Plant Design 1 s
-
Upload
peace-chawisa -
Category
Documents
-
view
218 -
download
0
Transcript of Plant Design 1 s
-
8/13/2019 Plant Design 1 s
1/20
-
8/13/2019 Plant Design 1 s
2/20
2
DesignDesign
1. Conceptual design: develop a preliminaryflowsheet using approximate methods.
2. Preliminary design: use rigorous simulators toevaluate steady-state and dynamic
performance of proposed flowsheet.
3. Detailed design:specify type of trays, no. of
sieve tray holes, piping, pumps etc.
-
8/13/2019 Plant Design 1 s
3/20
-
8/13/2019 Plant Design 1 s
4/20
1.1 Creative Aspects of1.1 Creative Aspects of
Process DesignProcess Design
The propose of engineeringis tocreate new material wealth.
Process and plant design is thecreative activity whereby generate idea
and then translate them into equipmentand processes for producing newmaterials or for significantly upgradingthe value of existing materials.
-
8/13/2019 Plant Design 1 s
5/20
In any particular company, we might
try to generate new idea:
To produce a purchased raw materialTo convert a waste by-product to avaluable product
To create a completely new material(synthetic fibers, food, bioprocessing)To find a new way of producing an
existing product (a new catalyst, abioprocessing alternative)To exploit a new technology (genetic
engineering, expert systems)
-
8/13/2019 Plant Design 1 s
6/20
TABLE 1.1-1 Types of design estimates1.1. Order of-magnitudeOrder of-magnitude(ratio estimate) base on similar previous cost(ratio estimate) base on similar previous cost
data; probable accuracy exceeddata; probable accuracy exceed ++40%40%2.2. Study estimateStudy estimate(factored estimate) base on knowledge of major(factored estimate) base on knowledge of major
item of equipment; probable accuracy up toitem of equipment; probable accuracy up to ++2525
3.3. Preliminary estimatePreliminary estimate(budget aut!ori"ation estimate; scope(budget aut!ori"ation estimate; scope
estimate)based on sufficient data to permit t!e estimate to beestimate)based on sufficient data to permit t!e estimate to bebudgeted; probable accuracy wit!inbudgeted; probable accuracy wit!in ++#2#2
4.4. Definition estimateDefinition estimate(project control estimate) based on almost(project control estimate) based on almost
complete data$ but before completion of drawing and specifications;complete data$ but before completion of drawing and specifications;
probable accuracy wit!probable accuracy wit! ++%%
5.5. Detail estimateDetail estimate(contractor&s estimate) based on complete(contractor&s estimate) based on complete
engineering drawings$ specifications$ site surveys; probableengineering drawings$ specifications$ site surveys; probable
accuracy wit!accuracy wit! ++''
Frome A. Pikulik and H.E. ia!" #$ost Estimating %a&or ProcessEquipment"' $hem. Eng." ()*+,- ,/0*,122-
Level of Engineering DesignsLevel of Engineering Designs
-
8/13/2019 Plant Design 1 s
7/20
3ess than3ess than4 , million4 , million 4,5464,546
millionmillion46546/46546/
millionmillion
7ype of estimate7ype of estimate PlantPlant PlantPlant PlantPlant
8tudy *48tudy *4thousands-thousands-
65,665,6 ,+59/,+59/ +/5)/+/5)/
Preliminary*4Preliminary*4thousands-thousands-
,6596,6596 9/50/9/50/ 6/51/6/51/
efinitive *4efinitive *4thousands-thousands-
+650/+650/ 0/5,+/0/5,+/ ,//5+9/,//5+9/
TABLE 1.1-2 Engineering Costs to Prepareestimates1!""#
Frome A. Pikulik and H.E. ia!" #$ost Estimating %a&or ProcessEquipment"' $hem. Eng." ()*+,- ,/0*,122-
-
8/13/2019 Plant Design 1 s
8/20
E$ample %ydrodeal&ylation of
Tol'ene
H +
$ H 9
$ H )
7 o l u e n e : e n ! en e
,
+ H +
: e n ! e n e i p h e n y l
,.+ A Hierarchical approach to $onceptualesign
-
8/13/2019 Plant Design 1 s
9/20
1
%DA Process%DA Process
molBtuH(2#5')
*+ip!enyl,en"ene2-*,en"ene*.oluene
2
/2
=
+
++
Basic information:1. Reactions take place between 1150-1300 F.
2. Pressure is about 500 psi.3. Ecess !"#ro$en %5&1 ratio' pre(entscokin$.
). Effluent $as must be *uenc!e# to1150 Fin or#er to re(ent cokin .
-
8/13/2019 Plant Design 1 s
10/20
,/
HDA Process
-
8/13/2019 Plant Design 1 s
11/20
,,
HDA Process
-
8/13/2019 Plant Design 1 s
12/20
,+
HAD Process
-
8/13/2019 Plant Design 1 s
13/20
$ondensation*high P or low 7" or$ondensation*high P or low 7" or
both-both-
AbsorptionAbsorption
AdsorptionAdsorption
A membrane processA membrane process
As a vapor reovery system !e ould use one of t"ese
-
8/13/2019 Plant Design 1 s
14/20
,)
Simplified #lo!s"eet for t"e Separation Systems
-
8/13/2019 Plant Design 1 s
15/20
,6
$eyle Struture of t"e #lo!s"eet
-
8/13/2019 Plant Design 1 s
16/20
,0
%nput-Output Struture of t"e #lo!s"eet
-
8/13/2019 Plant Design 1 s
17/20
,2
Hierarchy of decisions______________1. Batch versus continuous
2. Input-output structure of the flowsheet
. !ecycle structure of the flowsheet
". #eneral structure of the separation system
a. vapor recovery system $. li%uid recovery system
&. 'eat-exchanger networ(______________
The goal (f concept'al design is to find the) +
Possi&le 'imitation
-
8/13/2019 Plant Design 1 s
18/20
,(
Deomposition Proedures for ()isting Proesses
,. ;emove all the heat exchangers"drums" and storage vessels.
+.
-
8/13/2019 Plant Design 1 s
19/20
,1
%PA Plant
-
8/13/2019 Plant Design 1 s
20/20
+/
(t"y&en*ene Proess