Pogue Construction Co., LP

40
Pogue Construction Co., LP Contractor Safety Requirements Version 1.1 Updated: 05-06-19

Transcript of Pogue Construction Co., LP

Page 1: Pogue Construction Co., LP

Pogue Construction Co., LP

Contractor Safety Requirements

Version 1.1 Updated: 05-06-19

Page 2: Pogue Construction Co., LP

1

Table of Contents

2

3

4

5

5

6

7

8

10

11

11

13

14

14

15

15

16

17

18

18

19

20

21

21

22

22

23

25

25

25

26

26

26

26

26

27

Responsibilities

General Requirements for Accident Prevention

Training – New Hire and Safety Training

General Rules

Subcontractor Safety Representation

Medical Treatment and Incident Reporting

Disciplinary Action Policy & Program

Required Plans

General Safety / Health – CFR 1926 Subpart C

Hazardous Communication (HAZCOM) - CFR 1926.59 Subpart D

Personal Protective Equipment (PPE) - CFR 1926 Subpart E

Fire Protection and Prevention - CFR 1926 Subpart F

Signs, Signals and Barricades – CFR 1926 Subpart G

Material Handling and Storage – CFR 1926 Subpart H

Tools, Hand and Power – Subpart I

Welding and Cutting – CFR 1926 Subpart J

Electrical - CFR 1926 Subpart K

Lockout Tagout

Scaffolding - CFR 1926 Subpart L

Fall Protection – CFR 1926 Subpart M

Motor Vehicles & Equipment – CFR 1926 Subpart O

Excavations – CFR 1926 Subpart P

Concrete and Masonry – CFR 1926 Subpart Q

Steel Erection - Precast Erection – CFR 1926 Subpart R

Ladders and Stairs – CFR 1926 Subpart X

Confined Spaces in Construction – CFR 1926 Subpart AA

Cranes – CFR 1926 Subpart CC

Hoists – Material/Personnel

Respiratory Protection

Permit to Work Systems

General Public Protection

Site Specific Safety Considerations

Moisture Damage Prevention

Power Actuated Fastening Tools

Overhead Protection

EPA Compliance

Forms 29

Page 3: Pogue Construction Co., LP

2

Responsibilities

Pogue, through written policies and procedures, implementation of the Safety Plan process, employee training and orientation, pre-employment Drug and Alcohol Testing program, will make every attempt to ensure the continued health and safety of its employees. Each project employee must accept responsibility for their own behaviors and personal safety and for the safety of others around them by working safely and insisting that others do the same.

Every project employee is empowered by the Safety Program to:

Conduct their work and behavior in a safe manner.

Stop work immediately to correct any unsafe condition.

Take corrective action so that work may proceed in a safe manner.

Subcontractors and Suppliers

Subcontractors shall have and implement a written Safety & Health Program that meets or exceeds the provisions contained in this Safety Program in addition to complying with all Federal, State and Local codes, laws, regulations and contracts. Subcontractors must also address the project specific aspects of their contract as they relate to safety, health, and the environment.

Safety Pre-Construction Meeting

The Subcontractor’s on-site Supervisor and the Subcontractor’s Designated on-site Safety Representative must schedule and attend a Pre-Construction Safety Meeting with the Project Superintendent to discuss the Subcontractor Safety Requirements. The Pre-Construction Safety Meeting should take place at least five (5) working days before startup to allow for review of required documentation.

Pre-Construction Safety Meetings will include, as a minimum: a review of the safety section(s) of the contract, Pogue Construction Subcontractor Safety Package Requirements (including Job Hazard Analyses (JHA) and other safety submittals) and applicable Subcontractor specific safety programs.

Subcontractor’s Lower Tier Subs, Venders and Suppliers

Subcontractors are responsible for their lower tier contractors, suppliers, and vendors safety, health and security requirements.

Subcontractors, who in turn contract out parts of their work, have total responsibility to insure their lower tier contractors comply with project safety requirements. Additionally, Pogue’s Project Manager and/or the Company's Project Safety Representative shall be notified that the lower tier contractors are arriving at least five (5) days before work starts. Subcontractors will be held directly accountable for all lower tier contractors.

Subcontractor Oversight

Pogue is committed to establishing and maintaining a safe and healthy environment for all Project personnel, its customers, and members of the general public affected by our construction projects.

Pogue is actively involved in the oversight of our Subcontractor’s from an environmental, health and safety perspective. Our Safety Director partners with Project Supervision to oversee the Risk Assessment process to identify the Safety, Health and Environmental, (SH&E) aspects/hazards associated with the Project.

Page 4: Pogue Construction Co., LP

3

The Pogue Safety Department, along with Project Management, use the following to evaluate the Project Safety, Health and Environmental, (SH&E) risks:

1. Risk Assessments – These identify the Safety, Health, and Environmental aspects/hazardsassociated with the Project. Risk Assessments uses specific guidance to identify the nature of thehazards and require site input to identify the specific hazards. The Risk Assessment also usesspecific guidance to identify the nature of the controls in place and require site input tocontrol/mitigate the hazards.

2. Pre-Construction Meetings – Each subcontractor is required to attend a Pre- ConstructionMeeting in which Environmental, Health, and Safety items are discussed with the subcontractor,Pogue Project Management and the Safety Director. The Pre-Construction Safety Meetings willinclude a review of their contract’s safety section(s), Pogue Subcontractor Safety PackageRequirements including activity specific JHAs and other safety submittals, and applicableSubcontractor specific safety programs.

3. Site Specific Safety Programs – Subcontractors submit their safety program to Pogue, alongwith Site Specific Safety Plans, to correct specific hazards (i.e. Fall Protection)

4. Job Hazard Analysis (JHA’s) – Subcontractors are required to submit their daily JHA’s to Poguefor review and comment. The JHA’s are then used by the subcontractor as a planning tool.

5. Project Safety Meetings – Weekly Tool Box Talks – Project employees attend Weekly “ToolBox Talk” Safety Meetings and sign attendance sheets (kept on-site in the Safety File). ToolBox Talk Safety Meeting Topics are distributed by the Superintendent or the Loss PreventionDepartment and are made available for Subcontractors.

6. Weekly Project Safety/Progress Meeting – Every Project Safety/Progress Meeting addressessafety related issues, this includes Safety Audit Reports, recent incidents, and injury, andplanning safety aspects of future activities. Issues discussed are documented as part of theSafety/Progress Minutes.

General Requirements for Accident Prevention

Pre-construction Survey - A Pre-Construction Survey of non-restricted areas/items including photos and/or video and a report of findings will be completed. The survey will identify and document the conditions of on and off site property, structures and other loss risk considerations.

Signs and Postings - Federal, State, Local, Pogue Construction and Contract required Signs & Postings including the "Emergency Phone Numbers and Procedures" and "Emergency Action Site Plan" will be displayed in either the Project Office, the Project Display Case and/or other appropriate locations.

Visitors - All visitors to the site must first obtain permission from an authorized Pogue Construction representative, sign a Visitor's Release Form and obtain and wear a hard hat and safety glasses and work boots.

Radios - Communication radios only. No music radios or other personal music listening devices are permitted.

Cell Phones and Texting - Cell phone use while operating vehicles or equipment is prohibited. The use of “ear buds” / ear phones is also prohibited during work activities. Personal phone calls and texting are restricted to breaks and emergencies.

Drug Policy Statement

Pogue reserves the right to test anyone working on our projects for alcohol or drugs and reserves the right to remove any contractor or employee found in violation of any safety rules or policies.

Subcontractors and others performing work on a Pogue site must have a Substance Abuse Program substantially similar to Pogue’s program. The Subcontractor must supply verification to an authorized Pogue Construction Co., LP representative indicating they can and will comply with these requirements.

Page 5: Pogue Construction Co., LP

4

A “Substantially similar” program would be a program that contains, at a minimum:

1) Pre-employment testing

2) Post-accident / incident testing

3) Testing upon suspicion

Training – New Hire and Safety Training

Every new employee will attend a general orientation with Pogue representative. Attendance at this meeting will be documented.

In addition to a general orientation and basic safety training, specific project safety topics will also be covered. Those topics will typically include, but not be limited to, the following as applicable:

Hard Hat Sticker (if the project site specific requirements)

Speed Limits

Parking

Photography restrictions

Restricted Access Areas and Buildings

Emergency Action Plan

Emergency Procedures and Accident Reporting

Severe Weather Procedures

100% Mandatory GFCI Protection

100% Fall Protection – 6’ Rule

100% Eye Protection

Job Hazard Analysis (JHA)

Noise Protection

Environmental Protection

Permit to work system (hot work, excavation and trenching, electrical room access, etc.)

Hazardous Waste

Non-Hazardous Waste Management

Spill Procedures

Mandatory / Certified Training

Mandatory and/or certified training is required for certain activities including those related to, but not limited to the following:

Hazard Communication (HazCom)

Stair and ladder use

Scaffolding – erection, dismantling and use

Fall Protection

Personal Protective Equipment selection and use

Excavation

Crane Operation

Forklift Operation

Powder Actuated Tool Operation

Confined Space Entry

Page 6: Pogue Construction Co., LP

5

General Rules

1) All personnel on the Pogue Construction Co., LP project are required to attend a safety orientationprior to starting work. Some projects may have badging processes, drug screens, backgroundchecks or other customer requirements.

2) Contractors that employ temporary labors are fully responsible for their safety and their actions.Temporary labor should go through a “site specific” orientation with their contractor to assure theyunderstand the site rules, their limitations, who they report to and what they are expected to do.

3) Unsafe conditions or unsafe acts should be reported immediately to your Supervisor forcorrection.

4) Employees on the Pogue Construction Co., LP project shall not be permitted to work alone;employees shall always be close enough (within “ear shot”) to another worker(s) that they couldget help if they needed it.

5) Report all injuries, regardless of how slight, to your Supervisor or to the Pogue Constructionassigned Safety Manager when they occur.

6) Fighting, creating a disturbance, threats against others, bad attitudes or horseplay will not betolerated and are grounds for dismissal from the project.

7) All employees are expected to act in a professional manner. Sexual harassment of any kind willbe grounds for removal from the Pogue Construction project.

8) Site specific smoking and tobacco use rules must be followed, some projects may not allowsmoking at all.

9) All employees should be trained in proper lifting techniques.

10) Glass containers of any kind are not permitted on the jobsite.

11) Radios are not allowed on the Pogue Construction projects; this also includes personal radios withheadphones or earphones.

12) All persons on the Pogue Construction Co., LP project are expected to exercise safe behaviorwhich includes having the proper attitude, looking ahead and making the commitment to worksafely. Safety belongs to all of us and it is the utmost importance that we take care of ourselvesand each other on a daily basis.

Supervisor and Employee Periodic Safety / Health Training

Pogue Field Staff, Superintendents and Safety Personnel will complete an OSHA 30 Hour course for Construction Industry Safety & Health conducted by / at the direction of the Pogue Safety Director.

Hourly employees will attend a Weekly “Tool Box Talk” Safety Meeting conducted by their Supervisor and sign an attendance sheet which is kept in the on-site Safety File. Training materials are available for use by Subcontractors.

Subcontractor Safety Representation

Each Subcontractor, while working on the Pogue project, must appoint a Competent Person as their Safety Representative as defined in CFR 1926.32(f). The Subcontractor’s Safety Representative can be a Superintendent, Supervisor, or other designated individual whose safety responsibilities include, but may not be limited to the following:

1) Present on the jobsite at all times when subcontractor employees are working on the project. Noexceptions.

2) Can communicate effectively with Pogue Superintendent.

3) Capable of instructing workers in hazard recognition and safe work practices.

4) Capable of assembling and reviewing JHA’s for each major portion of work and reviewing JHA’son a daily basis.

5) Take immediate action to correct unsafe acts and/or conditions when discovered and be able to

Page 7: Pogue Construction Co., LP

6

stop the work of his employees if needed.

6) Provide, inspect, and enforce the proper use of personal protective equipment, tools, and otherequipment for workers.

7) Attend supervisory safety meetings as scheduled.

8) Conduct and submit Weekly “Tool Box” Meetings with workers that include:

a. Discussion of observed unsafe acts and conditions.

b. Review of the accident or near miss experience of the crews and discuss corrective actiontaken to prevent reoccurrences.

c. Ensure each person understands this safety plan and all other safety requirements whileworking on the project.

9) Immediately notify Pogue of any existing hazardous condition(s) to which the workers underhis/her supervision may be exposed.

10) Monitor and control housekeeping issues daily.

Medical Treatment and Incident Reporting

All incidents and injuries must be reported to the Pogue representative immediately. In the event of an incident or injury, each subcontractor must follow the site specific emergency action plan.

Incidents, injuries, or near miss events that occur on a Pogue project SHALL be reported to the Project Superintendent (or their appointee) at the time they occur, these accidents are described as:

1. Any injury to a member of the public

2. Any injury to a contractor or a Pogue employee that requires them to leave the site for medicaltreatment

3. An auto or equipment incident that involves a member of the public

4. An incident that causes damage to equipment or property

5. A significant “near miss”

All incidents and near misses will require a full incident report that shall be submitted to the Safety Director within 24 hours, the JHA that covered the event or task shall be included in the reports.

Return to Work Program

All contractors and subcontractors shall agree to develop and implement a return-to-work program to provide for an early return to work of employees who are temporarily disabled due to an injury or illness sustained while working on this project.

The contractor or subcontractor shall provide light or modified work until the employee is able to resume regular duties. Modified duty positions may be offered at any location of the project or on any shift. Modified work can also be provided at other work locations of the contractor or subcontractor with approval of the Pogue Construction Team.

Injury & Illness Log

Subcontractors must maintain a monthly first aid log of all work related injuries & illnesses and submit the log to Pogue by the end of month.

Incident Investigations and Reports

Pogue Supervisors and/or Subcontractor's Supervisors must conduct an incident investigation and complete a Supervisor's Incident Investigation Report for all injuries and incidents including close call/near miss incidents. The degree and detail of the investigation and report will be dependent upon the severity of the accident. Reports must be submitted to Pogue within 24 Hours of occurrence.

Major Accident Notification

Follow the Posted Emergency Action Plan for Fire, Medical and Environmental Emergencies. The "Crisis Management Program" will be implemented, as applicable.

The Pogue Superintendent shall be notified immediately for all emergencies, any injuries to project personnel and any incident that could possibly result in an insurance claim.

Page 8: Pogue Construction Co., LP

7

1) All incidents resulting in Lost Time Injuries or Property Damage will be reported to the PogueSafety Director. A verbal notification will be made immediately followed by a written reportsubmitted within 24 hours.

2) Major incidents will be immediately reported to the Pogue Safety Director.

3) Pogue will randomly check in with workmen to find out if they are receiving training. Pogue’sintent is to instill a supportive culture during the entire construction period.

Medical Support

On-Site First Aid /CPR Supplies & Trained Individuals

Pogue will maintain a first aid kit at each site for the treatment of minor injuries to Pogue employees, and Subcontractors are required to set up and maintain their own first aid kits.

Each subcontractor shall provide at least one (1) individual currently trained in Red Cross, or equivalent, First Aid & CPR. This individual will be immediately available whenever work is in progress.

Job Hazard Analysis (JHA)

JHAs are an essential part of planning safety into every project activity; JHAs are required by Pogue for every task.

1) Each contractor will assemble a complete, comprehensive JHA for each portion of his work. TheJHA must be clearly communicated to workers prior to starting the task.

2) All discrete tasks with significant hazards to people or property should have a written JHAsubmitted to a Pogue designated representative.

3) Each subcontractor supervisor shall prepare the JHA with their crew who are performing thework and each member of the crew must sign the JHA.

4) JHA’s must be assembled and reviewed each morning with the crew that is using it and anychanges or additions to the JHA are to be initialed by each worker..

5) When the task changes, so must the JHA.

6) JHAs shall be turned in to the designated Pogue representative for review and acceptance oneach specific phase of work or task before work is started.

7) Contractors shall keep their JHAs where the work is being conducted and made available forcrew members and Pogue management.

Contractors that are actively working on a task without a JHA in place will be stopped until a proper JHA can be assembled and communicated with the crew.

Disciplinary Action Policy & Program

Pogue Construction Co., LP Safety Violation Disciplinary Action Program:

Safety violations will not be tolerated and superintendent/foreman will be held accountable for the conduct of their employees. The Superintendents and foremen are required to take action when a violation is observed and immediate action to control or eliminate a hazard is required.

All Project Personnel shall be subject to fair, consistent and constructive disciplinary action for policy non-compliance and be subject to disciplinary action for violations of Pogue policies, procedures and safety rules. Such action may include any one or more of the following depending on the severity of the violation.

All Project Personnel shall be afforded instructive counseling and/or training to assure a clear understanding of the infraction and the proper conduct under Pogue guidelines.

However, nothing in Pogue’s policies, procedures or this safety, health and environmental program will preclude management from terminating an employee for a safety violation.

This is not a progressive discipline system and any safety violation may lead to an employee’s termination from the project without prior instruction or warning. Pogue management reserves the right to impose whatever disciplinary action it deems appropriate.

All serious and life threatening situations, especially fall protection and exposed energized electrical situations, will be treated on a case by case basis. The minimum action could be at least a second offense action.

Page 9: Pogue Construction Co., LP

8

Required Plans

Site Logistics Plan

For the safety of all workers on site the Pogue Construction Project Team is required to assemble a site logistics plan prior to starting work.

Site logistics plans must be assembled by the project team in joint effort to separate man frommachine.

The plan should include but not be limited to the locations of:

Eating areas Driveways Concrete washout areas

Site roads Toilet locations Sprinkler valves

Catering truck access and egress

Muster points Eyewash station(s)

Walk paths for workers Fences and gates Hand wash station(s)

Loading zones Delivery routes Spill kits

Trailer locations Laydown/storage areas Fire hydrants

Signage Parking areas Dumpster location

First aid kit/stations

Site logistics plans should be assembled in an electronic version that is clearly laid out and easilyunderstood.

The project plan will be a “living document” and must be updated and modified as the projectprogresses or changes.

The plan must be reviewed with all workers on site at the safety orientation.

Contractors that operate equipment on a Pogue Construction Co., LP project must be prepared toprovide flaggers for their equipment when working in the proximity of other workers.

Emergency Action/Evacuation Plan

Emergency Action Phone Numbers & Procedures will be posted at phones and other appropriate locations in all trailers and office space. In the event of an emergency, call 911 and indicate that the emergency is at (location).

An Emergency Site Plan with access gate numbers, building names, flammable storage areas evacuation routes, muster points, etc. indicted will be posted at strategic locations and the Plan will be updated as necessary. Copies will be maintained on site by Pogue.

The Pogue Crisis Management Plan must be kept on site with emergency contact information kept up to date. The Plan should be immediately implemented in the event of a crisis situation.

Fire Prevention & Protection Plan

Pogue will provide and maintain general duty fire extinguishers at designated locations throughout the Project. Subcontractors are required to provide their own fire extinguisher protection for hot work and work involving flammable liquids/gasses. Hot work permits must be completed prior to commencing a hot work activity, which may include, but is not limited to cutting, burning, welding, and braising.

In addition to OSHA, and other applicable regulatory restrictions on quantities of flammable liquids and gasses, combustible debris from trade activities will not be allowed to accumulate and become a fire hazard. Combustible waste materials should be removed from buildings daily, or as soon as possible.

Dumpsters should be kept 20' or more from buildings.

Hazard Communication (HazCom) Plan

All subcontractors shall have a site specific HazCom Program, chemical inventory list and corresponding Safety Data Sheets (SDS). The subcontractors complete HazCom Plan shall be accessible to all Project employees.

Page 10: Pogue Construction Co., LP

9

A copy of this plan must be submitted to Pogue for verification.

Signs will be posted notifying all employees on the project of the location and accessibility of the SDS. One or more computers should be set up to rapidly access the SIRI SDS index or similar Internet site.

Demolition Plan

Prior to the start of demolition activities, the responsible subcontractor(s) must prepare and submit a demolition plan including the JHAs for each phase of the demolition process. Subcontractor(s) are responsible for obtaining all required permitting for demolition activities from the JHA prior to commencing work.

Respiratory Protection Plan

An assessment of work areas will be conducted as appropriate to determine what if any respiratory protection is necessary to prevent harm to employees from potential overexposures to hazardous levels of dust, fumes, mists, vapors or gasses. Each contractor is responsible for conducting assessments and/or sampling for respiratory hazards associated with their scope of work. A written Respiratory Protection Plan must be submitted and authorized for use by the Pogue Superintendent prior to commencing activities requiring respiratory protection.

Confined Space Plan

No one will enter a Confined Space on the Project without advance notification given to the Pogue Superintendent and Safety Director and then only as authorized by a qualified Entry Supervisor. A written Confined Space Entry Plan and the JHA must be submitted to Pogue and accepted by the Superintendent and Safety Director prior to entry. (A confined space is a space with limited egress, not designed for continuous human occupancy and has or could reasonably be expected to have physical hazards and/or a hazardous atmosphere.)

Steel Erection Safety Plan

The Steel Erector must submit a Steel Erection Safety Plan to Pogue as required and detailed in the "Steel Erection Safety -- Attachment to Contract"

Severe Weather Action and Inclement Weather Plans

In the event of a predicted severe storm warning, or inclement weather the appropriate Plan(s) will be implemented.

Excavation/Trenching and Shoring Plan

The maximum depth where no protective system is required for employees in an excavation is four feet (4’) versus the five feet (5’) maximum depth that may be allowed by Federal OSHA / other Standards.

An Excavation Plan including slope angle profile(s) i.e. cross-sections must be submitted and acceptable to the Pogue Project Superintendent prior to starting excavations over four feet (4’) in depth.

Substance Abuse Plan

This is a DRUG-FREE WORKPLACE. The unlawful manufacture, distribution, dispensing, possession or use of an illegal intoxicating substance is prohibited on this Project. Employees are subject to Pre- employment, Reasonable Cause, and Post-Incident Drug and/or Alcohol screens/tests. Failing to take or to produce a negative result for a post-accident/incident drug/alcohol test may result in disciplinary action up to and including termination, and may reduce or eliminate Workers' Compensation and/or Unemployment Compensation benefits.

*All Pogue Construction Project employees will be subject to the requirements the Drug/Alcohol TestingProgram which includes: * Except where prohibited by Union Contract

Pre-Employment -- Drug Testing

Post-Accident / Incident -- Drug Testing

Reasonable Cause -- Drug/Alcohol Testing

Blanket – Drug Testing

Page 11: Pogue Construction Co., LP

10

The designated Project personnel will ensure Drug/Alcohol Testing is conducted in accordance with the Pogue Corporate Drugs, Alcohol and Other Prohibited Items Program and the Pogue Drug/Alcohol Testing Procedures.

Subcontractors and others performing work on Company Property shall have a Substance Abuse (Drug and Alcohol) Program for the project that is substantially similar to Pogue’s Program. Subcontractors will be responsible for the cost of testing all of its personnel performing work under all Company subcontracts.

All questions regarding Drug/Alcohol Testing will be directed to the Human Resources Department and/or the Safety Director.

General Safety / Health – CFR 1926 Subpart C

Housekeeping will be made an absolute priority for all subcontractors on all Pogue Construction projects. A project that is unorganized, dirty, or is covered with trash and debris does not reflect professionalism and is indicative of an unsafe work environment.

Pogue shall ensure that the Subcontractors “effectively” clean the Project site continuously throughout each workday. "Effective clean-up" shall adequately address all of the following housekeeping issues:

1) All construction waste, trash, and debris shall be placed in designated receptacles. Glass bottlesshall not be permitted on the Project site.

2) Stack (or restack) all whole and scrap materials in locations that shall not obstruct a clearpathway nor create a risk for toppling onto a person passing through the area.

3) Place all hoses, cords, cables and wires in locations that prevent them from being damaged byequipment, sharp edges or pinch points and from creating tripping hazards.

4) Secure and effectively cover all materials on roofs or elevated levels that may be displaced bywind.

5) Restore all signs, barricades, fire extinguishers, guardrails, gates, etc. to proper locations andsound condition.

6) Properly store and secure all flammable and combustible liquids and gases.

7) Collect and place all cut-off or waste pieces of rolling stock, as they are created, into waste orscrap containers.

8) All puncture and impalement exposures shall be covered or eliminated as soon as they arecreated.

9) Pogue reserves the right to stop the work of a subcontractor to clean up trash and debris theymay have created.

10) Pogue reserves the right to “back charge” cleanup costs to subcontractors that refuse to complywith proper housekeeping.

11) Each subcontractor should provide its employees an adequate supply of fresh drinking water anddisposable cups. Used paper cups must be thrown into a trash receptacle. Water coolers must beemptied and properly sanitized each day before use. Cooler lids shall be taped in place and datedso workers will know the water is fresh.

12) Each subcontractor should supply its workers with an updated and properly stocked first aid kit.

13) Each subcontractor should have a clinic established for treatment of its employees in case of aninjury where medical treatment is needed. In the event of a major injury where an ambulance isneeded, the emergency crew will determine which hospital the injured party will go to.

14) Refer to the site specific emergency action plan for detailed information.

Housekeeping - Cleanup must be performed daily. Subcontractor’s failing to provide effective Safety and/or Cleanup Programs will have their requisitions adjusted accordingly.

1) Glass containers are not permitted on site.

2) Containers must be provided and used with water kegs for the disposal of drinking cups.

3) Protruding nails must be removed as the work proceeds and before disposal.

4) Off cuts of welded wire mesh must be tied into the pour or placed in a trash container as they are

Page 12: Pogue Construction Co., LP

11

cut.

5) Banding iron must be flattened and/or placed in a proper trash container as the bands are broken.

6) Off cuts of round stock such as all thread rod and conduit must be contained as they are cut.

Sanitation

Portable toilets and/or flush toilets meeting or exceeding the quantity specified in the OSHA Standards and/or as indicated by the vendor will be stationed and maintained in sanitary condition and in reasonable proximity to work areas.

Potable water shall comply with city and community health requirements.

Non-Potable Water sources shall be labeled “Non-Potable Water – Do Not Drink”.

One or more hand washing stations with soap will be available to all project employees in close proximity to toilet facilities.

Hazardous Communication (HAZCOM) - CFR 1926.59 Subpart D

All subcontractors must submit a complete copy of their written HAZCOM Program to the Pogue superintendent. The HazCom plan shall include the Chemical Inventory List and copies of all SDS for chemicals that are on site.

1) Major deliveries of flammable, combustible or toxic chemicals must be coordinated with Poguesite management. Subcontractors will be responsible for SPCC, Tier II and EPA compliance forHazardous Materials that they bring to Pogue projects.

2) Refer the Pogue HAZCOM Program for further guidance.

A Hazard Communication area will be established at the Pogue Construction Project that is accessible to all Project employees. There will be Project Specific Chemical Binder(s) with site specific Chemical Inventory Lists and SDS for all subcontractors on site.

Signs will be posted notifying all employees on the Project of the location and accessibility of the SDS.

Personal Protective Equipment [PPE] - CFR 1926 Subpart E

All subcontractors are required to provide their workers with proper PPE in which to perform their work safely. They are also required to train their employees in the proper use and maintenance of the PPE provided. PPE that is required by a contractor will be provided by the contractor.

Employees must be trained in the function and proper use of each piece of personal protective equipment prior to actual use. Training must also include proper inspection and maintenance procedures.

Proper Work Dress

Long pants, shirts with sleeves and proper work boots must be worn at all times.

Shirts shall not have noticeable holes and shall be free of profane, inflammatory, sexually explicit or discriminatory messages. Sleeve length shall cover the ball of the shoulder and shirt length shall reach waist of pants.

Pants shall be full length. Holes must not be large enough to catch on snag points or offer measurable amounts of exposed skin.

Hard Hats

Hard hats must be worn at all times while on site. Hard Hats must be rated ANSI Type G for general hazards or Type E for electrical hazards. Hard Hats must be worn bill forward except for Field Engineers looking though survey instruments, iron workers conducting steel erection operations and welders while welding.

Welding Shields

Welding shields must be worn with a hard hat.

Eye Protection

Eye protection is required for all employees at all times. Specific protection will be necessary for high eye injury potential activities including, but not limited to: chipping, grinding, welding, cutting and drilling.

Page 13: Pogue Construction Co., LP

12

Face Protection

Face shields shall be worn in addition to safety glasses when grinding, chipping, jack hammering, drilling overhead, power sawing or when conducting other tasks that involve flying particulate and debris hazards. Face shields shall also be worn in addition to safety glasses or chemical goggles for chemical splash hazards.

Foot Protection

Sturdy work boots are required except that Safety Boots are required for high foot impact hazard activities and full Foot Covers (“moon boots”) must be used with jumping jack compactors and jackhammers.

Hand Protection

All workers are required to wear gloves when working with their hands. Glove selection shall be based on the tasks to be performed and the hazards associated with those tasks.

Arm Protection

All workers are required to wear cut resistant arm protection when handling sharp items and also when working above the ceiling grid. Arm protection shall be based on the tasks to be performed and the hazards associated with those tasks.

Hearing Protection

Hearing protection is to be worn as necessary for noisy construction activities. An assessment of work areas will be conducted as appropriate to determine what if any personal hearing protection is necessary to prevent harm to employees from potential overexposures to hazardous levels of noise. Each contractor is responsible for conducting assessments and/or sampling for noise hazards associated with their scope of work.

Respiratory Protection

An assessment of work areas will be conducted as appropriate to determine what if any respiratory protection is necessary to prevent harm to employees from potential overexposures to hazardous levels of dust, fumes, mists, vapors or gasses. Each contractor is responsible for conducting assessments and/or sampling for respiratory hazards associated with their scope of work. A written Respiratory Protection Plan must be submitted and authorized prior to activities requiring respiratory protection.

Fall Protection

Personal Fall Arrest Systems must be designed by a qualified and competent person. Fall protection is required for all employees exposed to a fall hazard of 6' or more above a walking or working surface on this project. Where conventional fall protection is deemed infeasible or to create a greater hazard, an alternative fall protection plan may be permitted if it is submitted in writing and authorized by the Pogue Safety Director.

All subcontractors shall submit a fall protection plan for the following activities:

1. Roofing Operations

2. Leading Edge Work

3. Scaffold Assembly/Disassembly

4. Work off ladders above 6 feet in height

5. Steel Erection

6. Elevator Installation

7. Other Hazardous Activities as deemed by Pogue

General Personal Protective Equipment Requirements:

1) Employees are required to wear a shirt with at least 4” of sleeves. Tank tops or sleeveless shirtswill not be allowed.

2) PPE, including hard hats, safety glasses, and Class II Hi-Viz safety vests or Class II Hi-Viz Shirtare to be worn at all times. Any exceptions to this rule will be decided by the Pogue SafetyDirector and Pogue Construction site management. Hardhats must be a “cap” or “full brim” style,“cowboy type” hardhats will not be allowed.

Page 14: Pogue Construction Co., LP

13

3) Prescription glasses are not acceptable as safety glasses unless they have an ANSI Z-87 ratingwith side shields attached.

4) Employees are required to wear proper footwear. Leather hard sole boots are required. Tennisshoes or other soft sole shoes are not allowed. Any exceptions to this rule will be decided by thePogue Safety Director and Pogue Construction management. Safety toe boots may be requiredon some projects as a customer requirement.

5) Face shields and safety glasses are required when operating a chop saw (“quickie saw”), anglegrinders, powder actuated tools and drilling overhead.

6) All workers are required to wear gloves when working with their hands. Glove selection shall bebased on the tasks to be performed and the hazards associated with those tasks.

7) Contractors that provide their employees with respirators as part of their required PPE must alsoprovide the required medical exams, fit testing, maintenance and user training. The burden ofrespirator use and compliance is solely the responsibility of the contractor that is using them.

8) Employees must be provided with hearing protection when exposed to excessive noise levels asdescribed in CFR 1926.52, Table D-2.

9) Chain saw operators are required to wear hardhats, safety glasses, face shields, hearingprotection, chaps and gloves as a minimum.

Fire Protection and Prevention - CFR 1926 Subpart F

Subcontractors should help to eliminate fire hazards by practicing proper housekeeping and storage of flammable/combustible products.

1) A fire watch shall be provided when facility fire protection or alarm systems are out of service andthe affected areas are unattended.

2) Fire watchers shall be trained in the use of fire extinguishers, shall keep other people fromentering exposure areas, and shall not be assigned other duties until the rekindling possibly isover.

3) Fire watchers shall be posted at every operation that produces sparks, flames or sufficient heat tocreate an ignition or to fall onto another person.

4) The fire watch shall be provided during, and for a minimum of 30 minutes after, welding, cutting,brazing, grinding or any work with open flame in areas where a potential exists that sparks, slag, orhot material coming in contact with flammable or combustible substances.

5) When sparks, slag, or fire may fall to a different level, a separate watcher shall monitor each leveldirectly below the work (including exterior locations).

6) All work that creates a spark is considered “hot” work and a Hot Work Permit will be issued to thesubcontractor prior to the start of work being conducted. The Hot Work Permit shall be issued foractivities conducted, kept at the work area, and shall cover a one-shift period only.

7) Subcontractors engaged in welding, cutting or grinding operations must have a fire extinguisher inthe area in which they are working. This operation in an unenclosed area or operational buildingalso requires a “fire watch” to insure that fires will not be created.

8) Employees should all be trained in the use of fire extinguishers and be familiar with the “sitespecific emergency action plans”.

9) Fire extinguishers must not be tampered with or removed from their designated locations.

10) Smoking will not be permitted

11) The project shall have a site specific Emergency Action Plan assembled, which shall include anemergency notification system for alerting workers of emergency situations.

Pogue Construction will provide and maintain general duty fire extinguishers. Subcontractors are required to provide their own fire extinguisher protection for hot work and work involving flammable liquids/gasses.

In addition to OSHA and other applicable regulatory restrictions on quantities of flammable liquids and gasses, combustible debris from trade activities will not be allowed to accumulate and become a fire hazard. Combustible waste materials should be removed from buildings as soon as possible.

Page 15: Pogue Construction Co., LP

14

Dumpsters should be kept 20' or more from buildings whenever possible, except when located beneath a trash chute. Local Fire Department personnel should be asked to visit the site as soon as it is appropriate to acquaint them with the Project and any special hazard considerations.

Signs, Signals and Barricades – CFR 1926 Subpart G

Subcontractor employees are required to read, understand, and abide by all warning signs that are posted on site. Subcontractors are responsible to communicate safety to all their employees regardless of language barriers.

Barricades shall be used in order to alert employees to potential hazards and indicate if authorization, protective measures, or protective equipment is required.

1) Barricades shall be properly erected on all 4 sides if applicable to warn of a potential hazardouscondition. Employees shall be trained to understand and respect various types of barricades.

2) Protective barricades shall be used to provide personnel with physical protection from the hazard,in addition to providing warning of the hazard. Hazards requiring physical protective barricadesare trenches and excavations, openings in grating or platforms, or any other exposure whereworkers may fall to a lower level.

3) Protective barricades must be capable of supporting 200 pounds of force in all directions.Barricade tape (Danger or Caution) shall not be used to protect workers from falling to a lowerlevel, open holes, trenches or floor openings.

4) Barricades must be complete and the hazard area shall be entirely isolated. A permanentstructure that prevents entry into the hazard area may be used as part of the barricade. Thebarricaded area shall be of sufficient size to afford adequate protection.

5) A sign/tag shall be used to provide communication to personnel outside the barricaded area of theidentified hazards, company name, person who is responsible for the barricade, the current dateand their telephone number.

6) All barricades shall be 39 inches to 42 inches high, neat, uniform, level and shall be a minimum of6 feet back from the edge of excavations, holes, platforms, and roofs. If barricades are tied tovertical supports they shall be kept secure to prevent collapsing and hanging onto the ground.

7) Barricades shall not block emergency equipment, such as fire extinguishers, safety showers,power panels, etc.

8) Red flagging tape means “Danger - Do Not Cross.” Yellow flagging tape means “Caution.”

9) All open excavations shall be barricaded using orange barrier fence at least 6 feet from theexcavation edge.

10) When personnel are exposed to a fall of 6 feet or greater, then the barricade shall be a minimumof 6 feet away from the leading edge or the vertical drop.

11) Removal or relocation of barricades or warning signs should be approved by the contractor thatinstalled it.

12) Plastic red danger tape or plastic yellow caution tape must not be used as a warning line forcontrolled access zones (CAZ). Refer to CFR 1926.502(f) for guidance.

13) Employees on a Pogue Construction project are required to use designated walkways, buildingentrances, designated parking areas, drive only on designated site roadways and abide by allwarning and directive signage.

14) City streets and thoroughfares cannot be closed without a traffic control plan that is issued fromthe city, county or state in which it is to be used.

Material Handling and Storage – CFR 1926 Subpart H

Subcontractors are required to keep their tools, materials, and equipment organized in a safe, professional, and efficient manner.

1) Subcontractors should use dunnage, pallets, racks or other means to keep materials off of thefloor. This practice will also provide means to keep it dry and allow movement the materials with apallet jack or a fork lift.

Page 16: Pogue Construction Co., LP

15

2) No material should be stored within six (6) feet of a floor opening or ten (10) feet of the perimeterof the building. Subcontractors are responsible for securing their own tools, materials andequipment.

3) Subcontractors are responsible for keeping their materials, equipment, and debris secure on highrise projects to prevent it blowing off the structure in high wind conditions.

4) Major material or equipment deliveries should always be coordinated with Pogue Constructionsite management.

5) Subcontractors will be expected to keep their storage trailers or “conex containers” in a neat andsafe manner. Storage [semi type] trailers must have proper access provided as required in CFR1926.1052(c) (1), employees are not allowed to climb in and out of semi-trailers.

6) All storage areas must have a fire extinguisher in place.

7) Flammables and combustibles must be stored as per the OSHA standards and manufacturers’requirements.

8) Forklift operators are required to have an operator’s training card on their person for the machinethey are operating, and they will also be required to follow all the manufacturer’s requirements foroperation.

9) “Free hoisting” with a forklift is prohibited; a hoisting attachment is required when using slings orchokers to hoist loads suspended from the forks.

10) Contractors that use forklifts must be prepared to provide a flagger when driving or maneuveringamong other workers or working in congested areas.

Tools, Hand and Power – Subpart I

The manufacturer’s rules and guidelines must be followed for safe operations of tools.

1) No safety device should ever be removed from any tool, such as a guard or a T-handle on a handheld grinder.

2) Grinding wheels shall be the proper size and rated for the same RPM’s as the grinder.

3) Eye protection must be worn when operating any power tool. Safety glasses are minimalprotection; some tools or operations may require goggles and / or face shields. Refer to themanufactures requirements for proper eye protection.

4) Operators of powder actuated tools shall have in their possession an “operator's card” or othersimilar documentation of training for that particular tool being used. Training must be updated asrequired.

5) Safety glasses, a faceshield and hearing protection are required for using a powder actuated,pneumatic and gas cylinder powered tools.

6) Spent powder actuated tool loads must not be thrown on the floor at any time and shall also bedisposed of in accordance with manufacturer’s guidelines.

7) The use of and hazards associated with hand and power tool use must be included in the JHA.

8) Workers shall wear tool lanyards to eliminate the possibility of a dropped hand tool falling to alower level.

9) All electric power tools must be properly grounded or double insulated.

10) All hand and power tools must be inspected each day before use.

11) “Caution Laser in use” signage must be provided in areas where lasers are in use to warn othersof the hazard.

Welding and Cutting – CFR 1926 Subpart J

Subcontractors performing cutting or welding are responsible for controlling the fire and electrical hazards they create.

1) All work that creates a spark or flame is considered “hot” work and a Hot Work Permit will beissued to the subcontractor prior to the start of work being conducted. The Hot Work Permit shall

Page 17: Pogue Construction Co., LP

16

be issued for the activities conducted, kept at the work area and shall cover a one-shift period only.

2) A fire watch shall be implemented and in place for at least thirty (30) minutes after the hot workhas concluded. A fire extinguisher is required during welding or cutting operations.

3) When welding operations can create arcs that could affect other workers, the subcontractorperforming the welding has the duty to protect the other workers in the area from this hazard.

4) Compressed gas cylinders must be stored in the upright position, handled properly, and besecured into position. Flash arrestors or back flow preventers must be used on alloxygen/acetylene torches.

5) Employees must not work under cutting or welding operations. It is the duty or the welding orcutting crew to coordinate this operation with the other trades on site.

6) Welding leads shall be maintained and free of exposed conductors, repairs [if needed] shallcomply with CFR 1926 directives.

7) No repairs will be permitted on the electrode lead.

8) Anti-flashback devices are required on the fuel side of all gas and oxygen cutting torches. Cutting,welding and other open flame work (hot work) require a hot work permit or be addressed inapplicable JHA.

9) Welding rod heater boxes for welding electrodes shall have a manufacturer's label that certifiesthe purpose of the unit. Job-built heaters boxes shall be prohibited.

10) The unused stubs of welding electrodes (“rod butts”) shall be collected and placed in properdisposal containers (i.e. metal bucket with sand or water) as soon as each one is expended.Whenever operation is idle, the electrode shall be removed from stinger.

Electrical - CFR 1926 Subpart K

Electrical work must be performed by electricians trained for the classification of work being performed. When the subcontractor’s work involves electrical work, its safety program must include training, required PPE, methods of testing, and emergency procedures specifically addressing electrical hazards.

Work will not be performed on or near energized electrical systems unless they are secured under a site specific, comprehensive lockout/tagout procedure approved by Pogue Construction. To the extent the lockout/tagout involves electrical systems in an operating facility, the process must be coordinated with Pogue site superintendent and all Owner facilities and maintenance personnel with access to the locked out circuit each day prior to commencing work. “Energized Electrical Work” will not be permitted unless a detailed JHA and Method of Procedure (MOP) is assembled by the subcontractor competent person trained in this work and approved by the Pogue Safety Director prior to starting the work.

1) Ground Fault Circuit Interruption (GFCI) shall be the primary protection from exposure toelectrical current for all workers on the Project. Only exit lighting and medium-high (greater than240) voltage service will not be GFCI protected.

2) GFCI protection is required on all 15 and 20 amp, 120 volt receptacles. When using “housepower”, welding machines or generators for 120 volt power, GFCI protection is still required. AGFCI “pigtail” may be used to provide the required protection. GFCI pigtails should be plugged inat the source of power, which will protect the extension cord and all loads down line.

3) All portable electrical generators shall be properly grounded using an earthen grounding roddriven at least six(6) feet in depth.

4) The electrical subcontractor shall conduct an inspection of all GFCI outlets in accordance withtheir policy and shall provide a copy of the inspection to the Pogue Superintendent.

5) All strings of temporary lights shall be fully lamped and guarded regardless of height, and shall becontinuously maintained. Adequate and consistent levels of illumination for the work operations ineach area must be maintained at all times.

6) 16 gauge (or less) or flat extension cords are prohibited. All extension cords must be rated forhard or extra hard usage. All extension cords will be a “three wire type” with the ground prong inplace.

Page 18: Pogue Construction Co., LP

17

7) Extension cords and electric power tools should be inspected daily before each use. Damagedextension cords, tools or equipment must be removed from service immediately. PogueConstruction reserves the right to destroy or confiscate extension cords or tools that are not safefor use.

8) All receptacles and switches shall have trim plates installed before they are energized.

9) Trades (other than trained electricians) must not operate circuit breakers, switch gears, motorcontrol centers, starters, disconnects or any other electrical devices without prior approval fromthe electrical subcontractor’s superintendent.

10) Energized electrical rooms, vaults, closets and panels must be locked to prohibit the entry ofunauthorized personnel.

11) The appropriate Danger signs shall be posted on the doors of all electrical rooms, doors, panelboards, switchgears, etc. to inform workers of electrical hazards.

12) All power distribution panels shall have full covers installed before primary power is brought intothe panel. When energized panels are located in open areas, covers shall be locked exceptwhen an electrician is present.

13) When panels are located inside separate rooms or closets, automatic closers and automaticallylocking hardware shall be installed on doors as soon as equipment is energized, and onlyauthorized persons shall be provided a key. Doors shall not be wedged to stay open.

14) Energized equipment must have the permanent covers in place to protect workers from electricalhazards.

15) Electrical subcontractors will be expected to make the work areas free from electrical hazards.

16) Temporary lighting must be installed at least seven feet above working or walking surfaces. Alllamps must have a guard.

17) Temporary High Intensity Discharge (HID) lights shall be installed and inspected in accordance tothe Pogue Construction HID Lighting Policy/Procedure.

18) All high intensity discharge lamps used in the temporary lighting system shall be the self- extinguishing type.

19) When Romex, tri-plex, quad-plex, SE cables or similar wire sets are used for temporary powerand lighting they must be suspended and protected from physical damage, at no time are theyallowed on the floor. Type SO and equivalent hard usage cords may lie on the floor in limitedareas.

Lockout Tagout (LO/TO)

Subcontractors shall implement their Lockout/Tagout (LO/TO) Program. This program must bespecifically addressed in the Subcontractors Safety Program and implemented in a proceduredeveloped by the Subcontractor and submitted to Pogue for review and approval prior to use.

o Subcontractor and sub-tier workers who are required to work under the protection oflockout/tagout shall be trained.

The Electrical Subcontractor will act as the "Controlling Organization" as defined in the Pogue’sProgram and the Subcontractors implementing LO/TO procedure unless otherwise directed.

o When acting as the Controlling Organization, the Electrical Subcontractor will install theirlockout/tagout based on a graded approach prior to the installation of authorized workerlockout/tagout. The Electrical Subcontractor authorized and qualified workers will installlockout/tagout to control hazardous energy or materials, and verify adequate control ofhazardous energy or materials for personal protection prior to performing service ormaintenance in accordance with the Subcontractors LO/TO procedure.

The Controlling Organization and Subcontractor authorized and qualified worker locks and tagsshall be recorded in the Project's "Lockout/Tagout Log" maintained by Pogue.

Page 19: Pogue Construction Co., LP

18

Scaffolding - CFR 1926 Subpart L

All employees working on scaffolding or lifts must be protected from falls at a height of 2 feet or greater. A Competent Person for each trade that is working on scaffolds must be on site at all times while its workers are on a scaffold.

1) Scaffolds must be inspected daily prior to use by the Competent Person from each trade.Scaffolds must have a tag that indicates it is safe or not safe for use; the tag must be signed anddated by the competent person for that scaffold.

2) All employees that are required to work on scaffolds must be trained.

3) Employees engaged in scaffold erection, disassembly, or modifications must use personal fallprotection.

4) Rolling scaffolds must be assembled and used as per CFR 1926.452(w) along withmanufacturers’ rules and recommendations.

5) Brakes on rolling scaffolds shall be secure at all times, except when the scaffold is being moved.Workers shall not be allowed on the platform when the scaffold is being moved.

6) “Baker” scaffolds must be used as per the manufacturers’ requirements without exception.

7) Fall protection above 2 feet is required on all scaffolds.

8) All other scaffold regulations and rules will be followed per CFR 1926 Subpart L.

9) Personal fall protection is required in boom lifts and articulating boom lifts.

10) Workers are not allowed to stand on the rails of a scissor lift or aerial boom lift. Adding planks ordevices for additional height is also prohibited.

11) Personal fall protection is required when operating a scissor lift.

12) Employees that use aerial boom lifts or scissor lifts must be trained in the safe and properoperation. All manufacturer’s rules and recommendations must be followed.

Fall Protection – CFR 1926 Subpart M

Fall protection is required for any worker exposed to a fall of 6 feet or more with the exception of scaffolds where fall protection is required at 2 feet.

All work that requires personnel to work in a fall arrest situation requires a fall protection plan which shall include a rescue plan and shall be reviewed and accepted by the Pogue Superintendent or Safety Director.

Pogue prohibits the use of positioning devices as the sole means of fall protection when working above six feet. Positioning device means a body belt or body harness system rigged to allow a worker to be supported on an elevated vertical surface, such as a wall, and work with both hands free.

1) When working on a ladder, employees will be required to have fall protection at 6 feet or higher.

2) Personal fall protection must be provided by a full body harness, lanyards and proper anchorpoints. Lanyard types and lengths must be determined be a competent person.

3) Fall protection systems must be designed, installed, and inspected by a qualified person or anengineer.

4) Tie off points must be capable of supporting a 5,000 pound static load per person without failure.

5) All manufacturers fall protection equipment guidelines and recommendations must be followed.

6) Lanyards, snap-hooks, and tie off points must be compatible as per manufacturers design anddirections.

7) Employees that are required to work with fall protection must be trained in the hazards, properuse, and inspection of their equipment.

8) Employees engaged in roofing operations on flat roofs will be allowed to work inside of warningline systems without fall protection provided the systems are 6 feet or more back from the edge ofthe roof. The warning line system must not have any openings around the perimeter unless theopening is for access to the area.

9) Monitors will not take place of personal or conventional fall protection methods under any

Page 20: Pogue Construction Co., LP

19

circumstances.

10) No employee will alter a temporary guardrail, handrail, perimeter cable or floor opening coverwithout specific authority from Pogue site superintendent. Any protective device removed must bereplaced immediately after task is performed. Subcontractors who create a hazard areresponsible for controlling or eliminating it.

11) Ropes must not be used as a horizontal life line unless it has been manufactured for the purpose.

12) Contractors that create fall hazards or any other safety hazard on a Pogue Construction projectare responsible for controlling or eliminating the hazard; this will include sleeve openings or leaveouts in walking or working surfaces.

13) Floor hole/opening covers must be installed and maintained by the Subcontractor creating thehole and/or the end user. The covers must be of adequate strength to support potential loads,secured against displacement and labeled as a hole cover using the designated project specificlabeling system consisting of a red or orange “X”. Supervisors must inform their workers of thismarking method for hole covers. Hole covers greater than one foot (12”) in their least dimension,shall be fastened when it can be reasonably anticipated that the covers will remain in place for anunusually long duration and/or it may be difficult to maintain the labeling.

14) Whenever tools are used at elevation and there is a potential hazard of falling objects, the toolshall be tethered to prevent the falling tool / object. The area below elevated work may bedeemed as a “no work zone” with the proper barricades and signage installed.

15) Contractors may use controlled access zones (CAZ) around the building perimeter for loadingupper levels with tools, material or equipment. The CAZ must first be flagged off or barricaded100% of the perimeter, personal fall protection must be provided for all employees inside of theCAZ and at that time the perimeter fall protection can be removed to allow for loads to come ontothe floor.

16) The removal of perimeter fall protection within a CAZ must not compromise the remainingperimeter protection outside the CAZ. This operation must be approved by the projectsuperintendent or his representative before starting work.

17) Fall Protection is required to be used by workers working on a scaffold that is 2’ or higher.

18) Personal Fall Arrest Systems are required to be used when workers are operating an articulatingaerial boom lift and mobile elevated work platforms (known as MEWP’s or scissor lifts).

19) A Self Retracting Lifeline (retractable lanyard) and full body harness shall be used whenoperating an aerial boom lift.

20) When operating a MEWP’s/Scissor lift workers may not tie-off to an existing structure.

21) All subcontractors shall submit a fall protection plan for the following activities:

a. Roofing Operations

b. Leading Edge Work

c. Scaffold Assembly/Disassembly

d. Work of ladders above 6 feet in height

e. Steel Erection

f. Elevator Installation

g. Other Hazardous Activities as deemed by Pogue Construction Co., LP

Motor Vehicles & Equipment – CFR 1926 Subpart O

1) If seat belts are provided, they must be worn.

2) Employees shall not be transported in the back of a pickup truck, on a flatbed truck or on trailers.

3) Employees are not permitted to ride on any equipment that is intended for one person.

4) Backup alarms on equipment must not be disabled or removed.

5) Project posted speed limits must be complied with.

Page 21: Pogue Construction Co., LP

20

6) Motorized equipment must be operated in a safe and responsible manner. Equipment must havea documented inspection conducted each day before the equipment is put to use. Allmanufacturers’ guidelines must be followed.

7) Operators of equipment or drivers of vehicles on a Pogue Construction project are not permittedto use cell phones or similar devices while the vehicle or equipment is moving.

8) Operators must not exit the seat in their equipment if a load is hoisted or the motor is running.

9) All vehicle accidents must be reported to Pogue Construction Safety Director at the time theyoccur.

10) Privately owned vehicles are prohibited from driving or parking on a Pogue Construction siteexcept in designated areas. All company vehicles must have their company name clearly postedon their vehicles and current auto insurance is required.

11) Heavy Equipment Operators must be Employer Certified (e.g. Forklift Operator Certification) andverification of same must be submitted to Pogue Construction prior operating Heavy Equipmenton site.

12) Pre-Shift Equipment Inspections must be completed and logged using applicable InspectionReport Forms for all Heavy Equipment (including skid steer loaders and forklifts). Inspection Logsmust be made available upon request to any Pogue Construction Representative.

13) Random Verification Checks must be performed by Pogue Construction Project Staff to ensurePre-Shift Operational Inspections & Tests and Reports are completed.

14) Suspension hoisting by Heavy Equipment (other than cranes) is prohibited, except when anattachment point and/or hoisting device designed and engineered for use with the specific pieceof Heavy Equipment is used in conjunction with the applicable load chart. Potentially excessivemovement of suspended loads must be controlled. (e.g. tag lines)

15) Heavy equipment accessory, “Quick-Hitch” attachment devices must be of the Twin-Locking (fail-safe), Fully-Automatic, type. The hitch-type must be verified by a Pogue ConstructionRepresentative. Operators must conduct a visual inspection and operational test to ensure “new”accessories are properly attached.

Excavations – CFR 1926 Subpart P

1) The property owner and Pogue shall determine historical knowledge of existing utilities andadvise the subcontractors of any and all pertinent information. Where applicable, a phone call forutility "locates” shall be completed seventy-two (72) hours in advance.

2) “Potholing” and/or hand digging shall be required within three (3) horizontal feet of “located”centerlines, and in areas where knowledge is lacking.

3) Each employee in an excavation must be protected from cave-ins at a depth of four (4) feet ormore.

4) The “toe” of spoil piles that are less than four feet (4’) in height shall be at least two feet (2’) fromthe edge of any excavation. Spoil piles greater than four feet (4’) in height shall add one foot (1’)of distance from the excavation for every additional foot in height. Spoils shall be managed toprevent airborne dust.

5) A means of egress must be provided at every 25’ of trench distance.

6) Sloping, shoring systems or trench boxes will be used to protect employee(s) from cave- ins inexcavations that are deeper than 4'.

7) Shoring systems and trench boxes must be used as per manufacturer’s recommendations, endclosures are required where trenches and excavations terminate if the soil is not properly slopedor stepped.

8) All trench and excavations should be backfilled at the end of each shift.

9) When a trench or excavation cannot be backfilled in the same day as it is created, a highly visiblebarricade shall be erected at a minimum distance of six feet (6’) from all approachable edges.

10) All portable means of access shall be removed at the end of each workday.

Page 22: Pogue Construction Co., LP

21

11) Earth ramps that are to be used for walking access shall not exceed twenty percent (20%) ingrade slope. Steeper slopes shall be gate controlled for equipment only, and alternate accessshall be added for pedestrian traffic.

12) All subcontractors must have a Trench Safety Plan in place for all excavations or trenches prior tocommencement of work.

13) A Competent Person for excavation work must be on site at all times. The Competent Person willalso be responsible for daily inspections of all excavations.

14) Trenches or excavations in excess of 20-foot deep must be designed by an Engineer.

15) Subcontractors will be responsible for keeping their excavations safe and protecting others fromthe hazards they may create. This protection includes barricades (only orange barrier fence) andsignage.

16) Deep excavations should be considered a confined space with all applicable OSHA requirementsof air monitoring, PPE, and training of personnel entering the space.

17) Subcontractors that are digging on the Pogue Construction project will be fully responsible forlocating and excavating around new and existing utilities. All utilities should be “brought to light”by potholing, hand digging or other non-damaging methods before using heavy equipment in theproximity of utilities.

18) Subcontractors are required to complete an excavation permit for all excavations over one (1)foot in depth. The excavation permit must be signed by the contractor’s competent person, PogueConstruction supervision / safety and kept in the field until turned in at the end of the day.

19) The subcontractor’s competent person is responsible for determining the soil classification andthe protective measures to put into place to protect the entrant’s.

20) The subcontractor’s shall provide Pogue Construction with the manufacturer’s tabulateddata/rating information for all protective systems used to protect their employees.

Concrete and Masonry – CFR 1926 Subpart Q

1) Vertical rebar posing an impalement hazard must be protected from impalement hazards, verticalrebar must also be protected when employees are working above them.

2) Horizontal rebar that poses a scratch hazard must also be protected.

3) Mushroom (round) rebar caps shall not be used to protect workers from impalement and/orscratch hazards.

4) Employees assigned to mixing of dry cement base products must be protected from the inhalationof dusts.

5) Employees pouring, placing, finishing, mixing or patching concrete must be protected from theexposure of concrete products (wet or dry) to the skin.

6) Form materials or lumber must be free of nails that could cause puncture hazards. Nails shouldbe bent over or removed.

7) Pier drilling operations require 100% fall protection for the crew tending the hole on piers that aregreater than 18” in diameter, the use of “hay rings”, barricades or personal fall protection systemswith tie off points are accepted practices.

Steel Erection - Precast Erection – CFR 1926 Subpart R

Erectors are required to submit a site specific steel / precast erection plan before starting the steel erection process. This plan must be reviewed and approved by the Pogue Safety Director and site superintendent prior to starting work.

1) Steel Erectors must use 100% fall protection for all of their activities without exception.

2) Trades other than Ironworkers are not allowed to work under erection activities.

3) The “site specific erection plan” will be expected to lay out the complete safety plan for theerection of the structure(s).

Page 23: Pogue Construction Co., LP

22

4) Multiple picks or “Christmas treeing” of similar structural steel members may be allowed if all thecriteria in CFR 1926 are met.

5) Erectors must inspect their rigging each day before use. Defective rigging or rigging that is notproperly tagged will be removed from use.

6) Erectors will not be permitted to hoist workers with a crane without the approval of PogueConstruction site management. All criteria in CFR 1926.1431 must be met as a minimum.

7) Precast erectors must have an approved “engineered” erection plan for their operations prior tostarting work. The plan shall include (but not limited to) grouting plans, bracing details, weldingprocedures and the sequence of setting the precast sections. Erection plans for precast mustundergo a third party engineer’s review.

8) Erection plans must include a comprehensive fall protection plan detailing the fall protectionmethods for their activities.

9) Engineered plans will be required for rigging and hoisting of precast members.

10) Cranes used for hoisting precast should be large enough to safely hoist all anticipated loads,multiple critical lifts should be avoided.

For Subparts S, T, U, V, W & Y

Refer to OSHA 1926 Regulations.

Ladders and Stairs – CFR 1926 Subpart X

1) Fall protection is required when working on ladders in excess of 6 feet.

2) All employees who use ladders must be trained.

3) Ladders must be inspected each day prior to use. Defective ladders must be removed fromservice.

4) The manufacturer’s recommendations and safety rules must be followed at a minimum, laddersthat do not have the manufacturer’s labels in place should be removed from service.

5) Although personal fall protection is required on ladders when working at or above 6 feet, whenemployees are on ladders and working above or close to perimeter or interior fall hazards, theymust use personal fall protection regardless of standing height on the ladder.

6) Steel stair pans are not to be used for access until they are filled with blocking or concrete and ahandrail/stair rail system is in place.

7) Stairs must be blocked or barricaded until they are safe for use.

8) All job-built ladders must comply with ANSI A14.4-1979 and must be inspected and tagged eachday. Job-built ladders in excess of 20 feet will not be permitted.

9) Elevation changes in walking surfaces greater than 19” will require a ladder, steps or stairs forsafe access.

10) Extension ladders SHALL be set up at a 4 to 1 ratio, extend at least 3 feet above the upperlanding, and tied off at the top to prevent movement.

11) Employees are forbidden to stand on the top step or on the top of any step ladder even when fallprotection is provided.

12) Manufactured portable (step and extension) ladders shall display ANSI heavy-duty rating (Class I-A) and be inspected daily for condition and set up. Legible labels must be maintained on allladders.

13) Trestle ladders are not permitted on Pogue Construction projects.

14) Aluminum ladders are not permitted on Pogue Construction projects.

Confined Spaces in Construction – CFR 1926 Subpart AA

Confined space entry work must follow a documented hazard assessment and safe work planning, rescue process and confined space permit, which must be submitted to Pogue for review and approval prior to entry.

Page 24: Pogue Construction Co., LP

23

Refer to the Pogue Construction Confined Spaces in Construction Program and OSHA CFR 1926 Subpart AA Regulations.

Cranes – CFR 1926 Subpart CC

All cranes must be thoroughly inspected and certified as safe for use by a qualified 3rd party inspection firm at least annually, and evidence of the inspection must be retained on the crane at all times. All crane operators must provide a recent drug test and be certified to operate the specific crane or demonstrate at least 2 years of operation on the same or similar crane under similar conditions.

1) The manufacturers’ operation manuals and load charts must be with the crane at all times; dailydocumented inspections are required on all cranes by a qualified person.

2) Crane procurement and operational pre-planning is required on all Pogue Construction projects,planning must include, but not be limited to:

Weight of loads to be hoisted No fly zones

Public areas within swing radius Other cranes on site

FAA compliance Swing radius

Delivery plans and routing Assembly areas

Soil stabilization Erection Process

Disassembly processes CCO operators

Designated flaggers Inspection processes

Critical lifts Rigging operations

Overhead power lines Communications plans

Underground utilities Tower crane foundations

3) Cranes that are on the Pogue Construction project must have an “independent third party”inspection completed at the time the crane is brought onto the project. The annual inspection ona crane will not satisfy this requirement regardless of the date that it occurred.

4) An “Assembly / Disassembly Director” must be appointed before a crane can be assembled ordisassembled, this A/D Director must be qualified and competent to supervise this task and directhis crew as per the manufacturer’s guidelines or guidelines he has created for a safe process.

5) All crane operators must possess a certification to operate the type of crane they are using, CCOor equivalent is required. Operators should have at least two years of experience with the cranethey are to operate.

6) The crane operator is ultimately responsible for safe operation of his crane and he has the right tostop work if he feels the hoist or maneuver could be unsafe.

7) Before crane operations begin, flagmen must be designated. Flagmen must be kept to aminimum for each crane on site, two flagmen per crane is the recommended practice.

8) The ground conditions must be properly graded and compacted before a mobile crane can beused to assure that it will support the crane, rigging and all intended loads without failure.

9) All safety devices and operational aids on a crane must be functional and never removed oraltered.

10) The swing radius of the crane’s counterweights must be barricaded or flagged completely.

11) When outriggers are used on cranes, they shall be fully extended. Float pads shall be landedonto leveled and properly designed and sized slabs or cribbing. Where steel plate is used forcribbing, welded or bolted cleats shall be attached to upper surface to prevent float pads frommoving horizontally.

12) All cranes must be equipped with a 5BC rated fire extinguisher.

13) Cranes must not work in the proximity of power lines until the line voltage has been determined;at that point refer to CFR 1926.1407-1411 for guidance.

Page 25: Pogue Construction Co., LP

24

14) A lift plan shall be submitted to Pogue supervision for review.

15) “Safety factors” of any kind will not be considered when calculating crane loads, the load chartmust be considered 0%-100% of the crane capacity. Load charts and computer programs mustmatch the configuration of the crane assembly (boom length, jib lengths, counter weights added,etc.).

16) Critical Lifts shall include, but not be limited to: (1) Tandem Lifts, (2) Lifts greater than seventy- five (75%) percent of Load Chart, (3) Crane Suspended Personnel Hoists, (4) Non-ConventionalOutrigger placements and (5) “Blind” picks and/or placements. All of these events shall requiresubmittal of custom designed plans by qualified persons.

• Other activities that should be considered for classification by Pogue as a critical lift wouldinclude:

• Lifts made where the load or crane boom passes over or adjacent to active oroccupied offices, warehouses, process facilities, pipelines, etc., or within 20 feet ofpower lines

• Lifts using more than 200 feet of boom

• Use in confined or tight work areas

• Lifts for highly valuable or hazardous materials

17) Tag lines will be used on all crane loads.

18) Only the designated rigger and/or signal persons shall issue lift instructions to the operator. Theonly exception shall be an emergency stop signal, which may be delivered by anyone on theProject who knows how to alert the operator.

19) Anyone that is performing rigging or flagging with a crane must be trained regardless of trade.

20) Hoisting operations must not be made over persons not directly involved with the hoist.

21) Rigging must be inspected by a competent person each day before use. Defected rigging orrigging that is not properly tagged must be removed from service.

22) Wire rope slings, alloy chain slings, synthetic web slings, round slings, etc. must all have aManufacturers’ tag permanently affixed that indicates the safe working loads and other pertinentinformation. Tags must be legible and must not be altered or modified.

23) Sling inspection must be conducted as per ANSI / ASME B30.9.

24) Tower cranes must be erected; load tested, calibrated and operated as per the manufacturer’srequirements.

25) When one or more tower cranes are erected in the same area and have the ability to makecontact anti-collision devices shall be installed to help prevent accidental contact.

26) Tower cranes that have the ability to fly over public areas shall be fitting with zone control devicesto assure the public is safe from the hoisting operations.

27) Cranes that have been shock loaded or damaged must be taken out of service until repairs andre-certifications have been completed.

28) Cranes may not be erected on site unless communications have been made with the FAA toassure that the crane will not interfere with air traffic.

29) Clear communications must be established and maintained between flagmen and craneoperators and operator to operator, the use of radios with a designated channels for each craneis a recommended practice.

30) Cranes must have a properly functioning “anti-two-block” device for each load hoisting line. Thisrequirement may be waived by a Pogue Construction Representative for certain craneoperations, e.g. pile driving leads.

31) Load lines (hoist lines) may only be “tied-back” to the crane using a method acceptable to aPogue Construction Representative, which must include a “back-up safety system.”

32) Palletized loads may only be suspension-hoisted overhead using one of the following methods:

Page 26: Pogue Construction Co., LP

25

a. Hoisting Forks of adequate capacity with the load stable and secured to the pallet.

b. Equipment Lifting Eyes with the pallet removed.

c. Properly rigged Hoisting Container.

d. An alternative method authorized by a Pogue Construction Representative.

Hoists – Material/Personnel

Hoists must be inspected and tested following erection or “jumping,” and every 3 months thereafter by a 3rd party Crane Inspector acceptable to Pogue Construction. A detailed Inspection Report must be completed by the Inspector that ultimately Certifies that the Hoist (“Device”) “Meets” or “Passed” the examination / inspection. i.e. no uncorrected deficiencies. A copy of the report must be submitted to Pogue Construction for review and consideration.

Pogue Construction will collect a hard copy of hoist operator qualification documentation, file and log into a tracking database.

Respiratory Protection

1. Subcontractors shall select, use and maintain respiratory protection devices in accordance withthe requirements of OSHA 29 CFR 1910.134 and ANSI Standard Z88.2 (or most currentOSHA/ANSI respiratory protection standard).

2. Respiratory protection shall be provided to employees when feasible engineering controls andwork practices cannot be implemented. The Subcontractor shall enforce the proper use ofrespirators and assure that their employees are trained and qualified to use the specificequipment provided.

3. The Subcontractor shall determine the respiratory protection needs and requirements bypreliminary or job hazards analysis and prescribe needs and requirements in their Project Safetyand Health Plan, work procedure, or work permit.

4. The Subcontractor shall justify the level of respiratory protection selected by the hazardsidentified and shall consider factors other than just protection, such as tripping hazards, mobility,heat stress, vision and other ergonomic factors.

5. The Subcontractor shall ensure employees are instructed in the use and limitations of therespiratory protective equipment used. Training and fit testing shall comply with requirements inthe most current OSHA/ANSI standards.

6. The Subcontractor shall ensure their employees and lower-tier Subcontractors are medicallyqualified to use the respirator selected.

7. All personnel who go into the exclusion zone shall wear the required level of respiratoryprotection and comply with training, medical and fit testing requirements as specified in thissection.

8. Subcontractors shall be responsible for labor costs associated with the training and fit test forrespiratory protection required for their employees.

Permit to Work Systems

Permits-to-work provide a formal safety control system aimed at prevention of accidents, damage to property and damage to products,

It is probable that it would be necessary to obtain permits-to-work during the following operations:

Asbestos Abatement

Confined Spaces

Core Drilling

Demolition

Electrical Hot Work

Electrical Shutdown and Start-up

Page 27: Pogue Construction Co., LP

26

Elevator Shaft Work

Excavations and Trenching

Gas Line Services

High and Low Voltage Electrical Works

Hot Works – Welding, cutting, brazing, operations generating a spark

Impairment of Fire Protection Systems

Restricted / Hazardous Areas

Testing Pressure Systems

Using Toxic/Hazardous Chemicals

Work on Lifts

General Public Protection

Pogue Construction will provide perimeter fencing and/or other appropriate measures as necessary for separating and protection the general public from construction activities. The perimeter sidewalks, entrances and roadways will be included in the Project Safety Surveys to address activities and/or conditions that could be harmful to the general public or the environment.

"Attractive nuisance" items such as tower cranes, tall ladders, fire escapes, large excavations, etc. shall require additional and separate security measures.

Pogue and all subcontractors shall challenge any visitor or member of the public who attempts to enter a construction area without an authorized escort.

All visitors to the project must abide by all project safety requirements. Visitors shall be provided with a basic safety orientation and sign the Visitor’s log.

An adequate number of properly trained and equipped flaggers must be provided to ensure public safetywhere construction activities may endanger pedestrian or vehicle traffic.

Site Specific Safety Considerations

Subcontractor project management/supervision must submit a site specific Safety program and JHA for each phase of their work to the Pogue Construction and attend a Pre-Construction Meeting that includes Project Safety requirements and hazard prevention planning.

Subcontractor employees must attend a New Employee Project Orientation that includes Basic Safety & Health Training and thereafter a Weekly “Tool Box Talk” Safety Meeting.

On-site Safety inspections will be performed by each subcontractor and Pogue Construction Management. Safety violations will be addressed immediately and if warranted follow the disciplinary procedures.

Moisture Damage Prevention

Materials prone to fungal growth (mold) after becoming moist, such as drywall, insulation and lined ductwork, must be stored off the floor/ground on dunnage and covered.

Materials prone to fungal growth must be checked following a potential moisture exposure event, and then thoroughly dried or removed immediately (process completed within 72 hours) if moist conditions are discovered.

Materials with visible fungal growth (mold/mildew) must not be removed or otherwise handled without the authorization and oversight of the Safety Director and compliance with the Mold Prevention Plan (MPP). Consult the Safety Director for details.

Power Actuated Fastening Tools

The firing mechanism shall be designed so that the tool cannot fire during loading or preparation to fire or if the tool is dropped while loaded. Firing the Power Actuated Fastening Tool shall be dependent upon at least two separate and distinct operations of the operator. Each Power Actuated Fastening Tool is required to have a manufacturer’s redundant safety system (two safeties).

Page 28: Pogue Construction Co., LP

27

Overhead Protection

At no time will one trade work over/under another unless the activities are planned as such, and precautions as specified in a Job Hazard Analysis are implemented to prevent injury from falling objects.

Pogue Construction will provide designated overhead protected entrances/exits.

Overhead protection will be provided using designated overhead protected entrances/exits and a minimum of one of the following methods or an equivalent.

1. Orange barrier fencing will be installed on all access levels below open sided exterior and atriumfloors to restrict access to the protected entrances/exits. Additionally, debris and materials will besecured or kept a safe distance from the edge. Pogue will paint a line ten feet (10’) inboard fromopen sided floors edges where feasible to delineate “Debris and Material Storage Free Zones” forthe purpose of overhead protection.

2. Toe boards and /or vertical debris netting (secured at the floor) installed and maintained alongopen edges below which employees may walk or work.

Shafts without pits will be covered or have guardrails with toe boards and/or be barricaded at the bottom floor.

All employees are to be made aware as to the markings and methods of overhead protection provisions implemented by Pogue Construction and the Project Subcontractors.

Supervisors shall direct the employees in their charge to comply with the access restriction system and use only the overhead protected access points.

Employees shall not remove or by-pass any of the overhead protection devices unless authorized and directed to do so by their Supervisor or a Pogue Construction Supervisor.

Alternative provisions to ensure overhead protection for others are the responsibility of the Supervisor during activities where the Supervisor's employees have removed or compromised the standard protection provisions. An exclusion zone delineated with self-supporting barricades.

Employees are responsible for notifying their Supervisor of the need to remove overhead protection devices and the proper replacement of the devices. Employees are to notify their Supervisor of defects or deficiencies of protection.

EPA Compliance

1) As contractors are obligated to abide by all laws and regulations for EPA compliance, and PogueConstruction responsibility under any environmental permits and NOI’s for such compliance isshared by all subcontractors.

2) Each subcontractor will be liable for any damage he causes to silt fences, inlet protections,retention ponds, stabilized entrances or any other Best Management Practice (BMP’s) that are inplace. If BMP’s are in the path of work, this should be communicated to the Pogue Constructionsite superintendent for coordination.

3) Subcontractors will be liable for dumping any chemicals, trash or debris on site or in trashreceptacles in violation of Federal, State or municipal environmental laws.

4) Subcontractors are responsible for proper storage of their fuels or bulk chemicals that mayrequire secondary containment, dikes, emergency spill plans, etc.

5) Subcontractors that track mud into streets will be responsible for immediate cleanup.

6) Water cannot be pumped from the work site into streets or storm inlets without prior approvalfrom Pogue Construction superintendent.

7) Spills or contaminations of soil will be the responsibility of those that created it to clean it up andsee to its proper disposal.

Page 29: Pogue Construction Co., LP

28

Note:

This Exhibit is a basic set of safety guidelines and expectations that are intended for use as a subcontract document and reference.

This Exhibit is not an all-inclusive safety program. If additional information or guidance is required refer to CFR 1926 or whichever regulations have presence in the location of the project.

Page 30: Pogue Construction Co., LP

POGUE CONSTRUCTION CONTRACTOR JOB SAFETY PLAN (PC.01.001.F01)

Form must be completed by the Pogue Construction Designated Project Manager and Contractor Party Supervisor(s) prior to the start of the assigned job. Completed forms must be maintained by the Contractor Party Supervisor for the duration of the job scope.

Date: Pogue Construction Designated Project Manager:

Contractor Party: Contractor Supervisor:

Condition of Work Area:

All Equipment Down Equipment Running

Assigned Work Area:

Project Description: ____________________________________________________________________________________

______________________________________________________________________________________________________

Prior To Beginning Work:

1. Confirm Contractor Approved For Work

2. Review Scope of Work (Including Plan Drawings if Required)

3. Walk The Job- List Job Requirements and Note Designated Work Area

4. Estimated Number of Contractor Employees Required _____________

5. Confirm Need and Responsibility for All Contractor Employees to Have Site Specific Training

6. Confirm Need for Contractor Vehicles in Work Area How Many? ____________

7. Review Procedures Specific to Job:

Lockout/Tagout Housekeeping Confined Space Compressed Gas Storage Hot Work Hot Material or Material Piles Fall Protection Hot Equipment and Areas Excavations Dusty Areas/Creating Dusty Conditions Emergencies Overhead Work Mobile Equipment Inspections Barricade Tape of Work Area Smoking Plant Speed Limit Ladders Scaffolding Spill Response/Chemical Storage Waste Disposal Water Safety Other (Specify) _____________________

8. Hazardous Materials Brought to Site (SDS Required)

9. Reporting Procedure for Accidents, Injuries, and Unsafe Conditions

10. Review Pre-Shift Safety & Hazard Analysis Requirements

Permits Required:

Confined Space Permit Excavation Permit Lift Plan

Confined Space Reclassification Hot Work Permit High Voltage Permit

Page 31: Pogue Construction Co., LP

List Contractor Competent Persons Area of Competency Name

Confined Space Excavation/Digging Fall Protection Lock, Tag, Try Scaffolding Workplace Examinations

PRE-JOB HAZARD ASSESSMENT List Potential Hazards List Solutions

Personal Protective Equipment Required:

Hard Hat Face Shield Tyvek Suit

Safety Glasses Dust Mask Goggles (Chemical)

Steel Toe Shoes Cloth/Leather Gloves Goggles (Welding)

Ear Plugs Chemical Gloves Heat Resistant Clothing

Harness Life Jacket/Floatation Devices Respirator

I have reviewed the information on this checklist with the contractor party(s) listed.

______________________________________ ____________________ Pogue Construction Designated Project Manager Date

I acknowledge it is my responsibility to train all of my contract employees on the hazards of their work area and will review this job-specific information with all of my employees and subcontractors. I understand that violations of the safety rules covered may result in a monetary penalty, loss of future work, and/or immediate dismissal from the project.

______________________________________ ____________________ Contractor Party Supervisor Date

Page 32: Pogue Construction Co., LP

POGUE CONSTRUCTION PRE-SHIFT HAZARD ASSESSMENT (PC.01.001.F02)

This form must be completed and posted by the Contractor Party at the job site prior to beginning work on every shift. Completed forms for each shift must be returned to the Pogue Construction Designated Project Manager each normal business day.

Contractor Party: Date:

Time:

Pogue Construction Designated Project Manager:

Contractor Party Supervisor: Number of Contractors: Emergency Contact:

Designated Work Area:

Job Description: ______________________________________________________________________________________________

_____________________________________________________________________________________________________________

Permits and Requirements:

Confined Space Permit Hot Work Permit Excavation Permit

Confined Space Reclassified Lockout Required Workplace Examination

Lift Plan Mobile Equipment Pre-Shift Insp. High Voltage Permit

Job Specific Hazards:

Dust Engulfment Compressed Gas Storage

Contact Burn Hot Material/Piles Lack of Lighting

High Noise Fumes Overhead Work

Fall Protection Heat/Cold Stress Chemical Handling

Atmosphere High Voltage Lifting/Rigging

Manlift/Spotter Body of Water Other- Specify _____________

Personal Protective Equipment Required:

Hard Hat Face Shield Tyvek Suit Safety Glasses

Dust Mask Goggles (Chemical) Cloth Gloves Steel Toe Shoes

Goggles (Welding) Ear Plugs Chemical Gloves Heat Resistant Clothing

Harness Respirator Life Jacket

Work Area Preparation:

Barricades/Signs Posted Lockout Complete Work Area Defined

Ladders Secured Permits Posted Fire Extinguisher (Hot Work)

Page 33: Pogue Construction Co., LP

Aerosol Cans Labels Secondary Containment Storage Tanks (>55 Gallons)

Paint Supplies Chemicals Washing of Equipment Creating Dusty Conditions

PRE-SHIFT HAZARD ASSESSMENT List Potential Hazards List Solutions

I fully understand the job scope, the nature of the hazards involved, the personal protective equipment, the designated work area, and the procedures necessary to work safely on this job assignment. I agree to comply with safety procedures and stay within the designated work area.

Name (Print) ID # Signature

I certify that the above list is all-inclusive of contractor employees assigned to work this job during this shift.

_______________________________________________ ________________________ Contractor Party Representative Date

Environmental Considerations:

Page 34: Pogue Construction Co., LP

POGUE CONSTRUCTION CONFINED SPACE ENTRY PERMIT

DATE: __________________________ TIME: (maximum 1 shift) _______________________________ LOCATION OF SPACE: ________________________________________________________________ PURPOSE FOR ENTERING SPACE: ______________________________________________________

AUTHORIZED ENTRANTS: (must have completed Authorized Entrant training for confined spaces)

NAME IN OUT NAME IN OUT

PRECAUTIONS CHECKLIST YES NO N/A PROTECTIVE EQUIPMENT YES NO N/A

ALL ENTRANTS QUALIFIED _____ _____ _____ BELT/HARNESS/LIFELINE _____ _____ _____

SAFETY OBSERVER _____ _____ _____ NON-ENTRY RESCUE DEVICE _____ _____ _____

SPACE IS CLEAN _____ _____ _____ BREATHING APPARATUS _____ _____ _____

LOCKOUT IS IN PLACE _____ _____ _____ WARNING SIGNS _____ _____ _____

COMMUNICATION IN PLACE _____ _____ _____ PROTECTIVE EQUIPMENT _____ _____ _____

ATTENDANT NAME: ___________________________________ FIRE EQUIPMENT _____ _____ _____

ATMOSPHERIC CONDITIONS - INITIAL TESTS: FORCED VENTILATION ______ ____ ______ OXYGEN PERCENTAGE: (must be greater than 19.5% and less than 23.5 %) RESCUE EQUIPMENT IN PLACE ______ _____ _____

OXYGEN PERCENTAGE: __________________% 19.5 to 23.5 MISC. PROTECTIVE EQUIPMENT__________________ EXPLOSIVE: ____________________________% LFL <10% TOXIC: _______________________________PPM <10PPM H2S _________________________________________________ VOCs_________________________________

LIST TOOLS / EQUIPMENT AUTHORIZED FOR USE DURING THIS ENTRY: ________________________________________________________________________________________________________________________________________________________________________________________________

WILL HOT WORK BE PERFORMED YES ________ NO________

SUPERVISOR AUTHORIZING ENTRY___________________________________________________

SUPERVISOR AUTHORIZING HOTWORK_______________________________________________

ADDRESS OF THIS LOCATION IS ______________________________________________________

EMERGENCY PHONE NUMBER IS 911

Page 35: Pogue Construction Co., LP

PERMIT VALID FOR DATE OF ISSUE ONLY. PERMIT MUST BE CLEARLY DISPLAYED AT SITE OF EXCAVATION AT ALL TIMES. PERMIT REQUESTER MUST RETURN PERMIT(S) TO SAFETY OFFICE UPON COMPLETION OF PROJECT.

CONSULT PLANT PROCEDURE FOR ADDITIONAL INFORMATION AND REQUIREMENTS. PERMIT FORM REVISED 08/2017. ALL PREVIOUS VERSIONS OBSOLETE AND SHOULD BE DISCARDED.

POGUE CONSTRUCTION EXCAVATION INSPECTION AND ENTRY PERMIT FORM

LOCATION: DATE:

REASON FOR EXCAVATION: TIME:

WEATHER CONDITIONS: APPROX. TEMP.:

CREW LEADER: PROJECT SUPERVISOR:

DIMENSIONS: PLANNED DEPTH =

Yes No SPECIAL/HAZARDOUS CONDITIONS

Note: Trench over 20’ TOP = W L .......... Saturated soil / standing or seeping waterdeep requires P.E. BOTTOM = W L .......... Cracked or fissured wall(s)

SOIL TYPE: TESTED: .......... Bulging wall(s)

Solid rock (most stable) Yes .......... Floor heaving

Average soil (clay mix) [Type A] No .......... Intersecting trenches (contact Safety)

Fill material [Type B] .......... Suspended loads

Loose sand [Type C] .......... Vibration or vehicle traffic within 20 feet

Other ______________ Previous Excavation? Y N .......... Nighttime or darkness [special requirements]

PROTECTION METHOD(S) PLACEMENT OF SPOILS & EQUIPMENT

BENCHING SHORING/SHIELDING SLOPING .......... Spoils at least 3 feet from edge of trench

SHORING/SHIELDING TYPE .......... Equipment at least 5 feet from edge

Timber .......... Backhoe/equipment at end of trench

Pneumatic .......... Compressor, etc. at remote location

Hydraulic LADDER LOCATION

Screw Jacks .......... Located in protected area

Trench Shield Metal Wood Other _________ .......... Within 25 feet of safe travel of any worker

UNEVEN, IRREGULAR WALLS .......... Secured against falling or tipping

Trench Box (pre-fabricated and inspected/certified) .......... Extends 36 inches above the landing

Sloping: 1:1 (45°) 1½:1 (34°) .......... Leads to safe landing or stable ground

Yes No ENVIRONMENTAL CONDITIONS OTHER

Is heavy machinery to be used to excavate? Hot work to be conducted? [PERMIT REQUIRED]

Confined space permit necessary/issued? Utilities in area identified and marked?

Extreme weather conditions? (rain, heat, cold, etc.) Plans/blueprints available for excavation site?COMMENTS/OTHER PERMIT REQUIREMENTS/CONDITIONS:

Date/Time of Completion: Permit Requested By:

NOT E

ALL TRENCH ENTRANTS MUST SIGN IN ON BACK.

ANY CHANGE IN CONDITIONS REQUIRES THAT ALL ENTRANTS EXIT THE TRENCH IMMEDIATELY AND PROJECT BE RE-EVALUATED & PERMIT RE-ISSUED.

Permit Approved By: Competent Person

Page 36: Pogue Construction Co., LP

Hot Work Permit Before initiating hot work, can this job be avoided? Is there a safer way?

This Hot Work permit is required for any temporary operation involving open flames or producing heat and/or sparks. This includes, but is not limited to: Brazing, Grinding, Soldering, Thawing Pipe, Torch Applied Roofing and Welding.

Instructions: 1. Verify precautions listed below or do not proceed with work.2. Complete this permit and issue to person(s) performing the work.3. Retain this copy in the project file.

Permit #: Date:

Location of Work: Equipment Number:

Purpose of work: Name of Subcontractor doing the work:

Name of fire watch person:

I verify the above location has been examined, the precautions checked on the Precautions Checklist below to minimize the chance of fire.

Supervisor’s Name: Signature:

Duration (Hrs): Start Time: Stop Time:

Hot Work Permits may not be authorized for more than one calendar day! Yes No N/A Item

Are water hoses or fire extinguishers available and in good repair? Is hot work equipment in good repair? Have flammable liquids, dust, lint and oily deposits within 35 ft. been removed? Have explosive atmosphere been eliminated? Test results: Has the work surface area been cleaned of grease, paint, etc.? Have combustible floors been wet down, covered with damp sand or covered with

fire resistant sheets? Have surface areas below work area been protected? Have access ways below work area been barricaded? Are UV shields in place? Has enclosed equipment been cleansed of all combustibles? Have all containers been purged of flammable liquids and vapors? Will fire watch be provided during and for 60 minutes after work, including coffee

and/or lunch breaks? Has fire watch been provided with suitable fire extinguishing devices? Has the fire watch person been trained in use of fire extinguishing devices and in

sounding alarm(s) or other emergency communications? Has additional fire watch been assigned to adjoining areas, above and below? Hot work area will be monitored for 4 hours after completion of work? Other: Other:

Page 37: Pogue Construction Co., LP

CONTRACTOR:

DATE:

Jib Point

Lift Accomplishment Date:

Jib to be Used

No. Sections:

Jib Offset Angle:

Jib Max Load Radius

Jib Max Capacity of Lift Point

Jib Length of Boom

Other:

Down Haul Weight:

Jib Stowed:

QTY: Weight of Crane Components

QTY:

Type:  Capacity:

QTY: Total Weight Plus Factor of:

Type:  Capacity: PERCENT CAPACITY THIS LIFT

#

%#

#

#

#

#

Rigging ‐ Shackles

Total Weight of Lifted Load 

and Crane Components

#

5. LIFT WEIGHT DATA AND CALCULATIONS

Weight of Load to be Lifted

Jib Angle of Boom at Set (Deg)

Max. Load Line Weight

Load Block Weight

Rigging ‐ Lifting Beams

Rigging ‐ Slings

#

#

#

#

#

CRANE LIFT PLAN

Jib Length:

Jib Type:

3. LOAD DATA

B. Maximum Operation Radius to be

used During Lift (ft.)

Jib Size:

Boom Length:

Boom Type:

Hoisting From Main Boom:

Main Boom Parts of Line:

Main Crane Lifting Points:

Main Boom Line Size (Dia)

Type of Surface Size:

Structural Supports Required

Ground Compact & Stable

Jib Capacity of Line @ Parts:

Jib Angle of Boom at Pick 

(Deg)

Manufacturer:

Model:

Serial No.:

Crane Description:

A. Lift Description:

1. Equipment Number/Name:

2. Dimensions (L/W/H):

3. Total Gross Weight:Rated Capacity:

1. PROJECT DATA

2. CRANE DEFINITION

Page 1 of 3

WORK PERFORMED:

JOB NUMBER: WORK ORDER BY

PROJECT NAME: LOCATION:

MAIN BOOM

4. From Location to Location:Area of Operation:

Main Boom Max. Capacity

of Lift Point

Angle of Main Boom at

Pick (Deg)

Capacity of Line @ Parts:

Max. Load Radius

Length of Main Boom

Crane Yearly Inspection 

Date:

Angle of Main Boom at Set

(Deg)

4. CRANE CONFIGURATION

MAIN BOOM

No. Sections:

Boom Size:

Yes

Yes

Yes

No

No

No

Page 38: Pogue Construction Co., LP

6. LIFT ADMINISTRATION CHECKLIST

Print: Sign:

Print: Sign:

Tag lines are to be used: Description: Diameter Length

Weather:

Electricity:

Surrounding Obstacles:

Person responsible for lift: (Operator)

Lift Plan Supervisor:

Pogue Representative:

Other:

Critical Lifts:

1. Any lift over an operating unit, shelter or building.

2. Any lift with a load greater than 50 tons.

3. Any lift in which the combination of weight and lift radius will load the crane in the use above 75% of its rated capacity

4. Any lift requiring the use of more than one crane.

5. Any lift in which a significant risk of personnel injury or equipment damage is possible.

PRE‐LIFT WORKSHEET

Page 2 of 3Note: To be filled out before a lift

Location:

Has pre‐lift meeting been held with Signal Person/Riggers/Operator/Site Supervisor

Has JHA been completed?

Has swing clearance been checked?

Has area been checked for safe entry and exit?

Signal person designated (Name)

Operator assigned for the Lift (Name)

Operator Certification Card (MUST BE CURRENT)

Communications will be held by: Hand Radio, Both or Other (Please insert on line)

7. SIGNATURES OF PLAN DEVELOPERS & REVIEWERS

Pre‐Lift Huddle Conducted/Permit Secured

Potential Hazards to be Addressed:

If yes, please explain:

What is the Wind Speed?:

If yes, please explain:

Print Signature Date

Signature Date

If yes, please explain:

Print Signature

Print

Date

Print Signature Date

Yes No

Yes No

Yes NoYes NoYes No

Yes No

Yes No

Yes No

20 MPH - consider shutting down lift

Yes No

25 MPH - cancel lift

Page 39: Pogue Construction Co., LP

LIFT PLAN SKETCH

LIFT PLAN SUPERVISOR:

POGUE REPRESENTATIVE: DATE:

DATE:

Page 3 of 3

Page 40: Pogue Construction Co., LP

Visitor’s General Waiver and Release

Project Name:

Project Number: ______________ Location:

To ensure that all visitors to Pogue Construction projects understand the potential hazards and project safety rules associated with our construction site, ALL VISITORS entering the site must first report to the construction trailer and adhere to the safety protocols and instructions from the Pogue Const ruct ion project team.

Initials

Initials

Initials

Initials:

Initials:

I acknowledge that I will observe and follow all project safety procedures, including any warning signs or safety instructions posted on or about the premises.

I acknowledge that proper safety vests, hard hats and safety glasses have been provided to me for my visit. I am wearing closed toed shoes that the project superintendent or foreman has acknowledged will be appropriate for my visit.

I hereby waive, release and hold harmless, as well as forever discharge, Pogue Construction and all project subcontractors, their agents and employees from all claims which I, or my heirs, executors or administrators shall or may have, because of bodily injury or death to me or damage to my property resulting from any act or omission of the Released Parties. I AM NOT AGREEING, HOWEVER, TO RELEASE THE RELEASED PARTIES FROM GROSS NEGLIGENCE.

I hereby agree to indemnify, defend and hold harmless the Released Parties for any bodily injury, death or damage to other persons or property caused by my acts or omissions while visiting the project.

I, the undersigned, acknowledge that I (1) have requested permission from Pogue Cons t ruc t ion to visit the project site; (2) have executed this Waiver and Release as a condition of and in consideration for being permitted to visit the project site; and (3) agree to exercise extreme care while on the project site and to comply with allsafety rules and requirements.

Date:

Visitor Printed Name

Visitor Signature

Visitor Company / Group Name or Affiliation

Pogue Construction Project Manager / Superintendent Signature