PMBok Processes with CCPM Best Practices
-
Upload
ricardo-leite -
Category
Business
-
view
327 -
download
4
description
Transcript of PMBok Processes with CCPM Best Practices
©
PMBoK Processes + CCPM Procedures
©
Initiating Planning Executing Closing
Monitoring & Controlling
PMBoK and CCPM Frameworks
Reducing WIP(Bad Multitasking)
Full KittingCritical Chain
Planning/Buffering
Managing Execution
POOGI Processes
©
Develop Project Charter
Project Management Initiating Processes
Integration Overview – Initiating
Identify Stakeholders
Initiating Planning Executing Closing
Monitoring &
Controlling
©
During the Initiation Processes in CCPM is necessary to evaluate the ratio between the Load of work of the new project versus the Capacity of the team deliver more.
The exercise here is to analyze the priority of this new project against the portfolio which is already running, and re-allocate dates and resources according the business needs and or legal/compliance requirements.
The final product is to have a common and strategic vision about the projects and initiatives comes first and assure proper resources to start, execute and deliver them.
Integration Overview – Initiating
Identify Stakeholders
Develop Project Charter
©
Initiating Planning Executing Closing
Monitoring &
Controlling
Plan Scope Management
Collect Requirements
Define Scope
Create WBS
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity
Durations
Estimate Activity
Resources
Develop Schedule
Plan Cost Management
Estimate Costs
Determine Budget
Plan Quality Management
Plan HR Management
Plan Communications
Management
Plan StakeholdersManagement
Plan Risk Management
Identify Risks
Quantitative Risk Analysis
Qualitative Risk Analysis
Plan Risk Responses
Develop Project Management Plan
Integration Overview - Planning
Project Management Planning Processes
©
Estimate Activity
Durations
Estimate Activity
Resources
Develop Schedule
During the Planning Processes the activities involved in to building the Schedule are different in CCPM:
- Duration estimative cannot have local safeties, which means they will be shorter (most part of the times);
- Resources, when allocated to a task, will work exclusively in the task, with no other parallel work;
- The final CCPM schedule need to be “buffered”. All local safeties are gathered in the Feeding Buffers, Project Buffers and Milestones Buffers (where appropriate).
Integration Overview - Planning
©
Integration Overview - Planning
Plan HR Management
The project HR structure need to be defined:- Project Manager;- Resource Manager;- Task Manager;- Full Kit Manager;- Task Participants.
According their roles the team need to be properly trained in CCPM and the accesses and profiles in the CCPM and Project Management tools need to be set.
The CCPM support team need to be defined (when is the case).
©
Integration Overview - Planning
Plan Communications
Management
The Communication Plan has to consider the CCPM main tool of reporting is the Fever Chart. So, the stakeholders and the “customers” of information need to be prepared (trained) to understand and assess it.
All the information about issues, problems, work execution, performance, etc. need to be linked with the Fever Chart and it´s data. This assure a single
consistent channel of communication between the project and it´s stakeholders.
©
Initiating Planning Executing Closing
Monitoring &
Controlling
Direct and Manage the Project Work
Integration Overview - Executing
Manage Communications
Acquire Project Team
Develop Project Team
Manage Project Team
Manage Stakeholder Engagement
Conduct Procurement
Perform Quality Assurance
Project Management Execution Processes
©
Direct and Manage the Project Work
The process is based on frequent (preferably daily) meetings between the Project Manager and the Project Team (Task Managers, Full Kit Managers, Resource Managers, etc.) where the progress is measured and issues are addressed.
The key is to be sure the project work is synchronizedwith other activities (other projects and non project work - day by day activities).
Guidelines:• Whenever a task starts it shouldn’t stop until be
concluded;• The resources that are working in a task, must
work in the task only. No Multitask!!!• Do not start a task earlier than planned. The work
is do as late as possible.Tools:
• Buffer Recovery Plan;• Help Needed;• Escalation.
Integration Overview - Executing
©
Manage Project Team
The Project Manager, together with the Task Manager and the Resource Manager need assign the people to the tasks.
In the Planning Phase the tasks are linked with the roles (functions) to analyze the capacity to perform the work.
Now it is time to distribute the work to the teams according the plan. Eventual lack of resources have to be immediately addressed, before to cause major damages in the project.
Integration Overview - Executing
©
Manage Communications
The way to communicate the status the project is the “Fever Chart”. This tool allow all the team and stakeholders follow the speed of progress and have a clear picture of the work remaining to finish.
The chart shows the ratio between the % of Critical Chain completion (based on the remaining time to finish the ongoing tasks) and the % of buffer consumption.
Integration Overview - Executing
% B
uff
er
Co
ns
um
ed
% Chain Complete
©
Initiating Planning Executing Closing
Monitoring &
Controlling
Monitor and Control Project Work
ControlCommunications
Validate Scope
Control Scope
Control Risks
Control Quality
Project Management Monitoring & Controlling Processes
Integration Overview – Monitoring & Controlling
Perform Integrated Change Control
Control Procurements
Control Stakeholder Management
Control Schedule Control Costs
©
Control Schedule
Tracking the project progress through the Fever Chart is possible to identify the pace of the work and work in the issues before they cause major damage in the schedule.
Integration Overview – Monitoring & Controlling
Monitor and Control Project
Work
% B
uff
er
Co
ns
um
ed
% Chain Complete
A quick view in the tendency can give a valuable information:• Vertical progression means the project is
consuming buffer (safety) with lower progress;• Horizontal movements (from left to right) means
you are moving forward in the project critical chain with lower buffer consumption.
©
Initiating Planning Executing Closing
Monitoring &
Controlling
Close Project (or Phase)
Project Management Closing Processes
Integration Overview – Closing
Close Procurements
©
Close Project(or Phase)
During the project closure the team gather all the data available in the system, identifying opportunities of improvement and assessing the problems and issues happened along the project.
In CCPM this is called POOGI process, where the key is to search the most frequent causes for the most part of the problems (root cause). To do so, informations like these one is used:• Tasks that caused the highest buffer consumption
(number of occurrences and total time);• Tasks stuck (number of occurrences and total
time);• More frequent “Help Needed” (assigned to who
and what problems);• Project Managers, Full Kit Managers and Task
Managers assigned to the highest level of buffer consumption.
Integration Overview – Monitoring & Controlling
©
CCPM touch all of the five PMBok groups of processes, being present from the Initiation until the Closing. Around 13 processes are directly related with the CCPM best practices.
The main purpose of CCPM in simple. Protect and prioritize the flow. Which means avoid any interruption in the project work.
Everybody need to have a clear priority about what is the work to do now and what is the next.
The Critical Chain is the constraint of a project. So, need to be protected against uncertainty and Murphy through buffers, strategic placed in points were delays will cause critical damage.
Preparation is everything. So, use Full Kits to make sure once something start, can be finished with no breaks.
Conclusions
©
Focus, focus and focus. Avoid Multitask. Do one thing at the time. This will reduce stress and help to bring good quality.
In summary CCPM is not a Project Management methodology, is a “way” to how to manage and execute the Project. It does not specify phases; documents; and/or steps.
CCPM implementations, as any other cultural and behavior changes, require discipline and high management intensive support in the beginning, but significant improvements are proven in terms of reducing the projects cycle time, increasing the due date performance (deliver when it is originally planned) and the overall reliability.
Conclusions
©
Questions