Policy and planning processes for delivering the Commission's recommendations: Scene-setting &...
-
Upload
justin-price -
Category
Documents
-
view
222 -
download
0
Transcript of Policy and planning processes for delivering the Commission's recommendations: Scene-setting &...
Policy and planning processes for delivering the Commission's
recommendations:Scene-setting & process
Robbie Owen
Head of Infrastructure Planning and Government Affairs
Pinsent Masons LLP
Introduction
• What is the recommended wider package – “key supporting policies”?
• What needs to be done to deliver it?• For the development consenting aspects, the part to be
played by:– a Hybrid Bill; or– a Development Consent Order
• Key differences between those two consenting routes
• Deciding factors?
Recommended wider package (1)
Congestion or
access charge?
Tie-in to progress on EU air
quality targets
UK aviation
‘noise levy’
Independent aviation noise
authority
Ban on night flights
Legal commitment - No 4th Runway
Legally binding ‘noise
envelope’
Recommended wider package (2)
Wider community package
Joint Oversight
Board
Dedicated delivery
body
Surface access
improvements
Airspace change
Community Engagement
Board
Public service obligations on an airport-to-airport basis
Delivering a wider package…..
• HMG and HAL discussions and negotiations• Role of other bodies (local authorities, GLA, TfL, CAA, airlines, Highways
England, Network Rail, environmental regulators)• Initial House of Commons vote/motion?• Green, White and Command Papers• DfT consultation before any decision?• Paving Bill?• Civil Aviation Bill (‘Programme Bill’)?• Non-hybrid (i.e. public) aspects in a Hybrid Bill?
Two consenting options (1)
Development Consent Order (DCO) Hybrid Bill
Order made under Planning Act 2008 Primary legislation
Most major infrastructure projects, e.g. TTT, Hinkley Point C, Swansea Tidal Lagoon
Used less often: HS2, Crossrail 1, HS1 – suited to big projects
Promoter in control Government in control
PINS examines; Secretary of State decides
Select Committees review; Parliament decides but capacity issues?
Heavily proscribed and very onerous statutory process (e.g. consultation and examination)
More flexible and less onerous; more of a one stop shop
Definitive, shorter timeline No programme certainty
Easier for public to engage? Easier for public to obtain changes?
Less politicised Immunity from legal challenge
Two consenting options (2)
Both options need the Government to take action:
• DCO ideally supported by an Airports National Policy Statement (NPS) - to be prepared, consulted on and ‘designated’
• A Hybrid Bill needs:– to be promoted by the
Government– Parliamentary time and support
Consenting for major infrastructure identified
in Planning Act 2008 (including airports)
Consent is a statutory instrument called an
‘Order’
Can authorise more than one piece of major
infrastructure in a single DCO
Streamlined consenting process (planning, land
acquisition, licences, permits in one place)
Guaranteed timelines after submission =
Decision by SoS 16-18 months from submission
of application
Promoter prepares application Detailed
public review by Planning Inspectorate
(PINS)
DCO
DCO process
Pre-submission
c.9 months – 3 years
Post-Submission: -acceptance -initial assessmentc. 4-5 months
Examination
6 months
PINS ReportingandSoS Decision
6 months
Prelim
inary
Meetin
g
• Front loaded• Extensive consultation & notice requirements• Examination:
– Extremely intensive 6 months! – Written process, supplemented by hearings
• Decision-making period is 3 months + 3 months max
Rookery SouthIpswich Rail Chord
North Doncaster Rail ChordKentish Flats Extension
Brechfa Forest West Wind FarmHeysham to M6 Link Road
Hinkley Point C New Nuclear Power StationPreesall Saltfield (Underground Gas Storage)
Galloper Offshore Wind FarmTriton Knoll Offshore Wind Farm
East Northants Resource Management FacilityPort Blyth New Biomass Plant
M1 J10a Grade Separation - LutonRedditch Branch Enhancement Scheme
Able Marine Energy ParkKings Lynn
StaffordNorth London
East AngliaDIRFT
Rampion Offshore Wind FarmKnutsford to Bowdon Roads Improvement
North Killingholme New Power StationThames Tunnel
Clocaenog Wind FarmBurbo Bank Wind Farm Extension
Woodside Connection (Road)South Hook Combined Heat & Power Station
Walney Extension Offshore Wind FarmHornsea Offshore (Round 3 Zone 4)
Willington Gas PipelineMorpeth
A160 ImminghamA30 Cornwall
Dogger Bank (Creyke Back)Knottingley Power Station
WhitemossNorwich Northern Distributor Road
Tidal Lagoon Swansea Bay
-1000 -500 0 500 1000 1500
-105-398-391-394
-561-270
-557-486
-578-649
-149-693
-338-442
-361-823-783
-555-914
-991-942
-1094-861
-1041-1071-1030
-316-420
-1062-1091-1191
-418-1255
-239-1221-1255
-455-327
-690
212227272617242228232827282824282828282828282828262828262423232319252719282827
1441111201041041021181231621511061131099513313891208189
107110105142168142160
119119113111142162881511478812411896
178133167179183169183182
183181
179183180
144183181
179182181
184184179180180
180180
177181180180171179
131179179
131403391
383
9085
778290
909077
8685
808378
90297
6987
8391
879087
9292
9292
889292917690
909192
908992
91
505
309
706
254632
283
109
290290
829010190
908990
9086
908992
649292
8192
858989919292
9292
919187929291
639291
638689
90
528
Days Taken Per Stage (Decided Projects)
Pre-App (COSMO) Acceptance Pre-Exam Examination Recommendation
Decision SPP JR Re-determination
Source: Planning Inspectorate, July 2015
DCO timelines
Possible R3 DCO timeline
Source: Heathrow Airport Limited, July 2015
DCOs – key considerations
• Promoter leads –in control but can be ‘lonely’• Less political – PINS are independent body, focussed
on planning merits (but NPS still cornerstone)• Extensive consultation and pre-application steps are
statutory obligations• Process has limited flexibility:
– after application made; and– once consent has been given.
• Certainty of delivery timelines the key advantage
Mix of ‘Public’ and ‘Private’ Bill characteristics and
process
Details reviewed by Select Committee
Those specially and directly affected can ‘petition’ against
and be heard
Promoted by Government Department
Principle debated and then approved
Flexible process (changes via Additional Provisions) and flexible
consent
No minimum or maximum timelines
Output = Primary legislation cannot be challenged (except on
EU grounds)
Contains everything needed to deliver project (and more?
e.g. regeneration power in HS2 Bill)
Hybrid Bills
Hybrid Bill process
1. Bill deposit (Bill, Plans & Sections, Environmental Statement, etc.)
2. 1st reading (i.e. publication) in the House of Commons
3. Public consultation on environmental impact assessment
4. 2nd reading (i.e. debate on general principle)
5. “Petitioning” period between 2nd Reading and Select Committee
6. Petitions heard by Select Committee
7. Public Bill Committee (line by line review)
8. Report stage (i.e. report of Committee stage to whole House)
9. 3rd Reading (i.e. final debate on final version of Bill)
10. House of Lords – petitioning and Select Committee
11. Any further amendments approved by the Commons
12. Royal Assent
Example Timeline – HS2 Bill so farConsultation on ES
29 November 2013
Independent Assessor’s Report
9 April 2014
Second Reading
28 & 29 April 2014
Petitioning Deadline
23 May 2015
Committee sat first 6 May 2014
Interim Report
26 March 2015
Hybrid Bills – current and recent statistics
Crossrail Act 2008 HS2 Bill (to 23 June 2015)
10 MPs on Select Committee
5 MPs (previously 6)
457 petitions deposited in Commons
1,918 petitions deposited
84 public sessions 80 public sessions
205 petitioners heard in Commons
More than 400 petitioners heard
7 site visits from Commons Committee
9 site visits from Commons Committee
4 series of amendments to the Bill were recommended and accepted
2 APs so far – more to come
40 months in total 19 months and counting…Anticipated Royal Assent Q1 2017
Hybrid Bills – key considerations
• Political support – need Government backing and wider parliamentary support
• Different policy basis – no NPS required• Flexibility – in process and final consent, more suited to an
outline or hybrid design• Limited scope for legal challenge – as Act is primary
legislation • Ability to incorporate supporting & wide ranging
measures• Timelines are uncertain – Crossrail took 40 months, HS2 is
19 months and counting…• Parliamentary capacity
Political Support
Risk of legal
challenge
Consultation
Obligations
Flexibility of
Consent
Certainty &
Speed
Promoter Control
vs. Governm
ent SupportTransparency
& Public Engagement
Multi-Agency Coordin
ationCost
Deciding factors?
Pinsent Masons LLP is a limited liability partnership registered in England & Wales (registered number: OC333653) authorised and regulated by the Solicitors Regulation Authority, and by the appropriate regulatory body in the other jurisdictions in which it operates. The word ‘partner’, used in relation to the LLP, refers to a member of the LLP or an employee or consultant of the LLP or any affiliated firm of equivalent standing. A list of the members of the LLP, and of those non-members who are designated as partners, is displayed at the LLP’s registered office: 30 Crown Place,
London EC2A 4ES, United Kingdom. We use 'Pinsent Masons' to refer to Pinsent Masons LLP, its subsidiaries and any affiliates which it or its partners operate as separate businesses for regulatory or other reasons. Reference to 'Pinsent Masons' is to Pinsent Masons LLP and/or one or
more of those subsidiaries or affiliates as the context requires. © Pinsent Masons LLP 2015
For a full list of our locations around the globe please visit our websites:
www.pinsentmasons.com
www.Out-Law.com