Human Services CommitteeJune 3, 2013
Consideration of Piven Theatre Construction Loan
![Page 2: Piven hsc presentation final 3.18.13](https://reader036.fdocuments.net/reader036/viewer/2022082420/54995f4cb47959e77f8b49b9/html5/thumbnails/2.jpg)
For ConsiderationOrdinance 43-O-13: “Authorizing the City
Manager to Negotiate and Execute a Lease and Construction Agreement with Piven Theater Workshop”
Resolution 8-R-13 “Authorizing the City Manager to Execute an Amendment of a Lease Agreement with Piven Theatre Workshop, Inc”
![Page 3: Piven hsc presentation final 3.18.13](https://reader036.fdocuments.net/reader036/viewer/2022082420/54995f4cb47959e77f8b49b9/html5/thumbnails/3.jpg)
Summary of Proposed ProjectPiven seeks to renovate space to:
Create 200 seat black box theatreAdditional office spaceIncrease classroom spaceCreate larger rehearsal space
Total Cost is estimated at $3.55 MillionSeeking a $2.2 million loan from CityPiven will raise $1.35 million in a
combination of: cash, pledges, private financing, and in kind contributions.
![Page 4: Piven hsc presentation final 3.18.13](https://reader036.fdocuments.net/reader036/viewer/2022082420/54995f4cb47959e77f8b49b9/html5/thumbnails/4.jpg)
Summary of Proposed Loan & Lease AgreementCity Construction Responsibilities for the
entire building: Roof repair and asbestos and lead abatement
30 Year Lease with 4, 5-Year Extensions (up to 50 years)
Tenant to construct the proposed improvements and contemplates completion by Winter 2014
Tenant Contribution to Capital Improvements
![Page 5: Piven hsc presentation final 3.18.13](https://reader036.fdocuments.net/reader036/viewer/2022082420/54995f4cb47959e77f8b49b9/html5/thumbnails/5.jpg)
Loan DetailsTotal Loan $2.2 millionInterest rate is 2.0% per annumPiven must raise $355,000 in cash prior to
the City loaning the money. Loan payments start 2 years after
construction is completedLoan secured by fixtures, equipment, and
personal property
![Page 6: Piven hsc presentation final 3.18.13](https://reader036.fdocuments.net/reader036/viewer/2022082420/54995f4cb47959e77f8b49b9/html5/thumbnails/6.jpg)
Rent Details 2013: $60,000 per annum ($10,000 in
cash/$50,000 credit for in kind work)2014+: $60,000 per annum ($20,000 in
cash/$40,000 credit for in kind work) Loan repayment period: $1.00 per annum 2043 – 2063 (Option Periods): $100,000 per
annum ($75,000 in cash/$25,000 credit for in kind work)
![Page 7: Piven hsc presentation final 3.18.13](https://reader036.fdocuments.net/reader036/viewer/2022082420/54995f4cb47959e77f8b49b9/html5/thumbnails/7.jpg)
Activities to Date Noyes Cultural Arts Center floor plans have
been revised (Attachment 2 to Transmittal Memo/pg. 249-251 of packet)
Piven: removal of intention to occupy studios 217 and 218 on second floor and agreed to occupy basement studio space in B13 in the proposed renovations
Rent: Piven will be paying rent before and after the loan repayment period
Fleetwood Jourdain
![Page 8: Piven hsc presentation final 3.18.13](https://reader036.fdocuments.net/reader036/viewer/2022082420/54995f4cb47959e77f8b49b9/html5/thumbnails/8.jpg)
Estimated Economic ImpactCurrent estimate of 32-37 FTE and PTE
employees spend $83,200 and $96,200 per year in Evanston
Growth in employment this number could grow over $100,000
30,000 patrons annually could result in $612,900 of impact for economy