PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

41

Transcript of PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Page 1: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.
Page 2: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

PLANNING ENGINE

Presented by: Dave ParkerSr. Business Analyst

Page 3: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Agenda• Overview of Planning Process• Net Change vs. Regenerative Planning• Planning Triggers Explained• Avoiding ‘Clutter’• Typical Planning Cycle• Curveballs• Q&A

Page 4: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Overview

• Independent Demand = Forecast or Sales Order Line• Infinite Capacity Planning Model

MPS (Master Production Schedule)

• Prioritize (Color, Allergens, Setup, etc.)• Heel-to-Toe

Schedule

• Dependent Demand based off MPS; also Component Forecasts• Infinite Capacity Planning Model

MRP (Material Requirements Planning)

Page 5: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Balance Supply vs. Demand

Demand

Supply

Page 6: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

MPS Inputs

MPS Calculation

Planning “Triggers”

Sales Orders

Production Forecast (Sales)

Inventory Stock Levels

Open Documents

(Backorders)

Page 7: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

MPS Outputs

FG Production

FG Purchases

FG Transfers

MPS Suggestions

Page 8: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

MRP Inputs

MRP Calculation

Planning “Triggers”

Production Forecast

(Component)

Demand from MPS

Inventory Stock Levels

Open Documents

(Backorders)

Page 9: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

MRP Outputs

WIP Production

RM/PKG Purchases

RM/PKG Transfers

MRP Suggestions

Page 10: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Net Change vs. Regenerative

• Net Change Plan– Direct changes to the demand requirements

• Ex: Change in forecast, sales order, production order

– Changes to standard data or planned supply• Ex: Change to BOM, safety stock, inventory, purchase order

– Saves time and system resources• Only re-plans items with demand or supply changes since last plan

Page 11: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Net Change vs. Regenerative

• Regenerative Plan– Plans for ALL items

• Starts by deleting all ‘planned’ supply orders that are currently loaded

• Consumes more time and system resources to execute

– Necessary if there are changes to capacity or standard data that would affect the total plan

• Ex: Change to shop calendar, overall safety lead time

Page 12: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Planning Policies

• Blank – do not include in planning• Maximum Inventory – what is needed to get to value of

Maximum Inventory• Order – separate supply per demand instance• Fixed Reorder Quantity – when need is identified,

always suggest value of Reorder Qty.• Lot-for-Lot – whatever supply is needed within the

Reorder Cycle

Page 13: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Planning Triggers

• Vendor Lead Times– “No matter WHAT I buy from this vendor, it takes x days.”

• Item Lead Times– “No matter WHO I buy this item from, it takes x days.”

• Vendor Item Catalog– “Item A from vendor A takes x days. Item B from vendor A takes y

days.”

• Safety Lead Times (Manufacturing Setup, Item Card)– Added to any other lead times

- Lead Times

Page 14: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

+ Lot Acc. Per. (6D)

Looks out 6 days past the first demand date and suggests 25 cases.

Planning Triggers - Lot Accumulation Period

Page 15: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

+ Lot Acc. Per. (7D)

Looks out 7 days past the first demand date and suggests 30 cases.

Planning Triggers - Lot Accumulation Period

Page 16: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Planning Triggers - Lot Accumulation Period

Page 17: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

- Reorder Point vs. Safety Stock

• Reorder Point– Reactive response to an inventory level

• Safety Stock– Proactive response to an inventory level

Planning Triggers

Page 18: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Reorder Point

Reorder Point

Inventory

Lead Time

Replenishment (Reorder Quantity)

Time

Qu

an

tity

Page 19: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Safety Stock

Safety Stock

Inventory

Lead Time

Replenishment

Time

Qu

an

tity

Page 20: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

- Order Quantity Manipulators

• How to ensure orders are at least a full batch (or full pallet)?– Minimum Order Quantity

• How to ensure orders are in full batch (or full pallets) increments?– Order multiples

• How to ensure orders are split into standard run sizes?

– Maximum Order Quantity

Planning Triggers

Page 21: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Avoiding ‘Clutter’

If this is all you do, it’s not enough!Now you’ve doubled your supply – and the Cancel will be back again next time!

Page 22: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Avoiding ‘Clutter’

Scenario: Cancel one date, New order for another

WHY does this happen?

A) Demand changes (unavoidable!)B) The new supply needed is further away from original supply than the Reorder Cycle.

Page 23: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Avoiding ‘Clutter’ – How?

• Planning Flexibility–Any supply can be set to ‘None’ and the

plan will leave it alone

Page 24: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Avoiding ‘Clutter’ – Planning Flexibility option

Purchase LinesTransfer LinesProd. Order Lines

Req. WorksheetPlanning Worksheet

Page 25: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Avoiding ‘Clutter’ – How?• Planning Flexibility

• Dampeners–Plan only suggests change outside of a

‘tolerance’ (date or qty)– In 2013, these are at Item / SKU level, not

overall Manuf. Setup

Page 26: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Avoiding ‘Clutter’ - Dampeners

Page 27: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Avoiding ‘Clutter’ – How?• Planning Flexibility• Dampeners

• Rescheduling Period–Plan will use ‘Reschedule’ if within the

period (as opposed to Cancel + New)

Page 28: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Avoiding ‘Clutter’ – Rescheduling Period

For NAV 2013, Reorder Cycle split into two fields:

- Lot Accumulation Period

- Rescheduling Period

Page 29: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Planning Engine

What does a typical planning process look like?

Page 30: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

STEP 1 – Plan FG Production

• Filter for which FG to include• Dates - Longest lead time component

1.1. MPS

• Firm plan next week• Plan everything else

1.2 Carry Out Action

• Shortage report / meet with purchasing• Early detection of packaging issues

1.3 Shortage Analysis

Page 31: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

STEP 2 – Schedule FG Production

• Primary work center/machine center• Sort by Item Scheduling Property• Throughput based on routing setup/run

times• Heel-to-toe prioritizing

2.1 Capacity Task List

Page 32: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

STEP 2 – Schedule FG Production

• Heel-to-toe prioritizing

2.1 Capacity Task List

Page 33: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

STEP 2 – Schedule FG Production

Page 34: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

STEP 3 – Plan WIP Production

• Dates - Longest lead time component• Suggestions align with FG schedule

3.1 MRP (WIP)

• Firm plan next week• Plan everything else

3.2 Carry Out Action

• Shortage report / meet with purchasing• Early detection of component issues

3.3 Shortage Analysis

Page 35: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

STEP 4 – Plan RM/PKG

• Dates - Longest lead time component• Suggestions align with FG/WIP schedule

4.1 MRP (RM/PKG)

• Create PO for order date of today/tomorrow• Ignore everything else

4.2 Carry Out Action

• Shortage report / meet with purchasing• Double check plan

4.3 Shortage Analysis

Page 36: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

- Planning

• Make-to-Order Environment– Will need to combine MPS and MRP

• Co-pack / Subcontracting Environment– Will need to insert Subcontracting Worksheet into the

process– Links a production order and a purchase order

• Multi-location Environment– Transfer order suggestions may not represent your reality

Curve Balls

Page 37: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

• Schedule WIP instead of FG– Production Order Linking

• WIP Requirement is Line Specific– May need to use variants to trigger production suggestions

by line

• Batch Sizes Change by Line– Alternate Routings (or versions) with different batch UOMs

• Routing or BOM Changes Based on Production Location– Routing versions by Location

Curve Balls - Scheduling

Page 38: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Characteristics of successful implementations

• Maintain accurate data input– Forecasts, orders, inventory levels, BOMs, routings

• Proper treatment of expedited orders– Additional resources, multiple lines

• Close collaboration between sales/marketing and production– The forecast is a key contributor to successful planning

• Accurate and timely shop floor feedback and tracking

Page 39: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Questions?

Page 40: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.

Thank you!

Page 41: PLANNING ENGINE Presented by: Dave Parker Sr. Business Analyst.