    PRINCIPLES OF PLANNING 

  • 8/18/2019 POPBC Notes and Workshop and Answers

    2/36

    PRINCIPLES OF PLANNING 

    ©Copyright 2007 by Eastwood Harris Pty Ltd. No part of this publication may be reproduced or used in any

    form or by any method without the written permission of the author.

    This presentation was developed by Eastwood Harris Pty Ltd for Laing O’Rourke Pty Ltd. This presentation

    .

    For further information please contact:Paul E Harris

    Director 

    Eastwood Harris Pty Ltd

    P.O. Box 4032

    Doncaster Heights 3109

    Victoria

     Australia

    Phone: [61] 03-9846-7700Mobile: [61] 04-1118-7701

    Fax: [61] 03-9846-7900Email: [email protected]

    Web: www.eh.com.au

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  2

  • 8/18/2019 POPBC Notes and Workshop and Answers

    3/36

    PRINCIPLES OF PLANNING 

    The instructor will outline:

    Emergency Evacuation – the emergency evacuation procedures for the building.

    Timings – the course timetable.

    Meals – catering arrangements

    Mobile Phones – please turn your mobile phones off or switch to silent.

    Conduct of course – This course is lead by you instructor is based on a Power Point

     presentation. There are group exercises that you will asked to conduct in groups to

    .

    Introductions – After the instructor has introduced himself you will be asked to:

    Introduce your self 

    Your position and projects you are currently working on

    Your experience in project planning, scheduling and control.

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  3

  • 8/18/2019 POPBC Notes and Workshop and Answers

    4/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  4

  • 8/18/2019 POPBC Notes and Workshop and Answers

    5/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  5

  • 8/18/2019 POPBC Notes and Workshop and Answers

    6/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  6

  • 8/18/2019 POPBC Notes and Workshop and Answers

    7/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  19

  • 8/18/2019 POPBC Notes and Workshop and Answers

    8/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  20

  • 8/18/2019 POPBC Notes and Workshop and Answers

    9/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  21

  • 8/18/2019 POPBC Notes and Workshop and Answers

    10/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  22

  • 8/18/2019 POPBC Notes and Workshop and Answers

    11/36

    PRINCIPLES OF PLANNING 

    Plans are often created to meet contract requirements:

    1. They are used to keep the client happy and off the Project Managers back,

    2. They are left in the bottom drawer,3. Only updated to meet reporting requirements and

    4. Are not used to manage the project.

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  23

  • 8/18/2019 POPBC Notes and Workshop and Answers

    12/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  24

  • 8/18/2019 POPBC Notes and Workshop and Answers

    13/36

    PRINCIPLES OF PLANNING 

    Risk Analysis

    The process of planning a project may identify risks and this process may result in a requirement

    for risk mitigation tasks to be added to the schedule before it is submitted for approval. A Risk Logis usually created and as risks are identified they are added to the Risk Log where they are

    managed.

    Risk Management

    This is the process that should be continued throughout a project’s life. The Risk Log should be

    regularly reviewed and responses updated if necessary.

     AS/NZS 4360:2004 is a good guide to managing risks.

    Stakeholder Analysis

     A schedule is not complete unless it has included all the project tasks and all the work that has to

    be undertaken by people outside the project team. It is important that a stakeholder analysis is

    .

    Path but this calculation may be incorrect if all the tasks are not included in the schedule.

    Therefore, tasks such as client review and approval of documents and plans or statutoryapplications and approvals must be included for the schedule to be completed and calculated

    correctly.

    Stakeholder Management

    This process should be continued throughout the project life and the Communications Plan is the

    normal method of managing stakeholders.

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  37

  • 8/18/2019 POPBC Notes and Workshop and Answers

    14/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  38

  • 8/18/2019 POPBC Notes and Workshop and Answers

    15/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  39

  • 8/18/2019 POPBC Notes and Workshop and Answers

    16/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  40

  • 8/18/2019 POPBC Notes and Workshop and Answers

    17/36

    PRINCIPLES OF PLANNING 

    If a programme is to be updated every month then try to avoid activities greater than one month

    long and then the activity should be started one period and complete the next.

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  41

  • 8/18/2019 POPBC Notes and Workshop and Answers

    18/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  42

  • 8/18/2019 POPBC Notes and Workshop and Answers

    19/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  55

  • 8/18/2019 POPBC Notes and Workshop and Answers

    20/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  56

  • 8/18/2019 POPBC Notes and Workshop and Answers

    21/36

    PRINCIPLES OF PLANNING FOR BUILDING AND CONSTRUCTION 

    WORKSHOP 5 - QUESTION

    Assuming that the start of the first activity is on 1 April and the project is working 7 days per week:

    1.  Calculate the Early Dates, Late dates and Total Float on the picture below.

    2. 

    Draw a Gantt Chart on the next page.

  • 8/18/2019 POPBC Notes and Workshop and Answers

    22/36

    Blank Page

  • 8/18/2019 POPBC Notes and Workshop and Answers

    23/36

    PRINCIPLES OF PLANNING FOR BUILDING AND CONSTRUCTION 

    WORKSHOP 5 – QUESTION CONTINUED

  • 8/18/2019 POPBC Notes and Workshop and Answers

    24/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  58

  • 8/18/2019 POPBC Notes and Workshop and Answers

    25/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  73

  • 8/18/2019 POPBC Notes and Workshop and Answers

    26/36

    PRINCIPLES OF PLANNING 

    Many project fail because:

    - A programme is not created, or 

    - A poor programme is created, or - The programme is not used to manage the project.

    Programming tends to be the worst performed project management skill and surveys by

    companies such as Standish indicate that twice as many project failures can be attributed to poor

    programming than any other factor.

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  74

  • 8/18/2019 POPBC Notes and Workshop and Answers

    27/36

    PRINCIPLES OF PLANNING 

    The Data Date is known by a number of other terms including Status Date, Current Date,

    Report Date, Update Date and As-of-Date.

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  75

  • 8/18/2019 POPBC Notes and Workshop and Answers

    28/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  76

  • 8/18/2019 POPBC Notes and Workshop and Answers

    29/36

    PRINCIPLES OF PLANNING 

    Many companies keep historical records in document titled Lessons Learned Reports, or End

    Project Reports or Project Close Out Report. The information for these reports is used to

    improve the ability of the company to prepare tenders and perform work. These documents areprepared from project reports and other sources such as the Issues Log and Risk Log. It is

    important that these reports are continued right to the end of the project so the final picture is

    known.

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  77

  • 8/18/2019 POPBC Notes and Workshop and Answers

    30/36

    PRINCIPLES OF PLANNING 

    There is only so much that can be done with a programme, but any changes made to the

    programme must be agreed to by the stakeholders.

    -Contingent time must not be reduced without the project managers knowledge-Work should not be programmed in parallel unless it is possible to do the work safely.

    -Shortening of the durations of activities by increasing resources should only be done if the

    resources are available and they can all work effectively and safely in the area.

    -Be careful with long shifts as people quickly become burnt out working long hours.

    -Changing the method of executing such as changing from cast-in-situ concrete to pre-cast

    concrete may resolve problems.

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  78

  • 8/18/2019 POPBC Notes and Workshop and Answers

    31/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  91

  • 8/18/2019 POPBC Notes and Workshop and Answers

    32/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  92

  • 8/18/2019 POPBC Notes and Workshop and Answers

    33/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  93

  • 8/18/2019 POPBC Notes and Workshop and Answers

    34/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  94

  • 8/18/2019 POPBC Notes and Workshop and Answers

    35/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________  95

  • 8/18/2019 POPBC Notes and Workshop and Answers

    36/36

    PRINCIPLES OF PLANNING 

    Your notes:

     _______________________________________________  _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________ 

     _______________________________________________