MATERIALS IN ROOF
Length of Purlins of the roof=24 m
A. Corrugated Sheet (using 2 corrugations)
1) 22.5/0.6=37.5 40 sheets in one row.
2) Since length of rafter is 5.4m
3) Order 38(2)(2)=160 pcs 32x10
B. Rivets
1) For 10 long
160x22=3520 pcs
2) Convert to kilograms
3520/180=19.56Kg or 20 Kg
C. Washers
1) Double the no. of rivets
3520(2)=7040 pcs
2) Convert to kilograms
7040/126=55.
-
STEEL TRUSS
For top and bottom chords:
No of truss= 6
Steel Used=2x2x1/4
Length per truss=13+13+19=45m
Using standard 6m length
Total Length=45(6)=270m
270/6=50 pcs 2x2x1/4
For web members:
No of truss= 6
Steel used=2x2x3/16
Length per truss=(1.5+1.32+2.64+3.63+3.5+3.82+4.43)2+5
=51.6852m
Using standard 6m length
Total Length=52(6)=312m
312/6=52 pcs 2x2x3/16
Sag rods:
No of lines= 6
Steel used=10mm diameter
Using standard 6m length
Total Length=6(31)=186m
-
186/6=31 pcs 10mm dia. sag rods
Purlins:
No of lines=14
Length per line=23.79 or 24
Total Length=14(23.79)=333m
Using standard 6m length
333/6=55.556 pcs 6m long 120x40x20x2.0
Tie Rods:
No of points=84
Total Length=84(0.051)=4.27 m
Buy 1 6m long 2.5x2.5x1/4
SUMMARY:
-
Corrugated GI sheets 160 pcs 32x10
Rivets 20 kg
Washers 56 kg
Top and Bottom Chords 2x2x1/4 (6m) 50 pcs
Web members2x2x3/16 (6m) 52 pcs
Sag rods (6m) 31 pcs 10mm dia.
Purlins 120x40x20x2.0 (6m) 56 pcs
Tie rods 2.5x2.5x1/4 (6m) 1 pc
-
ROOFING MATERIALS
Length of Rafter on 1side of the roof= 5.75m
Length of Purlins of the roof=22.5 m
Corrugated Sheet (using 2 corrugations)
22.5/0.6=37.5 38 sheets in one row.
Since length of rafter is 5.75m
use a combination of two 3m long GI sheet
Order 38(2)(2)=152 pcs 32x10
Rivets
For 10 long
152x22=3344 pcs
Convert to kilograms
3344/180=18.57kg19kg
Washers
Double the no. of rivets
3344(2)=6688 pcs
Convert to kilograms
6688/126=53.01kg54kg
-
STEEL TRUSS
For top and bottom chords:
No of truss= 6
Steel Used=2x2x1/4
Length per truss=13+13+19=45m
Using standard 6m length
Total Length=45(6)=270m
270/6=45 pcs 2x2x1/4
For web members:
No of truss= 6
Steel used=2x2x3/16
Length per truss=(1.5+1.32+2.64+3.63+3.5+3.82+4.43)2+5
=46.6850m
Using standard 6m length
Total Length=47(6)=282m
282/6=47 pcs 2x2x3/16
-
Sag rods:
No of lines= 6
Steel used=10mm diameter
Length per truss=13+13=26m
Using standard 6m length
Total Length=6(26)=156m
156/6=26 pcs 30pcs 10mm dia. sag rods
Purlins:
No of lines=14
Steel Used=120x40x20x2.0
Length per line=22.5m
Total Length=14(22.5)315m
Using standard 6m length
315/6=52.555 pcs 6m long 120x40x20x2.0
Tie Rods:
No of points=84
Steel Used=2.5x2.5x1/4
Length per point=0.051m (2)
Total Length=84(0.051)=4.27 m
Buy 1 6m long 2.5x2.5x1/4
-
SUMMARY:
Corrugated GI sheets 152 pcs 32x10
Rivets 19 kg
Washers 54 kg
Top and Bottom Chords 2x2x1/4 (6m) 45 pcs
Web members2x2x3/16 (6m) 50 pcs
Sag rods (6m) 30 pcs 10mm dia.
Purlins 120x40x20x2.0 (6m) 55 pcs
Tie rods 2.5x2.5x1/4 (6m) 1 pc