PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group...

42
PLS-CADD Advanced Training and User Group Meeting Leg and Body Extensions / XML July 20 th , 2011 Kenny Construction Company and Power Engineers 1

Transcript of PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group...

Page 1: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

PLS-CADD Advanced Training and User Group Meeting

Leg and Body Extensions / XML

July 20th, 2011

Kenny Construction Company and Power Engineers 1

Page 2: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Project Location Map

July 20th, 2011

Kenny Construction Company and Power Engineers 2

Page 3: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Project Overview

• 671 total structures (536 Lattice and 135 Tubular)

• 151.2 Miles of 500kV Transmission Line (25 miles with 138kV Underbuild)

• 252 Miles of access roads required due to mountainous terrain

• 17,176 tons of lattice steel

• >$900M Total Project Cost (Allegheny Power/TrAILCo Portion)

July 20th, 2011 Kenny Construction Company and Power Engineers 3

Page 4: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Engineering Design • Series 8 tower family was developed for 3-bundle 1113 Finch ACSS

conductor

• Family consisted of 7 tower & poles types (Short/Medium/Long Span Tangents, 10˚ Angle, 30˚ Angle, 49˚ Deadend, 90˚ Deadend)

July 20th, 2011

Kenny Construction Company and Power Engineers 4

Page 5: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Designed for Helicopter Installation • Splices set for each section of the tangents

July 20th, 2011

Kenny Construction Company and Power Engineers 5

Page 6: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

What’s the Push on Design & Engineering?

• Aggressive project timeline in conjunction with the risk of foreign sourcing and ocean delivery of lattice steel delivery forced the early material ordering to support construction

• The TrAIL Project Management Team wanted the tower material ordering process to uphold several basic philosophies : – Accommodate landowner requests in relation to structure

location to reduce condemnations – Construction materials would not become critical path

items – Construction would never have to wait on materials.

July 20th, 2011 Kenny Construction Company and Power Engineers 6

Page 7: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Tower Testing • Tested 3 Towers (one tangent, one angle, one deadend)

• Testing is important, fabrication and detail mistakes will become apparent under failure loading conditions

Incorrectly detailed bolt pattern failed during testing of 10 degree angle

structure

Deadend Structure passed all loading without a failure

July 20th, 2011

Kenny Construction Company and Power Engineers 7

Page 8: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Structure Pads • Drilled Pier Foundations – “If you can get concrete trucks there you can

get a tower crane there.”

July 20th, 2011 Kenny Construction Company and Power Engineers 8

Page 9: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Stub Angles • Stubs needed to be onsite for the foundation sub-contractor

July 20th, 2011 Kenny Construction Company and Power Engineers 9

Page 10: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Steel Erection • Steel must be available to crews June 2009 to January 2011

• At peak there were 7 x 14 man crews

July 20th, 2011

Kenny Construction Company and Power Engineers 10

Page 11: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Lattice Steel Procurement

• Procurement began in 2007

• Invited North American & International companies to bid due to timeline and tonnage required

• Existing Allegheny Structure Family drawings used for RFP

July 20th, 2011

Kenny Construction Company and Power Engineers 11

Page 12: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Material Ordering • 29 Material Releases - each release was based on tonnage and tower

types

July 20th, 2011

Kenny Construction Company and Power Engineers 12

Page 13: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Tubular Steel Procurement

• Procurement began in 2008

• Invited six North American companies to bid

July 20th, 2011

Kenny Construction Company and Power Engineers 13

Page 14: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Material Ordering • 11 Material Releases – based upon confirmed structure locations

July 20th, 2011

Kenny Construction Company and Power Engineers 14

Page 15: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Material Delivery • Liaison at delivery port set up trucking to three

major material yards

• From material yards, delivered to staging yards every 5 miles along the Transmission Line route

• Barcoding System used for all bundles

July 20th, 2011 Kenny Construction Company and Power Engineers 15

Page 16: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Material Yard Locations

July 20th, 2011 Kenny Construction Company and Power Engineers 16

Page 17: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Use of Differential Legs

• Reduction in Earthwork on Tower Construction Pads

• Permitting and Permit Closeout

– Requires less reclamation work

– Return site to near as original contours as practical

• Compressed and Aggressive Schedule

Page 18: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Engineering Dilemma

• Lattice tower orders were required prior to the completion of the design

• With over 500 lattice towers on the project, a time consuming, iterative process would have to be performed numerous times

• Solution: develop an Excel spreadsheet that manipulates PLS-CADD data via XML exports to assist in developing the required material order

Page 19: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

History Leading to XML Tower Leg Extension Spreadsheet

• Prior to the TrAIL project, an XML Excel spreadsheet was developed to determine the pole lengths of multiple pole structures in steep terrain

• Values were analyzed from PLS-CADD’s Leg-Guy Extension report

19

Page 20: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

History Leading to XML Tower Leg Extension Spreadsheet

20

Note: PLS-CADD now has a command that will automatically snap the legs to the TIN, but will not determine if the magnitude of an overburied leg warrants shortening.

Page 21: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Developing the XML Tower Leg Extension Spreadsheet

• Challenges Faced:

– Working with a 3-D structure configuration

– Battered legs

– Leg designations

– Set up spreadsheet to only add leg length

• Spot PLS-TOWERS with shortest leg lengths

• Height adjust towers to obtain desired attachment heights

– Defined allowable body & leg combinations

21

Page 22: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Developing the XML Tower Leg Extension Spreadsheet

22

Page 23: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Developing the XML Tower Leg Extension Spreadsheet

• Assumptions & Criteria:

– Minimum pier reveal: 1.0’

– Maximum pier reveal: 5.0’

– Tower families were previously defined

– Tower legs were in 5.0’ increments

• Definition:

– T.O.C. = Top Of Concrete pier

23

Page 24: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Developing the XML Tower Leg Extension Spreadsheet

• Theory:

– Determine if it is beneficial to increase the length of 1 (or more) legs by increasing the T.O.C. of the remaining piers

– Set the maximum amount for raising the T.O.C. of the 3 piers in order to lengthen 1 of the legs (1.0’ was used on the TrAIL project)

24

Page 25: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Hand Calculation Example

AL AR

BL BR

Reveal Length 5.2’ 1.0’ w/ 5’ Leg Extension 1.5’ w/ 5’ Leg Extension 2.7’ w/5’ Leg Extension

Reveal Length 4.7’ 5.5’ 1.0’ w/ 5’ Leg Extension 2.2 ‘ w/ 5’ Leg Extension

Reveal Length 1.0’ 1.8’ 2.3’ 3.5’

Reveal Length 3.5’ 4.3’ 4.8’ 1.0’ w/ 5’ Leg Extension

Original Design before Top Of Concrete (T.O.C) Adjustments 1st Iteration, Adjust T.O.C. by 0.8’ = (5’ leg + 1’ min reveal) – 5.2’ 2nd Iteration, Adjust T.O.C. by 0.5’ = (5’ leg + 1’ min reveal) – 5.5’ 3rd Iteration, Adjust T.O.C. by 1.2’ = (5’ leg + 1’ min reveal) – 4.8’

Total Amount of Concrete Reveal for ALL 4 Piers 14.4’ 12.6’ with 1 Leg Lengthened 9.6’ with 2 Legs Lengthened 9.4’ with 3 Legs Lengthened

TOTAL PIER LENGTH SAVING = 0.2’

NOT BENEFICIAL

Page 26: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Cost Saving Breakdown

• Leg Extension Cost – 5’ Leg Extension Weight ≈ 300 lbs @ $0.97

– $291 per 5’ Leg Extension

• Concrete Installed Costs – Approximately $1,200 per Yard

– Average Pier Diameter ≈ 3.5’

– $420 per Linear Foot (@ 3.5’ Diameter Pier)

• Labor for Earth Work – $520 per 4 man crew hour

Page 27: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Cost Saving Breakdown

DESIGN ITERATION # 5’ LEG

EXTENSIONS TOTAL PIER REVEAL

(ALL 4 PIERS) EXTENDED COST

Original Design 0 14.4’ -

Approx Cost $0 $6,048 $6,048

1st Iteration 1 12.6’ -

Approx Cost $291 $5,292 $5,583

2nd Iteration 2 9.6’ -

Approx Cost $582 $4,032 $4,614

3rd Iteration 3 9.4’ -

Approx Cost $873 $3,948 $4,821

• Approximate Cost Savings for 2nd Iteration = $1,434 • If $1,500 is Assumed as the Average Cost Savings per Tower, Extended Savings for 536 Towers ≈ $800,000

Page 28: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Cost Saving Breakdown

DESIGN ITERATION EXTENDED COST

(Leg Extension + Pier Costs)

EQUIVALENT CREW HOURS FOR COMPLETING

EARTH WORK

Original Design $6,048 12 Hours

1st Iteration $5,583 11 Hours

2nd Iteration $4,614 9 Hours

3rd Iteration $4,821 9.5 Hours

• The Additional Costs for Permitting and Reclamation is NOT Accounted for in the Above Values

Page 29: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

XML Exporting / Importing Overview

• What is XML?

– eXtensible Markup Language

– A file in this format allows for the easy sharing and managing of data between computer softwares (i.e. PLS-CADD and Excel or other software)

– A civil engineer’s interpretation: it is a way of copying data from one program to another in an organized way

29

Page 30: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

What does a XML file look like?

<staking_table rownum="1">

<structure_number>1</structure_number>

<station units="ft">205.102</station>

<orientation_angle units="deg" />

<x_easting units="ft">2496105.399</x_easting>

<y_northing units="ft">2087913.337</y_northing>

<tin_z_elevation units="ft">736.566</tin_z_elevation>

<ahead_span units="ft">378.952</ahead_span>

<line_angle units="deg">42.8919</line_angle>

<structure_description>138kV, 3-PoleDead-End </structure_description>

<struct_height units="ft">77.000</struct_height>

<embedded_length units="ft">13.000</embedded_length>

Starting Tag

Ending Tag

Data Assigned to the Tags

Attribute Assigned to

the Data

30

Page 31: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Demonstrations

• Demonstrate an XML export in PLS-CADD

• Overview of importing and manipulating an XML file in Excel

• Run the Lattice Tower Leg Extension XML Excel spreadsheet

Page 32: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Why Use XML?

• Once the original setup is complete:

– Mapping the elements

– Setting up the equations

– Formatting

• The XML data can be updated or referenced to a new project, while the equations and formatting will remain unchanged with the new data

32

Page 33: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

XML Spreadsheets Created

• H-frame & lattice tower leg extension calculations

• Reorganization of the wire stringing charts

• Calculating level sag and angle of sight stringing values

• Reformatting PLS-CADD tables and reports such as the Construction Staking Table

• Line rating analysis calculations

33

Page 34: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Lattice Steel Procurement

July 20th, 2011

Kenny Construction Company and Power Engineers 34

0.00%

20.00%

40.00%

60.00%

80.00%

100.00%

120.00%

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

01-Jun-08 09-Sep-08 18-Dec-08 28-Mar-09 06-Jul-09 14-Oct-09 22-Jan-10 02-May-10 10-Aug-10 18-Nov-10 26-Feb-11

To

ns o

f S

teel

Period

Lattice Tower Weight History

WT Ordered WT Received WT Erected % of Engineering Complete Construction Start

Page 35: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Construction • Structure 200 towards 199

July 20th, 2011

Kenny Construction Company and Power Engineers 35

Page 36: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Construction • Structure 159L

July 20th, 2011

Kenny Construction Company and Power Engineers 36

Page 37: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Construction • Structure 116

July 20th, 2011

Kenny Construction Company and Power Engineers 37

Page 38: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Construction • Structure 248

July 20th, 2011

Kenny Construction Company and Power Engineers 38

Page 39: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Construction • Structure 106 – Parallel existing 500kV

July 20th, 2011

Kenny Construction Company and Power Engineers 39

Page 40: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Construction • Structure 104

July 20th, 2011

Kenny Construction Company and Power Engineers 40

Page 41: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Questions?

July 20th, 2011

Kenny Construction Company and Power Engineers 41

Page 42: PLS-CADD Advanced Training and User Group Meeting … · PLS-CADD Advanced Training and User Group Meeting ... •Reduction in Earthwork on Tower Construction ... •Lattice tower

Thank You

July 20th, 2011

Kenny Construction Company and Power Engineers

42