Power distribution and transmission
-
Upload
saman-nazim -
Category
Documents
-
view
231 -
download
0
Transcript of Power distribution and transmission
-
8/12/2019 Power distribution and transmission
1/60
1
Lecture-21
Dr. Tahir Izhar
-
8/12/2019 Power distribution and transmission
2/60
Overcurrent Uses current to determine magnitude of fault Simple
May employ definite time or inverse time curves
May be slow Selectivity at the cost of speed (coordination stacks)
Inexpensive
May use various polarizing voltages or ground currentfor directionality
Communication aided schemes make more selective
2
-
8/12/2019 Power distribution and transmission
3/60
The operating characteristic of an overcurrent relay can be presented
as a plot of the operating time vs. the current.
Level detection. Over-current relays
This figure represents the operating
time for an independent delay time
overcurrent relay.
It will operate always at the same time
for currents over the pick up setting This relays are defined by the pick up
current, as number of times the normal
current, and the operating time
Coordination of different protections of
this type is achieved by time delayingand pick up setting
It must be a minimum of 0,3 sec. to
permit operating of the first breaker
t
iIn n*In
t 0
50 (ANSI)
3
Time Indepedent
-
8/12/2019 Power distribution and transmission
4/60
Relay closest to fault operatesfirst
Relays closer to sourceoperate slower
Time between operating forsame current is called CTI(Clearing Time Interval)
Distribution
Substation
-
8/12/2019 Power distribution and transmission
5/60
This type of relay will have an operating time depending on the value
of the current, generally with an inverse characteristic, that is to say,the bigger the current, the shorter the time.
Over-current relays. Dependent time delay
This characteristic permits a
reasonable coordination between
protections just changing the pick
up setting. These relays will be defined by the
pick up setting and the type of
tripping curve, which can be
adjusted
There are usually three types ofcurves, Normal (NI), Very inverse
(VI) and Extremely inverse (EI)
t
iIn n*In
Transfer
curve
Inverse t ime
t 0
Time Indep edent
50/51
5
-
8/12/2019 Power distribution and transmission
6/60
Relay closest to fault operates
firstRelays closer to source
operate slowerTime between operating for
same current is called CTI
Distribution
Substation
-
8/12/2019 Power distribution and transmission
7/60
Selection of the curvesuses what is termed as a
time multiplier or time
dial to effectively shift
the curve up or down on
the time axis
Operate region lies
above selected curve,
while no-operate region
lies below it
Inverse curves can
approximate fuse curve
shapes
Time Overcurrent Protection (TOC)
7
-
8/12/2019 Power distribution and transmission
8/60
Multiples of pick-up
Time Overcurrent Protection
(51, 51N, 51G)
8
-
8/12/2019 Power distribution and transmission
9/60
The working principle of an inverse time overcurrent relay is depicted in
this figure.
Overcurrent protection
The current to be controlled feeds
a coil with multiple taps which
allow the pick up current setting.
The generated magnetic field
makes the disc rotate with a
speed proportional to the current.
A timing dial allows the
adjustment between contacts and
hence sets the op. time.
The braking magnet lessens the
rotating speed and acts as anopposing force to the rotation.
Varying the magnetization,
different tripping curves can be
achieved.
Current
taps
Induction
disk
Laggingcoil
Timing
dial
Braking
2 4 6
1
2
9
-
8/12/2019 Power distribution and transmission
10/60
Differential current in = current out
Simple
Very fast Very defined clearing area
Expensive
Practical distance limitations
Line differential systems overcome this using digitalcommunications
11
-
8/12/2019 Power distribution and transmission
11/60
Note CT polarity
dots
This is a
through-current
representation
Perfect
waveforms, nosaturation
12
-
8/12/2019 Power distribution and transmission
12/60
Note CT
polarity dots
This is aninternal fault
representation
Perfectwaveforms, no
saturation
13
-
8/12/2019 Power distribution and transmission
13/60
It is triggered when the current exceeds the reference value and also
the energy or power flow has the determined direction. An overcurrent element controls the current magnitude
A directional element controls the direction of the power flow
Directional overcurrent protection
V
I
Cylinder
Magnetic
core
IV
IIII
IV
I
V
14
-
8/12/2019 Power distribution and transmission
14/60
87
With internal fault Id> 0 Trip
With external fault Id= 0 No trip
It compares the current entering the transformer with the current leaving theelement.
If they are equal there is no fault inside the zone of protection
If they are not equal it means that a fault occurs between the two ends
15
-
8/12/2019 Power distribution and transmission
15/60
No Relay Operation if CTs Are Considered Ideal
ExternalFault
IDIF
= 0
CT CT
50
Balanced CT Ratio
Protected
Equipment
16
-
8/12/2019 Power distribution and transmission
16/60
Internal
Fault
IDIF > ISETTING
CTR CTR
50
Relay Operates
Protected
Equipment
17
-
8/12/2019 Power distribution and transmission
17/60
False differential current can occur if a CT
saturates during a through-fault Use some measure of through-current to
desensitize the relay when high currents are
present
External
Fault
ProtectedEquipment
IDIF
0
CT CT
50
18
-
8/12/2019 Power distribution and transmission
18/60
Protected
Equipment
R
S
CTR CTR
Compares:
Relay
(87)
OP S RI I I
| | | |
2
S R
RT
I Ik I k
RPSP
19
-
8/12/2019 Power distribution and transmission
19/60
Communications
Channel
Exchange of logic information
on relay status
RL
Relays Relays
T
R
R
T
LI
RI
-
8/12/2019 Power distribution and transmission
20/60
Bus protection
Transformer protection
Generator protection
Line protection Large motor protection
Reactor protection
Capacitor bank protection
Compound equipment protection
21
-
8/12/2019 Power distribution and transmission
21/60
The overcurrent differential scheme is simpleand economical, but it does not respond well to
unequal current transformer performance
The percentage differential scheme responds
better to CT saturation Percentage differential protection can be
analyzed in the relay and the alpha plane
Differential protection is the best alternative
selectivity/speed with present technology
22
-
8/12/2019 Power distribution and transmission
22/60
Voltage Uses voltage to infer fault or abnormal
condition May employ definite time or inverse time
curves May also be used for under-voltage load
shedding Simple
May be slow Selectivity at the cost of speed
Inexpensive
23
-
8/12/2019 Power distribution and transmission
23/60
-
8/12/2019 Power distribution and transmission
24/60
PowerUses voltage and current to determine
power flow magnitude and direction
Typically definite time Complex May be slow
Accuracy important for many applications
Can be expensive
25
-
8/12/2019 Power distribution and transmission
25/60
-
8/12/2019 Power distribution and transmission
26/60
-
8/12/2019 Power distribution and transmission
27/60
A B
IA IB
Internal fault = IAe IBare in phase reversal = Trip
External fault = IAe IBare in phase = No tr ip
28
-
8/12/2019 Power distribution and transmission
28/60
The breaker may have a mechanical failure if it is not ableto open any of the poles when it is ordered to do so, or
even an electrical failure if although open, is not capable of
breaking the current, which will keep on flowing as an arc.
This implies a current flow that keeps on feeding thefault which can be used to detect the breaker failure
itself.
In those applications which even though the mechanical
failure exist, the current could not be high enough to be
detected, the opening must also be verified by means of
breaker auxiliary contacts.
29
-
8/12/2019 Power distribution and transmission
29/60
87B+FI
21
I falta A tripping order for the
circuit breaker initiates
the time delay count
down for the protection.
30
-
8/12/2019 Power distribution and transmission
30/60
87B+FI
TELEDISPARO
21
I falta
T 250 ms
Once the time delay is over,if the breaker is not yet
open, the protection sends a
tripping order to all the
adjacent breakers, including
those at the end of the linesif necessary.
Sometimes two time
delays are used, the first
one to repeat the
tripping order for thebreaker itself, and the
second for the other
breakers.
31
-
8/12/2019 Power distribution and transmission
31/60
Generation-typically at 13kV
Transmission-typically at 230kV
Sub-transmission-typically at 132kV
Receives power from transmission
system and transforms into sub-
transmission level
Receives power from sub-
transmission system and transforms
into primary feeder voltageDistribution network-typically 11kV
Low voltage (service)-typically 230V 32
-
8/12/2019 Power distribution and transmission
32/60
1. Generator or Generator-Transformer Units
2. Transformers
3. Buses
4. Lines (transmission and distribution)5. Utilization equipment (motors, static loads, etc.)
6. Capacitor or reactor (when separately protected)
Unit Generator-Tx zone
Bus zone
Line zone
Bus zone
Transformer zoneTransformer zone
Bus zone
Generator
~
XFMR Bus Line Bus XFMR Bus Motor
Motor zone
33
-
8/12/2019 Power distribution and transmission
33/60
1. Overlap is accomplished by the locations of CTs, the key source for protectiverelays.
2. In some cases a fault might involve a CT or a circuit breaker itself, which
means it can not be cleared until adjacent breakers (local or remote) are
opened.
Zone A Zone B
Relay Zone A
Relay Zone B
CTs are located at both sides of
CB-fault between CTs is cleared from bothremote sides
Zone A Zone B
Relay Zone A
Relay Zone B
CTs are located at one side of CB-fault between CTs is sensed by both relays,
remote right side operate only.
34
-
8/12/2019 Power distribution and transmission
34/60
-
8/12/2019 Power distribution and transmission
35/60
Partial listing
36GE Consumer & IndustrialMultilin
-
8/12/2019 Power distribution and transmission
36/60
Non-dimensioned diagram showing how
pieces of electrical equipment are
connected
Simplification of actual systemEquipment is shown as boxes, circles and
other simple graphic symbols
Symbols should follow ANSI or IECconventions
37
-
8/12/2019 Power distribution and transmission
37/60
38
-
8/12/2019 Power distribution and transmission
38/60
39
-
8/12/2019 Power distribution and transmission
39/60
-
8/12/2019 Power distribution and transmission
40/60
41
C t T f
-
8/12/2019 Power distribution and transmission
41/60
Current transformers are used to step primary system currents to
values usable by relays, meters, SCADA, transducers, etc.
CT ratios are expressed as primary to secondary; 2000:5, 1200:5,
600:5, 300:5
A 2000:5 CT has a CTR of 400
Current Transformers
42
St d d IEEE CT B d (5 A )
-
8/12/2019 Power distribution and transmission
42/60
Standard IEEE CT Burdens (5 Amp)(Per IEEE Std. C57.13-1993)
44
V lt T f
-
8/12/2019 Power distribution and transmission
43/60
VP
VS
Relay
Voltage (potential) transformers are used to isolate and step down
and accurately reproduce the scaled voltage for the protective
device or relay
VT ratios are typically expressed as primary to secondary;
14400:120, 7200:120
A 4160:120 VT has a VTR of 34.66
Voltage Transformers
46
-
8/12/2019 Power distribution and transmission
44/60
Case ground made at IT location
Secondary circuit ground made at first point of
use
Case
Secondary Circuit
-
8/12/2019 Power distribution and transmission
45/60
Prevents shock exposure of personnel
Provides current carrying capability for the ground-
fault current
Grounding includes design and construction of
substation ground mat and CT and VT safety
grounding
48
-
8/12/2019 Power distribution and transmission
46/60
-
8/12/2019 Power distribution and transmission
47/60
1. Ungrounded: There is no intentional
ground applied to the system-however
its grounded through natural
capacitance. Found in 2.4-15kV
systems.
2. Reactance Grounded: Total system
capacitance is cancelled by equal
inductance. This decreases the currentat the fault and limits voltage across the
arc at the fault to decrease damage.
X0
-
8/12/2019 Power distribution and transmission
48/60
3. High Resistance Grounded: Limitsground fault current to 10A-20A. Used
to limit transient overvoltages due to
arcing ground faults.
R0= 2X0
51
-
8/12/2019 Power distribution and transmission
49/60
5. Solidly Grounded: There is a
connection of transformer or generatorneutral directly to station ground.
Effectively Grounded: R0
-
8/12/2019 Power distribution and transmission
50/60
Medium/High
Resistance Ground
Low/No
Resistance Ground
58
-
8/12/2019 Power distribution and transmission
51/60
Relay performance is generally classed as
(1) correct,
(2) no conclusion
(3) incorrect.
Incorrect operation may be either failure to trip or false tripping.
The cause of incorrect operation may be (1) poor application, (2) incorrect
settings, (3) personnel error, or (4) equipment malfunction.
Equipment that can cause an incorrect operation includes current transformers,
voltage transformers, breakers, cable and wiring, relays, channels, or station
batteries.
Incorrect tripping of circuit breakers not associated with the trouble area is oftenas disastrous as a failure to trip. Hence, special care must be taken in both
application and installation to ensure against this.
Noconclusionis the last resort when no evidence is available for a correct or
incorrect operation. Quite often this is a personnel involvement.
59
-
8/12/2019 Power distribution and transmission
52/60
Protective relays or systems are not required to functionduring normal power system operation, but must be
immediately available to handle intolerable system
conditions and avoid serious outages and damage.
Thus, the true operating life of these relays can be on theorder of a few seconds, even though they are connected
in a system for many years.
In practice, the relays operate far more during testing and
maintenance than in response to adverse service conditions.
In theory, a relay system should be able to respond to an
infinite number of abnormalities that can possibly occur
within the power system.
60
-
8/12/2019 Power distribution and transmission
53/60
-
8/12/2019 Power distribution and transmission
54/60
The first step in applying protective relays is to state the protection problemaccurately.
Although developing a clear, accurate statement of the problem can often
be the most difficult part, the time spent will pay dividends particularly
when assistance from others is desired.
Information on the following associated or supporting areas is necessary:
System configuration
Existing system protection and any known deficiencies
Existing operating procedures and practices, possible future expansions
Degree of protection required
Fault study
Maximum load, current transformer locations and ratios
Voltage transformer locations, connections, and ratios Impedance of lines,
transformers, and generators 62
-
8/12/2019 Power distribution and transmission
55/60
System configuration is represented by a single-line diagram showing
the area of the system involved in the protection application.
This diagram should show in detail the location of the breakers, bus
arrangements, taps on lines and their capacity, location and size of the
generation, location, size, and connections of the power transformers
and capacitors, location and ratio of ct's and vt's, and system
frequency.
Transformer connections are particularly important. For ground
relaying, the location of all ground sourcesmust also be known
63
-
8/12/2019 Power distribution and transmission
56/60
-
8/12/2019 Power distribution and transmission
57/60
An adequate fault study is necessary in almost all relay applications.
Three-phase faults, line-to-ground faults, and line-end faults should all
be included in the study.
Line-end fault (fault on the line-side of an open breaker) data are
important in cases where one breaker may operate before another. For ground-relaying, the fault study should include zero sequence
currents and voltages and negative sequence currents and voltages.
These quantities are easily obtained during the course of a fault study
and are often extremely useful in solving a difficult relaying problem.
65
-
8/12/2019 Power distribution and transmission
58/60
Multifunctional
Compatibility with
digital integrated
systems
Low maintenance
(self-supervision)
Highly sensitive,
secure, and
selective
AdaptiveHighly reliable
(self-supervision)
Reduced burden
on
CTs and VTs
Programmable
VersatileLow Cost
-
8/12/2019 Power distribution and transmission
59/60
-
8/12/2019 Power distribution and transmission
60/60
THANK YOU
FOR YOUR ATTENTION