Plant Over View Report
-
Upload
konda-venkat-reddy -
Category
Documents
-
view
131 -
download
3
Transcript of Plant Over View Report
1
KTPS-B STATION
REPORT FOR A MINI PROJECT ON
OVER VIEW OF THERMAL
POWER STATION
SUBMITTED BY:
NAME ROLL NO.
BEZAWADA CHAKRADHAR 09232
P.VAMSHI KRISHNA 09236
R.ADITYA ANVESH 09257
B.NAGESWARA RAO O8258
National Institute Of Technology-Warangal
2
ABSTRACT
Concern over the electrical demand in the country,
Kothagudem Thermal Power Station was established
extending the wide electrical network in the state of Andhra
Pradesh.
We are going through a detailed study of various steps
involved in generation of power in a thermal power plant.
Ideas of Efficient combustion of coal, efficient utilization of
heat energy through a Regenerative system, Water Cycle,
Steam Cycle, Working of Turbine, Self utilization of Power,
Transferring the generated power to the Grid, Handling of
Ash are mainly focused.
New ideas for Handling of Ash, efficient pulverizing of coal,
better water treatment, effect of pressure of steam on turbine,
developing required pressure to attain required RPM and
construction of boiler that suits for requirement of KTPS are
studied and analyzed.
3
ACKNOWLEDGEMENT
WE SINCERELY THANK MR.LAKSHMAN
(ADE/EM/KTPS-B STATION) SIR FOR GUIDING US
TO COMPLETE THE PLANT OVER VIEW.
WE SINCERELY THANK MR.VEDA KUMAR
(ADE/EM/KTPS-B STATION) SIR FOR HIS
CONCEPTUAL GUIDENCE IN UNDERSTANDING THE
MECHAISM OF POWER STATION
WE SINCERELY THANK MR.VENU
(ADE/EM/KTPS-B STATION) SIR FOR HIS CO-
OPERATION TO STUDT THE POWER PLANT.
WE SINCERELY THANK MR.T.SATYANARAYANA
(DE/EM/KTPS-B STATION) SIR FOR PERMITTING
US TO DEAL WITH THIS MINI PROJECT.
WE HEARTFULLY THANK MR.RAMBABU
(SWITCH YARD) SIR & MR.RAMAKRISHNA
(LIFT MAINTENANCE) SIR FOR THEIR SUPPORT
AND GUIDENCE IN STUDYING THE POWER STATION
4
5
CONTENTS
Topic P.No.
All Thermal Power Stations in India 6
Introduction to APGENCO 7
Introduction to KTPS 9
In to the working of the plant 13
Coal Handling Plant 16
Coal Milling Plant 18
Water Handling System 26
Working of Thermal Power Plant 27
Working of the Boiler 29
Steam with the Turbine 31
Cooling Towers 37
Boiler Feed Pump 40
Regenerative System 42
Handling of Ash 43
Generator 46
Transformers 55
KTPS Switch Yard 58
MCR & UCB 71
6
A broad view of Thermal Power Plants in INDIA
7
INTRODUCTION TO APGENCO
Andhra Pradesh Power Generation Corporation Limited (APGENCO) is the electricity generation company of the Government of Andhra Pradesh found in the year 1998 as a part of the network of APSEB (Andhra Pradesh State Electricity Board) in India. It has an installed capacity of 7048.4 MW which makes it the third largest power generation company in India.
Andhra Pradesh Power Generation Corporation Limited is one of the pivotal organizations of Andhra Pradesh, engaged in the business of Power generation. Apart from operation & Maintenance of the power plants it has undertaken the execution of the ongoing & new power projects scheduled under capacity addition programme and is taking up renovation & modernization works of the old power stations. APGENCO came into existence on 28.12.1998 and commenced operations from 01.02.1999. This was a sequel to Governments reforms in Power Sector to unbundle the activities relating to Generation, Transmission and Distribution of Power. All the Generating Stations owned by erstwhile APSEB were transferred to the control of APGENCO. The installed capacity of APGENCO as on September 30, 2010 is 8135.9 MW comprising 4382.50 MW Thermal, 3751.40 MW Hydro and 2 MW Wind power stations, and contributes about half the total Energy Requirement of Andhra Pradesh. APGENCO is third largest power generating utility in the Country next to NTPC and Maharashtra. It's installed Hydro capacity of 3703.4 MW is the second highest among the Country.
8
Statistical Information Regarding Different Thermal Power Plants Operating
Under APGENCO
Power Station
Operator Location District Unit Wise Capacity
Installed Capacity
Plant Coordinates
Ramagundam B Thermal Power Station
APGENCO Ramagundam Karimnagar 1 x 62.5 62.5 18°43′31″N79°30′47″E
Kothagudem Thermal Power Station
APGENCO Paloncha Khammam 4 x 60, 4 x 120
720 17°37′18″N80°41′15″E
Kothagudem Thermal Power Station V Stage
APGENCO Paloncha Khammam 2 x 250 500 17°37′24″N80°42′06″E
Dr Narla Tatarao TPS
APGENCO Ibrahimpatnam Krishna 6 x 210, 1 x 500
1760 16°35′58″N80°32′12″E
Rayalaseema Thermal Power Station
APGENCO Cuddapah YSR 4 x 210 840 14°42′14″N78°27′29″E
Kakatiya Thermal Power Station
APGENCO Chelpur Warangal 1 x 500 500 18°23′02″N79°49′42″E
9
INTRODUCTION TO KTPS
With a concern of increase in demand for electrical energy
in INDIA, to meet the required demand for energy in Andhra
Pradesh Kothagudem Thermal Power Station (KTPS) was
established extending wide electrical network in the state in
the year 1966.
Under Japanese collaboration KTPS was established in
1966 with an initial capacity of 120 MW (2 X 60 MW) and then
in the 1967 it was extended to 240 MW (4 X 60 MW) which is
popularly known as KTPS-A station. The highlight point is, this
is one of the oldest power plants in the world under Japanese
collaboration. It is not exaggerating to quote that engineers
from Japan still attend here for case study and update their
report for their future investments. Station A consists of four
units, popularly called as 1st, 2nd, 3rdand 4th units of KTPS with
each unit capable of generating a power of 60 MW. In due
course of time the total A-station got Indianized.
In the view of progress later in the year 1974 KTPS-B
station came in to existence with a initial capacity of 220 MW
(2 X 110MW). But later these units were upgraded to 120 MW
each with total production increased to 240 MW (2 X 120MW)
in B-station itself. The two units in this B-station are popularly
called as 5th and 6th units.
10
Successfully running on the track of development KTPS-C
station came on to the screen in the year 1977 with a capacity
of 110 MW (1 X 110 MW) and with in no time production was
extended to 220 MW (2 X110 MW) in the year 1978. Later the
total production of C-station was successfully upgraded to 240
MW (2 X 120 MW). These two units are called 7th and 8th units
of KTPS.
In due course of development a new stage of power plant
has been constructed with larger capacity turbines capable of
producing 250 MW in the year 1998. Two such turbines are
being installed in this station popularly called as KTPS-5th stage.
Total production capacity of 5th stage is 500 MW (2 X 250 MW).
Now recently the proposal of KTPS-6th stage is successful.
The estimated capacity is 500 MW (1 X 500 MW). This was
thought to be synchronized with the grid by March 31st, 2011.
This observed to be successfully running.
11
A Tabulated view of Production in different units of KTPS
Stage Unit
Number
Installed Capacity
(MW)
Date of Commissioning
Status
Station A 1 60 04-07-1966 Running
Station A 2 60 27-11-1966 Running
Station A 3 60 27-05-1967 Running
Station A 4 60 08-07-1967 Running
Station B 5 110 13-08-1974 Uprated to 120 MW
Station B 6 110 19-12-1974 Uprated to 120 MW
Station C 7 110 10-03-1977 Uprated to 120MW
Station C 8 110 10-01-1978 Uprated to 120 MW
12
Stage Unit
Number
Installed Capacity
(MW)
Date of Commissioning
Status
5th stage 9 250 27-03-1997 Running
5th stage 10 250 28-02-1998 Running
6th stage 11 500 2011 Running
The station has been the recipient of many prestigious
awards from various organizations including Meritorious
awards instituted by the government of India. The station has
received Meritorious productivity awards for nine times and
Incentive award for eight times.
For the 5ht stage the station has received the meritorious
productivity award for four consecutive years (1999-2000,
2000-01, 2001-02, 2002-03) by the government of India. The
station has received Meritorious productivity awards for nine
times and Incentive award for eight times.
13
IN TO THE WORKING OF PLANT
BASIC PRINCIPLE INVOLVED IN WORKING:
The basic principle involved is Faraday’s law of electro-
magnetic induction i.e. “whenever a conductor cuts a
magnetic flux emf is induced across its ends”.
BASIC IDEA OF OPERATION:
The very first thing we need to provide is a conductor
cutting magnetic flux. So this can be done in two basic ways i.e.
either the conductor can be moved in the magnetic field or the
field can be varied according to the required emf that is to be
generated. The process we follow here is we rotate the rotor of
a generator in the magnetic field and emf is generator at the
stator and this generated emf is further utilized according to
the purpose.
To meet the purpose of rotating the rotor of a generator,
the rotating shaft is in turn connected to a turbine which is
made to rotate at a rated speed by an external energy source.
So we need an energy source to rotate the turbine. To rotate
the turbine energy must be transferred from a medium to the
turbine so that energy from the external source is converted to
rotational energy of turbine.
In general to rotate an object which is mounted we need
to apply some torque. To produce torque we need to apply
14
force in the tangential direction. For the purpose of application
of force we chose steam as a medium of transfer. For hydel
plants water is directly allowed from a very great height to
collide with the turbine blades with a great force.
In the same way we need to send the steam with a greater
force in turn with a greater pressure to make the turbine
rotate. The basic physics involved in this is the internal energy
and enthalpy of the steam gets converted to mechanical energy
that rotates the turbine.
Our target is to produce steam at a very high pressure.
Pressure of the steam can be increased by various auxiliaries
through different mechanisms. So basically we need to produce
steam. For the production of steam water is to be heated to
high temperatures with the help of available fuel. Combustion
of fuel is done and evolved heat is utilized for production of
steam.
Total idea is to be implemented in a highly efficient way to
balance the finance and economy. Environmental protection
should also be the point of concern because burning of fuel
may evolve gases which are responsible for harmful effects that
distract our ambience.
15
BASIC REQUIREMENTS:
Fuel
Water
Heating system
Steam circuit
Regenerating system
Steam turbine
Generator
Transformer
NOTE: ANY INFORMATION DISCUSSED FROM NOW ONWARDS
IS MAINLY CONSERNED TO KTPS-‘B’ STATION
FUEL:
The available fuel for us is COAL. Coal is transferred in
lump sum from nearby coal mines popularly called as
SINGERENI COLLARIES through wagons.
16
COAL HANDLING PLANT (CHP)
Daily 3 racks of coal will be transferred to the plant. Each
rack consists of 56 wagons each carrying coal around 60 tonnes.
E-grade and F-grade coal is being transferred to plant
whose calorific value varies in between 2700-3600 K.Cal/Kg.
WAGON TIPPLER:
The coal received from the collieries, is more than 100 rail
wagons a day, is unloaded mechanically by two ways, wagon
tipplers out of which one serves as a standby. Each loaded
wagon is emptied by tippling it in the underground coal hopper
from where the coal is carried by conveyor to the crusher
house. Arrangements have been provided for weighing each
rail wagon before and after tippling. Each tippler is capable of
unloading 6-8 rail wagons of 55-60 tonnes capacity in an hour.
CONVEYOR BELT:
It is a normal rubber belt carrying the coal from one place
to the other in the course of processing. The belt runs at a
speed of 2.5 m/s with the help of a induction motor in
connection with a speed reducing gear.
MAGNETIC PULLEYS:
17
On belt conveyor no. 4A and 4B, there have been provided high intensity electromagnetic pulleys for separating out tramp iron particles/pieces from the main stream of coal conveying. D.C. supply for the magnet is taken on 415 volt, 3phase, 50 cycles A.C. supply system. In addition to above high intensity suspension type electromagnets have also been provided on belt conveyors 4A and 4B for separating out tramp iron pieces/particles. CRUSHER HOUSE: The unloaded coal is dragged on to mesh with slots of size “300 X 300” mm2 with the help of dozers. The filtered coal through mesh is carried through conveyor belts to hoppers from where coal is sent to crushers.
Two nos. hammer type coal crushers are provided, which can crush coal to a size of “25 X 25” mm2. The crushed coal is then supplied to Boiler Raw Coal Bunkers (RC Bunkers). The surplus coal is carried to coal storage area by series of conveyors. Crushing of coal is an essential requirement for its optimum pulverizing and safe storage.
NOTE: To be on safe side coal required for one month will be
kept in reserve condition in the yard, the storage yard and the
raw coal is required for one day is kept in reserve condition in
the RC bunkers.
18
COAL MILLING PLANT
Raw Coal Bunkers (RC Bunkers)
Raw Coal Chain Feeders
Drum Mills or Coal Mills
Classifier
Cyclone Separator
Vapour Fan
Pulverized Cola Bunkers (PC Bunkers)
RAW COAL BUNKER: Each of three raw coal bunkers is fabricated from the sheet metal and is well stiffened all around. The storage capacity of each raw coal bunker is about 500 tones. There are four outlet gates with each bunker. The gates are electrically operated from site. In case of failure of the electric motors the gate can be hand operated from site. At a time only one gate opening is suffices but should be changed so that there is no pilling within the bunker.
19
RAW COAL CHAIN FEEDER:
The raw coal chain feeder transports coal from raw coal
bunker to the inlet chute leading to the pulverized/coal mills. There is a double link chain of high tensile strength steel, which moves on wheels and sweeps the raw coal falling over the top of the raw coal chute of the mill. The height of the coal bed in the chain feeder can be adjusted manually by means of lever operated damper.
The maximum and minimum heights of the coal bed are 200mm and 120mm respectively. The signaling equipment indicates the absence of coal flow in the feeder, which is annunciated in the unit control board (U.C.B.). The main shaft on the driving end is connected to the driving unit, consisting of variator, a gear box and a motor all mounted as a single unit. The chain wheel on the driving end shaft is provided with a shear pin, which will shear off and disconnect the driving mechanism if there is any overload on the feeder.
The speed of the chain feeder is regulated automatically/remotely by actuating the control spindle of the variator through a servomotor. A pump for circulating the oil in
20
the gear box of variator is an integral part of variator driven by a separator motor. Some of the technical data about the raw coal chain feeder is given here:- 1. Output of the chain feeder 10-45 tonnes/hr. 2. Speed variations 0.0503-0.151m/sec. 3. Main motor 7.5kW, 415V, 50Hz. 4. Oil pump motor 0.05kW, 220V 5. Operating motor of each gate 3HP, 415V and 50Hz.
We can change the quantity of coal which is fed to mill in two ways. -> By changing the speed of chain -> By changing the depth of coal in chain Speed of chain can be changed by adding a gear system to motor. We connect the gear system with motor with a pin called shear pin. This prevents the overloading of motor because when the coal quantity of coal on chain is greater than its capacity then the pin will break and prevent the pin from overloading. Speed of Raw Coal chain is 2” to 6”/sec. DRUM MILL:
Each mill consists of single compartment drum, bearings driving motor, coal inlet and discharge piping, ball change and lubricating equipment for mill bearings. Mill drum is fabricated from thick steel plates and is supported on to the anti-friction bearings. The mill is driven by an electric motor of capacity 630kW, 990 rpm, and 6.6kV through a reduction gear, which reduces the speed to 17.5 rpm.
21
Picture of Ball Mill or Coal Mill:
The ball charge for the mill consists of the three different
sizes of forged steel balls detailed as below. The capacity of each mill is 36.7 T/hr. 1. 40mm diameter 22500 kg 2. 50mm diameter 20000kg 3. 60mm diameter 10000kg 4. Total Ball Charge 52500kg
During operation only 60mm diameter balls are added is
approx. 500 kg per week and the guiding factor is the amperage of the coal mill, normally it should be 66-ampere approx. at full
22
load and when it falls below the above value ball charging of the mill is carried out. Lubricating system consists of the oil tank, gear pump, oil cooler and base frame to mount all these equipments.
Gear pump is driven by an electric motor of rating 1 H.P., 415 V, 1440 rpm. Suction side of the gear pump is connected to the tube oil tank and the delivery side is connected to inlet of the oil cooler and after cooling oil goes to the bearings. The oil from the bearings is cooled to the required temperature in the cooler by the means of plant bearing cooler water.
CLASSIFIER: The classifier is fabricated from the steel plates. It is the
equipment that separates fine pulverized coal from the coarser pieces. The pulverized coal along with the carrying as well as drying medium (flue gas) strikes the impact plate in the classifier and the coarser pieces get separated due to the change in the direction of flow and go back to mill. The stream then passes to the outlet branch of the classifier through an adjustable telescopic tube. At the outlet adjustable vanes are provided to change the size of coal when required. CYCLONE SEPARATOR:
The centrifugal type cyclone separator consists of two cyclones made up of welded sheets. It is equipment in the milling plant, which serves for separating the pulverized coal from the vapours i.e. carrying medium. The pulverized coal gets stored in the pulverized coal bunkers and vapours go to suction of vapour fan. At the bottom of the cyclone separator a rotary
23
valve (Trinket) is provided to transport coal from cyclone separator to P.C. bunker on the worm conveyor as the case may be. VAPOUR FAN: Pulverized coal from the cyclone separator is carried to the PC bunkers by the vapour fan. This is just a suction fan for carrying light coal particles. For this purpose a 3 Phase induction motor is used. Voltage applied 6.6 KV Rating 400 KW RPM 990 Current 44 amps PULVERIZED COAL BUNKERS (PC BUNKERS): After complete pulverizing of coal in to fine powder and separation of fine coal particles from coarse particles the final fine powder is sucked through vapour fan in to storage hoppers called PC Bunkers. From here coal is directly sent to furnace for combustion. NOTE: The actual need for pulverization of coal before sending it to furnace is combustion of powdered coal is more efficient than normal sized coal particles. So finer the particle is higher is the efficiency of combustion. So more is the combustion less is the evolution of poisonous gases like CO and less is the pollution and more is the energy collected.
24
PRIMARY AIR FAN:
The pulverized coal can directly be supplied to the boiler
furnace for combustion with the help of primary air fan
popularly called as “PA FAN”. The temperature of the coal is
maintained with the help of hot air stream supplied by the PA
fan.
25
MOTOR 3 Phase Induction Motor
400 KW, 900 RPM, 6.6 KV, 44 amps
Capacity 33 m3/ s
Suction Double
WATER:
Next basic requirement water is available in lump sum
from “KINNERASAANI RESERVOIR”. Kinnerasani is a tributary
for river Godavari. A reservoir was constructed across this
tributary from where water flows by gravity(due to difference
of height in ground level) to KTPS reservoirs.
During the construction of A-Station reservoir with
capacity of 120 Lakhs Gallons was constructed. Later for B-
station 2 reservoirs each with a capacity of 60 Lakhs Gallons
was constructed.
Even from here water flows to clarifier naturally by gravity.
26
WATER HANDLING SYSTERM
CLARIFIER:
Water from reservoir is directly filled in to ALUM
TANKS in which raw water is treated with ALUM for
precipitating mud. Chlorination of water is also done here to
remove different bacteria and algae present in the water. With
the help of Central Fraculator mud in the water gets separated
along with some amount of water and remaining clarified water
is pumped towards De-Mineralizing plant through Booster
Pumps.
DE-MINERALIZING PLANT:
Here water is sent through a series of sand filters to
remove any impurities present. Now-a-days carbon filters are
also used for this purpose. In the next step water is sent
through a CATIONIC EXCHANGE RESIN for the removal of any
metal cat ions. Now water is passed through DE-GASIFIER TANK
to remove the trace of CO2 whose output is connected to a tank
containing ANIONIC EXCHANGE RESIN for removal of non
metallic anions. As a final step this water is sent through
another tank containing both the resins called mixed beds.
From here water is sent to units for supplying to the boiler to
produce steam.
27
28
NOTE: THE MAIN REASON FOR DEMINERALIZING WATER IS TO
PREVENT THE DAMAGE IF PIPE LINES CARRYING STEAM, TO
PREVENT THE DAMAGE OF BOILER DRUM AND TO PREVENT
THE DAMAGE OF TURBINE BLADES.BECAUSE OF PRESENCE OF
SALTS IN WATER SCALES ARE FORMED ON THE PIPE SURFACE
AND DRUM SURFACE.THIS MAY DAMAGE PIPE AND
DRUM.EVEN THE BLADES OF THE TURBINE ARE ALSO
EFFECTED BY THIS.SO TO PREVENT DAMAGE AND CORROSION
WATER NEED TO BE DEMINERALIZED.
29
WORKING OF THE BOILER
Generating and maintaining fire:
Generation of fire is done with the help of oil and lighters.
Oil is sprayed from four corners of the furnace with the help of
oil guns and lighters at four ends of the furnace release sparks.
This sparks make the oil to catch fire. Now coal is carried from
PC Bunkers with the help of PA Fan. Cola is kept hot i.e. at a
temperature around 70oC for effective burning of coal. This
temperature is maintained with the help of hot air from PA fans
and secondary air.
Coal is released from four diagonal corners of the boiler
continuously to maintain the temperature through PC injectors.
In case of drop of temperature at any corner more amount of
coal is dropped at that end through adjustment in the valve
system. The temperature in the furnace will be around 1500oC.
For the coal to be burnt effectively oxygen should be
supplied uninterruptedly. For this FD fan is engaged.
FORCED DRAUGHT FAN:
This fan sucks air from the open atmosphere and supplies
it to the boiler furnace for effective combustion of coal. As the
open air contains 21% of oxygen this fan helps for combustion.
Capacity 62 m3/sec
30
16V control
3 Phase induction motor
400 KW, 6.6 KV, 990 REM and 44 amps.
Generating and processing steam:
Water from DM plant is fed to the pipes that are in contact
with the walls of the furnace. Heat evolved from the burning of
coal in the furnace is utilized to convert water in to steam.
Steam obtained here will be at a temperature of 350o C and at a
pressure around 140 Kg/cm2. This is fed to boiler DRUM where
an interface separates water and steam. The upper part of the
drum is filled with steam which is wet in nature and the down
part with water from Boiler Feed Pump (BFP).
But this steam will be wet in nature because of presence
of moisture in the steam. This is called wet steam. So, to make
it dry this steam is passed through SUPER HEATER COILS to
produce dry steam. Temperature of dry steam is around 540o C
and a pressure of 140 Kg/cm2.
Water from the drum is sent around the furnace and is
converted to steam (wet) and brought back to boiler drum.
Again from here it is sent to superheated coils to produce dry
steam and the process continues.
31
STEAM WITH THE TURBINE
To generate EMF the rotor of the generator need to be rotated
which in turn is operated by a shaft which is rotated with the
help of three turbines.
HIGH PREESSURE TURBINE (HP TURBINE)
INTERMEDIATE /MEDIUM PRESSURE TURBINE (IP
TURBINE)
LOW PRESSURE TURBINE
Each turbine has its own operating temperature and pressure.
Steam from the super heater coils is fed directly to the HP
turbine at a temperature of 540o C and a pressure around
140Kg/cm2. The enthalpy of the steam gets converted to
mechanical energy which makes the turbine to rotate. From the
law of thermodynamics “a perpetual motion machine of second
kind doesn’t exist”, heat energy cannot be completely
converted to work. So some amount of energy still remains in
the steam.
To re-utilize this energy this steam is made to interact with
another turbine called Intermediate/Medium Pressure
Turbine. Before making them to interact the outlet steam from
the HP turbine is sent back to furnace and reheated through
reheater coils .This is a part of regenerative system for efficient
utilization of heat energy. Steam from reheater coils is fed to IP
32
Turbine. Again from second law of thermodynamics some
amount of energy still remains in the steam.
The outlet steam from the IP Turbine is directly fed to LP
Turbine where maximum amount of energy is expected to be
utilized. The outlet steam of the LP Turbine contains very low
amount of energy as it is already used for 3 times with 3
different turbines this cannot be used for regeneration. So this
steam is allowed for condensation.
Turbine Lubricating Oil System:
Turbine lubricating-oil system seeks to provide proper
lubrication of turbo-generator bearings and operation of
barring gear.
The recommended working medium for governing and
lubrication system of the turbine is Turbine oil-14 of INDIAN OIL
COMPANY.
OIL SPECIFICATION:
1. Specific Gravity at 50”C 0.852
2. Kinematic Viscosity at 50”C 28 centistokes
3. Neutralization number 0.2
4. Flash Point 201”C(min)
5. Pour Point -6.6”C(max)
6. Ash % by Weight 0.01%
7. Mechanical Impurities Nil
33
The Turbine Lubricating oil system mainly consists of
Main Oil Pump (MOP)
Starting Oil Pump (SOP)
AC standby Oil Pumps
emergency DC oil pump
Jacking oil pump (JOP) (1 per UNIT) .
Main Oil Pump is used for the Lubrication system. It is
coupled with turbine rotor through a gear coupling and is used
when the turbine is running at normal speed (3000 rpm) or
greater than 2800 rpm.
Starting oil pump is a multi-stage centrifugal pump driven
by A.C electric motor. It is provided for meeting the
requirement of oil of the turbo-set during starting or stopping
and also as standby to maintain centrifugal oil pump.
Standby oil pump is a centrifugal pump by an A.C electric
motor, this runs for 10 min in the beginning to remove air from
the governing system and fill the oil system with the oil.
Emergency Oil Pump is a centrifugal pump driven by D.C
electric motor. This automatically cuts in whenever there is a
failure of A.C supply at POWER STATION and or the pressure in
lubrication system falls.
34
Jacking Oil Pump enable the main bearing of the complete
rotor assembly to be raised or floated in the bearing during
turbine generator start up and during shut down.
Oil Coolers:
The oil of the lubrication and governing system is cooled in
the oil coolers. Circulating water is used as the cooling medium
for these oil coolers.
5 oil coolers are available at the plant, out of which 4 are
for continuous operation and one remains as standby.
Steam turbine as prime mover:
The steam turbine offers many advantages over other
prime movers, both thermodynamically and mechanically.
From a thermodynamic point of view the main advantage
of steam turbine over say a reciprocating steam engine is that
in the turbine the steam can be expanded down to a lower back
pressure there by making available a greater heat drop, If a
reciprocating steam engine is to expand the steam down to a
back pressure of the order of an inch or two of mercury and the
low pressure cylinders would have to be a very large to deal
with large volume of steam resulting from these pressures.
From a mechanical point of view the turbine is ideal
because the propelling force is applied directly to the rotating
element of the machine and has not as in the reciprocating
35
engine to be transmitted to a system of connecting links which
are necessary to transform a reciprocating motion into a rotary
motion.
If the load on the turbine is kept constant that are
developed at the coupling is also constant. A generator at a
steady load offers a constant torque. Therefore a turbine is
suitable for driving a generator, particularly as they are both
high speed machines.
A further advantage of the turbine is the absence of
internal lubrication. This means that the exhaust steam is not
contaminated with oil vapour and can be condensed and fed
back to the boilers without passing through filters.
Steam cycle:
The steam plant uses a dual (vapour + liquid) phase cycle.
It is a closed cycle to enable the working fluid (water) to be
used again and again. The cycle used is “RANKING CYCLE”
modified to include super heating of steam, regenerative feed
water heating and reheating of steam.
36
CONDENSOR:
The outlet steam of the LP Turbine is sent to condenser
where steam is passed through pipe lines and cool water is
allowed to be in contact with these pipes. Because of the heat
exchange between steam and cool water steam gets converted
to water and stored in HOT WELL.
HOT WELL:
Water from the condenser pipes are pumped in to a
sump called HOT WELL. Water in this well is around 50o C. From
here water will be sent to cooling towers for cooling.
37
COOLING TOWERS:
From hot well water is sent to cooling towers for the
purpose of cooling. Here water will be taken to an elevation of
10-12 mts. and allowed to fall freely. Water is allowed to fall at
different points. At each and every falling point sprinkling
mechanism is arranged. At every small depth a grill
arrangement is fixed to collide with the water droplets falling
freely. A scale like arrangement is fixed at every small depth.
This is done because to make the water droplets to collide with
these grills and to decrease the size of the water droplets.
So smaller is the water droplet faster will be the heat
exchange with the medium in which it is present. As heat is
being evolved from every droplet of water some droplets of
38
water may absorb the heat. This makes some water droplets
increase their temperature rather than cooling. The heat
exchange takes place in such a way that the temperature
crosses its boiling point an even latent heat is also absorbed
converting water droplets to vapour.
This vapour is allowed in to the atmosphere at greater
heights. So in cooling towers water gets cooled and gets
converted to vapour too. To allow vapour in to free atmosphere
at greater heights vapour needs to be carried to greater
heights. Rather than spending energy to carry the steam to
greater heights some civil engineering techniques are applied in
construction of cooling tower.
The construction of cooling tower involves basic laws of
fluid mechanics. The walls are hyperbolic in shape following
SIPHON mechanism. These are also called HYPERBOLIC
NATURAL DRAUGHT COOLING TOWERS. Once vapour is left to
the atmosphere forcibly in the beginning the process continues
by itself until the vapour terminates which doesn’t happen
because vapour continuously emits.
This is called Natural Draught. The other mechanism that
can be followed is Forced Draught & Induced Draught in which
fans are arranged and vapour is sent out forcibly.
NOTE: KEEP IT IN MIND THAT WATER COOLED IN TOWERS IS
DEMINERALIZED WATER.SO THIS WATER SHOULD NOT BE
39
LEFT FREE OR WASTED.THIS WATER CAN BE USED AGAIN TO
PRODUCE STEAM AND RUN THE TURBINES.AS PROCESS OF
DEMINERALIZING WATER IS VERY COSTLY, THIS WATE IS USED
AGAIN.
Water from cooling tower is sent to condensate sump.
From here water is heated through a series a heaters called LP
heaters and HP heaters.
LP Heater is a heater which heats the water with the help of a
tapping from the steam line going to the LP Turbine. A series of
such LP Heaters are employed to increase the temperature. The
out let of LP Heater is fed to the Deaerator.
DEAERATOR:
Deaerators are mechanical devices that remove dissolved
gases from boiler feed water. Deaeration protects the steam
system from the effects of corrosive gases. It accomplishes this
by reducing the concentration of dissolved oxygen and carbon
dioxide to a level where corrosion is minimized. A dissolved
oxygen level of 5 parts per billion (ppb) or lower is needed to
prevent corrosion in most high-pressure (>200 pounds per
square inch) boilers. While oxygen concentrations of up to 43
ppb may be tolerated in low-pressure boilers, equipment life is
extended at little or no cost by limiting the oxygen
concentration to 5 ppb. Dissolved carbon dioxide is essentially
completely removed by the Deaerator.
40
Deaerators use steam to heat the water to the full saturation
temperature corresponding to the steam pressure in the
Deaerator and to scrub out and carry away dissolved gases.
The outlet of the Deaerator is fed to the BOILER FEED PUMP
BOILER FEED PUMP:
As the heart is to human body, so is the boiler feed pump to the steam power plant. It is used for recycling feed water into the boiler at a high pressure for reconversion into steam. Two nos. 100% duty, barrel design, horizontal, centrifugal multistage feed pumps with hydraulic coupling are provided for each unit. This is the largest auxiliary of the power plant driven by 3500 KW electric motor.
The 120 MW turbo set is provided with two boiler feed pumps, each of 100% of total quantity. It is of barrel design and is of horizontal arrangement, driven by an electric motor through a hydraulic coupling.
41
Type 200 KHI Delivery capacity 445 t/hr. Feed water temperature 158°C Speed 4500 rpm Pressure at suction 8.30 kg/cm2 Stuffing box mechanical seal Lubrication of pump by oil under pressure Motor bearing supplied by hydraulic
coupling Consumption of cooling water 230 L/min. The outlet of BFP is around 140 Kg/cm2. This is fed to HP Heaters. HP Heater is a heater that heats the outlet of BFP with the help of a tapping from the steam line of HP Turbine. A series of such HP Heaters are employed and then finally its outlet is fed to ECONOMISER in the furnace. ECONOMISER: It is a part of regenerative system for efficient utilization of heat energy from the furnace. Steam from HP Heater is fed to the economiser tubes. Here steam gets heated up to 350o C. the outlet of economiser is fed to the boiler drum. In the boiler drum steam and water gets separated and steam is sent to super heater coils and same process repeats as explained earlier.
42
REGENERATIVE SYSTEM: It is a designed loop for effective utilization of energy to increase the efficiency of the process. In general furnace is meant to produce the steam from water. But total energy evolved from combustion of coal is excessive for this. So this heat energy from the furnace is repeatedly utilized wherever necessary through
SUPER HEATER COILS
REHEATER COILS
ECONOMISER
43
HANDLING OF ASH
After combustion of coal ash will be remained in the furnace. Handling of ash is the major problem for any thermal power plant. In the bygone ash was dumped at a far place, because of this a lot of land is being wasted.
In general two types of ashes need to be handled.
Bottom Ash
Fly Ash Bottom Ash is collected at the bottom of the furnace in the hoppers provided. The ash deposited at the bottom of the furnace is collected in a water impounded hopper where a continuous flow of water is maintained to limit the temperature of ash inside the hopper. The bottom ash cleaning is done in every cycle of 8 hours. The bottom ash system is local manually operated. On opening of feed gate ash is allowed to discharge into a double roll Linder grinder where it is grounded to smaller size, which can be transported through the pipe line below the linker grinder there is a venturi which sucks the ground ash the vacuum created at the venturi throat by the flow of high pressure water tapped. Dawn stream of the discharge of the ash water pumps. The pressure recovered at the end of venturi is adequate to convey the slurry to disposal area. Fly Ash is collected with the help of a fan called induced draught fan.
44
INDUCED DRAUGHT FAN: Two nos. axial flow Induced Draught Fans are provided for
each unit to exhaust ash laden flue gases from boiler furnace through dust extraction equipment and to chimney. The fan is driven by an electric motor through a flexible coupling and is equipped with remote controlled regulating vanes to balance draught conditions in the furnace. The fan is designed to handle hot flue gases with a small percentage of abrasive particles in suspension. This fan sucks the ash [particles from the mouth of the furnace to the chimney passing through the electrostatic precipitators. 3 phase induction motor 800 KW ELECTROSTATIC PRECIPITATORS: Particles travelling due to the effect of ID fan are made to
enter in to ESP’s. In this section those particles are made to
travel in between two plates with a potential difference of
40KV (DC Voltage is applied). The positive and negative ions
formed by the burning of coal are precipitated here. At regular
intervals these plates were hit by the hammers so that
precipitated ions get separated from the plates in the form of
powder. This powder is the byproduct and can be sold. This is
used by the cement industries.
45
The un-precipitated particles are carried away by the ID
fan in to the chimney.
CHIMNEY:
Finally, the un-precipitated particles are left to the
atmosphere from a greater height, nearly twice the height of
cooling tower. The construction of chimney is also done in the
same way as cooling towers. Walls are hyperbolic in nature
following the SIPHON mechanism with a natural draught outlet.
46
GENERATING POWER:
We have gone through the process how steam is
generated and interacted with turbine. As we have discussed
the 3 turbines rotate a single shaft at a rated speed of 3000
RPM. This shaft is in turn connected to a TURBO GENERATOR
which can generate an EMF of 11 KV.
Generator Components :
Rotor :
The electric rotor is the most difficult part of the generator
to design. It revolves at a speed of 3,000 rpm hence high care
has to be taken during its design. The passage of current
through the windings generates heat but high temperature
results in insulation problems. To keep the temp down rotor
cross section has to be reduced but that results in mechanical
weakness of the rotor. Hence it has to be designed such that it
carries more current at the same time it is mechanically strong.
This can be achieved with good design and great care in
construction.
The rotor is a cast steel ingot, and it is further forged and
machined. A hole is bored through the centre of the rotor
axially from one end to other for inspection. Slots are then
machined for windings and ventilation.
47
Rotor Windings:
Silver bearings copper is used for the winding with mica as
the insulation between conductors. The designs of large rotor
windings incorporate combination of hollow conductors with
slots or holes arranged for circulation of cooling gas. To prevent
the windings from flying off away at high speeds due to
centrifugal force wedges are provided. The two ends of
windings are connected to slip rings.
Rotor Balancing:
To provide mechanical balance for the rotor , so that it
rotates without vibrations arrangements have been made in all
designs to fix adjustable balance weights around the
circumference at each end.
Stator:
Stator comprises of an inner frame and an outer frame.
The outer frame is a rigid fabricated structure of welded steel
plates, within this shell is a fixed cage of grinder built circular
and axial ribs. The hydrogen for cooling of stator flows through
these ribs.
The inner cage is usually fixed in to the yoke by an
arrangement of springs to dampen the double frequency
vibrations present in 2 pole generators.
48
Stator Windings:
Each Stator conductor must be capable of carrying the
rated current without overheating. The insulation must be
sufficient to prevent leakage currents flowing between the
phases to earth. On recent generators the windings are made
up from copper tubes instead of strips through which water is
circulated for cooling purposes. The water is fed to the
windings through plastic tubes.
EXCITATION SYSTEM:
The excitation system of a generator consists of :
The main exciter
The pilot and auxiliary exciters
The voltage control system
Development Of excitation system:
Initially the dc excitation system was being used. The
development of improved techniques resulted in the increased
capacity of generators which in turn raised demand of
excitation power. But it found that dc excitation could not meet
the demands of large capacity turbo-generators due to
following reasons.
High excitation currents at comparative low voltage were
required and these would entail a large number of brushes
49
operating on exciter commutator. This will create difficulties in
operation and will require extensive maintenance of
commutator and brush gear.
The other disadvantage of dc exciter is that commutator
may be satisfactory during steady state during load fluctuations
there is a risk of flash over at the commutator. The maximum
peripheral speed of commutator for proper operation should
not be more than 45 meters per second.
Reliability is one of the main requisites of excitation
system of the generator. This accelerated development of AC
excitation system, where AC generator along with rectifier
system is used for field excitation.
DC EXCITATION SYSTEM:
Direct current exciters are shut wound machines and
compounding can be included to improve response. The open-
circuit characteristics and basic diagram of a self excited
compound shut wound exciter are shown in the following
figure. It is important to note that the unstable voltage region
HB on open circuit characteristics of the exciter. Since OE is the
excitation current when voltage BE is across the shunt field
BE/OE is the value of the critical resistance of the circuit. The
line of this critical resistance coincides with slope of voltage
characteristic. Therefore, the voltage is indefinite and can vary
freely between the value due to exciter permanent magnetism,
50
and value B the voltage due to field current OE. Even small
temperature increases in the field winding will contribute to
voltage instability. A method of overcoming this effect is to
insert a saturation liner behind each pole piece. Because of
reduced magnetic section the liner is saturated much sooner
than the pole body, thereby
it
introducing the required non-linearity in the open-circuit
characteristic. One adverse effect of the saturation line
however, is to depress the ceiling voltage of the exciter.
51
Basic schematic diagram of DC excitation system
Exciter field windings can compromise two or three
separate windings. The main field winding are often duplicated
to provide parallel current paths to reduce contact wear and
field rheostat wear.
The provision of a negative field gives a negative bias in
the exciter by which response is improved when load is thrown
off. It also improves the lowering response of the exciter
system following as external fault clearance and reduces the
range of main exciter field current needed for a given change in
exciter voltage. But this negative field constitutes a constant
load on pilot exciter and necessitates a more powerful positive
main field than would be the case without negative bias. These
disadvantages are justified. However, on the ground of improve
52
exciter performance, it should be noted that negative excitation
like this cannot be achieved in present AC exciter systems.
AC excitation system:
The AC exciter for large units gained favor because it was
possible to use 2 or 4 pole revolving field type machines
possessing all the robustness associated with the generator.
Commutator and DC brush gear were eliminated giving place to
the simple rotor slip-rings and associated brush gear. A pilot
exciter is a necessary part of the ac exciter system. It is
common practice to have pilot exciter, itself an ac machine. The
pilot exciter can also be a permanent magnet generator. It must
operate over a wide range with ceiling valves considerably
greater than the rated full load valve. Furthermore the exciter
output must respond quickly to excitation changes at its own
rotor terminals. The excitation is controlled by the AVR. The
excitation for pilot exciter is obtained from a permanent
magnet of exciter where output is rectified. The pilot output,
which excites the field of AC main exciter, is controlled by
automatic voltage regulator. The rectified output of main
exciter then energies the rotor of the synchronous generator. In
main exciter the AC supply can be taken from the grid or
generator itself rectified and given to the generator field. This is
called Static Excitation.
53
Bsic schematic diagram of AC excitation system
Generator Cooling & Sealing System
The 120 MW Generator is provided with an efficient
cooling system to avoid excessive heating and consequent wear
and tear of its main components during operation.
Rotor Cooling System:
The rotor is cooled by means of gas pick up cooling. The H2
gas in the air gap is sucked through the scoops on the rotor
wedges and is directed to flow along the ventilating canals
milled on the sides of the rotor coil. Due to rotation of the
rotor, a +ve suction as well as discharge is created due to which
a certain quantity of gas flows and cools the rotor.
54
H2 Cooling System:
Hydrogen is used as cooling medium in large capacity
generator due to its high capacity of heat carrying and low
density. But in view of its forming an explosive mixture with
oxygen, proper sealing system has to be provided and see that
there is no escape of hydrogen from the generator. Mainly oil
sealing is used to seal hydrogen.
Stator Cooling System:
The stator winding is cooled by distillate which is fed from
one end of the machine by Teflon tube and flows through the
upper bar and returns back through the lower bar of another
slot. Turbo-generators require both water cooling arrangement
as well as hydrogen cooling steam .The cooling water is used
for cooling of stator winding , hence high quality water(de-
mineralized water) is used for its cooling.
Generator Sealing System:
Seals are employed to prevent leakage of hydrogen from
the stator at the point of rotor exit. A continuous film between
the rotor collar and the seal liner is maintained by means of the
oil at a pressure which is about to start above the casing
hydrogen gas pressure, which is regulated in relation to the
hydrogen pressure and provides a positive maintenance of the
oil film thickness.
55
This 11 KV voltage is stepped up or stepped down using
different type of transformers.
TRANSFORMERS:
Different types of transformers are used for stepping up and
stepping down the generated voltage either for supplying to
the grid or for self utilization.
GENERATOR TRANSFORMER
UNIT AUXILIARY TRANSFORMER
STATION TRANSFORMER
GENERATOR TRANSFORMER: (GT)
Generated 11 KV is stepped up to 220 KV using generator
transformers for transmitting to the grid through the switch
yard. The 11 KV voltage is stepped up for transmitting because
to reduce I2R losses. If voltage is maintained high then current
is maintained low since the produced power remains constant.
If current is low then I2 is low and loss of power is low.
The produced power is in AC 3 Phase, so we need 3 Phase
transformer to step up or step down.
56
3Phase 11 KV / 220 KV TRANSFORMER.
Manufacturer BHEL
UNIT AUXIALIARY TRANSFORMER: (UAT)
We have seen that many motors need to be run in the
plant such as ID, FD, PA fans etc. and for the internal needs of
the plant power is needed. So rather than collecting the power
from the grid 10% off the produced power is self utilized by the
57
plant. For this purpose produced 11KV is stepped down to 6.6
KV using UAT.
This 6.6 KV is fed to different motors as per requirement
and for remaining purposes this voltage is again stepped down
to required levels.
STATION TRANSFORMER: (ST)
This is also a step down transformer 220 KV / 6.6 KV. The
primary of the transformer is directly connected to the 220KV
bus from the grid through the switch yard and is stepped down
to 6.6 KV. This is a safety transformer i.e. keeping in the view
that if there is some problem with UAT’s and the system getting
failed by chance the required power is collected directly from
the grid and is stepped down for plant requirements so that
there is no obstacle for power production.
58
KTPS SWITCH YARD
INTRODUCTION:
An electrical substation is an assemblage of electrical
components including bus bars, isolators, circuit breakers,
transformers, lightning arresters, instrument transformers, etc.
Electric power between incoming and outgoing circuits, in
substation takes place through bus bars. We can say, the bus
bars are junction points capable of carrying huge power.
Bus bars are conducting bars to which a number of
incoming or outgoing circuits are connected. Electrical
components of each circuit are connected in a definite
sequence such that a circuit can be switched on/off during
normal operations. In KTPS O&M we are using Double Bus Bar
system with quadrantone ACSR conductor.
TASKS OF THE SWITHCH YARD :
a. Protection of transmission system (to isolate faulty
network from the healthy one)
b. Controlling the exchange of power (i.e. to control the
power transmission to load points as per requirements
and instructions of LDC.)
c. Maintain the system frequency within targeted limits.
(This can be done by raising/ lowering of generation or
load shedding.)
59
d. Determination of power transfer through transmission
lines.
e. Fault analysis and subsequent improvements.
f. Communication: data transfer via power line carrier for
the purpose of network monitoring, control and
protection.
Equipments in Switch Yard:
Insulators
Conductors & Accessories
Clamps & Connectors
Circuit Breakers
Isolators
Earth Switch
Instrument Transformers
Surge Arrestors
Wave Traps
Insulators:
60
The flexible ACSR conductors of transmission line and
substation bus bars are supported on string insulators. The rigid
tubular bus bars in SS are supported on Solid insulators/Post
insulators.
Conductors & Accessories:
Conductor consists of several strands (individual wires)
wound in layers spiraled along the length of conductor.
Consecutive layers are twisted spirally in opposite direction to
provide good interlayer grip and gives strength and flexibility to
the total conductor.
Electrical Grade Aluminum wires or Al alloy wires are used
for conductor for carrying current. In the core, Galvanized Steel
wires are used for reinforcement .The core gives high tensile
strength & conductor has low resistance.
Clamps & Connectors:
Tee-Connectors: For connecting ACSR conductor to ACSR tap
conductor (dropper)
Parallel-Grove Connectors (PG clamp): For connecting two
ACSR flexible conductors in parallel.
Fixed type bus post Clamps: For supporting tubular bus on post
insulators.
Pad Clamps: For Isolator to ACSR conductor connections
Spacers.
61
For twin conductor bundle.
For quadruple conductor bundle
Hardware for string insulator assembly.
62
CIRCUIT BREAKERS:
Circuit breakers are switching devices, design to close or
open contact members, thus closing or opening an electrical
circuit under normal or abnormal conditions.
Circuit breaker is automatic switching Device which can
carrying normal current & switching in & out
normal loads
Interrupt short circuiting currents.
can able to performer auto-reclose duty.
Classification of circuit breakers:
Based on LOCATION
Indoor
Outdoor.
Based on INTERUPTING MEDIUM
Air break Air Break Circuit Breaker (ACB)
Air blast Air Blast Circuit Breaker (ABCB)
Bulk oil Bulk Oil Circuit Breaker (BOCB)
Minimum oil Minimum Oil Circuit Breaker (MOCB)
SF6 gas insulated SF6 Circuit Breaker (GCB)
Vacuum Vacuum Circuit Breaker (VCB)
63
ISOLATORS:
In sub-stations it is often desired to disconnect a part of
the circuit for maintenance or repairs of conductors, clamps,
CBs etc. This is accomplished by an Isolator (Isolating
switch).Isolators are switches operated when the line in which
they are connected carry no current.
Isolator (disconnecting switch) operates under no load
condition. It does not have any specified current breaking
capacity or current making capacity. Isolator is not even used
for breaking load currents. In some cases isolators are used for
breaking charging current of transmission line.
Isolators used for power systems are generally 3-pole
isolator. The 3-pole isolator has three identical poles. Each pole
consists of two or three insulator posts mounted on a
fabricated support. The conducting parts are supported on the
insulator posts. The conducting parts consist of conducting
copper or aluminum rod, fixed and moving contacts. During the
opening operation the conducting rod swings apart and
isolation is obtained. The simultaneous operation of three poles
is obtained by mechanical inter locking of the three poles.
Further, for all three poles, there is a common operating
mechanism.
The operating mechanism is manual plus one of the following:
64
1. Electrical motor mechanism
2. Pneumatic mechanism
Further, the isolator can be provided with earthing switching
when required. The earthing switch consists of a conductor bar.
When the earthing switch is to be closed, these bars swing and
connect the contact on line unit of isolator to earth.
65
EARTHING SWITCH:
Earthing switch is connected between the line
conductor and earth. Normally it is open. When line is
disconnected, the earthing switch is closed so as to discharge
the voltage trapped on the line. Though the line is
disconnected, there is some voltage on the line to which the
capacitance between line and earth is charged. This voltage is
significant in high voltage system. Before proceeding, with the
maintenance work these voltages are discharged to earth by
closing the earth switch.
INSTRUMENT TRANSFORMERS:
CURRENT TRANSFORMERS:
Protective relays in a.c power system are connected in the
secondary circuit of the current transformers .
Current transformers are classified into two groups
1. Protective current transformers
2. Measuring current transformers
Ratio error and phase angle errors are the important
errors of these transformers .The ratio error is very important
in protective current transformers ,and phase angle error may
be less important .
66
Larger cores and air gaps are introduced in CT`S for fast
protective relays , in order to prevent saturation of current
transformer cores during sub-transient current.
DESCRIPTION OF CT`S:
The current transformer types IT 245 are out door, single
phase post type with oil impregnated paper insulation and
hermitically sealed enclosures.
The primary winding is of eyebolt design with capacitance
graded voltage insulation. Primary currents are more than one
value is obtained by providing either primary reconnection or
secondary tapping.
The core is made of high-grade electrical steel through
which the required numbers of secondary turns are wound
torridly. This assembly is located in the eye of the primary
winding. The active part is located inside tank. There is more
than one secondary, to achieve various functions like metering
or protection. A high voltage porcelain insulator serves as the
external insulation. One oil sight glass is provided and section
head contains the primary terminals.
A Nitrogen valve in the dome, Nitrogen gas which acts as a
cushion for expansion and contraction of oil.The transformer is
hermetically sealed to eliminate moisture absorption and oil
contamination.
67
OPERATION:
CT`S whose primary windings have been energized
must not be open on the secondary side. The secondary
winding should either be short-circuited or closed by a load
corresponding to the rated burden indicated on the rating
plate.
68
VOLTAGE TRANSFORMERS:
Voltage transformers are used for measurement and
protection. These are necessary for voltage directional,
distance protection. The primary of the voltage transformer is
connected directly to power circuit between phase and ground
depending upon rated voltage and application. The volt ampere
rating of voltage transformer is smaller.
There are two types of construction:
- Electromagnetic potential transformer, in which primary
and secondary are wound in magnetic cores like usual
transformer.
- Capacitor potential transformer, in which the primary
voltage is applied to a series capacitor group. The voltage
across one of the capacitor is taken to auxiliary voltage
transformer. The secondary of auxiliary voltage transformer is
taken for measurement or protection.
NOTE:CT’S AND PT’S ARE EXTERNALLY VISIVBLE WITH
COMBINATION OF DISC SHAPED STRUCTURES CALLED PETTI
COATS.THIS STRUCTURED IS PREFERRED TO ERADICATE THE
SHORT CIRCUITIN AND EARTHING DURING RAINING.WATER
FALLS ON THE DISC SHAPED STRUCTURE AND IS DEVIATED IN
ITS DIRECTION NOT FORMING A CONTINUOUS LINE OF WATER
69
DROPLETS WHICH CAUSES GROUNDING OR SHORT
CIRCUITING.
A View of a PT:
70
Surge Arrestors:
Metal oxide surge arrester also known as zinc oxide surge
arresters are well accepted as voltage clippers for effective
protection against over voltages. Metal oxide surge arresters
protect the costly outdoor electrical equipment from over voltages
caused by atmospheric disturbances due to lightning and internal
disturbances due to switching surges. The assembly consists of
Metal Oxide elements with contact plates between discs and held
rigidly by a tie rod assembly. The striking aspect of this arrester is
its simplicity of construction.
Working: This zinc oxide acts as an insulator up to the voltage
of 220 KV and if voltage exceeds to a greater extent due to
lightening or internal disturbances breakdown of zinc oxide
occurs and charge is completely passed in the ground. High
frequency high voltage waves are discharged in to the ground.
WAVE TRAPS:
It is also called "Line trap". It is connected in series with
the power (transmission) line. It blocks the high frequency
carrier waves (24 kHz to 500 kHz) and let power waves (50 Hz -
60 Hz) to pass through. It is basically an inductor of rating in
milli Henry.
71
Main Control Room (MCR):
Each and every part of the switch yard can be operated
with computer based software technique from Main Control
Room. Any problem anywhere in the BUS, FEEDER, CB,
ISOLATER etc., can be found out without manual effort from
MCR.
Unit Control Board (UCB):
Each and every unit in the thermal power station can be
controlled and operated with computer based software
techniques from UCB. Any problem anywhere in the turbine,
BFP, Fans, bunkers, boilers etc., can be found at UCB without
any manual effort.