspapers have reported concerns about a large number of sinkholes which have developed during the past week, especially near the airport, due to numerous days of heavy rain.

8:05 a.m.

Upon hearing this news, as a precaution, the Business Continuity Manager alerts the Crisis Management Team Leader.

8:45 a.m.

The Team Leader requests a Crisis Management Team meeting for 9:30 a.m.

Page 8: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 8

kpmg

Scenario

(continued)

8:46 a.m. [The Airport Campus Facility Manager calls the CM Team Leader.]

A

• At 8:35 a.m., a portion of the ground, about 30’ wide x 40’ deep, gave way just inside the entrance to the campus.

• Three cars, a van, and a truck were on the road at the time of the collapse.

• Presumably employees and a delivery vendor

• Emergency personnel have arrived and are trying to access the sinkhole.

• Able to hear someone yelling and a child crying

• National Bring Your Child to Work Day

Page 9: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 9

kpmg

Scenario

(continued)

A8:55 a.m. [Facility Manager calls the Crisis Management Team Leader]

• The fire department assessed that the sinkhole is getting larger and that other large sinkholes are developing in the area at a fast rate.

• They have determined that 12 people are in the sink hole.

• Still do not know their identities.

• The van was the ‘Car Pool Van’ from Mecklenburg County. Not sure if it was leaving or arriving.

• The car is a red Corvette.

• Employees are not able to get in or out of the facility with their vehicles.

• Numerous media trucks and helicopters are arriving.

Page 10: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 10

kpmg

Scenario

(continued)

A9:00 a.m. - Status• The 8:30 a.m. daily shipments did not leave the facility.

• Unable to contact the plant manager.

• Drives a red corvette . . .

• Family members are clogging the company PBX.

• Many are unable to contact their relatives (employees).

9:20 a.m.

• Battalion Chief Mark Sparks has requested the campus be evacuated for an indefinite period of time.

Page 11: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 11

kpmg

Lessons Learned

Page 12: Power Point Presentation

© 2004 KPMG LLP, the U.S. member firm of KPMG International, a Swiss cooperative. All rights reserved. Printed in the U.S.A.3470maric 12

kpmg

This document was prepared by:

KPMG LLP

Risk Advisory ServicesRobbie Atabaigi, CBCP

Senior Associate – Atlanta – BCM Services

[email protected] – (404) 222-3257

Jeff Dato, MBCP

Senior Manager – Atlanta – BCM Services [email protected] – (404) 222-7378

Martin Myers, MS, MBCP

Senior Manager – Richmond – BCM Services

[email protected] - (804) 782-4237