Power distribution and transmission

download Power distribution and transmission

of 60

Transcript of Power distribution and transmission

  • 8/12/2019 Power distribution and transmission

    1/60

    1

    Lecture-21

    Dr. Tahir Izhar

  • 8/12/2019 Power distribution and transmission

    2/60

    Overcurrent Uses current to determine magnitude of fault Simple

    May employ definite time or inverse time curves

    May be slow Selectivity at the cost of speed (coordination stacks)

    Inexpensive

    May use various polarizing voltages or ground currentfor directionality

    Communication aided schemes make more selective

    2

  • 8/12/2019 Power distribution and transmission

    3/60

    The operating characteristic of an overcurrent relay can be presented

    as a plot of the operating time vs. the current.

    Level detection. Over-current relays

    This figure represents the operating

    time for an independent delay time

    overcurrent relay.

    It will operate always at the same time

    for currents over the pick up setting This relays are defined by the pick up

    current, as number of times the normal

    current, and the operating time

    Coordination of different protections of

    this type is achieved by time delayingand pick up setting

    It must be a minimum of 0,3 sec. to

    permit operating of the first breaker

    t

    iIn n*In

    t 0

    50 (ANSI)

    3

    Time Indepedent

  • 8/12/2019 Power distribution and transmission

    4/60

    Relay closest to fault operatesfirst

    Relays closer to sourceoperate slower

    Time between operating forsame current is called CTI(Clearing Time Interval)

    Distribution

    Substation

  • 8/12/2019 Power distribution and transmission

    5/60

    This type of relay will have an operating time depending on the value

    of the current, generally with an inverse characteristic, that is to say,the bigger the current, the shorter the time.

    Over-current relays. Dependent time delay

    This characteristic permits a

    reasonable coordination between

    protections just changing the pick

    up setting. These relays will be defined by the

    pick up setting and the type of

    tripping curve, which can be

    adjusted

    There are usually three types ofcurves, Normal (NI), Very inverse

    (VI) and Extremely inverse (EI)

    t

    iIn n*In

    Transfer

    curve

    Inverse t ime

    t 0

    Time Indep edent

    50/51

    5

  • 8/12/2019 Power distribution and transmission

    6/60

    Relay closest to fault operates

    firstRelays closer to source

    operate slowerTime between operating for

    same current is called CTI

    Distribution

    Substation

  • 8/12/2019 Power distribution and transmission

    7/60

    Selection of the curvesuses what is termed as a

    time multiplier or time

    dial to effectively shift

    the curve up or down on

    the time axis

    Operate region lies

    above selected curve,

    while no-operate region

    lies below it

    Inverse curves can

    approximate fuse curve

    shapes

    Time Overcurrent Protection (TOC)

    7

  • 8/12/2019 Power distribution and transmission

    8/60

    Multiples of pick-up

    Time Overcurrent Protection

    (51, 51N, 51G)

    8

  • 8/12/2019 Power distribution and transmission

    9/60

    The working principle of an inverse time overcurrent relay is depicted in

    this figure.

    Overcurrent protection

    The current to be controlled feeds

    a coil with multiple taps which

    allow the pick up current setting.

    The generated magnetic field

    makes the disc rotate with a

    speed proportional to the current.

    A timing dial allows the

    adjustment between contacts and

    hence sets the op. time.

    The braking magnet lessens the

    rotating speed and acts as anopposing force to the rotation.

    Varying the magnetization,

    different tripping curves can be

    achieved.

    Current

    taps

    Induction

    disk

    Laggingcoil

    Timing

    dial

    Braking

    2 4 6

    1

    2

    9

  • 8/12/2019 Power distribution and transmission

    10/60

    Differential current in = current out

    Simple

    Very fast Very defined clearing area

    Expensive

    Practical distance limitations

    Line differential systems overcome this using digitalcommunications

    11

  • 8/12/2019 Power distribution and transmission

    11/60

    Note CT polarity

    dots

    This is a

    through-current

    representation

    Perfect

    waveforms, nosaturation

    12

  • 8/12/2019 Power distribution and transmission

    12/60

    Note CT

    polarity dots

    This is aninternal fault

    representation

    Perfectwaveforms, no

    saturation

    13

  • 8/12/2019 Power distribution and transmission

    13/60

    It is triggered when the current exceeds the reference value and also

    the energy or power flow has the determined direction. An overcurrent element controls the current magnitude

    A directional element controls the direction of the power flow

    Directional overcurrent protection

    V

    I

    Cylinder

    Magnetic

    core

    IV

    IIII

    IV

    I

    V

    14

  • 8/12/2019 Power distribution and transmission

    14/60

    87

    With internal fault Id> 0 Trip

    With external fault Id= 0 No trip

    It compares the current entering the transformer with the current leaving theelement.

    If they are equal there is no fault inside the zone of protection

    If they are not equal it means that a fault occurs between the two ends

    15

  • 8/12/2019 Power distribution and transmission

    15/60

    No Relay Operation if CTs Are Considered Ideal

    ExternalFault

    IDIF

    = 0

    CT CT

    50

    Balanced CT Ratio

    Protected

    Equipment

    16

  • 8/12/2019 Power distribution and transmission

    16/60

    Internal

    Fault

    IDIF > ISETTING

    CTR CTR

    50

    Relay Operates

    Protected

    Equipment

    17

  • 8/12/2019 Power distribution and transmission

    17/60

    False differential current can occur if a CT

    saturates during a through-fault Use some measure of through-current to

    desensitize the relay when high currents are

    present

    External

    Fault

    ProtectedEquipment

    IDIF

    0

    CT CT

    50

    18

  • 8/12/2019 Power distribution and transmission

    18/60

    Protected

    Equipment

    R

    S

    CTR CTR

    Compares:

    Relay

    (87)

    OP S RI I I

    | | | |

    2

    S R

    RT

    I Ik I k

    RPSP

    19

  • 8/12/2019 Power distribution and transmission

    19/60

    Communications

    Channel

    Exchange of logic information

    on relay status

    RL

    Relays Relays

    T

    R

    R

    T

    LI

    RI

  • 8/12/2019 Power distribution and transmission

    20/60

    Bus protection

    Transformer protection

    Generator protection

    Line protection Large motor protection

    Reactor protection

    Capacitor bank protection

    Compound equipment protection

    21

  • 8/12/2019 Power distribution and transmission

    21/60

    The overcurrent differential scheme is simpleand economical, but it does not respond well to

    unequal current transformer performance

    The percentage differential scheme responds

    better to CT saturation Percentage differential protection can be

    analyzed in the relay and the alpha plane

    Differential protection is the best alternative

    selectivity/speed with present technology

    22

  • 8/12/2019 Power distribution and transmission

    22/60

    Voltage Uses voltage to infer fault or abnormal

    condition May employ definite time or inverse time

    curves May also be used for under-voltage load

    shedding Simple

    May be slow Selectivity at the cost of speed

    Inexpensive

    23

  • 8/12/2019 Power distribution and transmission

    23/60

  • 8/12/2019 Power distribution and transmission

    24/60

    PowerUses voltage and current to determine

    power flow magnitude and direction

    Typically definite time Complex May be slow

    Accuracy important for many applications

    Can be expensive

    25

  • 8/12/2019 Power distribution and transmission

    25/60

  • 8/12/2019 Power distribution and transmission

    26/60

  • 8/12/2019 Power distribution and transmission

    27/60

    A B

    IA IB

    Internal fault = IAe IBare in phase reversal = Trip

    External fault = IAe IBare in phase = No tr ip

    28

  • 8/12/2019 Power distribution and transmission

    28/60

    The breaker may have a mechanical failure if it is not ableto open any of the poles when it is ordered to do so, or

    even an electrical failure if although open, is not capable of

    breaking the current, which will keep on flowing as an arc.

    This implies a current flow that keeps on feeding thefault which can be used to detect the breaker failure

    itself.

    In those applications which even though the mechanical

    failure exist, the current could not be high enough to be

    detected, the opening must also be verified by means of

    breaker auxiliary contacts.

    29

  • 8/12/2019 Power distribution and transmission

    29/60

    87B+FI

    21

    I falta A tripping order for the

    circuit breaker initiates

    the time delay count

    down for the protection.

    30

  • 8/12/2019 Power distribution and transmission

    30/60

    87B+FI

    TELEDISPARO

    21

    I falta

    T 250 ms

    Once the time delay is over,if the breaker is not yet

    open, the protection sends a

    tripping order to all the

    adjacent breakers, including

    those at the end of the linesif necessary.

    Sometimes two time

    delays are used, the first

    one to repeat the

    tripping order for thebreaker itself, and the

    second for the other

    breakers.

    31

  • 8/12/2019 Power distribution and transmission

    31/60

    Generation-typically at 13kV

    Transmission-typically at 230kV

    Sub-transmission-typically at 132kV

    Receives power from transmission

    system and transforms into sub-

    transmission level

    Receives power from sub-

    transmission system and transforms

    into primary feeder voltageDistribution network-typically 11kV

    Low voltage (service)-typically 230V 32

  • 8/12/2019 Power distribution and transmission

    32/60

    1. Generator or Generator-Transformer Units

    2. Transformers

    3. Buses

    4. Lines (transmission and distribution)5. Utilization equipment (motors, static loads, etc.)

    6. Capacitor or reactor (when separately protected)

    Unit Generator-Tx zone

    Bus zone

    Line zone

    Bus zone

    Transformer zoneTransformer zone

    Bus zone

    Generator

    ~

    XFMR Bus Line Bus XFMR Bus Motor

    Motor zone

    33

  • 8/12/2019 Power distribution and transmission

    33/60

    1. Overlap is accomplished by the locations of CTs, the key source for protectiverelays.

    2. In some cases a fault might involve a CT or a circuit breaker itself, which

    means it can not be cleared until adjacent breakers (local or remote) are

    opened.

    Zone A Zone B

    Relay Zone A

    Relay Zone B

    CTs are located at both sides of

    CB-fault between CTs is cleared from bothremote sides

    Zone A Zone B

    Relay Zone A

    Relay Zone B

    CTs are located at one side of CB-fault between CTs is sensed by both relays,

    remote right side operate only.

    34

  • 8/12/2019 Power distribution and transmission

    34/60

  • 8/12/2019 Power distribution and transmission

    35/60

    Partial listing

    36GE Consumer & IndustrialMultilin

  • 8/12/2019 Power distribution and transmission

    36/60

    Non-dimensioned diagram showing how

    pieces of electrical equipment are

    connected

    Simplification of actual systemEquipment is shown as boxes, circles and

    other simple graphic symbols

    Symbols should follow ANSI or IECconventions

    37

  • 8/12/2019 Power distribution and transmission

    37/60

    38

  • 8/12/2019 Power distribution and transmission

    38/60

    39

  • 8/12/2019 Power distribution and transmission

    39/60

  • 8/12/2019 Power distribution and transmission

    40/60

    41

    C t T f

  • 8/12/2019 Power distribution and transmission

    41/60

    Current transformers are used to step primary system currents to

    values usable by relays, meters, SCADA, transducers, etc.

    CT ratios are expressed as primary to secondary; 2000:5, 1200:5,

    600:5, 300:5

    A 2000:5 CT has a CTR of 400

    Current Transformers

    42

    St d d IEEE CT B d (5 A )

  • 8/12/2019 Power distribution and transmission

    42/60

    Standard IEEE CT Burdens (5 Amp)(Per IEEE Std. C57.13-1993)

    44

    V lt T f

  • 8/12/2019 Power distribution and transmission

    43/60

    VP

    VS

    Relay

    Voltage (potential) transformers are used to isolate and step down

    and accurately reproduce the scaled voltage for the protective

    device or relay

    VT ratios are typically expressed as primary to secondary;

    14400:120, 7200:120

    A 4160:120 VT has a VTR of 34.66

    Voltage Transformers

    46

  • 8/12/2019 Power distribution and transmission

    44/60

    Case ground made at IT location

    Secondary circuit ground made at first point of

    use

    Case

    Secondary Circuit

  • 8/12/2019 Power distribution and transmission

    45/60

    Prevents shock exposure of personnel

    Provides current carrying capability for the ground-

    fault current

    Grounding includes design and construction of

    substation ground mat and CT and VT safety

    grounding

    48

  • 8/12/2019 Power distribution and transmission

    46/60

  • 8/12/2019 Power distribution and transmission

    47/60

    1. Ungrounded: There is no intentional

    ground applied to the system-however

    its grounded through natural

    capacitance. Found in 2.4-15kV

    systems.

    2. Reactance Grounded: Total system

    capacitance is cancelled by equal

    inductance. This decreases the currentat the fault and limits voltage across the

    arc at the fault to decrease damage.

    X0

  • 8/12/2019 Power distribution and transmission

    48/60

    3. High Resistance Grounded: Limitsground fault current to 10A-20A. Used

    to limit transient overvoltages due to

    arcing ground faults.

    R0= 2X0

    51

  • 8/12/2019 Power distribution and transmission

    49/60

    5. Solidly Grounded: There is a

    connection of transformer or generatorneutral directly to station ground.

    Effectively Grounded: R0

  • 8/12/2019 Power distribution and transmission

    50/60

    Medium/High

    Resistance Ground

    Low/No

    Resistance Ground

    58

  • 8/12/2019 Power distribution and transmission

    51/60

    Relay performance is generally classed as

    (1) correct,

    (2) no conclusion

    (3) incorrect.

    Incorrect operation may be either failure to trip or false tripping.

    The cause of incorrect operation may be (1) poor application, (2) incorrect

    settings, (3) personnel error, or (4) equipment malfunction.

    Equipment that can cause an incorrect operation includes current transformers,

    voltage transformers, breakers, cable and wiring, relays, channels, or station

    batteries.

    Incorrect tripping of circuit breakers not associated with the trouble area is oftenas disastrous as a failure to trip. Hence, special care must be taken in both

    application and installation to ensure against this.

    Noconclusionis the last resort when no evidence is available for a correct or

    incorrect operation. Quite often this is a personnel involvement.

    59

  • 8/12/2019 Power distribution and transmission

    52/60

    Protective relays or systems are not required to functionduring normal power system operation, but must be

    immediately available to handle intolerable system

    conditions and avoid serious outages and damage.

    Thus, the true operating life of these relays can be on theorder of a few seconds, even though they are connected

    in a system for many years.

    In practice, the relays operate far more during testing and

    maintenance than in response to adverse service conditions.

    In theory, a relay system should be able to respond to an

    infinite number of abnormalities that can possibly occur

    within the power system.

    60

  • 8/12/2019 Power distribution and transmission

    53/60

  • 8/12/2019 Power distribution and transmission

    54/60

    The first step in applying protective relays is to state the protection problemaccurately.

    Although developing a clear, accurate statement of the problem can often

    be the most difficult part, the time spent will pay dividends particularly

    when assistance from others is desired.

    Information on the following associated or supporting areas is necessary:

    System configuration

    Existing system protection and any known deficiencies

    Existing operating procedures and practices, possible future expansions

    Degree of protection required

    Fault study

    Maximum load, current transformer locations and ratios

    Voltage transformer locations, connections, and ratios Impedance of lines,

    transformers, and generators 62

  • 8/12/2019 Power distribution and transmission

    55/60

    System configuration is represented by a single-line diagram showing

    the area of the system involved in the protection application.

    This diagram should show in detail the location of the breakers, bus

    arrangements, taps on lines and their capacity, location and size of the

    generation, location, size, and connections of the power transformers

    and capacitors, location and ratio of ct's and vt's, and system

    frequency.

    Transformer connections are particularly important. For ground

    relaying, the location of all ground sourcesmust also be known

    63

  • 8/12/2019 Power distribution and transmission

    56/60

  • 8/12/2019 Power distribution and transmission

    57/60

    An adequate fault study is necessary in almost all relay applications.

    Three-phase faults, line-to-ground faults, and line-end faults should all

    be included in the study.

    Line-end fault (fault on the line-side of an open breaker) data are

    important in cases where one breaker may operate before another. For ground-relaying, the fault study should include zero sequence

    currents and voltages and negative sequence currents and voltages.

    These quantities are easily obtained during the course of a fault study

    and are often extremely useful in solving a difficult relaying problem.

    65

  • 8/12/2019 Power distribution and transmission

    58/60

    Multifunctional

    Compatibility with

    digital integrated

    systems

    Low maintenance

    (self-supervision)

    Highly sensitive,

    secure, and

    selective

    AdaptiveHighly reliable

    (self-supervision)

    Reduced burden

    on

    CTs and VTs

    Programmable

    VersatileLow Cost

  • 8/12/2019 Power distribution and transmission

    59/60

  • 8/12/2019 Power distribution and transmission

    60/60

    THANK YOU

    FOR YOUR ATTENTION