![Page 1: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/1.jpg)
www.energy.gov/EM 1
Portsmouth/Paducah Project OfficePORTS X-326 Process Building
Robert E. Edwards III, ManagerDennis Carr, Project Manager, Fluor BWXT
National Cleanup WorkshopWashington D.C.
September 13, 2017
![Page 2: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/2.jpg)
www.energy.gov/EM 2
PPPO Portsmouth Site Overview
The Portsmouth Gaseous Diffusion Plant site is located in South Central Ohio.
Plant occupies approximately 1,200 acres of a 3,777-acre federal site.
Uranium Enrichment Operations began in 1954 and ceased in 2001.
DOE cleanup mission began in 1989.
![Page 3: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/3.jpg)
www.energy.gov/EM 3
• PORTS mission evolved over the years as uranium enrichment efforts moved from a focus on nuclear defense to a commercial nuclear power mission.
• PPPO began management of cleanup efforts in 2003.
COLD WAR1954-1989
Nuclear Defense
POST COLD WAR1989-2001
Commercial Nuclear Power
CLEANUP2001-Current
• Environmental Cleanup• Decontamination &
Decommissioning• Reuse
PPPO Portsmouth’s Evolving Mission
![Page 4: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/4.jpg)
www.energy.gov/EM 4
CURRENT STATE
PPPO’s Cleanup Strategy at Portsmouth
• D&D• Deactivation and demolition of 415 buildings and
structures, ~1.2M yd3 of debris• Removal of infrastructure not needed for future use
• Environmental Remediation• Excavation and consolidation of selected landfills and
plumes to be used as OSWDF engineered fill, ~3M yd3 soil
• Monitored natural attenuation post-D&D• Waste disposition
• Installation and operation of OSWDF for process building waste, ~5M yd3 capacity
• Offsite disposal of all waste that does not meet OSWDF WAC
• Processing of legacy nuclear inventory• Disposition of 23,000 DUF6 cylinders
• Property Transfer• Reduction of federal site footprint from 3,773 acres
to ~400 acres
AT COMPLETION
![Page 5: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/5.jpg)
www.energy.gov/EM 5
PPPO PORTS Comprehensive Site-Wide Closure Plan
• Lifecycle Baseline
• Regulatory decisions and agreements
• Consensus with public on final land use (stakeholder/regulator alignment)
• Technological approach
• Focused workforce
PPPO PORTS Comprehensive Site-Wide Closure Plan
![Page 6: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/6.jpg)
www.energy.gov/EM 6
PPPO PORTS Critical Path to Successful Cleanup
![Page 7: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/7.jpg)
www.energy.gov/EM 7
PPPO PORTS D&D Project
• Final paperwork is in process to declare X-326 “cold and dark”and ready for demolition in FY22
PPPO PORTS D&D Project
![Page 8: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/8.jpg)
www.energy.gov/EM 8
PORTS D&D Project
X-326 High Enrichment Uranium Processing Plant • Hazard Category 2 Nuclear Facility;• ~1/2 mile long; ~56 acres under roof on two floors;• 200 cells arranged in 10 enrichment units;• 7,020 converters, compressors & coolers characterized and
removed;• Over 300,000 feet of interconnecting piping, withdrawal
facilities and process exhaust systems• 600 miles of copper tubing
![Page 9: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/9.jpg)
www.energy.gov/EM 9
PORTS D&D Project
X-326 Deactivation • Over one year without a recordable injury• 94% cell floor, 45% operating floor complete;• 4 of the 10 enrichment units deactivated by EOM;• Over 98% of converters, compressors and coolers
characterized, removed and shipped offsite for disposal;• 1.1 of 1.3 M NDA measurements required to confirm
equipment can remain in building for demolition complete;• Achieve Cold & Dark in early 2018
![Page 10: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/10.jpg)
www.energy.gov/EM 10
PORTS D&D Project
X-326 Deactivation • Remove and ship offsite converters, compressors and coolers• Achieve “Criticality Incredible” status (no NCS controls required)
for all remaining equipment• Remove hazardous, universal and other wastes prohibited from
disposal in the on-site cell.• Isolate facility from site utilities to achieve Cold & Dark
![Page 11: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/11.jpg)
www.energy.gov/EM 11
PORTS D&D Project
X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning
Workforce to D&D• Underestimated magnitude/implications of PPPO Quality System for
NDA (QSNDA) – Trained & Qualified 250 Person NDA Organization• NOx Generation During Plasma Arc Cutting• Restoring Deteriorated Infrastructure – Cranes, Elevators, Lighting,
Fire Protection . . . • Deploying Qualified NDA Platforms Addressing
All Configuration of Equipment, Piping, Valves.
![Page 12: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/12.jpg)
www.energy.gov/EM 12
Access Road
OSWDF
Impacted MaterialTransfer Area (IMTA)
Interim Leachate Treatment System
Raw Water Line
Haul Road (IMTA + IMHR)To X-326
PORTS D&D Project
On Site Waste Disposal Facility
![Page 13: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/13.jpg)
www.energy.gov/EM 13
PORTS D&D Project
On Site Waste Disposal Facility• Regulatory Decision in Place• CD3A Approved• Preliminary DAS in Place • 100% Design Package Underway • Field Construction/Site Prep Underway
Moving 1.4M/cy by Xmas• Seeking Final DAS in FY18• Project Objective – FIRST WASTE PLACEMENT
BY FY21 (end of CY20)
![Page 14: Portsmouth/Paducah Project Office PORTS X-326 Process Building · 2017. 10. 2. · X-326 Deactivation Challenges Overcome • PORTS First Time Adoption of ISMS & Work Planning; Transitioning](https://reader035.fdocuments.net/reader035/viewer/2022081617/6024a445c115a65d52003f2d/html5/thumbnails/14.jpg)
www.energy.gov/EM 14
Reindustrialization at PORTS
First Property is currently being prepared for transfer
• DOE received a proposal from SODI for 80 acres at the site• State of Ohio concurrence received, final transfer package being
completed for submission to DOE-HQ• Requires Congressional approval to finalize transfer