Comparing PMBOK Guide 4th Edition, PMBOK Guide 5th Edition ...
(PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute,...
Transcript of (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute,...
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 1©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 1
A Guide to the
PROJECT MANAGEMENT
BODY OF KNOWLEDGE
(PMBOK ® GUIDE ) – Sixth edition
Chapter 7 – Project Cost Management
PMBOK is a registered mark of the Project Management Institute, Inc
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 2© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 2
Project Cost Management. *Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so the project can be completed within the approved budget.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 3©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 3
Topic
A cost that does not change with an increase or decrease in the amount of goods or services produced.
Fixed Cost
Ge
ne
ral C
on
cep
ts
Description
Costs that vary depending on a company's production volume; they rise as production increases and fall as production decreases
Variable Cost
A price that can be completely attributed to the production of specific goods or services.
Direct Cost
Costs that are not directly accountable to a cost object (such as a particular project, facility, function or product).
Indirect Cost
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 4©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 4
Topic
In economics and business decision-making, a sunk cost is a cost that has already been incurred and cannot be recovered.
Sunk Cost
Ge
ne
ral C
on
cep
ts
Description
The process of identifying and documenting all the costs involved over the life of an asset is known as Life Cycle Costing (LCC).
Lifecycle Cost
The loss of other (highest) alternatives when one alternative is chosen.Opportunity Cost
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 5©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 5
Topic
Value engineering (VE) is a systematic method to improve the "value" of goods or products and services by using an examination of function. Value, as defined, is the ratio of function to cost. Value can therefore be increased by either improving the function or reducing the cost.
Value Engineering
Ge
ne
ral C
on
cep
ts
Description
Cost escalation is defined as changes in the cost or price of specific goods or services in a given economy over a period.
Cost Escalation
In economics, inflation is a sustained increase in the general price level of goods and services in an economy over a period of time.
Inflation
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 6©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 6
Chapter 7
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
Project Cost Management
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 7© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 7
7.1 Plan Cost Management. *The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 8©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 8
7.1 Plan Cost Management (ITTO)
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-2, Page 235.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 9© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 9
7.2 Estimate Costs. The process of developing an approximation of the monetary resources needed to complete project work.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 10©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 10
7.2 Estimate Costs (ITTO)
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-4, Page 240.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 11© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 11
7.3 Determine Budget. *The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 12©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 12
7.3 Determine Budget (ITTO)
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-6, Page 248.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 13© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 13
In bottom-up cost aggregation, individual activities are added up, or aggregated.
Example: Cost Aggregation
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 14© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 14
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-8, Page 255.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 15© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 15
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-9, Page 255.
Cost Baseline, Expenditures, and Funding Requirements
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 16© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 16
7.4 Control Costs. *The process of monitoring the status of the project to update the project costs and manage changes to the cost baseline.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 17©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 17
Process 7.4 Topics covered in this process
7.4 Control Costs
5.6.1 Control Costs: Inputs
5.6.2 Control Costs: Tools and Techniques
5.6.3 Control Costs: Outputs
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 18©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 18
7.4 Control Costs (ITTO)
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 19©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 19
Inputs
Cost management plan, cost baseline and performance measurement baseline are inputs to this process.Project
Management Plan
7.3
Co
ntr
ol C
ost
s -
Inp
uts
Relevance
Lessons learned register.Project
Documents
1
2
The project funding requirements are an important input into the Control Costs process because they enable you to determine when expenditures will be incurred and when funding for the project will be available and to therefore assess actual versus planned project funding requirements and control any changes to these elements.
Project Funding Requirements
3
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 20©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 20
Inputs
The types of organizational process assets that will be useful as inputs into the Control Costs process are any existing organizational policies, procedures, templates, or any other element relating to how costs will be monitored and reported on in your project.
Organizational Process Assets
7.3
Co
ntr
ol C
ost
s -
Inp
uts
Relevance
5
Work performance data contains data on project status such as which activities have started, their progress (e.g., actual duration, remaining duration, and physical percent complete), and which activities have finished.
Work Performance
Data
4
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 21©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 21
T & T
Examples of expert judgment during the Control Costs process include but are not limited to:
1. Variance analysis2. Earned value analysis3. Forecasting, and4. Financial analysis
Expert Judgment
7.3
Co
ntr
ol C
ost
s –
T &
T
What is it?
1
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 22©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 22
T & T
Earned Value Management. *A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
EVM develops and monitors three key dimensions for each work package and control account:
1. Planned Value2. Actual Cost3. Earned Value
Data Analysis
7.3
Co
ntr
ol C
ost
s –
T &
T
What is it?
2
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 23©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 23
T & T
Actual Cost (AC). *The realized cost incurred for the work performed on an activity during a specific time period.
Planned Value (PV). *The authorized budget assigned to scheduled work.
Earned Value (EV). *The measure of work performed expressed in terms of the budget authorized for that work.
Data Analysis
7.3
Co
ntr
ol C
ost
s –
T &
T
What is it?
2
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Earned Value is calculated using the formula.
EV = % Completed x Budget
Percent Completed is the progress of the work package or control account for which the progress is measured using different measurement techniques.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 24©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 24
T & T
Each work package has its own unique characteristics; therefore, there is not one single best way to measure progress. To accommodate the different types of work, there are several accepted methods to measure work performance. There are three classes of work, as follows:
1. Discrete effort
2. Apportioned effort
3. Level of effort
Progress Measurement
Techniques
7.3
Co
ntr
ol C
ost
s –
T &
T
What is it?
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 25©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 25
T & T
Discrete Effort. * An activity that can be planned and measured and that yields a specific output.
Discrete effort is directly related to specific end products or services with distinct and measurable points, and outputs that result directly from the discrete effort.
The four discrete effort measurement methods are:
1. Fixed formula
2. Weighted milestone
3. Percent complete
4. Physical measurement
Progress Measurement
Techniques
7.3
Co
ntr
ol C
ost
s –
T &
T
What is it?
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 26© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 26
1. Fixed Formula Methods
Fixed formula assigns a specified percentage of the budget value of the work package to the start milestone of the work packages. The remaining budget value percentage is assigned when the work package is completed.
Another important point is to note is that this method is only used on smaller work packages that are planned to start and end within two reporting time periods.
Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-2, Page 37.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 27© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 27
2. Weighted Milestone
The weighted milestone method divides the work package into measurable segments, each ending with an observable milestone; it then assigns a weighted value to the achievement of each milestone.
The weighted milestone method ismore suitable for longer duration work packages (i.e., those longer than two time periods) that haveintermediate and tangible results, or milestones.
Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-3, Page 38.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 28© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 28
3. Percent Complete
The percent complete method shows an estimate of the percentage of work that is complete at the end of each measurement period. This method should be based on objective and quantifiable work completion.
The planned value is determined by the time-phased resources required to accomplish the work package. The earned value (EV) is determined by multiplying the work package BAC by the percent complete.
Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-4, Page 39.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 29© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 29
4. Physical Measurement
The physical measurement, unlike the weighted milestone and the percent complete, can be related more explicitly to the completion of the work.
Measurement can include any units that can be explicitly related to the completion of the work.
Examples may include the length of cable laid, the area and quantity of concrete poured, and the quantity of spokes in the case of the bicycle’s wheel. The method of measurement and specific measurement with the cost or efforts spent should be defined and agreed upon in advance.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 30©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 30
T & T
Apportioned Effort. Apportioned effort is used for work with a direct, supportive relationship to discrete work. The value for the support task is determined based on the earned value of the referenced base activity.
Apportioned effort can include such work as quality assurance, inspection, and testing activities. An apportioned work effort is estimated as a percentage of the referenced discrete work effort.
The percent allocation to discrete effort is used when there are sufficient performance records and knowledge of the interrelationship between the apportioned effort and the discrete effort.
Progress Measurement
Techniques
6.6
Co
ntr
ol S
che
du
le:
T &
T
What is it?
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 31© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 31
Apportioned Effort
In this figure, the discrete effort at the second measurement point is 5,200. The apportioned effortis 10% of the discrete effort. Therefore the apportioned value at the second measurement point is 10% of 5,200 or 520.
In actuality, the actual discrete effort accomplished at the end of the second period was 7,800; therefore the apportioned earned value at the second measurement point is 10% of 7,800 or 780.
Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-5, Page 40.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 32©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 32
T & T
Level-of-effort (LOE) activities do not directly produce definitive end products that can be delivered or measured objectively.
LOE work, such as project or program management and contract management, consume project resources and should be included in the EVM Planning, Executing, and Monitoring and Controlling Process Groups.
LOE is not necessarily characterized by a uniform rate of work over a period of time. A planned value is assigned to each LOE task for each measurement period, and this planned value is credited as EV at the end of the measurement period.
EV is accrued in line with PV which means LOE activities will not havea schedule variance. However cost variance can be incurred because the actual cost (AC) is usually different from EV.
Progress Measurement
Techniques
7.3
Co
ntr
ol C
ost
s –
T &
T
What is it?
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 33© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 33
Level of Effort
Earned value equal to the planned value at all measurement points.
Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-6, Page 41.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 34
Earned Value Calculation
Wall 1
Wal
l 2
Wall 3
Wal
l 4
Schedule PlanSchedule: To complete the work in 4 weeks –work is equally distributed
Budgeted CostUSD 10000 / wall
Status at the end of week 3Wall 1 – Progress 100% - AC $12000Wall 2 – Progress 100% - AC $13000Wall 3 – Progress 50% - AC $7000Wall 4 – Progress 0% - AC $0
Calculate BAC, PV, AC and EV
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 35
Work Package Planned Value Actual Cost Progress Earned Value
Wall 1 10000 12000 100 % 10000
Wall 2 10000 13000 100 % 10000
Wall 3 10000 7000 50 % 5000
Wall 4 10000 0 0 % 0
Total 40000 32000 25000
Solution
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 36©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 36
T & T
Variance Analysis. * A technique for determining the cause and degree of difference between the baseline and actual performance.
There are 4 formula to calculate variance
1. Cost Variance2. Cost Performance Index3. Schedule Variance4. Schedule Performance Index5. Variance At Completion (VAC). * A projection of the amount of budget
deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion. (Explained later)
Data Analysis
7.3
Co
ntr
ol C
ost
s –
T &
T
What is it?
2
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 37
Cost Performance
Cost Variance Cost Performance Index
Earned Value – Actual Cost𝑬𝒂𝒓𝒏𝒆𝒅 𝑽𝒂𝒍𝒖𝒆
𝑨𝒄𝒕𝒖𝒂𝒍 𝑪𝒐𝒔𝒕Positive = Under planned costNeutral = On planned costNegative = Over planned cost
Greater than 1.0 = Under planned costExactly 1.0 = On planned costLess than 1.0 = Over planned cost
Schedule Performance
Schedule Variance Schedule Performance Index
Earned Value – Planned Value 𝑬𝒂𝒓𝒏𝒆𝒅 𝑽𝒂𝒍𝒖𝒆
𝑷𝒍𝒂𝒏𝒏𝒆𝒅 𝑽𝒂𝒍𝒖𝒆Positive = Ahead of ScheduleNeutral = On scheduleNegative = Behind Schedule
Greater than 1.0 = Ahead of scheduleExactly 1.0 = On scheduleLess than 1.0 = Behind schedule
Vari
ance
An
alys
is
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 38
Cost Performance
Cost Variance Cost Performance Index
25000 – 32000 = (7000) 25000 / 32000 = 0.781
Schedule Performance
Schedule Variance Schedule Performance Index
25000 – 30000 = (5000) 25000 / 30000 = 0.833
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 39©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 39
T & T
Trend Analysis. An analytical technique that uses mathematical models to forecast future outcomes based on historical results.
Trend analysis uses Charts and Forecasting techniques to measure project performance over time to determine if performance is improving or deteriorating.
(Explained in subsequent slides)
Data Analysis
7.3
Co
ntr
ol C
ost
s –
T &
T
What is it?
2
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
PMIS is often used to generate, capture and report project performance.PMIS
3
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 40© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 40
Charts
This chart uses S-curves to display EV data for a project that is performing over budget and behind the schedule.
Earned Value, Planned Value, and Actual Costs
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-12, Page 264.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 41
Estimate At Completion
EAC EAC
𝑩𝑨𝑪
𝑪𝑷𝑰AC + (BAC – EV)
CPI is expected to be the same for the remainder of the project
Future work will be accomplished at the planned rate
EAC EAC
AC + (𝑩𝑨𝑪 −𝑬𝑽)
(𝑪𝑷𝑰 𝒙 𝑺𝑷𝑰) AC + Bottom up ETC
CPI and SPI influence the remaining work Initial plan is no longer valid
Forecasting EAC
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 42
Estimate At Completion
EAC EAC
𝟒𝟎𝟎𝟎𝟎
𝟎.𝟕𝟖𝟏= 51216 32000 + (40000 – 25000) = 47000
CPI is expected to be the same for the remainder of the project
Future work will be accomplished at the planned rate
EAC EAC
32000 + (𝟒𝟎𝟎𝟎𝟎 −𝟐𝟓𝟎𝟎𝟎)
(𝟎.𝟕𝟖𝟏 𝒙 𝟎.𝟖𝟑𝟑)= 55055 32000 + Bottom up ETC
CPI and SPI influence the remaining work Initial plan is no longer valid
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 43
Estimate To Complete
ETC ETC
EAC – AC Re-Estimate
Assumes work is proceeding on plan. Re-estimate the remaining work from the bottom up.
Forecasting ETC
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 44
Estimate To Complete
ETC ETC
51216 – 32000 = 19216CPI is expected to be the same for the
remainder of the project.
Re-Estimate
Assumes work is proceeding on plan. Re-estimate the remaining work from the bottom up.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 45©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 45
T & T
* A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance
Index
7.3
Co
ntr
ol C
ost
s –
T &
T
What is it?
3
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
To Complete Performance Index
TCPI TCPI
(BAC – EV)/(BAC – AC) (BAC – EV)/(EAC – AC)
The efficiency that must be maintained in order to complete on plan.
The efficiency that must be maintained in order to complete the current EAC.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 46
To Complete Performance Index
TCPI TCPI
(BAC – EV)/(BAC – AC)
(40000-25000) / (40000-32000)
1.875
(BAC – EV)/(EAC – AC)
(40000-25000) / (51216-32000)
0.781
The efficiency that must be maintained in order to complete on plan.
The efficiency that must be maintained in order to complete the current EAC.
TCPI
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 47
Variance At Completion
VAC
BAC – EAC
40000 – 51216 = (11216)
The estimated difference in cost at the completion of the project.
VAC
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 48©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 48
Outputs
The easiest way to display work performance information based on the work performance data is by using the earned value calculations for cost variance (CV), schedule variance (SV), cost performance index (CPI), schedule performance index (SPI), and the to-complete performance index (TCPI).
Work Performance Information
7.3
Co
ntr
ol C
ost
s –
Ou
tpu
ts
Description
1
Cost Forecasts
2EAC and ETC will be communicated to the stakeholders.
Change Request
3Change requests may include preventive or corrective actions.
PMP and PD Updates
4 & 5Project Management Plan and Project Documents will be updated.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 49©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 49
Emerging Concept
Chapter 7 – Project Cost Management
PMP and PMBOK are registered marks of the Project Management Institute, Inc
Earned Schedule
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 50©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 50
Topic
Earned schedule (ES), developed by Lipke in 2003, extends the graphical method of projecting EV accrued onto the PV curve.
The idea of Earned Schedule is similar to Earned Value. However, instead of using cost for measuring schedule performance, we would use time.
Earned Schedule is determined by comparing the cumulative EV earned to the performance baseline. The time associated with EV, i.e. Earned Schedule, is found from the PV S-curve. The significance of using the Earned Schedule concept is that the associated schedule indicators behave appropriately throughout the entire period of project performance.
Earned Schedule
EAR
NED
SC
HED
ULE
Description
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 51© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 51
Earned Schedule Concept
Schedule Variance (time)SV(t)= ES - AT
Schedule Performance Index (time) SPI(t)= ES / AT
Schedule Variance (time)SV(t)= 6 – 10 = -4
Schedule Performance Index (time) SPI(t)= 6/10 = 0.60
When the ES exceeds AT, the SV(t) is positive and negative when it lags. The SPI(t) is greater than 1.0 when ES exceeds AT, and less than 1.0 when ES is less than AT. SV(t) will only revert to zero and SPI(t) to unity at project completion
when the project completes on time.
Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. D1, Page 100.
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 52© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 52
Activity 7.2
Instruction
Cost Baseline
Calculate various component of a cost baseline (BAC, PV, AC and EV).
Format Individual Exercise
Time Limit 10 Minutes
Discussion 5 Minutes
Learning Outcome
7.2
Abu Dhabi : 02-6670660Dubai: 04-3574622
www.3foldtraining.comwww.pmexamstudy.com
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 53© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 53
Activity 7.3
Instruction
Cost Control
Evaluate project performance using various cost control techniques.
Format Individual Exercise
Time Limit 10 Minutes
Discussion 5 Minutes
Learning Outcome
7.3
©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 54©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 54
End of Seminar
PMP and PMBOK are registered marks of the Project Management Institute, Inc