Port Operations

download Port Operations

of 15

description

Planning and designing a port structure with demand forecasting, capacity assessment, and optimization

Transcript of Port Operations

  • 5/24/2018 Port Operations

    1/15

    Port Engineering 1

    Port Engineering

    Planning, Design and Analysis

    Prepared by:

    Jeremy Molayem

    CE 589 Port Engineering: Planning and Operations

    Professor Hanh Le-Griffin

    Submittal Date:

    24 June 2014

  • 5/24/2018 Port Operations

    2/15

    Port Engineering 2

    Table of Contents

    Abstract 3

    Introduction 3

    Demand ForecastingA Trilogy of Scenarios 4

    Capacity AssessmentMethodology and Assessment 5

    ImprovementsInfinite Scenarios 8

    ImprovementsA Reasoned Approach 10

    ImprovementsFinancial Motivations 12

    Simulation and Summary of Results 13

    Citations 14

    Appendix 15

  • 5/24/2018 Port Operations

    3/15

    Port Engineering 3

    Abstract

    Port capacity planning is an increasing crucial task in an economy continuing to globalize. This

    paper addresses three components to planning: demand forecasting, capacity analysis, and

    potential capacity improvements. Furthermore, these components assert the following three

    questions: 1) where is the bottleneck in the system? 2) what are the physical and operational

    improvements? 3) how should these improvements be implemented to minimize cost and

    increase utility? In addressing these questions, Microsoft Excel is used to both model and

    simulate various demand scenarios, conduct sensitivity analysis due to parameter adjustment,

    and optimize capacity parameters to minimize cost.

    Introduction

    With scattering supply chains, increasingly connected populations, and maturing markets in

    developing countries, international trade is and will continue to undergo a new level of change.

    While technology has not necessarily been a cause for a global market, it has certainly been an

    accelerant. For example, the internet is increasingly separating traditional supply chains. A

    United States car company can operate a factory in Germany, ship its metals from West Africa

    and utilize a technical team from South Korea. And, this is simply the beginning. In five years, 5

    billion people, 70% of the worlds population, will have permanent access to the internet for the

    first time (Schmidt, et al). The central part of this paper is to attemptto plan and design a port for

    this unpredictable and global future.

    Certainly, the degree of future variability due to technology is immense. One such

    scenario for a new manufacturing world is the rise of the household 3D printeran increasingly

    affordable technology that allows a person or business to printalmost any object such as a cup

    or bicycle wheel. Simply through downloading the cup file from the internet, anyone from

    anywhere in the world such as Nigeria or Ecuador can print a cup. This can fluidize and

    revolutionize manufacturing, especially in regions that must use outsourced manufacturers (Chen

    2012). How will this future look for cup factories in China? Will they go out of business and the

    international trade for cups decline? This is unforeseen, and that is the point of this anecdote.

    There has never been a more difficult and exciting time for port planning in history.

  • 5/24/2018 Port Operations

    4/15

    Port Engineering 4

    Demand Forecasting A Trilogy of Scenarios

    The Port of Panama will progressively become a hub for traffic between the Pacific and Atlantic

    spheres. Demand for trade is reaching astounding levelsworld container distribution is

    growing at three times world GDP growth (Melford, 2008). From the year 2012 to 2020, the

    terminal is expected to increase its handling from 400,000 TEUs to 568,000 during a low growth

    scenario and 824,300 TEUs during a high growth scenario (Fig. 1). By 2030, demand will reach

    a maximum of 1.754 million TEUs and a minimum of 1.0015 TEUs. The modelling of this

    growth consists of two parts. For component one, from FY 2012 to FY 2020, a low forecast

    gives 4.5%, a high of 9.46%, and a median of 6.98%. For component two, 2020 to 2030, both

    initial and final values are known. Therefore, a growth curve can be extracted. An example of the

    low demand growth is shown below:

    Solve for X

    X = 0.058 or 5.8%

    Similar calculations yield X= 6.8% and 7.8% for median and high demand, respectively.

    Figure 1. Forecasting various demand scenarios from FY 2012 to FY 2030

    In calculating demand, the data allows for analysis of container type as well. The demand is

    expected to be distributed of 50% import, 25% export, and 25% empty.

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    1.4

    1.6

    1.8

    2

    2010 2015 2020 2025 2030 2035

    TEUs

    Millions

    Year

    Demand Forecast

    Low

    Median

    High

  • 5/24/2018 Port Operations

    5/15

    Port Engineering 5

    Capacity Assessment Methodology and Comparison

    Assessing the capacity is disaggregated into four main componentsberth, container

    yard, gate, and rail. The purpose of a capacity assessment is to determine the bottleneck of the

    systema determination which will guide the process for improvements and recommendations.

    Before calculating the capacities, two considerations must be made. First, in analyzing potential

    bottlenecks, the capacities of both gate and rail are addedsince one mode can support the other

    and vice versa. Second, capacities are artificially decreased due to a bottleneck constraint

    where capacity at 80% of demand constitutes a bottleneck. The following figure shows an

    accurate description of all capacities in relation to demand growth.

    Figure 2. Capacity thresholds in relation to growth demand from FY 2012 to 2030

    The optimizing of berth operations has received considerable research over the past few years

    particularly the berth allocation problem (BAP). Several researchers contend that that the berth

    allocation problem and the quay crane scheduling problem are in fact one single problem that is

    tied together. Berth scheduling is a function of the crane that is assigned for the ship. (Park et al.,

  • 5/24/2018 Port Operations

    6/15

    Port Engineering 6

    Liu et al.). For practical purposes in this analysis, berth allocation is separated from berth

    capacity planning. Our analysis of berth capacity focused on three main factors: 1) crane

    productivity, measured in moves per crane-hr, 2) working hours, and 3) the number of cranes.

    The port has made the following improvements already: namely, the replacement of three older

    cranes with two Post-Panamax cranes in 2013. Currently, there are nine ship-to-shore gantry

    cranes (QCs). Berth capacity was calculated as follows:

    ( )

    Furthermore, there are three more considerations in calculating capacity. First, total lifts is

    converted to TEUs by multiplying a factor of 1.7 to yield for TEUs (twenty-equivalent units).

    This process is used to account for the presence of FEUs (forty-equivalent units). Second, toattain work hours, the holidays were considered as follows: 52 weeks/yr with 1 weeks(5 days)

    worth of holidays. Third, capacity is reduced by 20% to ensure the following constraint:

    bottleneck exists when capacity is 80% of demand. The following is current berth capacity:

    ( )( ) (

    )(

    ) (

    )

    The capacity assessment of the container yard is separated into two components: an area

    based approach and an equipment based approach. In regards to an area based approach, the

    following formula is used:

    Total ground slots is given as 3650 TEUs. To acquire stack height, total throughput is divided by

    total stack height. In this case total throughput is given as 11,680 TEUs. Stack height yields the

    following:

    Finally, turnover rate is a function of average dwell time, calculated as 5.33 days. Turnover rateyields the following:

    ()

    Therefore, dynamic capacity using an area approach yields:

  • 5/24/2018 Port Operations

    7/15

    Port Engineering 7

    Using an equipment based approach, different parameters apply: 1) the number of RTGs in the

    container yard, 2) the productivity of an RTG, and 3) the hours of operation per year. The

    following expression shows this relationship.

    ( ) (

    )

    ( ) Since equipment capacity is far greater than the calculated area capacity, the bottleneck analysis

    will used the area calculated through area (0.65 million TEUs).

    In calculating the rail capacity, the port exists with the following characteristics: a) 20%

    of the terminal throughput is through rail transportation b) a train can handle 250 TEUs c) it

    takes seven to eight hours to load an entire train d) operation is 2 eight-hour shifts. The following

    is methodology behind determining rail capacity:

    ( ) ()

    The following figure shows rail capacity,

    Figure 3. Rail Capacity with respect to a 20% throughput of current demand

    0

    0.05

    0.1

    0.15

    0.2

    0.25

    0.3

    0.35

    0.4

    2010 2015 2020 2025 2030 2035

    TEUs

    Millions

    Year

    Rail Demand and Capacity

    Capacity

    20% Demand

  • 5/24/2018 Port Operations

    8/15

    Port Engineering 8

    Although it may appear that rail capacity is a bottleneck in the system due to low capacity, gate

    capacity also plays a role in offsetting rail loading during peak times. The two capacities can and

    should be considered. Gate capacity is determined as follows:

    The following yields an actual calculation:

    ( )(

    ) (

    )

    The following table illustrates a summary of capacity calculations and results.

    Type Berth Container Yard Rail Gate

    Parameters Work hours

    ProductivityNumber of Cranes

    Dwell Time

    UtilizationStack Height

    TGS

    Turnover Rate

    Work hours

    ProductivityHandle Number

    RTG Lifts

    Work hours

    Productivity

    TEUs (Million) 1.65 0.65 0.14 0.66

    Bottleneck (Year) 2028 2017 2018 2018

    Table 1: A piece by piece approach to capacity analysis for the port

    Improvements Infinite Scenarios

    With forecast projected and capacity determined, the implementation of improvements is perhaps

    the most difficult yet creative task for planning and design. In this endeavor, over 15

    permutations of plans and horizons were tested. Three scenarios were ultimately finalized for

    high, median, and low outcomes. The following figure illustrates an attempted approach at

    formulating a sound strategy for cost savings, efficiency, and practicality.

    There are two reasons why this strategy ultimately failed:

    1. The option for Rail Mounted Gantry cranes (RMGs) was exhausted before considerationsfor land purchases. RMGs represent an inflexible and high capital cost. Financial analysis

    (page x.) indicates that this warrants further decision analysis.

    2. Gate productivity was increased simply through maximizing shifts. However, automationas an option was not considered.

  • 5/24/2018 Port Operations

    9/15

    Port Engineering 9

    Figure 4. Test trial without consideration for gate automation and importance of land

    Figure 5. Suggested improvement for high demand scenario

  • 5/24/2018 Port Operations

    10/15

    Port Engineering 10

    While a side by side comparison of the improvements is crucial to illustrate the infinite number

    of improvement scenarios, analysis of improvements will primarily focus on the latter case,

    figure 5.

    Improvements A Reasoned Approach

    Container YardPhase 1

    The first bottleneck and therefore, the first area for improvement is the container yard in FY

    2017. The initial improvement options were as follows: increase stack height, improve

    productivity with replacement of RTG, increase the number of total ground slots, or increase the

    average dwell time. The latter three improvements were postponed for longer term adjustments

    because a) they represent a high, inflexible capital cost (RMG), b) drastically affect the ability to

    retain clients (dwell time), or c) introduce newer layers of bureaucracy (land acquisition).

    Therefore, the most sensible conclusion was to first increase stack height utilization.

    Gate AdjustmentPhase 1

    The second bottleneck occurs for the inland transportation capacity (gate and rail) at FY 2019. It

    is important to note that rail capacity was considered fixed because improvements to the system

    only represented negligible changes. This is illustrated in figure 3. In focusing on gate

    improvements, the primary driver for optimization is an automation system which can improve

    productivity from 10 to 30 moves/lane-hr.

    Point of Discussion: The decision for a partial implementation of this system went through

    considerable review. Ultimately, the team eventually came to a full position reversal after

    hearing an opposing opinion. A full implementation of automation now makes financial sense for

    the following reasons:

    1. The benefits of waiting and partially installing automation on gates are minorconsidering a) hardware capital cost is relatively low and b) software is a one-time

    purchase which would incentivize a full hardware installation to maximize the purchase.

    2.

    A partial gate automation system would present problems for the standardization ofpractices. Two separate systems require different protocols for truck drivers, security,

    data management, and a host of other parameters.

    Our team initially viewed partial implementation to be superior for flexibilitywith a justifiable

    convincing strategy. However, full automation offers slightly better benefits.

    Container YardPhase 2

  • 5/24/2018 Port Operations

    11/15

    Port Engineering 11

    Around year 2023, the container yard presents an additional bottleneck. However, this bottleneck

    requires a high capital investmentpurchases of RMGs or land implementation. Additional land

    implementation ultimately is a sound strategy demonstrated in Table 2.

    FY 2023 Improvement RMG Option Land Acquisition

    Advantages a) No additional land needed

    b) Limited bureaucratic or

    community barriers

    c) RMG may ultimately be

    required in the future

    a) Land expansions will be

    increasingly difficult as

    Balboa City, Panama grows

    b) Appreciates over time

    c) Immune to technology

    Disadvantages a) New yard foundation

    necessary

    b) Construction interrupts port

    operations

    c) Depreciates over time

    d) Outdated by newer

    technology

    a) Bureaucratic barriers (EIR,

    community support required)

    b) Additional development

    required

    c) Consideration needed for

    effect on terminal operations

    Table 2: Comparison between RMG and Land Acquisition

    RMG represents a high capital cost. The future twenty years and beyond will present a) RMGs at

    a substantially reduced rate and b) possible new technologies that could drastically make an

    RMG outdated. Furthermore, equipment depreciates over time and a newer, stronger foundation

    is needed to support a rail system. This implementation could severely limit port operations.

    However, the decision between land acquisition and RMG use warrants further investigation

    specifically with an eye towards a) bureaucratic barriers, b) community support, c) proposed site

    placement, d) land usability, and e) projections for the growth of Balboa City around the port.

    Such specificity is outside the scope of this recommendation for land expansion. However, if

    feasibility permits, acquiring additional land as soon as possible presents a strong position for

    future growth.

    Berth CapacityPhase 1

    Berth capacity reaches a bottleneck in FY 2028. Therefore, two feasible improvements are to

    increase productivity or to increase the working hours. The construction of an additional crane

    may not be feasible due to a) land constraints, b) ship constraints, and c) high capital cost. The

  • 5/24/2018 Port Operations

    12/15

    Port Engineering 12

    recommendation is to increase productivity with operational improvements to the crane. One

    such improvement is the double cycling technique which allows for the loading and unloading of

    containers simultaneously. Research has found that this process can induce a 10% reduction in

    operating time and 25% reduction in chassis requirement (Goodchild et al.).

    Improvements Financial Motivations

    The proposed plan takes an adaptive approach to growthplanning for a future that is neither

    too great nor too small in demand. The port reserves its capital investments to a later date while

    maintaining a competitive port. Early improvements, I1 to I5, represent low cost additions:

    container yard utilization increases, gate automation, and land expansions. These improvements

    constitute all improvements until 2028. This yields a significant delay, 14 years, before higher

    level investments, shown as I6 to I8 in the figure. These high investment improvements

    namely, the addition of RMGsis not required until the year 2028. If demand falls short of

    expected forecasts, investments I6 to I8 will not be even exercised.

    Figure 6. An overview of an adaptive financial strategy for a dynamic market

    0 5 10 15 20 25

    I1

    I2

    I3

    I4

    I5

    I6

    I7

    I8

    Cost ($ Millions)

    ImprovementMeasure

    Improvement Measures

    Inexpensive

    (Target low cost measures for

    early improvements)

  • 5/24/2018 Port Operations

    13/15

    Port Engineering 13

    Simulation and Summary of Results

    In the event of different demand scenarios, the above recommendation shown in figure 6

    significantly changes. For the purpose of report brevity, simulation results are included in the

    appendix. However, the main differences in proposed improvements in highlighted in figure 7.

    Figure 7. An action plan for various demand scenarios

    Demand in the low scenario falls low enough that the port need not make any physical

    improvements or expansions to any of its systemszero capital costs. However, the demand

    scenario still justifies operational improvementsincreased stack height utilization and increase

    in the number of gate shifts. Finally, it is important to distinguish that as demand scenarios

    signal higher volume, the ports capital investments will inevitably increase as well.

  • 5/24/2018 Port Operations

    14/15

    Port Engineering 14

    Citations

    Chen, Baizhu, Yes, We Can Make iPhones in America.Forbes Magazine. 1 Sep. 2012.

    http://www.forbes.com/sites/baizhuchen/2012/09/07/yes-we-canmake-iphones-in-america/

    Goodchild, A.V., C.F. Daganzo, Crane double cycling in container ports: planning methods and

    evaluation

    Y.-M. Park, K. Kim, A Scheduling method for Berth and quays cranes, OR Spectrum 25 (2003)

    1-23.

    J. Liu, Y-M Wan, I. Wang, Quay crane scheduling at container terminals to minimize the

    maximum relative tardiness of vessel departures, Naval Research Logistics 53 (2005) 60-

    74

    Melford International Port, Container Port and Intermodal Logistics Park Project,

    www.toledoportauthority.org/docs/Melford%20Presentation.pdf ,2008 (accessed on June

    13, 2014)

    Schmidt, Eric and Jared Cohen. The New Digital Age: Reshaping the Future of People, Nations

    and Business. Alfred A. Knopf. New York 2013

    http://www.toledoportauthority.org/docs/Melford%20Presentation.pdfhttp://www.toledoportauthority.org/docs/Melford%20Presentation.pdfhttp://www.toledoportauthority.org/docs/Melford%20Presentation.pdf
  • 5/24/2018 Port Operations

    15/15

    Port Engineering 15

    Appendix

    Low Demand Scenario and Action Plan

    Median Demand Scenario and Action Plan