Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a...

84
Pipeline Consultation Plan Enterprise Project - Victoria

Transcript of Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a...

Page 1: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation PlanEnterprise Project - Victoria

Page 2: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan Enterprise Project – Victoria

Plan

S4700AN718451

Revision Date Reason for issue Reviewer/s Consolidator Approver

0 13/09/2019 Issued for use – Ministerial approval DELWP

Page 3: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

1 of 56

Table of contents

Definitions/Acronyms 4

Responsibilities 5

1 Introduction 7

1.1 About Beach Energy 7

1.2 The Enterprise Project 7

1.3 Project Scope 8

1.4 The Enterprise Pipeline 9

1.5 Pipeline route selection 9

1.6 Project considerations 11

1.7 Project timeline 12

2 Purpose of this plan 14

3 Consultation approach 15

3.1 Consultation principles 15

3.2 Consultation principles 15

3.3 Consultation objectives 15

3.4 Leadership commitment 16

4 Consultation Methods 18

4.1 Consultation with landowners and occupiers 18

4.1.1 Face-to-face consultation 19

4.1.2 Letters 19

4.1.3 Webpage 19

4.1.4 Phone and email 19

4.1.5 Public Display of Regulatory Documentation 20

5 Sequence and Duration of Consultation 21

6 Communication materials 24

6.1 Communications materials 24

6.2 Contractor awareness of materials 25

7 Stakeholders 27

7.1 Stakeholder assessment 27

7.2 Stakeholder identification 27

7.2.1 Private landowners and occupiers 27

7.2.2 Public landowners and occupiers 27

7.2.3 Crown Land 27

7.2.4 Aboriginal groups 28

7.2.5 Near Neighbours 28

7.2.6 Otway Gas Plant Community Reference Group (CRG) 28

7.2.7 Corangamite Shire Council 28

7.2.8 Elected officials 28

7.2.9 Government departments and agencies 29

7.2.10 Other groups 29

8 Information for Landowners and Occupiers 30

8.1 General 30

Page 4: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

2 of 56

8.2 Statement of independent advice 30

8.3 Procedure for Agreements and Notices 30

8.4 Schedule for Agreements and Notices 30

8.5 Notice of intention to enter land for survey 32

8.6 Notice of Pipeline Corridor 32

8.7 Notice of Pipeline License Application 32

8.8 Agreements with landowners and occupiers 32

9 Evaluation of consultation 34

10 Collection of Stakeholder Information and Records Management 36

10.1 Record keeping 36

10.1.1 Privacy and Use of Confidential Information 36

10.1.2 Internal Records Management 36

10.2 Response to Stakeholders 36

10.2.1 Responding to concerns issues or claims 36

10.3 Statutory reporting 37

10.4 Media enquiries 37

11 Compulsory Acquisition of Land 38

11.1 Pipelines Act 38

11.2 Land Acquisition and Compensation Act 38

12 Overview of Pipeline Construction Process 40

12.1 Initial survey 40

12.2 Setting up Work Areas 40

12.3 Clear and grade 40

12.4 Typical set-up within the construction ROW 41

12.5 Trenching 41

12.6 Trenchless construction 41

12.7 Welding 42

12.8 Sand Padding and Lowering In 42

12.9 Backfill 42

12.10 Easement Rehabilitation 42

12.11 Hydrostatic testing 42

12.12 Eventual decommissioning of this proposed pipeline 43

13 Management of potential impacts 44

13.1 Pipeline construction 44

13.1.1 Construction Environmental Management Plan (CEMP) 44

13.1.2 Construction Safety Management Plan (CSMP) 44

13.1.3 Cultural Heritage Management 45

13.1.4 HDD Management Plan 45

13.2 Pipeline operation 45

13.2.1 Environmental Management Plan (EMP) 45

13.2.2 Safety Management Plan (SMP) 45

13.2.3 Pipeline Stakeholder Engagement Plan (PSEP) 45

13.2.4 Property Land Books 45

14 Further information 46

Page 5: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

3 of 56

14.1 Beach Energy Contact Information 46

14.2 Regulatory Agencies and Advocacy Groups 46

14.2.1 Organisations 46

14.2.2 Legislation 47

14.2.3 Other Pipeline Publications and Information 47

15 Document Information 49

Table of figures

Figure 1: Enterprise concept development 9

Figure 2: Schematic of the proposed Enterprise Pipeline route 11

Figure 3: Indicative Project timeline 13

Figure 4: Beach Energy Community Engagement Principles 15

Figure 5: Typical pipeline ROW 41

List of tables

Table 1: Proposed consultation schedule between Beach and landowners and occupiers 21

Table 2: Communications materials 24

Table 3: Summary of Critical Notices and Deadlines for Pipeline Approval 31

List of appendices

Appendix A Checklist of requirements for a consultation plan 50

Appendix B Information Sheets 52

Appendix C Sample Notice of intention to enter land for survey 53

Appendix D Draft Notice of Pipeline Corridor 54

Appendix E Regulatory Approvals 55

Appendix F Sample Monthly Consultation Report 56

Page 6: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

4 of 56

Definitions/Acronyms

Term/acronym Definition/expansion

APGA Australian Pipelines and Gas Association

CEMP Construction Environmental Management Plan

CRG Otway Gas Plant Community Reference Group

DELWP Department of Environment, Land, Water and Planning

DJPR Department of Jobs, Precincts and Regions

EMP Environmental Management Plan

EMAC Eastern Maar Aboriginal Corporation

EPA Environmental Protection Agency

ERD Extended Reach Drilling

ESV Energy Safe Victoria

HBWS Halladale, Black Watch and Speculant Project

HDD Horizontal Directional Drilling

HSE Health, safety and environment

IAP2 International Association for Public Participation

Lattice Lattice Energy Limited (100% owned by Beach)

LACA Land Acquisition and Compensation Act 1986 (Vic)

LGA Local Government Authority

MEG Mono-ethylene Glycol lines are used in pipeline development to prevent hydrate formation

from occurring, which is the reaction of water and hydrocarbons that exist in the reservoirs.

OGP Otway Gas Plant

PCP Pipeline Consultation Plan

Pipelines Act Pipelines Act 2005 (Vic)

Pipelines

Regulations

Pipelines Regulations 2017 (Vic)

PMP Property Management Plan

PSEP Pipeline Stakeholder Engagement Plan

Q&A Questions and Answers

ROW Construction right-of-way

SMP Safety Management Plan

SMSS Short Message Service System (text messages)

The drilling

activities

The drilling activities associated with the Enterprise-1 Exploration Drilling Program

The Project The Enterprise Pipeline Project including construction and commissioning

Page 7: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

5 of 56

Term/acronym Definition/expansion

The Project area Includes the area between the Enterprise-1 wellsite and the Otway Gas Plant

VFF Victorian Farmers Federation

Responsibilities

Role Responsibilities

Community Advisor(s) • Prepare and update PCP

• Prepare external communications materials

• Document all correspondence and engagement with all stakeholders in

stakeholder engagement log and retain all written and email correspondence for

reports

• Issue postal and email notices to stakeholders, track mail and replies, manage

routine responses, and track progress of engagement

• Arrange purchase orders, book venues, liaise with designer and printer, arrange

signage, book advertisements

Community Relations

Manager (Victoria)

• Provide input to PCP, review and agree with approach and contents

• Review external communications materials

• Identify relevant stakeholders based on Project scope, environment description,

environment effects and impacts

• Lead engagement with community, landowners and occupiers

• Engage and negotiate with landowners and occupiers

• Engage with all other Project stakeholders

• Feed stakeholder concerns and issues to the Project team

• Seek Project, operational and environment information to respond to community,

landowner and occupier queries and concerns

• Participate in Project meetings and liaise with Project Manager to ensure time

frames and other Project deliverables are met

• Provide regular updates on engagement progress

• Raise Project schedule, media exposure or reputation risks

Community Manager • Approve PCP

• Review external communications materials

• Oversee engagement progress

• Engage with key stakeholders where required

Project subject matter

experts

• Provide content for development of external communications

• Review external published information for technical accuracy

• When requested by Community Relations Manager (Victoria) engage with

stakeholders where required

Environment Advisor

Health and Safety

Advisor

• Provide environment and safety information to enable identification of impacts

and key issues

• Provide content for development of external communications

• Review external published information for technical accuracy

Page 8: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

6 of 56

Role Responsibilities

• Assist with responses to stakeholder questions and concerns

• When requested by Community Relations Manager (Victoria) engage with

stakeholders

Legal Advisor • Review external published information for legal compliance

Corporate Affairs

Manager

• Review external communications and provide feedback

• Prepare Issues Brief and Q&As for managing media enquiries

• Manage government relations and media enquiries

Project Manager • Provide Project scope and description for development of the PCP and external

communications

• Approve all external correspondence

• When required by Community Relations Manager (Victoria) engage with

stakeholders

• Assist with responses to stakeholder questions and concerns

Land Liaison Officer • Establish and maintain proactive working relationship with landowner or occupier

• Ensure landowner or occupier is kept informed of any Project developments in a

timely manner

• Record all consultation with landowner or occupier

• Ensure any feedback from landowner or occupier is provided to Project Manager

and Community Relations Manager and considered as part of Project planning

• Act as a single point of contact for the landowner or occupier throughout the life

of the Project

Page 9: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

7 of 56

1 Introduction

1.1 About Beach Energy

Lattice Energy Limited (“Lattice”) a related body corporate of Beach Energy Limited (“Beach”) is the

proponent of the Enterprise Project and Enterprise Pipeline Project.

Beach is an ASX-listed, oil and natural gas, exploration and production company headquartered in

Adelaide, South Australia. Founded in 1961, Beach has operated and non-operated, onshore and

offshore, oil and natural gas production from five producing basins across Australia and New Zealand

and is a key supplier to the Australian east coast natural gas market.

In January 2018, Beach acquired permits and operational assets in Victoria through its acquisition of

Lattice Energy Limited (Lattice), a subsidiary of Origin Energy. As Lattice is now a wholly-owned

subsidiary of Beach, all assets outlined in this Pipeline Consultation Plan (PCP) will be operated under

the Lattice name, including all applications for regulatory approvals including the pipeline licence.

However, this plan and all consultation materials and activities will use the Beach Energy name and

branding.

Beach’s existing operations in the Victorian Otway Basin include natural gas production from the

offshore Halladale, Speculant, Geographe and Thylacine gas fields. Beach owns and operates several

natural gas pipelines that supply gas produced in these gas fields to the Beach-operated Otway Gas

Plant, located near Port Campbell. These existing pipelines include the PL250 Otway Gas Pipeline and

the PL006009 Halladale, Black Watch and Speculant Pipeline.

Natural gas processed at the Otway Gas Plant is sold to retailers and used for domestic or commercial

consumption in the eastern states of Australia, as well as South Australia.

As part of its Victorian operations Beach also operates the Bass Gas Plant at Lang Lang, located east of

Melbourne, and the associated PL243 raw gas pipeline and the PL244 sales gas pipeline.

1.2 The Enterprise Project

The Enterprise Project is a program which proposes to recover natural gas from offshore reservoirs in

the Victorian Otway Basin. The potential reservoirs are located offshore, up to 3 nautical miles (5.55

km) from the coastline, while the well site will be located onshore near Port Campbell, Victoria.

In early 2020, Beach proposes to begin drilling the offshore Enterprise-1 exploration well using

Extended Reach Drilling (ERD) technology from an onshore drill pad. The Enterprise-1 exploration well

is located in the Enterprise gas field located in Victorian licence block VIC/P42(v). The VIC/P42(v)

licence block is operated by Beach and is located in Victorian State waters.

Further reservoir diagnostics will be performed following the drilling of the Enterprise-1 exploration

well. Should the Enterprise-1 exploration well be deemed commercial, Beach plans to convert the

exploration well into a production well and start construction on the proposed Enterprise Pipeline.

Page 10: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

8 of 56

In future and depending on the success of the Enterprise-1 well, a further two exploration wells may be

drilled from the Enterprise-1 well site. Should these additional two wells be deemed commercial, the

recovered natural gas would also be transported to the Otway Gas Plant via the Enterprise Pipeline.

This PCP has been developed for the proposed Enterprise Pipeline and the consultation required as

part of its planning, construction and operation. The Enterprise Pipeline forms part of the broader

Enterprise Project.

For more information on the Enterprise Project, visit https://www.beachenergy.com.au/vic-otway-

basin/ and click on the “Enterprise Information Sheet”. Information on Beach’s Black Watch Project, a

similar project to the proposed Enterprise Project, can be found on the same page in the “Black Watch

Information Sheet”.

1.3 Project Scope

The current concept for the Project is:

• A new 200-300mm diameter production pipeline and accompanying 50-100mm diameter MEG

pipeline, both approximately 12km in length, to be constructed, for the major proportion of its

length, alongside the existing PL250 pipeline within existing easement to transport gas to the

Otway Gas Plant

• New easements to be created from the Enterprise-1 drill site to the existing easement associated

with the PL250 pipeline

• Additional new easements may be required along the existing PL250 easement route where the

current easement is insufficient to allow access to the new pipeline for operational purposes.

Where it is required to ensure the new pipeline can be constructed safely due to other subsurface

infrastructure nearby, temporary work areas during construction will be required.

The current concept for the Project is shown in Figure 1.

Page 11: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

9 of 56

Figure 1: Enterprise concept development

1.4 The Enterprise Pipeline

The proposed Enterprise Pipeline is an approximately 12km, 200-300mm diameter buried pipeline that

will run from the onshore Enterprise-1 drill site to the Otway Gas Plant. The Enterprise Pipeline includes

an accompanying 50-100mm diameter MEG pipeline.

The construction and commissioning of the proposed pipeline, including scraper launcher and receiver

barrels at each end, constitute the extent of the Project.

Construction of facilities at the Enterprise well site and tie-in facilities at the Otway Gas Plant are not

included as part of the Project or Pipeline Consultation Plan, and consultation for these activities will

be addressed separately.

1.5 Pipeline route selection

The proposed Enterprise Pipeline will run from the Enterprise-1 drill site to the Otway Gas Plant.

It is proposed that for the majority of its length the Enterprise Pipeline will run alongside the PL250

Otway Gas Pipeline within existing easements, where possible. See Figure 2 for the map of the

proposed pipeline route.

Beach has identified this preferred pipeline route based on several environmental, technical and

stakeholder-focused factors, including:

Page 12: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

10 of 56

• Existing easements

• Landowner considerations

• Options to minimise environmental and cultural impact

• Project requirements

• Gas flow within existing pipelines

• Geotechnical considerations

• Land tenure for both the construction and operational phases.

The selection process for the final proposed pipeline route will be determined by the consultation

process to be undertaken with stakeholders, landowners and occupiers, and the consideration of all

factors.

It is Beach’s preference to locate the proposed Enterprise Pipeline within the existing PL250 Otway Gas

Pipeline easement. Constructing and operating the pipeline within the existing PL250 Otway Gas

Pipeline easement has benefits including:

• Minimising impacts on land and the environment by using existing easements, thereby reducing

the need to encumber additional land with new easements

• Minimising any additional operational impact on farming operations for existing landowners and

occupiers

• The existing easement has already been scouted and assessed for previous pipeline construction,

thus minimising the impact on areas of commercial, environmental or cultural value.

Several options for a pipeline route that could use existing infrastructure in the Project area were

considered, including connection into either the PL250 Otway Gas Pipeline or PL006009 Halladale,

Black Watch and Speculant Pipeline. However, these options were determined unsuitable in meeting

technical and Project requirements.

Beach will continue to monitor other options which may become available, including using existing

pipelines operated by other oil and gas companies which may become available within the proposed

Project timeframe.

To facilitate the construction of the proposed pipeline, some temporary work space, in addition to

easement, may be required. Agreements regarding the use of these areas will be negotiated with

landowners and occupiers in advance of any activities being undertaken on the property following

approval of this PCP.

Page 13: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

11 of 56

Figure 2: Schematic of the proposed Enterprise Pipeline route

1.6 Project considerations

There are several environmental, social and commercial considerations associated with the Project,

including:

• Impact to directly affected stakeholders: Open and transparent consultation will be undertaken

with all directly affected stakeholders, landowners and occupiers. Where possible, feedback from

any individual or group will be incorporated into the design and planning of the Project

• Impact to land use: Construction methodology will be selected to minimise land disturbance.

• Local employment and economic spend: Construction of the pipeline will provide opportunity

for local employment, including the engagement of subcontractors. During planning and

construction there will be a requirement for local accommodation, meals, supplies and other

expenditure by the Project team within Port Campbell and the south west Victorian region.

Continued supply of gas to the Otway Gas Plant will ensure the viability of the plant as a source of

local jobs into the future.

• Energy supply and demand: The Project will help meet and balance the increasing demand for

supply of natural gas in the Australian east coast gas market.

Page 14: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

12 of 56

• Impact to community: Beach will actively seek feedback from community members and will

incorporate this feedback into the Project planning and design.

• Impact to environmental, cultural and heritage values: Using an existing easement for the

majority of the pipeline route will minimise, and in many cases avoid, any impacts to areas with

environmental, cultural or heritage considerations.

1.7 Project timeline

An overview of the proposed Project activities and timing is provided in Figure 3. The exact timeline

would depend on the duration, timing and scope associated with regulatory approvals, third party

agreements, construction techniques, and Project execution.

It is intended that the consultation process for the proposed Enterprise Pipeline commence in late

2019. If approval is received from the regulator, the earliest Beach would commence pipeline

construction would be in late 2020, dependent on internal technical and financial approvals, fair

weather conditions and the availability of contractors.

A detailed schedule of planned consultation in accordance with legislation requirements is found in

Section 5 of this document.

Page 15: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

13 of 56

Figure 3: Indicative Project timeline

Page 16: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

14 of 56

2 Purpose of this plan

As a pre-license condition, the Pipelines Act 2005 (Vic) (the Pipelines Act) specifies the requirement for

a Minister-approved Pipeline Consultation Plan (PCP) prior to Beach commencing activities compatible

with the Pipelines Act, such as serving Notice of intention to enter land for survey and Notice of

Pipeline Corridor.

Section 17 of the Pipelines Act outlines the requirements for a PCP. A checklist of these requirements

against the contents of this PCP is provided in Appendix A.

The purpose of this PCP is to demonstrate how Beach will consult with stakeholders, landowners and

occupiers about the proposed pipeline. The PCP should also demonstrate how Beach will meet the

consultation requirements laid out in the legislation.

This PCP also reflects industry consultation and engagement best practice, and is based on the

following documents:

• Australian Pipelines and Gas Association Guidelines for Stakeholder Engagement (2015)

• Australian Pipelines and Gas Association Code of Environmental Practice (2017)

• International Association for Public Participation Spectrum of Public Participation (2014)

• Former Australian Pipeline Industry Association – Victorian Farmers Federation Pipeline Easement

Guidelines (2009)

• Former Department of Primary Industry (now Department of Environment, Land, Water and

Planning (DELWP)) Guidelines for the Preparation of Pipeline Consultation Plans - Pipelines Act

2005.

Page 17: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

15 of 56

3 Consultation approach

3.1 Consultation principles

Beach’s Community Engagement Principles aim to build trust which leads to acceptance, and

ultimately respect from communities. These Community Engagement Principles underpin the

consultation approach, values and activities described within this PCP.

Beach’s Community Engagement Principles are demonstrated in Figure 4.

Figure 4: Beach Energy Community Engagement Principles

3.2 Consultation principles

Beach recognises that regular dialogue and engagement with stakeholders, landowners and occupiers

is essential to project success and maintaining its social licence to operate. Stakeholder engagement

on the Project will therefore be undertaken in line with the following principles of effective

consultation:

1. Communication – providing clear, effective and timely communication

2. Transparency – acting in a transparent manner with simple two-way communication, effective

reporting

3. Collaboration – enabling clear opportunities for collaboration with stakeholders, landowners,

occupiers

4. Inclusiveness – identifying opportunities to include stakeholder feedback in the planning process

5. Integrity – undertaking consultation with integrity and honesty at all times.

3.3 Consultation objectives

The consultation objectives of the Project are to:

• Identify the stakeholders, sequence of consultation, regulatory requirements, method and timing

of consultation for the Project;

Page 18: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

16 of 56

• Establish the means for open and transparent consultation between Beach and stakeholders

throughout the Project and ensure that accurate, clear and easy to read materials are provided;

• Ensure that Project information is distributed in a timely manner to allow stakeholders sufficient

time to assess the information provided and to provide feedback on any concerns they may have;

• Outline Beach’s responsibilities for community consultation and engagement;

• Facilitate landowner and occupier involvement in the decision-making process so as to allow

mutually beneficial outcomes for all parties;

• Establish and maintain regular and ongoing communication with all stakeholders to ensure issues

are captured and managed early;

• Demonstrate compliance with all regulatory

requirements for community and stakeholder

consultation;

• Plan and act in accordance with Beach’s

Community Engagement Principles; and

• Plan and act in accordance with Beach’s values:

◦ Safety

◦ Creativity

◦ Respect

◦ Integrity

◦ Performance

◦ Teamwork.

Beach acknowledges that the consultation objectives of the Project will evolve over the course of the

Project. As stakeholder concerns or issues are better understood throughout the execution of the

Project the objectives and associated consultation activities will adjust as necessary.

3.4 Leadership commitment

Corporate leadership commitment by Beach to this PCP and the consultation objectives of the Project

is essential to ensure adequate time and resources and avoid the risk of a ‘tick-the-box’ approach.

Leadership commitment to this PCP has been gained by:

• Participation by community team members in early Project planning

Meaningful

relationships

Open respectful

dialogue

Mutually benficial

outcomes

Page 19: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

17 of 56

• Demonstration of rigorous and fit-for-purpose consultation planning

• Endorsement of the consultation purpose, principles and objectives by the Project Manager and

Beach Energy Head of Development.

Page 20: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

18 of 56

4 Consultation Methods

4.1 Consultation with landowners and occupiers

Beach proposes to conduct all consultation with landowners and occupiers in a clear and concise

manner using plain English and minimising technical terms where possible.

The landowners and occupiers impacted by the proposed Enterprise Pipeline route all have existing

pipelines on their land, in some cases these are pipelines operated by other proponents. As a result,

they represent a knowledgeable stakeholder group with experience in managing pipeline construction

and operations on their property. Beach will take this into consideration when consulting with

landowners and occupiers to balance easy to understand information with an informed and

knowledgeable audience.

Beach proposes to use the following methods to consult with landowners and occupiers on the

proposed pipeline:

• Face-to-face discussions and meetings

• Letters, phone calls and email

• Information sheets, images and diagrams

• Webpage

• Public display of regulatory documentation

• Assigning a nominated Beach contact for each landowner and occupier

• Provide access to this PCP to each affected landowner and occupier, either via a link to a web

page, or where requested by the landowner and occupier, a printed copy.

Beach is committed to conducting face-to-face consultation as much possible with landowners and

occupiers to encourage active feedback. Beach will also maintain a single point of contact for each

landowner and occupier throughout the consultation process.

Initial consultation and introduction of the Project will be undertaken by Beach’s Community Relations

Manager (Victoria) and the Community Manager, supported by local Land Liaison Officers. Land

Liaison Officers will oversee property-specific requirements and liaise with the construction contractor

on the resolution of any issues.

To protect the rights of both parties involved in the consultation process, records of all contact

between Beach and landowners and occupiers during the Project are maintained by Beach, subject to

Information Privacy requirements. Any information exchanged with the landowner and occupiers is

managed in accordance with Beach’s Privacy Policy (as per https://www.beachenergy.com.au/privacy-

policy/).

Page 21: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

19 of 56

The preferred method of communication and receiving information from Beach will be agreed with

each landowner. All documents required under the Pipelines Act will be provided in hard copy to

landowners and occupiers (e.g. Notice of intention to enter land for survey, Notice of Pipeline Corridor,

etc.) unless a landowner has advised otherwise.

4.1.1 Face-to-face consultation

Face-to-face consultation is essential to ensure planning and construction processes are understood

and that concerns raised by landowners and occupiers are understood by Beach. These meetings will

help build relationships between landowners, occupiers and Beach and will assist in a two-way flow of

information.

4.1.2 Letters

Letters will be used to outline introductory project information and provide key milestone updates

throughout the life of the Project.

Letters will be tracked via mail to ensure landowners and occupiers have received the relevant

information in a timely manner.

4.1.3 Webpage

A webpage has been established to provide up-to-date Project information. The webpage is available

at: https://www.beachenergy.com.au/enterprise-pipeline-consultation/

The webpage contains:

• Information on Beach and the proposed Project

• The regulatory approvals process

• The benefits of the Project

• Any information sheets or new information as it is developed

• Details of publicly available notices and information sessions.

In addition, the webpage will:

• Allow documents produced for public display to be downloaded, including a copy of this PCP if

and when it is approved by the regulator

• Provide methods for contacting Beach in order to provide feedback or register a complaint.

4.1.4 Phone and email

Landowners and occupiers may wish to contact the Project team by phone or email in addition to

meetings, letters and obtaining information from the website. A toll-free phone number and email will

be provided to all landowners and occupiers.

Page 22: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

20 of 56

• Project phone line: 1800 797 011

• Project email: [email protected]

The phone line allows landowners and occupiers to immediately contact Beach representatives 24

hours a day, particularly in relation to urgent landowner issues or emergency situations should they

arise. All consultation via these channels will be recorded in the Enterprise Pipeline Project Stakeholder

Engagement Log.

4.1.5 Public Display of Regulatory Documentation

Relevant documents will be placed on public exhibition where required by the statutory process or as

directed by the Department of Environment, Land, Water and Planning (DELWP).

Page 23: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

21 of 56

5 Sequence and Duration of Consultation

The proposed sequence of timing for consultation with landowners and occupiers is provided in Table

1.

The consultation proposed in Table 1 has been prepared in accordance with the Project timelines set

out in Section 1.7 of this PCP and highlights key interactions between Beach and landowners and

occupiers. The sequence and timing of the proposed consultation has been designed to ensure that all

landowners and occupiers are kept informed of the Project, and to ensure that issues are identified

and resolved in a reasonable time.

The effectiveness of consultation will be reviewed on a regular basis, and additional measures and

processes added as required to address any particular issues or concerns that may arise.

Table 1: Proposed consultation schedule between Beach and landowners and occupiers

Purpose Method

Stage 1: Proposed Initial Consultation and Notice of intention to enter land for survey

Anticipated Timing: October / November 2019 – Following approval of Pipeline Consultation Plan, if approval is

obtained

1.

Introductory meeting to inform landowners along

proposed pipeline route of the potential for Enterprise

Pipeline.

Face-to-face meeting(s) where the

following information will be provided:

• Cover Letter introducing the Project

• Copy of the PCP (if requested)

• Enterprise Pipeline Information

Sheet (Appendix B)

• Notice of intention to enter land for

survey (Appendix C)

• Regulatory Approvals Information

Sheet (Appendix B)

• Beach’s Privacy Information Sheet

(Appendix B)

2. Identify any occupiers on the land.

3.

Inform landowner/occupier of sequence of consultation

activities, the provisions under the Pipelines Act for

compulsory acquisition and the notices that are required

to be provided to them.

4. Provide Notice of intention to enter land for survey. If

appropriate gain landowner consent to Enter.

5.

Consult with landowner and occupier regarding the

potential Enterprise Pipeline, answer any questions that

may arise and provide landowner/occupier with contact

details for the Beach representative.

6.

Follow up meeting(s) to agree to access arrangements

for surveys.

Meeting will also provide an opportunity to provide

input into potential construction working areas - i.e.

identifying key constraints of the landowner/occupier.

Page 24: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

22 of 56

Purpose Method

Stage 2: Ongoing Consultation while surveys are being carried out

Anticipated Timing: Initial surveys - October / November 2019, timing of other surveys to be advised; subject to

landowner consent - Following landowner providing access to land, if landowner consent is given

7.

Consult with landowners/occupiers prior to each survey

to confirm access and any changes to conditions.

Ongoing consultation with landowners, occupiers and

stakeholders in relation to Project progress.

• Contact made by preferred method

(phone, in person or mail) with

agreed notice prior to access

• Letter for each survey detailing

activities to be undertaken,

expected timing and duration,

names and addresses of any

subcontractors who will undertake

the survey.

8. Ongoing consultation addressing concerns and issues

raised by landowners/occupiers.

• Mail, phone or face-to-face

meeting.

Stage 3: Issuing of Notice of Pipeline Corridor

Anticipated Timing: Following surveys and selection of preferred pipeline corridor

9.

Meeting arranged with landowners/occupiers, to

discuss proposed Pipeline Corridor, proposed

construction ROW, easement area and any laydown

areas will be discussed.

• Face-to-face meeting.

10. Inform landowners/occupiers of the final pipeline

alignment and location on their property.

Mail (trackable) including:

• An updated Enterprise Pipeline

Information sheet (should updates

have been made)

• Notice of Pipeline Corridor

(Appendix D).

Stage 4: Discussions, Negotiations for Option for Easement and temporary access and workspace area for pipeline

construction

Anticipated Timing: Following surveys and selection of preferred pipeline corridor

11. Reach agreement on Option for Creation of Easement

where required.

• Face-to-face meeting(s); phone

calls, emails, as appropriate

12. Reach agreement for temporary access to land for

pipeline construction.

• Face-to-face meeting(s); phone

calls, emails, as appropriate

Stage 5: Notice of Pipeline Licence Application

Anticipated Timing: Post- assessment of commercial viability of Enterprise-1 well and following lodgement of

Pipeline Licence Application to the Minister

13.

Inform landowners/occupiers of Beach’s application for a

Pipeline Licence, where a copy can be viewed, Beach’s

submission date and the process for making written

submissions to the Minister.

• Trackable post.

14.

Ongoing consultation and Project updates on progress

of application. Addressing concerns and issues as raised

by landowners/occupiers.

• Face-to-face meeting, phone or

mail.

Page 25: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

23 of 56

Purpose Method

Stage 6: Pre-construction consultation

Anticipated Timing: Following Pipeline Licence Submission, subject to regulatory approvals

15.

Meetings held with landowners/occupiers prior to

construction to assist in preparing Property

Management Plans, Construction Line Lists,

Rehabilitation Plans and any other relevant

documentation.

• Face-to-face meeting and

walkthrough of pipeline route.

16. Meetings with asset owners affected by the pipeline

construction to establish construction protocols. • Face-to-face meeting, phone.

Stage 7: Construction consultation

Anticipated Timing: Following acceptance of relevant construction documentation and bonds by the Minister and

Energy Safe Victoria (ESV), if approval is obtained

17.

Ensure landowners/occupiers are aware of the dates for

key construction activities, timing and duration of

activities, any actions they need to undertake (i.e.

moving stock) and contact details for raising issues or

concerns.

• Face-to-face meeting; phone calls,

letters.

18.

Ongoing consultation throughout construction to

address any concerns or issued raised by the

landowners/occupiers.

• In person, phone or mail.

Stage 8: Post Construction consultation

Anticipated Timing: Following completion of construction

19.

Meeting with landowners/occupiers to ensure

rehabilitation and reinstatement has been completed.

Assess any outstanding actions or issues. When

appropriate gain consent from landowners and

occupiers to acknowledgement of completion of works.

• Face-to-face meeting.

Stage 9: Consultation through operation of the pipeline

Anticipated Timing: Onwards subject to regulatory approvals - Following consent to operate from the Minister and

ESV, if approval is obtained

20.

Update land book for each parcel to document agreed

access points for pipeline operations, contact details for

operational activities, constraints and so on.

Ongoing consultation through the operation of the

pipeline in accordance with the easement conditions for

access and safety awareness campaigns.

• Face-to-face meeting, completion

of property land book; Safety

Awareness documentation.

Page 26: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

24 of 56

6 Communication materials

6.1 Communications materials

Various materials will be considered, developed and adapted based on stakeholder, landowner or

occupier needs, questions being asked, or concerns raised as the consultation process progresses. The

materials outlined in Table 2 will be used at different stages of the Project.

Table 2: Communications materials

Communication materials Description and purpose

Information sheet – Enterprise

Pipeline

Detailed information sheet that aims to inform landowners, occupiers and

local community on the Project.

Information sheet to be published on company website.

The information sheet may contain:

• Company overview

• Project description

• Reasons for the Project

• Context of the Project within other proposed or adjacent assets

developments (minimising potential stakeholder fatigue)

• Pipeline route map

• Project timeline with proposed timings for engagement, approvals, pre-

work, commencement, duration, expected completion, and possible

movement of timing

• Detailed descriptions of the activities and methodologies including

construction overview

• Diagrams and images to illustrate the activities

• Descriptions of the environment, impacts, potential risks, protection and

mitigation measures

• Approach to consultation and regulatory approvals

• Approach to managing safety, including community members

• Questions and Answers

• Encouragement to ask questions, give feedback and seek further

information

• Contact details for further inquiries: phone number; email address

• How information will be recorded and provided to the Regulator.

Information sheet – Onshore

Pipeline Regulatory Approvals

Process

Information sheet detailing specific regulatory approvals required by the

Proponent to construct a pipeline.

Information sheet to be published on company website.

The information sheet may contain:

• List of regulatory approvals

• Approach to regulatory approvals

• Easement acquisition

• Contact details for further inquiries: including names and contact details

of relevant regulators; title; phone number; email address.

Page 27: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

25 of 56

Communication materials Description and purpose

Information sheet – Privacy Information sheet detailing Beach’s Privacy Policy pertaining to personal

information collected by the Proponent regarding landowners and occupiers.

Information sheet to be published on company website.

The information sheet may contain:

• How and why information will be collected, stored, recorded and

provided to regulators, and privacy statement

• How landowners and occupiers can access their personal information

• Contact details for further inquiries: phone number; email address.

Notices to landowners and

occupiers

Notices to landowners and occupiers to inform of:

• Intention to Enter Land for survey

• Pipeline corridor

• Pipeline Licence application.

Diagrams / maps Visual aids may include: pipeline route study map; Project area map; property

land maps; Project concept diagram; construction right-of-way diagram;

constrained work space diagram.

Images Images may include: the type of pipeline construction machinery to be used,

typical right of way and pipeline markers will be used in communications

materials to develop understanding of the Project.

Timeline graphic A timeline graphic may show key Project phases and decision points, such as:

approval of the PCP; initial consultation; field surveys; easement negotiation;

Enterprise-1 drilling program complete; application for pipeline licence and

approval; construct pipeline; commissioning; first gas; and rehabilitation.

Posters Posters to be used at local stores, halls, post offices etc. providing basic

summary of Project and contact details for further information.

Public notices A public notice for Notice of Pipeline Licence application.

News articles News articles for publication in local newsletters, which can provide a

summary of the proposed Project and contact details for further information.

Questions and Answers ‘Questions and Answers’ covering potential landowner and occupier or

stakeholder queries before, during and after pipeline construction. These will

be included in the ‘Information sheet – Enterprise Pipeline’ and updated or

new questions and answers will be provided to landowners and occupiers as

required.

Webpage All Project information will be provided on the Project webpage

https://www.beachenergy.com.au/enterprise-pipeline-consultation/

PCP A copy of the PCP approved by the Minster will be provided to all

landowners and occupiers and be available on the Projects webpage for

access by other stakeholders.

6.2 Contractor awareness of materials

While all consultation will be led by Beach and supported by contractors, Beach acknowledges that it

may be necessary to offer training on the requirements of the approved consultation plan to any

Page 28: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

26 of 56

contractors likely to be involved in interaction with landowners/occupiers, including Land Liaison

Officers and work crew.

Appropriate training will ensure that the information being provided is consistent with Beach’s policy

and the consultation plan.

Page 29: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

27 of 56

7 Stakeholders

This PCP acknowledges that consultation with relevant stakeholders, landowners and occupiers

relevant to the Enterprise Project commenced in August 2018 and is ongoing.

Separate landowner and occupier consultation for the Enterprise Pipeline will be undertaken in

advance of any pipeline planning, regulatory approval and construction. There is an overlap of

stakeholders involved in the proposed drilling program and pipeline construction and as such

information on the broader project, pipeline construction and Beach’s other operational activities in

the region will be shared with stakeholders as appropriate.

7.1 Stakeholder assessment

The overarching Enterprise Project stakeholder database includes a comprehensive list of parties who

have already been identified as impacted, involved, interested or to be informed as part of the Project.

This stakeholder database was reviewed for currency in the preparation of this PCP and has been

updated to include potential landowners and occupiers relevant to the proposed Enterprise Pipeline

and the current preferred pipeline route.

Additional desktop research has also been carried out to identify further stakeholders.

7.2 Stakeholder identification

7.2.1 Private landowners and occupiers

Preliminary project investigations have indicated that there are approximately 11 landowners of 17

freehold parcels of land that will be impacted by the proposed pipeline route. The initial consultation

phase will include identifying up to date information on the current occupiers of the freehold parcels.

The majority of these freehold properties consist of farming operations for grazing, plus some

cropping. The current use of each parcel of land will be discussed with the landowner and occupier as

part of Beach’s initial consultation to identify the impacts of the proposed pipeline construction.

While Beach has existing information on land ownership, updated title searches will be undertaken just

prior to the commencement of consultation to identify any recent changes to property ownership.

7.2.2 Public landowners and occupiers

The proposed pipeline route will traverse land parcels that are owned and managed by government

authorities. These authorities include: Corangamite Shire Council, DELWP, Parks Victoria, VicRoads –

Regional Roads Victoria and Wannon Water.

7.2.3 Crown Land

Beach will undertake further assessment of the proposed pipeline route and should Crown Land be

identified Beach will seek the consent from the appropriate authority, department and Crown Land

Minister for all or access and tenure agreements.

Page 30: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

28 of 56

7.2.4 Aboriginal groups

The Eastern Maar Aboriginal Corporation (EMAC) are the registered native title claimant for the

country on which the proposed pipeline is to be constructed. EMAC are party to an Indigenous Land

Use Agreement with Beach, which was entered into at the time of the development of the Otway Gas

Plant and the construction of the PL250 Otway Gas Pipeline.

Beach will undertake consultation with EMAC to inform them of the proposed Enterprise Pipeline and

to engage their services for cultural heritage scouting activities during pipeline construction. Beach will

work with EMAC to ensure effective management of any cultural and environmental impacts.

7.2.5 Near Neighbours

These stakeholder group identified as ‘near neighbours’ may experience impacts due to traffic, dust

and noise from construction of the proposed pipeline.

Consultation with these stakeholders will be undertaken closer to the time of proposed construction

when traffic routes, working hours and other relevant Project parameters have been identified. These

stakeholders will also be provided with contact details of Beach representatives and offered face-to-

face meetings to ensure they are fully informed about the Project and have an opportunity to raise any

concerns.

7.2.6 Otway Gas Plant Community Reference Group (CRG)

Beach has been consulting with the CRG over the Enterprise project since late 2018 and will include

updates on the proposed pipeline in due course. The CRG has been in operation since the Otway Gas

Plant and PL250 were constructed in 2007 and provide a valuable consultation mechanism for Beach.

The community representatives on the CRG are mostly pipeline landowners and their feedback on

Beach’s proposed Enterprise Pipeline will be most welcomed.

7.2.7 Corangamite Shire Council

Corangamite Shire Council is the local government authority in which the proposed Project and

pipeline will be constructed. As such Corangamite Shire’s assessment of the issues that are most

important to the community will be actively sought and their feedback incorporated into Project

planning.

Moyne Shire Council has jurisdiction immediately adjacent to the proposed pipeline route and will also

be consulted throughout the life of the Project.

7.2.8 Elected officials

Local political representatives may also have an interest in the proposed Project and pipeline. These

representatives include:

• Member for the Federal Division of Wannon, Dan Tehan MP

• Member for the State electorate of Polwarth, Richard Riordan MP.

Page 31: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

29 of 56

7.2.9 Government departments and agencies

Relevant government departments and agencies that will be consulted as part of legislative

requirements include:

• Aboriginal Victoria

• Department of Environment, Land, Water and Planning

• Department of Jobs, Precincts and Regions

• Department of Transport

• Energy Safe Victoria

• Environment Protection Authority Victoria

• Parks Victoria

• WorkSafe Victoria

• VicRoads - Regional Roads Victoria

• Appropriate Crown Land Ministers

7.2.10 Other groups

A number of local community, conservation and industry groups will also have an interest in the

proposed Project. These include:

• Australian Pipelines and Gas Association

• Victorian Farmers Federation

• Community groups including Nullawarre Inc, Peterborough Golf Club, Peterborough Residents

Group, Port Campbell Community Group, Port Campbell Progress Group, Port Campbell Rifle

Range and Timboon Action Group

• Conservation groups including Friends of Bay of Islands Coastal Park, Environment Victoria,

Victorian National Parks Association, Heytesbury and Districts Landcare Network, Sustainable

Agriculture and Communities Alliance and the Wilderness Society

• Other third-party asset owners in the proposed Project area including Telstra and SP Ausnet

• Other gas operators in the proposed Project area including Lochard Energy, APA, SEAGas and

Cooper Energy.

Page 32: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

30 of 56

8 Information for Landowners and Occupiers

8.1 General

Beach is committed to developing and maintaining positive relationships with landowners, occupiers

and the broader community. Beach will complete the legislative and regulatory requirements necessary

to obtain all approvals required as part of the proposed Project. The processes associated with

obtaining access to land and tenure for construction and operation of the pipeline will comply with the

Pipelines Act and Pipelines Regulations 2017 (the Pipelines Regulations).

An information pack will be developed and distributed to all landowners and occupiers. The pack will

contain the required consultation information, as set out in section 17(2) of the Pipelines Act. The

information pack will include:

• Information Sheet on the proposed Enterprise Pipeline, including an overview of a typical pipeline

construction process

• Information Sheet on the onshore pipeline regulatory approvals process

• Where Beach holds an existing easement over the land, a copy of the easement agreement will

also be provided to the landowner for their convenience. A copy of the title plan will also be

provided to support discussions around the existing PL250 easement and the proposed route of

the Enterprise Pipeline.

8.2 Statement of independent advice

Landowners and occupiers will be encouraged to seek independent advice in relation to the proposed

pipeline, pipeline easement documents and land valuations. Agreed reasonable costs associated with

professional fees incurred in obtaining independent advice will be reimbursed by Beach.

8.3 Procedure for Agreements and Notices

Beach, in conjunction with relevant Land Liaison Officers, will be responsible for giving all required

notices. The following is the intended procedure for the service of notices:

• Attempt to arrange a face-to-face meeting with the landowner or occupier, for the purpose of

explaining the notification and for giving the notice

• Should the landowner or occupier not be available for a face-to-face meeting, the notice shall be

given via trackable postage methods.

8.4 Schedule for Agreements and Notices

Table 3 provides a detailed summary of the proposed consultation activities required for approval of

the proposed Enterprise Pipeline and any associated notices that will require issue.

Page 33: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

31 of 56

Table 3: Summary of Critical Notices and Deadlines for Pipeline Approval

Item Event Timing

Access to land for purposes of pipeline survey (subject to prior regulatory approvals)

1.

Approval of the PCP (subject to regulatory

consideration)

21 days from submission date, or re-

submission date (subject to regulatory

consideration)

2.

Initial discussion with landowners to be accessed for

survey and issue of Notice of intention to enter land

for survey (subject to outcome of PCP

review/consideration by regulator)

Following approval of PCP (subject to

regulatory consideration)

3.

Provide Notice of Intent to Enter Land and seek

landowner consent

Enter into agreement with each landowner and

occupier to enter land and conduct pipeline survey(s)

As soon as practicable after Notice of

intention to enter land for survey issued to

owner

If no access agreement with owner

4. If no agreement reached on one or more parcels of

land, apply to Minister to enter relevant land

At least 14 days after issue of Notice of

intention to enter land for survey

5. Advise owners and occupiers of land where no access

agreements reached of application to Minister

At same time as application to Minister

issued

6. Owner and/or occupier has option to make

case for refusal to Minister

No more than 7 days after receiving

advice of the application to the Minister

7. Minister makes decision about application to Enter

Land

Decision made no more than 28 days

after receiving application

Notice of Pipeline Corridor

8. Provide formal Notice of Pipeline Corridor to owner

and occupier

As soon as practicable after decision

made on pipeline route

Creation of Pipeline easement (where required)

9.

Enter into agreement with landowner for temporary

access to workspace for pipeline construction. Where

new easements are required, enter into an Option for

Creation of easement over the relevant section of the

pipeline corridor

As soon as practicable after Notice of

Pipeline Corridor issued

If no easement purchase agreement reached

10.

If ongoing attempts to reach Option agreement with

landowner remain unresolved, submit application to

Minister to consider granting consent for Beach to

compulsorily acquire pipeline easement, and advise

owners of land to which the application/s relates of

the outcome of this decision

At least 6 months after issue of Notice

of Pipeline Corridor (but may be sooner

if Minister agrees)

11. Provide Notice of easement application to

Registrar of Titles

Without delay after application to

Minister to compulsorily acquire

Page 34: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

32 of 56

Item Event Timing

easement

12. Owner and/or occupier has option to make

submission about the pipeline corridor to Minister

Before 'submission date' of Application

to Construct and Operate a Pipeline

Application to construct and operate a pipeline

13.

Submit Application to Construct and Operate a

Pipeline

Minister determines 'submission date' once

satisfied the Application is complete.

Approval to be granted within

28 days, unless decision is referred to a

committee in which case the approval

duration is 88 days

8.5 Notice of intention to enter land for survey

Under Section 19 of the Pipelines Act, Beach is required to notify each landowner and occupier of the

impacted land (including Crown land) of the Beach's intention to enter the land for purpose any

survey. Appendix C provides an example of a Notice of intention to enter land for survey.

8.6 Notice of Pipeline Corridor

Before applying for a pipeline licence, Beach must give a Notice of Pipeline Corridor to each landowner

and occupier within the pipeline corridor, as prescribed in Regulation 7 and set out in Schedule 1 of

the Regulations (Notice pursuant to section 27 of the Pipeline Act). Appendix D provides an example

of a Notice of Pipeline Corridor.

8.7 Notice of Pipeline License Application

Following submission of the Pipeline Licence Application to the Minister, a Notice of Pipeline Licence

Application, pursuant to Section 32 of Pipelines Act, must be given by Beach to each landowner and

occupier directly affected by the Licence Application. Landowners and occupiers must be advised on

where to view a copy of the licence application and the accompanying information.

The Notice of Pipeline Licence Application will be published in the Herald Sun, and local newspapers,

the Cobden-Timboon Coast Times and Warrnambool Times (The Standard). A copy of the licence must

also be made available for public view, on display in hard copy at all Beach offices. See Section 14.1 of

this PCP for Beach information and office locations.

There is a statutory opportunity for landowners and occupiers to make submissions to the Minister

about the Pipeline Licence Application. This is described in the Pipelines Act. The Notice of Pipeline

Licence Application provided to the landowners and occupiers includes a date for submissions

determined by the Minister. Landowners and occupiers have until the submission date to make a

submission to the Minister regarding the Pipeline Licence Application.

8.8 Agreements with landowners and occupiers

Beach will require access to land in order to construct and operate the proposed pipeline and may

seek to establish either long-term or temporary access agreements with landowners and occupiers.

Page 35: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

33 of 56

This could include easement purchases or licencing arrangements for construction and operation of

the proposed pipeline.

Beach is committed to clear and transparent communications during tenure and other discussions with

landowners and occupiers to ensure they have an appropriate understanding of the requirements and

potential impacts of the construction and operation of the proposed pipeline.

Page 36: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

34 of 56

9 Evaluation of consultation

Beach will evaluate the progress of consultation that forms part of the proposed Project at key Project

milestones. This ongoing evaluation of consultation activities and records will enable the identification

of any risks that may conflict with the Project consultation values and objectives.

The consultation evaluation process will include:

• Progress of key consultation inputs against the proposed project timeline:

◦ Approval of the PCP subject to regulatory consideration

◦ Leadership commitment to PCP

◦ Final investment decision

◦ External communications materials completed

◦ Project Team support in responding to landowner, occupier or stakeholder questions or

concerns

◦ Landowner, occupier or stakeholder risks which may impact on Project success.

• Progress of consultation activity:

◦ Assessment of stakeholders reached

◦ Assessment of stakeholders responded

◦ Stakeholder meetings held

◦ Response times adherence

• Progress toward consultation outcomes:

◦ Key questions arising from landowners, occupiers or stakeholders

◦ Key concerns raised

◦ Assessment of positive, neutral, negative sentiments

◦ Key consultation risks

◦ Assessment of progress toward goals for each stakeholder group

Upon completion of the proposed Project, a full evaluation will be undertaken including:

Page 37: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

35 of 56

• A survey undertaken of a sample of landowners and occupiers about the efficiency and relevance

of consultation activities

• Final assessment of consultation activity against planned actions and timeline

• Final assessment of stakeholder responses (quantity; methods; and sentiment)

• Debrief with community and Project Team for feedback

• Lessons learned workshop to inform future projects.

Page 38: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

36 of 56

10 Collection of Stakeholder Information and Records Management

In order to accurately collect and store consultation on the proposed Project, Beach will use its existing

system for recording and managing stakeholder information.

The system is a central repository for important and confidential stakeholder, landowner and occupier

information such as correspondence, agreements, records of contact, feedback, complaints and claims

records and resolutions, incident records, meeting notes and monthly Project consultation reports.

A dedicated Enterprise Pipeline Project Stakeholder Engagement Log will also be used to track all

specific Project stakeholder, landowner and occupier consultation, including: text messages; phone

calls; emails; written correspondence; meetings; and feedback in public forums. The log is a ‘live’

document that shall be updated as consultation activities are undertaken as part of the proposed

Project.

The Enterprise Pipeline Project Stakeholder Engagement Log will be used to prepare the required

“Consultation Report” outlined in Section 10.3 Statutory Reporting.

All consultation records and entries will be secured by login username and passwords given only to

relevant Project team members who require access. Beach will maintain this system and system

maintenance and back-ups will be undertaken in accordance with IT requirements.

10.1 Record keeping

10.1.1 Privacy and Use of Confidential Information

Beach’s privacy policy (as per https://www.beachenergy.com.au/privacy-policy/) shall be followed

during all consultation and correspondence management.

10.1.2 Internal Records Management

All feedback, complaints and claims must be recorded in a permanent register of Community Feedback

and Complaints by a Community Team member.

All Complaints must also be recorded as an incident in Beach’s Incident Management System.

However, personal details must only be recorded where these details are restricted to the Corporate

Affairs and Community team members, in order to protect the privacy of community members.

All telephone and in-person meetings with complainants must be:

• Recorded in the Enterprise Pipeline Project Stakeholder Engagement Log

• Summarised with accurate meeting notes filed on the Community Team server.

10.2 Response to Stakeholders

10.2.1 Responding to concerns issues or claims

Any objections, concerns or claims that may be raised during the life of the proposed Project shall be:

Page 39: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

37 of 56

• Captured in the Enterprise Pipeline Project Stakeholder Engagement Log

• Raised with the relevant Project Team member responsible for reviewing, assessing, researching

the matter as applicable and preparing a response with genuine consideration of relevant

regulations

• Complex matters that cannot be resolved or replied to within 7 business days, shall be added to

the Project Complaints Tracking System until a response to the stakeholder is issued,

acknowledged and the matter closed.

Prior to construction, any objections, issues, concerns or claims will be acknowledged within 24 hours

and responded to within 5 business days.

During the construction phase of the proposed Project, matters raised will generally be of a more

time-critical nature. Acknowledgement will be made within 4 hours with responses including a

resolution timeframe aimed to be provided within 24 hours, unless agreement has been reached with

the stakeholder that a longer period is appropriate.

10.3 Statutory reporting

Beach will produce monthly reports to DELWP that contain the previous month's consultations with

external stakeholders, including particular references to any complaints or grievances.

Reporting will be undertaken from initial consultation with stakeholders, landowners and occupiers

through to completion of the regulatory approval process, providing consent of the Construction

Environmental Management Plan (CEMP) and safety management plans and subject to a pipeline

licence being issued. From then, reporting will be in accordance with the CEMP or other management

documents.

This reporting of consultation activities will be based on a calendar month and provided to DELWP

within five (5) business days of the end of the reporting period (being the end of the month). The

report template is provided at Appendix F.

10.4 Media enquiries

All media enquiries related to the proposed Project will be directed to Beach’s Corporate Affairs group

responsible for handling media enquiries.

Page 40: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

38 of 56

11 Compulsory Acquisition of Land

11.1 Pipelines Act

The Pipelines Act and the Pipeline Regulations outline a process to guarantee fair and equitable

treatment of landowners leading to the negotiation of easement rights. Beach is dedicated to

providing fair and equitable compensation to impacted landowners for the negotiation of easements

and additional temporary workspace arrangements. Compensation will be negotiated in line with the

Pipelines Act.

The proposed route for the Enterprise Pipeline requires only a small number of new easements to be

created as the route has been selected to utilise the existing easements for the PL250 pipeline.

Where negotiations with a landowner/occupier regarding the Options for Creation of Easement has

been unsuccessful, under the Pipelines Act, Beach is permitted to apply to the Minister responsible for

the Pipelines Act for approval to compulsory acquire the easement area after six months from the

service of the Pipeline Corridor Notice. This will only occur if negotiation has been unsuccessful and

Beach must be able to clearly demonstrate compliance with the required steps and measures for this

process.

11.2 Land Acquisition and Compensation Act

If a process for compulsory acquisition of land is required throughout landowner and occupier

negotiations, Beach must adhere to the relevant sections of the Land Acquisition and Compensation Act

1986 (Vic) (LACA) and the Land Acquisition and Compensation Regulations 2010. This process is only

established if Beach is successfully granted Ministerial consent pursuant to the Pipelines Act, of an

application for Consent to Compulsorily Acquire an Easement Over Private Land. A Notice of

Application, provided to all interested parties will contain a statement of rights and obligations, which

will include the interested party’s right to make a written submission to the Minister by a specified

date, determined by the Minister. Beach will also promptly provide the Registrar of Titles with the

prescribed Notice of Application, which the Registrar will record.

The outcome of the application for compulsory acquisition will be decided by the Minister within 28

days of the submission date. If the Minister grants the application, a Notice of Acquisition outlining the

acquisition will be published in the Government Gazette, as well as provided to all interested parties

and published in a local newspaper relevant to the era of acquisition.

Once the notice is gazetted, Beach has 14 days to make a fair and equitable compensation offer

payable to the landowner/occupier. The interested parties then have a three-month period to respond

to the offer and may lodge a counter claim for compensation with Beach within this period. Beach will

consider the counter claim and must respond within three months of receiving the claim. If a

settlement over the level of compensation payable cannot be reached, either Beach or the

landowner/occupier may refer the matter to the Victorian Civil and Administrative Tribunal for

amounts less than $50,000 or may seek a court hearing for disputes greater than $50,000.

Attempt to negotiate the terms of access must be undertaken by Beach, and a minimum seven days’

notice must be given before entry into tenure of the land. In the case where the land is the primary

Page 41: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

39 of 56

place of residence or business of the landholder, Beach must allow three months from the date of

acquisition to take tenure of the land, unless an agreement is reached with the landholder(s) for access

and tenure of the land.

Page 42: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

40 of 56

12 Overview of Pipeline Construction Process

12.1 Initial survey

The initial survey offers a consolidated suite of information that is used to refine the design of the

pipeline through a Safety Management Study (SMS) which is undertaken to assess the threats that

land usage, nearby infrastructure and topography represents to the pipeline. The safety of the public

and all personnel is paramount to the operating goals of the pipeline, along with minimising

environmental and property impacts. The SMS ensures that all threats are understood and controls to

mitigate them are as effective as possible.

Geotechnical investigations will also occur along the pipeline route at significant junctions such as

road or creek crossings, where methods such as horizontal directional drilling (HDD) may be required

to install the pipeline using minimal excavation.

Affected landowners and occupiers will be notified in advance of any survey activities including timing,

location and access requirements, and their views sought on local conditions relevant to pipeline

installation. Access protocols concerning biosecurity management, physical access requirements, hours

of operation and so on, will be documented.

12.2 Setting up Work Areas

Prior to construction, crews are required to prepare work areas and machinery such as pipe laydown

yards, construction material stockpiles, and areas for trenchless construction and HDD (where

applicable).

Additional temporary work areas and access points will be discussed and clearly defined with the

relevant landowners and occupiers, including changes to fences or gates and negotiated

compensation, prior to any activities being undertaken on the property. Wash down stations to stop

transfer of undesirable biological materials will be strategically located within the transport routes.

12.3 Clear and grade

Clear and grade involves preparing the pipeline easement for the pipeline and to allow construction

activities to commence. This includes any additional temporary work areas as agreed with landowners

and occupiers. The combined easement and additional work area is commonly referred to as the

construction right-of-way (ROW).

Any vegetation and topsoil is removed from the construction ROW and stockpiled separately to avoid

soil inversion and assist in rehabilitation works after the pipeline is completed. To minimise impact to

the surrounding environment, construction crews may only remove trees and vegetation only in

accordance with the receipt of appropriate permits.

Equipment that may be used during the clear and grade process can include graders, excavators and

bulldozers to clear and prepare the easement ready for construction activities to commence.

Page 43: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

41 of 56

12.4 Typical set-up within the construction ROW

The construction ROW includes the official easement and temporary additional work areas.

The construction ROW is clearly defined and fenced off if required. The common width of the

construction ROW is usually between 20 – 30m. Landowners and occupiers will be consulted over

elements including clear and grade timing, arrangements for fencing, dust and noise management and

biosecurity. Landowners and occupiers will have the opportunity to ensure actions agreed as part of

the Property Management Plan negotiations are satisfactorily managed.

Figure 5 demonstrates the typical pipeline ROW.

Figure 5: Typical pipeline ROW

12.5 Trenching

Following preparation of the construction ROW, construction crews will commence trenching for the

pipeline. Typically, specialised trenching machines or excavators are used to dig the trenches. Final

trenching techniques are to be determined in conjunction with the chosen construction contractor.

As with the clear and grade phase, soil removed from the trench will be stockpiled throughout the

duration of the construction process. Issues such as hours of operation and dust and noise

management will be discussed with the landowners and occupiers.

12.6 Trenchless construction

Trenchless construction is used when standard trenching techniques cannot be used, such as rivers

crossing, or some public roads.

Techniques such as HDD are used to install pipelines with minimal excavation. Specialist operators drill

a hole beneath the surface, at a shallow angle, and then pull a welded length of pipe through the hole

Page 44: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

42 of 56

without disturbing the surface. These operations are highly engineered and are used to eliminate

disturbances to infrastructure, environmentally sensitive areas, and to address construction issues.

Trenchless methods have been used consistently in pipeline construction for many years.

12.7 Welding

Pipe sections are joined together by a specialised welding crew. Welds are then testing using non-

destructive testing (NDT) techniques to ensure weld integrity and then coated to protect against

corrosion. Throughout the welding process, fire regulations and restrictions are followed at all times.

12.8 Sand Padding and Lowering In

After final assessment of the pipeline weld and coating quality, the trench is padded with sand and the

pipe is lowered into the trench using the specialised side boom trucks. Side boom operators

coordinate to move slowly and in unison to lower the pipe.

12.9 Backfill

Soil previously removed from the trench is compacted back into the trench to cover the pipeline. In

rocky terrain, further sand padding is used to protect the pipeline. Subsoil is screened and backfilled

before topsoil and care is taken to keep them separated to ensure that pasture or other groundcover

can be rehabilitated.

12.10 Easement Rehabilitation

As stated in Section 145 of the Pipelines Act, Beach is required to rehabilitate landowner and occupier

property as soon as practicable following pipeline construction to enable it to be used as far as

practicable for the purposes for which it was used immediately before the construction of that part of

the pipeline, or, with the prior approval of the Minister, for any other purpose agreed between Beach

and the landowner/occupier.

Following rehabilitation, the landowner and occupier are requested to acknowledge that rehabilitation

of the land has been completed to an acceptable standard and has met the above requirements.

12.11 Hydrostatic testing

The pipeline will be hydrostatically tested upon verification of construction completeness to ensure its

mechanical integrity. Hydrotesting involves filling the pipeline with water and pressurising and

sustaining pressure for a period of time, testing it for strength and leak tightness. The exact sequence

of the pipeline hydro testing is dependent on the construction sequence.

Sources and the disposal of water used for hydro testing will be determined during the detailed design

phase of the Project and documented in the Construction Environment Management Plan. They will

also be determined in consultation with local councils, relevant water authorities, the Environmental

Protection Agency, landowners and occupiers.

Page 45: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

43 of 56

Once the installed pipelines have successfully passed the hydrostatic pressure test, a process of

dewatering and drying will be conducted prior to the final tie-ins of the completed system. Following a

sequence of engineering and safety checks, gas will be introduced to pressurise the system.

12.12 Eventual decommissioning of this proposed pipeline

A licenced pipeline must be decommissioned in accordance with AS 2885, referring to the APGA

Environmental Code of Practice, specifically Section 9 and the approved decommissioning plan.

The Pipelines Act requires this decommissioning plan to be approved by the regulatory authority. An

environmental risk assessment process that identifies any potential effect on the environment and

other uses and users of the easement should support decommissioning preparation.

If the decommissioned pipeline is left in place, appropriate measures will be taken to prevent

contamination of soil or groundwater and to avoid land subsidence impacts.

Page 46: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

44 of 56

13 Management of potential impacts

Beach is committed to working with landowners and occupiers throughout the construction and

operation of the proposed pipeline so to ensure impacts are minimised and, where possible, avoided.

The potential impacts of the proposed pipeline to landowner and occupier property during

construction will be managed via data collected from initial surveys and the development of Property

Management Plans (PMP).

Beach will involve all affected landowners and occupiers in the development of their respective PMP to

ensure that concerns and issues are directly reflected in the alternatives developed and to provide

feedback on how landowners and occupiers' input influenced the pipeline construction on their

property.

Potential impacts to health, safety and the environment will be managed within Beach’s corporate and

Project HSE policies via a number of management plans to be developed and applied during each

phase of the Project and prepared to the satisfaction of the relevant regulatory agencies.

Subcontractors will be made aware of their commitment and responsibility to comply with quality

management and HSE requirements.

Key management plans that will be developed for the proposed pipeline are provided in Section 13.1

and 13.2.

13.1 Pipeline construction

During construction, Beach intends to collaborate with landowners and occupiers on ways to mitigate

any construction or operational impacts on the land. Feedback from these discussions will be fed into

Project management plans.

13.1.1 Construction Environmental Management Plan (CEMP)

A Construction Environmental Management Plan (CEMP) will be prepared by the pipeline contractor to

ensure that the construction of the pipelines meets all relevant environmental obligations. It is the key

document for managing potential environmental risks associated with the construction of the pipeline.

13.1.2 Construction Safety Management Plan (CSMP)

The pipeline will be designed, constructed and operated in accordance with the Australian Standard

for gas pipelines AS2885. AS2885 outlines the compulsory minimum requirements that the pipeline

must meet.

The Construction Safety Management Plan (CSMP) will be developed to meet the relevant polices and

AS2885 requirements. The construction contractor is required to implement the systems and

procedures outlined in the CSMP, including incident reporting, hazard alert protocols, hazard analysis

processes and safety meetings.

Page 47: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

45 of 56

13.1.3 Cultural Heritage Management

Beach will work closely with Aboriginal Victoria and EMAC to ensure pipeline activity does not impact

cultural heritage and is in compliance with the Aboriginal Heritage Act, 2006 (Vic).

13.1.4 HDD Management Plan

The HDD Management Plan will be developed to define the management system, procedures, workers

and equipment required for safe and reliable HDD crossings. These operations are highly engineered

and are used when standard trenching techniques are not suited to certain conditions, such as

crossing under rivers or some public roads.

13.2 Pipeline operation

13.2.1 Environmental Management Plan (EMP)

Ongoing activities that support the operation of the pipeline will be evaluated through development

of an Environment Management Plan (EMP), which identifies the risk to the environment arising from

the operation of the pipeline and specifies measures to manage those risks as detailed in the Part 7 of

the Pipelines Regulations.

13.2.2 Safety Management Plan (SMP)

The Operations Safety Management Plan will be developed to deliver an integrated safety

management approach in line with Beach’s existing safety management procedures and practices for

pipeline operations as per Part 9 of the Pipelines Act.

13.2.3 Pipeline Stakeholder Engagement Plan (PSEP)

In preparation for the operational phase of the Enterprise Pipeline, Beach’s internal Pipeline

Stakeholder Engagement Plan (PSEP) (Victoria) (CDN/ID 9139256) will be reviewed and updated to

include details of the Enterprise Pipeline, and incorporate any relevant obligations from the OEMP and

OSMP. This document outlines Beach’s approach and obligations with regard to stakeholder

consultation for its operational pipelines.

13.2.4 Property Land Books

As the pipeline becomes operational, Beach will meet with individual landowners and occupiers and

collect (or update existing) information regarding access to the pipeline for operations and

maintenance as well as any property specific requirements. This information is collected in a ‘Land

Book’ for each pipeline.

Page 48: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

46 of 56

14 Further information

14.1 Beach Energy Contact Information

Beach Energy is the proponent of the proposed Enterprise Pipeline.

Beach Energy’s contact details are:

Details

Titleholder Lattice Energy Limited

Titleholder representative Beach Energy Limited

Beach Energy business

address(s)

Head Office:

Level 8

80 Flinders Street

Adelaide SA 5000

Melbourne Office:

Level 15

150 Lonsdale Street

Melbourne VIC 3000

Beach Energy website

Beach Energy Enterprise Pipeline

Project webpage

https://www.beachenergy.com.au

https://www.beachenergy.com.au/enterprise-pipeline-consultation/

Beach Energy representative Enterprise Pipeline Project - Community Relations Manager Victoria

Project Phone, operated 24 hours, 7 days – 1800 797 011

Beach Energy email – [email protected]

14.2 Regulatory Agencies and Advocacy Groups

Beach has committed to providing stakeholders, landowners and occupiers with alternative sources of

information. These sources are also listed on the Onshore Pipeline Regulatory Approvals Information

Sheet.

14.2.1 Organisations

Victorian Department of Environment, Land, Water and Planning

W: energy.vic.gov.au

T: 0439 799 598

E: [email protected]

Energy Safe Victoria

Attn: Gas Technical Helpline

Phone - 1800 652 563

Email - [email protected]

Page 49: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

47 of 56

Victorian Farmers Federation

Attn: Land Management and Planning

Lisa Gervasoni - Phone - +61 1300 882 833

Email – [email protected]

14.2.2 Legislation

Victorian

Website: http://www.legislation.vic.gov.au

Federal

Website: http://www.comlaw.gov.au/ or www.austlii.edu.au

Relevant Acts and Regulations:

• The Pipelines Act -

http://www.legislation.vic.gov.au/domino/web_notes/ldms/pubstatbook.nsf/f932b66241ecf1b7ca2

56e92000e23be/5ef231c52d23ae2bca2570820023a8fc/$FILE/05-061a.pdf

• The Pipelines Regulations -

https://www.energy.vic.gov.au/__data/assets/pdf_file/0021/65082/Pipelines-Regulations-2017.pdf

• Land Acquisition and Compensation Act 1986 (Vic) (LACA) -

http://www.legislation.vic.gov.au/Domino/Web_Notes/LDMS/LTObject_Store/LTObjSt2.nsf/DDE300

B846EED9C7CA257616000A3571/F156CCF7A54A2272CA2577610024A4F8/$FILE/86-121a044.pdf

• Land Acquisition and Compensation Regulations 2010.

Relevant Australian Standards

• AS 2885.1-2012 Pipelines - Gas and Liquid Petroleum – Design & Construction

• AS 2885.3-2012 Pipelines – Gas and Liquid Petroleum – Operation & Maintenance

• AS 2885.4 defines the application of DNV OS-F101 (Det Norske Veritas, Offshore Standard for

submarine pipeline systems) for design, construction and operation of offshore submarine

pipelines within AS 2885.

14.2.3 Other Pipeline Publications and Information

APGA

• Pipeline Corridor Committee Publications - Investigations of land use around pipelines to guide

initial location classification under AS2885 guideline

https://www.apga.org.au/sites/default/files/uploaded-content/website-

Page 50: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

48 of 56

content/investigations_of_land_use_around_pipelines_to_guide_initial_location_classification_under

_as_2885_guideline.pdf

• Stakeholder Engagement Guidelines

https://www.apga.org.au/sites/default/files/uploaded-content/website-content/stakeholder-

engagement-guidelines.pdf

Energy Victoria

• Proposed Pipelines Regulations – Regulatory Impact Statement, Department of Environment, Land,

Water and Planning, 19 December 2016

https://www.energy.vic.gov.au/__data/assets/pdf_file/0025/72808/Final-Pipelines-RIS-.pdf

Energy Safe Victoria

• GPIS Information Bulletin 3 – Illegal repairs to damaged live gas infrastructure, March 2018

https://esv.vic.gov.au/wp-

content/uploads/2019/04/GPIS_Bulletin_Illegal_repairs_gas_infrastructure.pdf

• Gas and Pipeline Infrastructure Safety Case Policy

https://esv.vic.gov.au/wp-content/uploads/2019/07/Gas-and-Pipeline-Infrastructure-Safety-Case-

Policy.pdf

• Gas and Pipeline Infrastructure Safety Management Report, 2016-2017

https://esv.vic.gov.au/wp-content/uploads/2018/02/GPIS_SafetyManagementReport_2016-17.pdf

• Gas and Pipeline Infrastructure Safety Management Report, 2017-2018

https://esv.vic.gov.au/wp-content/uploads/2019/05/GPIS-Management-Report-2017-18.pdf

Earth Resources – Petroleum

• VGP Fact Sheet 1 – Assessing our Future Gas Resources potential

https://earthresources.vic.gov.au/__data/assets/pdf_file/0006/466962/Factsheet-VGP-Assessing-

our-future-gas-resource-potential.pdf

Property and Land Titles Victoria

• Victorian Government, Land Transactions Policy and Guidelines, April 2016

https://www.dtf.vic.gov.au/sites/default/files/2018-

01/Victorian%20Government%20Land%20Transactions%20Policy%20and%20Guidelines.pdf

Page 51: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

49 of 56

15 Document Information

Document custodian group

Title Name/s

Community Manager Amanda Keely

Document author

Position Name

Community Advisor Stephanie Eggleston

Process maintainer

Position Name

Community Relations Manager (Victoria) Linda French

Stakeholders and other contributors

Position Name

Patrick Flynn Project Manager

Mike Elliss Otway Onshore Lead Facilities Manager

Phil Chen Project Engineer

Catriona King Environmental Advisor

Chris Burford Corporate Affairs Manager

Document history

Rev Date Changes made in first document Reviewer/s Consolidator Approver

A 30/07/2019 Issued for community team internal

review

Amanda Keely,

Linda French

Stephanie

Eggleston

Amanda Keely,

Linda French

B 5/08/2019 First round review – CNC Project

Management

Sally Commins Tony Judd Tony Judd

C 13/08/2019 Review of First Draft Mike Elliss, Phil

Chen, Catriona King

Stephanie

Eggleston

Amanda Keely

D 27/08/2019 Second review – CNC Project

Management

Sally Commins Tony Judd Susie Bartlett

E 29/08/2019 DELWP review of draft Kim Cooper Stephanie

Eggleston

Amanda Keely

F 06/09/2019 Review of Final Draft Mike Elliss, Phil

Chen, Catriona

King, Patrick Flynn,

Amanda Keely

Stephanie

Eggleston

Amanda Keely

0 13/09/2019 Issued for use – Ministerial approval DELWP

Page 52: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

50 of 56

Appendix A Checklist of requirements for a consultation plan

Requirements for a consultation

plan

(s17, the Pipelines Act)

Reference to section of this

document

Reference to information

sheets

1. A consultation plan must–

a. be prepared in accordance with

the regulations; and

Pipelines Regulations does not

contain any requirements in relation

to the preparation of a consultation

plan.

b. set out the information that the

proponent is to provide to

owners and occupiers of land to

whom notice must be given

under Division 2 or 3.

Information on purpose, means,

timing and verification of each stage

of consultation is outlined in Section

8. Specific examples of information

are included in the Appendices.

Refer to Onshore Pipeline

Regulatory Approvals

information sheet “Notices to

landowners and occupiers”.

2. The information to be provided to owners and occupiers of land must include–

a. general information about the

types of activities to be

undertaken by the proponent

for the purpose of any survey

under Division 2 or the

construction and operation of

the pipeline;

Information on purpose, means,

timing and verification of each stage

of consultation is outlined in Section

5. Specific examples of information

are included in Appendices.

Refer to Enterprise Pipeline

information sheet “Questions

and Answers”.

b. information about how

potential adverse impacts of

the construction and operation

of the pipeline on land, health,

safety and the environment are

to be managed;

Information relevant to managing

potential impacts is outlined in

Section 13. Specific examples of

information are included in

Appendices.

Refer to Enterprise Pipeline

information sheet “Questions

and Answers”.

c. details of the procedures that

are to be followed under this

Act and any other Act to permit

the construction and operation

of the pipeline including the

procedures for any compulsory

acquisition of land.

Consultation undertaken in relation

to the construction and operation of

the pipeline are outlined in Section

5. Information relevant to the

compulsory acquisition of land is

contained in Section 11.

Refer to Onshore Pipeline

Regulatory Approvals

information sheet.

d. a statement–

i. advising that owners and

occupiers of land may seek

independent advice on the

pipeline proposal; and

Refer to Section 8.2 Refer to Enterprise Pipeline

information sheet “Questions

and Answers”.

ii. setting out current contact

information for the

Department.

Refer to Section 14.2 and landowner

information sheets contained in

Appendices.

Refer to Enterprise Pipeline

information sheet and Onshore

Pipeline Regulatory Approvals

Page 53: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

51 of 56

information sheet “Regulatory

Authorities”.

Page 54: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

52 of 56

Appendix B Information Sheets

Page 55: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 1 of 12

Enterprise Pipeline ProjectProject update | October 2019

Project overview The Enterprise Project is a program to develop additional offshore natural gas reservoirs in the Victorian Otway Basin. The potential reservoirs are located offshore, up to 3 nautical miles (5.55 km) from the coastline, while the well site will be located onshore near Port Campbell (see map overleaf). If Beach determines that the exploration well is commercially viable, a pipeline will be constructed to flow the raw gas for processing at the nearby Otway Gas Plant (OGP), for supply to the Australian domestic gas market. Timings for pipeline construction approvals require us to commence consultations early, before we have fully assessed commercial viability of the first Enterprise well. beachenergy.com.au

Beach Energy is an ASX listed oil and gas, exploration and production company headquartered in Adelaide. It has operated and non-operated, onshore and offshore, oil and gas production from five production basins across Australia and New Zealand and is a key supplier to the Australian east coast gas market.

In January 2018, Beach acquired permits and operational assets in Victoria through its acquisition of Lattice Energy Limited. As Lattice is a wholly owned subsidiary of Beach Energy, all assets on the project will be operated under the Lattice name, including all applications for regulatory approvals, such as the Pipeline License. Information sheets and other associated consultation materials and activities use the Beach Energy name and branding.

About Beach

Page 56: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 2 of 12

Pipeline information Initially, a single exploration well called Enterprise-1 will be constructed using ‘extended reach drilling’ (ERD) accessed from the Enterprise drill site to the offshore licence block VIC/P42 (v) in Victorian State waters. For more information please visit www.beachenergy.com.au/vic-otway-basin/

If the exploration well proves successful, construction will commence on a new high strength steel pipeline approximately 12km long, and 200-300mm in diameter. Buried at a minimum depth of 750mm, and 1200mm at road crossings, the pipeline will flow the raw natural gas from the Enterprise Well site to the Otway Gas Plant. Alongside the gas pipeline, a 50mm-100mm diameter mono-ethylene Glycol (MEG) line will be used to circulate MEG which acts as an anti-freeze, and to prevent corrosion of the pipeline. The pipeline trench will also carry a fibre optic cable to connect the well site monitoring systems to the control room at the OGP, to

enable 24/7 monitoring of the well site. It is proposed that the new Enterprise pipeline will be constructed alongside the existing Otway Raw Gas Pipeline (PL250) for the majority of its length. Several alternative pipeline connections were investigated but would have a negative effect on the production of existing wells.

The proposed pipeline, MEG line and fibre optic cable will be installed in the same trench, as highlighted in the diagram below. To safely construct the pipeline, additional temporary work space, in addition to easement, will be required. Agreements regarding the use of these areas will be negotiated with the relevant landowners and occupiers. A transparent and respectful consultation process will be undertaken to engage with landowners and occupiers who will be affected by the planning, construction and ongoing inspections to ensure the safe operation of the Enterprise pipeline.

Linda French – Community Relations Manager Victoria

Page 57: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 3 of 12

Pipeline Route & LocationThe current proposed pipeline route runs from the onshore Enterprise well site near Port Campbell, joining into existing easements housing Beach’s PL250 Otway pipeline, and connects to the existing gas processing facility, Otway Gas Plant. Where new easements are required Beach will consult with the relevant landowners, in addition to existing easement landowners.

Beach has been assessing and will continue to assess alternative pipeline routes, however the route described

above is the preferred option at this time. The selection process for the final pipeline route will include the outcomes of the consultation process and will consider many factors, including project requirements, existing easements, landowner considerations, options to minimise environmental and cultural impact, geotechnical considerations and land tenure for both the construction and operational phases. The proposed corridor is shown below.

Schematic showing vicinity of onshore project area and proposed pipeline route.

Port

Cam

pbel

l Cre

ek

Enterprise-1 Drill Site

Otway Gas Plant

Port Campbell

Great Ocean Road

Shar

ps R

oad

Curdievale

Port Campbell Road

Great Ocean Road

Port

Campbell Roa

dEastern Creek Road

VictoriaN

GD19-0086

Traditional CustodiansBeach would like to respectfully acknowledge the Eastern Maar Peoples, the Traditional Custodians of the land on which the Enterprise Pipeline Project will be located. Beach respects their historical and ongoing connection to country through cultural and spiritual sites, language and ceremony, and would like to pay our respect to their Elders past, present and emerging.

“Eastern Maar” is a name adopted by the people who identify as Maar, Eastern Gunditjmara, Tjap Wurrung, Peek Whurrong, Kirrae Whurrung, Kuurn Kopan Noot and/or Yarro waetch (Tooram Tribe) amongst others.

Page 58: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 4 of 12

Project timingsConstruction for the Enterprise Pipeline will not commence before late 2020, following extensive landholder, occupier and community consultation and after approval has been received for the project’s Pipeline Consultation Plan (PCP) by the relevant regulatory authority. Project timings will depend on several factors including regulatory approvals, internal technical and financial approvals and availability of suitably qualified and experienced contractors. Beach are aware of concerns and challenges about operating in wet weather conditions and are factoring these concerns into our planning. The project will run over phases with different levels of activity, vehicle movements and

people on site. The project phases and indicative timings are shown below. Confirmation of an actual start date for pipeline construction will be provided once all approvals and contracts are in place.

The duration of activity on individual properties will depend on the progress of the works as a whole, the scope of the work required on each property and the weather. Activities will continue to occur on each property throughout the construction period. Remediation of the land, following final pipeline testing, is the last access to property required during the construction phase.

• Approval of Pipeline Consultation Plan by the Minister (subject to regulatory consideration)

• Commence consultation with landowners and occupiers and issue Notice of intention to enter land for survey.

• Field surveys commence and clarification of pipeline alignment

• Ongoing consultation with landowners, occupiers and stakeholders

• Prepare appropriate regulatory approval documents and applications.

• Negotiations with landowners/occupiers commence for pipeline construction, including new easements where required.

• Drilling Project Complete (Enterprise-1 well)

• Notice of Pipeline Corridor provided to all landowners/occupiers and required stakeholders.

• Application for Pipeline Licence• Commence broader community consultation with other impacted stakeholders plus those

involved and those to be kept informed

• Pipeline License Approved (subject to regulatory consideration).

• Construction Environment Management Plan submitted for consideration for approval

• Rehabilitation Bond Accepted by the Minister

• Construction Safety Management Plan submitted to Energy Safe Victoria for consideration for approval

• Construct pipeline and tie-in works commence

• Easements executed with landowners.

• Operational Environmental Management Plan accepted by the Minister and Safety Management Plan accepted by Energy Safe Victoria (subject to regulatory consideration)

• Pipeline commissioning commences.

• First Gas – pipeline operational.

*The timing of First Gas is indicative only and subject to receiving regulatory approvals, internal technical and financial approvals, fair weather conditions and availability of contractors.

Late

2019

Early

2021*

Page 59: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 5 of 12

Compulsory acquisitionThe Pipelines Act 2005 (Pipelines Act) and the Pipeline Regulations 2017 (Pipelines Regulations) outline a process to guarantee fair and equitable treatment of landowners leading to the negotiation of easement rights. Beach is dedicated to providing fair and equitable compensation to impacted landowners for the negotiation of easements and additional temporary workspace arrangements. Compensation will be negotiated in line with the Pipelines Act.

The proposed route for the Enterprise Pipeline requires a small number of new easements to be created as the route has been selected to utilise the existing easements for the PL250 pipeline.

If negotiations with landowners and occupiers unfortunately lead to compulsory acquisition of land, Beach will follow the process referred to in relevant sections of the Land Acquisition and Compensation Act 1986 (Vic) (LACA) and the Land Acquisition and Compensation Regulations 2010. This process is only established if Beach is successfully granted Ministerial consent, pursuant to LACA, of an application for Consent to compulsorily acquire an easement over private land. Applications to the Minister can only be made if prior negotiations have been unsuccessful and Beach are able to clearly demonstrate compliance with the required steps and measures for this process. Beach is only permitted to apply to the Minister after six months has elapsed from the service of the Notice of Pipeline Corridor.

The Minister will determine the outcome of the application within 28 days of the submission date. If successful, a Notice of Acquisition will be published in the Government Gazette, as well as provided to all interested parties and published in a relevant local newspaper. Following this, Beach has 14 days to make a fair and equitable compensation offer payable to the landowner/occupier. Negotiations will continue between Beach and the landowner/occupier until a settlement is reached. If a settlement on the level of compensation payable cannot be reached, the matter is referred to the Victorian Civil and Administrative Tribunal for amounts less than $50,000 or either party may seek a court hearing for disputes greater than $50,000.

Attempts to negotiate the terms of access must be undertaken by Beach, and a minimum seven days’ notice must be given before entry into tenure of the land.

Further information on the regulatory approvals required for pipeline construction and operation are detailed in the “Onshore Pipeline Regulatory Approvals Information Sheet” located at www.beachenergy.com.au/enterprise-pipeline-consultation/

Seeking independent adviceLandowners and occupiers affected by the Project are encouraged by Beach to seek independent legal advice on any concerns they may have regarding legal implications of the Project, which could include the Project’s potential impact on their land and its use or any other legitimate concern. Pre-defined and agreed reasonable costs incurred in seeking advice in relation to the Project will be reimbursed by Beach.

Consultation Beach is committed to developing and maintaining positive relationships with landowners and occupiers and the broader community. Beach’s consultation with landowners and occupiers will be open and transparent, and aim to facilitate landowner and occupier involvement in the decision-making process so as to allow mutually beneficial outcomes for all parties.

All landowner and occupier feedback, records of consultation, copies of correspondence, including emails, will be communicated to the Department of Environment, Land, Water and Planning (DELWP) during planning and construction activities on the proposed pipeline.

Page 60: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 6 of 12

Pipeline ConstructionPipeline Construction working widthDuring pipeline installation working clearances will be required. Approximately 20 metres width will be required on the working side of the proposed gas pipeline and 5-10 metres on the soil stockpile side to enable access for excavation machinery, specialist pipeline laying and other vehicles, along with room for materials and equipment.

The trench in to which the lines will be placed is expected to be approximately 1m wide and depth of cover over the pipeline and MEG line is expected to be a minimum of 750mm, and 1200mm at road crossings.

Top Soil

Trench Soil

Open Trench

Distance 20-30m

Work Lane 1

PassingLane

GD19-0086

Existing PL250 pipelineExisting MEG line

Work Lane 2

Diagram showing typical construction right of way layout for pipeline construction

Temporary access requiredTo carry out the pipeline construction, temporary access will be required on the proposed easement on landowner/occupier properties. Some properties will require additional temporary work areas outside of the easement, for vehicle access, vehicle turn around areas, material and equipment lay-down areas.

Additional temporary work areas will be discussed and clearly defined with the relevant landowners and occupiers, including changes to fences or gates and negotiated compensation, prior to any activities being undertaken on the property.

In some instances it may be necessary to arrange access across some landowner’s properties, especially where direct road access is not available or to improve construction efficiency.

Beach’s Community team will work with landowners and occupiers to develop a plan including:

• identification of proposed access tracks;

• arrangements that may be required to minimize and manage any disturbance to farming operations.

Works carried out to facilitate temporary access and manage any disturbance during pipeline installation will be at Beach’s expense.

Page 61: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 7 of 12

Construction Methodology Beach will liaise with landowners and occupiers who may experience potential impacts such as noise, traffic, and dust, and will establish measures to minimise the disruption during the construction of the pipeline.

Standard onshore pipeline construction methods will be used for installing the raw gas pipeline and MEG line. This involves:

1. Initial survey The initial survey will collect information which will be used to refine the design of the pipeline through a Safety Management Study (SMS) which assesses the threats that land usage, nearby infrastructure and topography represents to the pipeline. The study ensures that all threats are understood and controls to mitigate them are as effective as possible. Geotechnical investigations will also occur along the pipeline route at significant junctions such as road or creek crossings, where methods such as horizontal directional drilling (HDD) may be required to install the pipeline using minimal excavation.

2. Setting up work areas Prior to construction, crews are required to prepare work areas for machinery such as dedicated pipe lay down yards along the pipeline route, construction material stockpiles, and areas for trenchless construction and HDD (where applicable).

3. Clear and grade Clear and grade involves preparing the pipeline easement to allow construction activities to commence. This includes any additional temporary work areas as agreed with landowners and occupiers. The combined easement and additional work area is commonly referred to as the construction right-of-way (ROW). Any vegetation and topsoil is removed from the construction ROW and stockpiled separately to avoid soil inversion and assist in rehabilitation works after the pipeline is completed. To minimise impact to the surrounding environment, construction crews may only remove trees and vegetation only in accordance with the receipt of appropriate permits.

4. Typical set-up within the construction (ROW) The construction ROW includes the official easement and temporary additional work areas. The construction ROW is clearly defined and

fenced off if required. The common width of the construction ROW is usually between 20 – 30m.

5. Trenching Following preparation of the construction ROW, construction crews will commence trenching for the pipeline. Typically, specialised trenching machines or excavators are used to dig the trenches. Final trenching techniques are to be determined in conjunction with the chosen construction contractor.

6. Trenchless construction Trenchless construction is used when standard trenching techniques cannot be used, such as river crossings, or some public roads. Techniques such as HDD are used to install pipelines with minimal excavation. Specialist operators drill a hole beneath the surface, at a shallow angle, and then pull a welded length of pipe through the hole without disturbing the surface. These operations are highly engineered and are used to eliminate disturbances to infrastructure, environmentally sensitive areas, and to address construction issues.

7. Welding Pipe sections are joined together by a specialised welding crew. Welds are then tested using non-destructive testing (NDT) techniques to ensure weld integrity and then coated to protect against corrosion. Throughout the welding process, fire regulations and restrictions are followed at all times.

8. Sand Padding and lowering in After final assessment of the pipeline weld and coating quality, the trench is padded with sand and the pipe is lowered into the trench using the specialised side boom trucks. Side boom operators coordinate to move slowly and in unison to lower the pipe.

9. Backfill Soil previously removed from the trench is compacted back into the trench to cover the pipeline. In rocky terrain, further sand padding is used to protect the pipeline. Subsoil is screened and backfilled before topsoil and care is taken to keep them separated to ensure that pasture or other groundcover can be rehabilitated.

Page 62: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 8 of 12

10. Easement rehabilitation As stated in Section 145 of the Pipelines Act, Beach is required to rehabilitate landowner and occupier property as soon as practicable following pipeline construction to enable it to be used as far as practicable for the purposes for which it was used immediately before the construction of that part of the pipeline, or, with the prior approval of the Minister, for any other purpose agreed between Beach and the landowner/occupier. Following rehabilitation, the landowner/occupier are requested to acknowledge that rehabilitation of the land has been completed to an acceptable standard and has met the above requirements.

11. Hydrostatic testing The pipeline will be hydrostatically tested upon verification of construction completeness to ensure its mechanical integrity. Hydrotesting involves filling the pipeline with water and pressurising and sustaining pressure for a period of time, testing it for strength and leak tightness. The exact sequence of the pipeline hydro testing is dependent on the construction sequence. Once the installed pipelines have

successfully passed the hydrostatic pressure test, a process of dewatering and drying will be conducted prior to the final tie-ins of the completed system. Following a sequence of engineering and safety checks, gas will be introduced to pressurise the system.

12. Eventual decommissioning of this proposed pipeline A licenced pipeline must be decommissioned in accordance with AS2285.1, referring to the APGA Code of Environmental Practice., specifically Section 9 and the approved decommissioning plan. The Pipelines Act requires this decommissioning plan be approved by the regulatory authority. An environmental risk assessment process that identifies any potential effect on the environment and other uses/users of the easement should support decommissioning preparation. If the decommissioned pipeline is left in place, appropriate measures will be taken to prevent contamination of soil or groundwater and to avoid land subsidence impacts.

Typical order of onshore pipeline construction activities

Construction equipment may include the following

• graders

• pipe trucks

• excavators

• side booms

• pipe bending machines

• welding rigs

• grit blasting rigs

• 4WD vehicles

Page 63: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 9 of 12

Questions and Answers What are you installing? If the exploration well proves successful, construction will commence on a new high strength steel pipeline approximately 12km long, and 200-300mm in diameter. Buried at a minimum depth of 750mm, and 1200mm at road crossings, the pipeline will flow the raw natural gas to from the Enterprise well site to the Otway Gas Plant. Alongside the gas pipeline, a 50mm-100mm diameter mono-ethylene Glycol (MEG) line will be used to circulate MEG which acts as an anti-freeze, and prevents corrosion of the pipeline. The pipeline trench will also be used to carry a fibre optic cable to connect the well site monitoring systems to the control room at the Otway Gas Plant, to enable the Enterprise Well Site to be monitored 24/7. The new Enterprise pipeline will be constructed alongside the existing Otway Raw Gas Pipeline (PL250) for the majority of its length.

What is a MEG line?The accompanying MEG line is used in pipeline development to act as an anti-freeze. This prevents hydrate formation from occurring, which is the reaction of water and hydrocarbons that exist in the reservoirs.

Is the project likely to proceed?If Beach determines that the exploration well is commercially viable, the proposed pipeline will be constructed to flow the raw gas for processing at the nearby Otway Gas Plant. The processed gas will then supply to the East coast gas market.

Are you experienced in pipeline installation?Beach, via its subsidiary Lattice Energy, has successfully and safely installed other pipelines in the project area. In 2006, Beach/Lattice installed the Otway Raw Gas Pipeline (PL250) to transport natural gas from the Geographe and Thylacine offshore gas fields to be processed at the Otway Gas Plant. In 2016, Beach (then Origin Energy) also successfully installed the 33km of Halladale Pipeline (PL006009) on the Halladale, Black Watch and Speculant Project. Beach has a team of highly skilled gas industry professionals with extensive experience to deliver this project.

What approvals are required for pipeline construction?The proposed Enterprise pipeline will be developed and constructed in accordance with the legislative provisions of the Pipelines Act 2005 (the Pipelines Act) and Pipeline Regulations 2017 (the Pipelines Regulations).

For more information on regulatory approvals, please refer to the “Onshore Pipeline Regulatory Approvals Information Sheet” located at www.beachenergy.com.au/enterprise-pipeline-consultation/

What’s in the Pipeline Consultation Plan (PCP)?The PCP demonstrates how Beach will consult with landowners and occupiers that will be affected by the Project about the proposed pipeline and meet the consultation requirements laid out in the legislation and regulations. The details of the PCP include identification of stakeholders, information on consultation and records management procedures, as well as setting out consultation material and notices. The approved Pipeline Consultation Plan can be downloaded from Beach’s website at www.beachenergy.com.au/enterprise-pipeline-consultation/

How was the proposed pipeline route selected? Did you consider connecting to existing pipelines such as Otway Raw Gas or HBWS?Beach has been assessing and will continue to assess alternative pipeline routes, however the route described in this information sheet is the preferred option at this time. The selection process for the final pipeline route will include the outcomes of the consultation process and will consider many factors, including project requirements, existing easements, landowner considerations, options to minimise environmental and cultural impact, geotechnical considerations and land tenure for both the construction and operational phases.

Several alternative pipeline connections utilising existing infrastructure in the Project area were considered such as hot-tapping into the existing PL250 (Otway Raw Gas) pipeline, and the existing PL006009 (HBWS) pipeline. However, these options were determined to be unsuitable in meeting the above factors and requirements. Beach will continue to monitor other options which may become available within the project timeframe.

Page 64: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 10 of 12

Where can I find detailed maps of the route?Once the final pipeline route has been selected, Beach will issue a Notice of Pipeline Corridor to all landowners and occupiers along the route as well as other stakeholders as outlined in the Pipelines Act. This will include the detailed route along with approved Project consultation information unless already provided to the landowner/occupier.

The current proposed pipeline route means you will be working next to a live pipeline. Is it safe to do this?Construction of the proposed Enterprise pipeline next to the existing PL250 pipeline will use special construction methods to ensure that no damage is caused to the existing line, no long term threats are imposed, and that it is still accessible once the proposed pipeline is operational. The existing pipeline will be precisely located using predetermined spacing to define the exact depth and position, including any curves or peaks in pipe bends. To do this, a pipe locator is used during preliminary walkthroughs, and vacuum pot-holing is used during construction to establish visual confirmation of the line, uncovering the top and sides of the pipe. Marker post signs and CP test points will also be scouted and avoided or managed to ensure there no increased risk to the integrity of the line, prior to clearing and quarantine of the local topsoil. Planning for the proposed pipeline route will consider and apply construction methods which maintain safe separation from the existing line and other infrastructure.

A construction Hazard Identification is the primary means of assessing the risks associated with construction in close proximity to PL250. All excavation works will be managed with both a spotter and excavation supervisor as key controls to ensuring the existing pipeline is not damaged and that approved excavation plans are followed.

A Safety Management Study (SMS) workshop will be conducted for the detailed design of the proposed pipeline. Operators of existing buried assets and services in the study corridor are presented with the initial design proposals and safeguards are assessed to ensure understanding of risk and the effectiveness of controls, through the construction program and ongoing operations. Landowner and occupier details such as land use, equipment and activities are gathered during preliminary engagement and used to inform the SMS workshop.

How will you consult with impacted landholders and occupiers?Beach is committed to conducting all communication and consultation with landowners and occupiers in a clear and concise manner using plain English and minimising technical terms where possible. Beach seeks to conduct as much consultation as possible on a face-to-face basis to encourage active feedback from each landowner and occupier.

Initial consultation and introduction of the Project will be undertaken by Beach’s Community Relations Manager (Victoria) and the Community Manager, supported by local Land Liaison Officers. Each landowner/occupier will be assigned a primary Beach representative for the duration of the Project and act as their principal contact throughout. During pre-construction and construction phases Beach will engage experienced Land Liaison Officers to oversee property-specific requirements and liaise with the construction contractor on the resolution of any issues. The sequence and timing of consultation has been designed to ensure that all landowners and occupiers are kept informed of the Project, and to ensure that issues are identified and resolved in a timely fashion.

A toll-free phone number and email are available for landowners and occupiers at all times, providing out-of-hours access to Beach representatives should urgent landowner issues or emergency situations arise.

As per the regulatory requirements, Beach will provide a copy of the PCP to each affected landowner and occupier, and provide advice on public display of regulatory documentation throughout each phase of the Project. Letters, information sheets and diagrams, and a project website will also be used to support consultation with landowners and occupiers along the pipeline route.

Otway Gas Plant

Page 65: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 11 of 12

What kind of surveys will you be conducting on my property?A variety of field surveys of the proposed pipeline route, including environment, cultural heritage and other surveys will be required to collect data to develop project assessment documentation, such as potential impacts and how they will be managed. The surveys that are required for the proposed pipeline include:

• Ecology survey

• Cultural Heritage

• Soil conductivity

• Hydrology survey

• Survey location

• Geotechnical

• Feature survey (terrain, trees, building outlines, dams, water courses etc.)

Details of the proposed surveys to be carried out in the proposed pipeline route are disclosed in the PCP as well as the Notice of intention to enter land for survey that has been provided to landowners and occupiers.

How will you manage impacts to my property during construction and operation?Beach is committed to working with landowners and occupiers throughout the construction and operation of the proposed pipeline to ensure impacts are minimised and, where possible, avoided. The potential impacts of the proposed pipeline to landowner and occupier property during construction will be managed via data collected from initial surveys and the development of Property Management Plans (PMP). Beach will involve all affected landowners and occupiers in the development of their respective PMP to ensure that concerns and issues are directly reflected in the alternatives developed and to provide feedback on how landowners and occupiers’ input influenced the pipeline construction on their property.

Subject to the Pipelines Act, key management plans such as the Construction Environmental Management Plan (CEMP) and the Construction Safety Management Plan (CSMP) will be also developed.

As the pipeline becomes operational, Beach will meet with each landowner/occupier and collect (or update existing) information regarding access to the pipeline for operations and maintenance as well as any property specific requirements. This information is collected in a ‘Land Book’ for each pipeline.

Beach’s internal Pipeline Stakeholder Engagement Plan (Victoria) (PSEP) will be referred to for the approach and obligations with regard to stakeholder consultation during the operational phase of the pipeline. Construction and operation of the proposed pipeline will be carried out using proven techniques.

Will you rehabilitate the site?As stated in Section 145 of the Pipelines Act, Beach is required to rehabilitate landowner and occupier property as soon as practicable following pipeline construction to enable it to be used as far as practicable for the purposes for which it was used immediately before the construction of that part of the pipeline, or, with the prior approval of the Minister, for any other purpose agreed between Beach and the landowner/occupier.

Areas of disturbance will be engineered and planned in a manner to limit the size of the disturbance and minimize rehabilitation requirements. Activities that may cause areas of disturbance requiring rehabilitation include, but are not limited to:

• pipeline construction;

• access tracks to certain pipeline sections and vehicle turn around areas;

• equipment lay down and storage areas.

Rehabilitation of any land which is disturbed or damaged due to installation of the pipeline will typically include reinstating top soil as far as practicable, reinstating fencing (if required), clean up and re-sowing/fertilizing disturbed pasture. All rehabilitation works will be carried out at Beach’s expense.

Following rehabilitation, the landowner/occupier is requested to acknowledge that rehabilitation of the land has been completed to an acceptable standard and has met the above requirements.

GD19-0086

Page 66: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Project Update | October 2019 | Rev 0 12 of 12

More information & key contacts Beach representativeBeach’s primary contact for the Enterprise Pipeline is:

Linda French Community Relations Manager M 0448 236 121 E [email protected]

Beach Enterprise Project Community Hotline

P 1800 797 011 E [email protected] www.beachenergy.com.au/enterprise-pipeline-consultation/

Regulatory Authorities The development of this project requires the involvement of different regulators and authorities summarised below:

Department of Environment, Land, Water and Planning (DELWP) DELWP is responsible for administration of the Pipelines Act and provides guidance to proponents, landowners and occupiers regarding pipeline projects and associated issues.

DELWP M 0439 799 598 E [email protected] energy.vic.gov.au

Energy Safe VictoriaESV regulates all sections of the natural gas and liquefied petroleum gas industry other than the production of gas, the transportation and storage of liquefied petroleum gas, and all aspects of the supply and use of autogas. Other fuel gases that form part of the energy supply to a gas installation are also regulated by ESV.

Energy Safe Victoria Gas Technical Helpline P 1800 652 563 E [email protected]

Other information sources

Victorian Farmers FederationVFF is the leading advocacy group for the interests of farmers and making a difference to communities in Victoria. They aim to promote best practice and a positive relationship between landowners and pipeline proponents.

Lisa Gervasoni Land Management and Planning P +61 1300 882 833 E [email protected]

About Beach

Page 67: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Regulatory Approvals | October 2019 | Rev 0 1 of 2

Enterprise PipelineOnshore Pipeline Regulatory ApprovalsOctober 2019

Project overview The Enterprise Project is a program to develop additional offshore natural gas reservoirs in the Victorian Otway Basin. The potential reservoirs are located offshore, up to 3 nautical miles (5.55 km) from the coastline, while the well site will be located onshore near Port Campbell. If Beach determines that the exploration well is commercially viable, a pipeline will be constructed to flow the raw gas for processing at the nearby Otway Gas Plant, for supply to the Australian domestic gas market. Timings for pipeline construction approvals require us to commence consultations early, before we have fully assessed commercial viability of the first Enterprise well.

Regulatory ApprovalsThe primary legislation required for the construction, operation, maintenance and decommissioning of the proposed Enterprise pipeline are:

• the Pipelines Act 2005 (Pipelines Act); and

• the Pipeline Regulations 2017 (Pipelines Regulations).

The Pipelines Act and the Pipelines Regulations oversee the management and regulation of high transmission pipelines in Victoria and are administered by the Department of Environment, Land, Water and Planning (DELWP). Energy Safe Victoria (ESV) is also involved in matters of safety in the approvals process on pipeline projects. Beach is committed to completing the legislative and regulatory requirements necessary to obtain all approvals on the Enterprise Pipeline Project.

Construction and installation of high transmission pipelines in Victoria require Ministerial approval in the form of a Licence to Construct and Operate a Pipeline.

Prior to obtaining a Pipeline Licence, Beach is required to develop a Minister-approved Pipeline Consultation Plan (PCP), to demonstrate how Beach will consult with landowners and occupiers about the proposed pipeline and meet the consultation requirements laid out in the legislation and regulations. Certain consultation activities compatible with the Pipelines Act, such as giving Notice of intention to enter land for survey and Notice of Pipeline Corridor, and Notice of Pipeline License Application cannot commence until an approved PCP is obtained.

Other statutory documents are required to be developed by Beach and approved by the Regulators. Approval to construct a pipeline requires development of a Construction Environmental Management Plan (CEMP) and Construction Safety Management Plan (CSMP). Approval to operate a pipeline requires development of an Environmental Management Plan (EMP); and Safety Management Plan (SMP).

beachenergy.com.au

Beach Energy is an ASX listed oil and gas, exploration and production company headquartered in Adelaide. It has operated and non-operated, onshore and offshore, oil and gas production from five production basins across Australia and New Zealand and is a key supplier to the Australian east coast gas market.

In January 2018, Beach acquired permits and operational assets in Victoria through its acquisition of Lattice Energy Limited. As Lattice is a wholly owned subsidiary of Beach Energy, all assets on the project will be operated under the Lattice name, including all applications for regulatory approvals, such as the Pipeline License. Information sheets and other associated consultation materials and activities use the Beach Energy name and branding.

About Beach

Page 68: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Regulatory Approvals | October 2019 | Rev 0 2 of 2

Relevant regulatory documents will be available for public display where required by the statutory process or as directed by the Regulator. As regulatory processes progress, Beach will provide further information to landowners, occupiers and other stakeholders.

Agreements with landowners and occupiersProcesses used to obtain access to land and tenure for construction and operation of the proposed pipeline will comply with the Pipelines Act and the Pipelines Regulations. Under the Pipelines Act, Beach is required to establish long-term or temporary land access arrangements with landowners and occupiers. This could include easement purchases or licencing arrangements for construction and operation of the proposed pipeline.

Easement acquisition The Pipelines Act and the Pipelines Regulations outline a process to guarantee fair and equitable treatment of landowners and occupiers leading to the negotiation of easement rights.

If negotiations with landowners and occupiers require compulsory acquisition of land, Beach will follow the process referred to in relevant sections of the Land Acquisition and Compensation Act 1986 (Vic) and the Land Acquisition and Compensation Regulations 2010. This process is only established if Beach is successfully granted Ministerial consent, pursuant to the Land Acquisition and Compensation Act, of an Application for consent to compulsorily acquire an easement over private land.

Regulatory Authorities The development of a project such as this requires the involvement of several key regulatory authorities. An overview of the roles and responsibilities of the key regulatory authorities involved in the Project is outlined below, along with contact details should further information be required.

Department of Environment, Land, Water and Planning (DELWP) DELWP is responsible for administration of the Pipelines Act and provides guidance to proponents, landowners and occupiers regarding pipeline projects and associated issues.

DELWP M 0439 799 598 E [email protected] energy.vic.gov.au

Energy Safe VictoriaESV regulates all sections of the natural gas and liquefied petroleum gas industry other than the production of gas, the transportation and storage of liquefied petroleum gas, and all aspects of the supply and use of autogas. Other fuel gases that form part of the energy supply to a gas installation are also regulated by ESV.

Energy Safe Victoria Gas Technical Helpline P 1800 652 563 E [email protected]

Victorian Farmers FederationVFF is the leading advocacy group for the interests of farmers and making a difference to communities in Victoria. They aim to promote best practice and a positive relationship between landowners and pipeline proponents.

Lisa Gervasoni Land Management and Planning P +61 1300 882 833 E [email protected]

More information & key contacts Beach representativeBeach’s primary contact for the Enterprise Pipeline is:

Linda French Community Relations Manager M 0448 236 121 E [email protected]

Beach Enterprise Project Community Hotline

P 1800 797 011 E [email protected]

For more information on the Enterprise Pipeline Project, please visit www.beachenergy.com.au/enterprise-pipeline-consultation/

Page 69: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Regulatory Approvals | October 2019 | Rev 0 1 of 2

Enterprise Pipeline PrivacyOctober 2019

The Enterprise Project is a program to develop additional offshore natural gas reservoirs in the Victorian Otway Basin. The potential reservoirs are located offshore, up to 3 nautical miles (5.55 km) from the coastline, while the well site will be located onshore near Port Campbell. If Beach determines that the exploration well is commercially viable, a pipeline will be constructed to flow the raw gas for processing at the nearby Otway Gas Plant, for supply to the Australian domestic gas market.

Beach is committed to protecting the privacy of individuals’ personal information. Throughout consultation on the Enterprise Pipeline Project, information exchanged with landowners, occupiers and other stakeholders (individuals) will be managed in line with Beach’s Privacy Policy.

“Personal information” is information or an opinion about an identified individual, such as names, addresses, phone numbers or emails, information following enquiries and communication between Beach and an individual.

All personal information exchanged on the project will be collected and used in line with the Privacy Act 1988 (Commonwealth) (the Privacy Act) and the Australian Privacy Principles that are contained in that Privacy Act.

Beach’s full Privacy Policy is available at www.beachenergy.com.au/privacy-policy/

Collecting your personal information Beach may collect personal information about individuals in a variety of ways, including when individuals contact Beach, or when Beach contacts the individual, in person or electronically. Beach will only collect personal information about individuals’ where the information is reasonably necessary for one or more of Beach’s functions, operations or activities, or to comply with the law.

Beach Energy is an ASX listed oil and gas, exploration and production company headquartered in Adelaide. It has operated and non-operated, onshore and offshore, oil and gas production from five production basins across Australia and New Zealand and is a key supplier to the Australian east coast gas market.

In January 2018, Beach acquired permits and operational assets in Victoria through its acquisition of Lattice Energy Limited. As Lattice is a wholly owned subsidiary of Beach Energy, all assets on the project will be operated under the Lattice name, including all applications for regulatory approvals, such as the Pipeline License. Information sheets and other associated consultation materials and activities use the Beach Energy name and branding.

About Beach

beachenergy.com.au

Page 70: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline Regulatory Approvals | October 2019 | Rev 0 2 of 2

Storing your personal information To protect the rights of both parties involved in the consultation process, records of all contact between Beach and the individual during the Project are maintained by Beach. Information exchanged during the Project will be held in a system for recording and managing important and confidential stakeholder information such as correspondence, agreements, records of contact, feedback, complaints and claims records and resolutions and incident records. Beach will provide monthly reports to the Department of Environment, Land, Water and Planning (DELWP) containing consultation with stakeholders, including particular references to any complaints or grievances. Reporting will be undertaken from initial consultation with stakeholders, landowners and occupiers through to completion of the regulatory approval process, providing consent of the Construction Environmental Management Plan (CEMP) and safety management plans and subject to a pipeline licence being issued. From then, reporting will be in accordance with the CEMP or other management documents.

Using your personal information Beach may collect and use personal information on the Enterprise Pipeline Project in order to:

• Provide individuals with information about the Project;

• Support the design and execution process of the Project;

• Minimise potential impacts to individuals;

• Respond to inquiries, feedback, concerns or claims on the Project;

• Discuss other matters relating to the Project with individuals;

• Assist ongoing pipeline operations and maintenance.

Organisations which Beach may disclose personal information to on the Project may include:

• Government agencies or regulatory authorities, where required;

• Related bodies corporate of Beach;

• Beach’s suppliers, service providers, professional advisers and agents;

• Joint Venture partners;

• Anyone to whom Beach’s assets or business (or any part of it) is transferred;

• Where necessary to protect the rights or safety of any of its employees or a third party;

• Where an individual to whom the personal information relates has consented to the disclosure; or

• Where otherwise required or permitted by law.

Accessing your personal information An individual can request to seek access to, and update or correct, any personal information that is being held by Beach about that individual. There are certain circumstances under the Privacy Act where Beach will not grant an individual such access, where this access may have unreasonable impact on the privacy of others, where it would reveal commercially sensitive information about the organisation or where providing access would be unlawful. Beach may need to verify an individual’s identity prior to providing access to their personal information.

Contact Us Beach Privacy PolicyFor further information about Beach’s privacy policies or practices, to request access to your personal information, or to lodge a inquiry, feedback, concern or claim, please contact the Company Secretary at (08) 8338 2833 or [email protected].

Beach representativeBeach’s primary contact for the Enterprise Pipeline is:

Linda French Community Relations Manager M 0448 236 121 E [email protected]

Beach Enterprise Project Community Hotline

P 1800 797 011 E [email protected]

For more information on the Enterprise Pipeline Project, please visit www.beachenergy.com.au/enterprise-pipeline-consultation/

Page 71: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

53 of 56

Appendix C Sample Notice of intention to enter land for survey

Page 72: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Beach Energy Limited | ABN 20 007 617 969

Level 8, 80 Flinders Street Adelaide, South Australia 5000

GPO Box 175, Adelaide, South Australia 5001

T +61 8 8338 2833 | F +61 8 8338 2336

beachenergy.com.au

Notice Template Rev 0 Page 1 of 5

NOTICE OF INTENTION TO ENTER LAND FOR SURVEY

Pursuant to Section 19 of the Pipelines Act 2005

Day Month 2019

Ref: BPT / [◌]/19

By Post / Express Post / Courier / Email

ENTERPRISE PIPELINE PROJECT

Lattice Energy Limited (“Lattice”) a related body corporate of Beach Energy Limited (“Beach”) is the pipeline

proponent – Lattice’s contact details are:

Attention: Enterprise Pipeline Project

c/o Beach Energy Limited

Level 8, 80 Flinders Street, Adelaide SA 5000

Enterprise Pipeline Project Hotline – 1800 797 011

Project Contact - Community Relations Manager Victoria – [email protected]

Dear: [landowner name]

Land: Volume xxx Folio yyy being rrrrrrr (the “Land”)

Address: [Address]

Status: [Landowner/Occupier]

Re: NOTICE OF INTENTION TO ENTER LAND FOR SURVEY

In accordance with Section 19(1) of the Pipelines Act 2005 (the “Act”), Lattice Energy Limited, a member of

the Beach Energy Limited group of companies (“Beach”) (ACN 007 845 338) of Level 8, 80 Flinders Street,

Adelaide SA 5000 hereby gives you Notice of its intention to enter your Land for the purpose of conducting a

series of low impact field surveys. These surveys are necessary for Beach to understand and to investigate the

Land for its suitability for the pipeline route.

In accordance with Section 19 of the Act, this Notice contains the required information and is accompanied

by the project information sheets.

Intended use of the proposed pipeline

The proposed pipeline will consist of a 200-300mm diameter production pipeline, accompanied by a 50-

100mm diameter MEG line, both approximately 12km in length. The proposed new pipeline would run from

the onshore Enterprise drill site near Port Campbell, joining into existing easements housing the Otway

pipeline, and then connecting to the existing gas processing facility, the Otway Gas Plant, both of which are

operated by the Proponent. If the Enterprise joint venture determines that the project is commercially viable,

Page 73: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

NOTICE OF INTENTION TO ENTER LAND FOR SURVEY

Notice Template Rev 0 Page 2 of 5

the proposed pipeline will be constructed and used to flow the raw gas for processing at the nearby Otway

Gas Plant, the processed gas will then supply to the East coast gas market.

Details of the proposed surveys

A variety of field surveys of the proposed pipeline route, including environment, cultural heritage and other

surveys, will be required to collect data to develop project assessment documentation, such as potential

impacts and how they will be managed as outlined in the Construction Environment Management Plan

(CEMP) and the Construction Safety Management Plan (CSMP). The surveys that are required for the

proposed pipeline include:

• Terrestrial and aquatic ecology (flora and fauna around land/Port Campbell Creek)

• Cultural Heritage

• Soil conductivity

• Hydrology survey

• Survey location

• Geotechnical

• Feature survey (terrain, trees, building outlines, dams, water courses etc.)

Details of the proposed surveys to be carried out in the proposed pipeline route are disclosed in Attachment

1 (“Surveys”).

Pegs and markers may be placed on the Land while undertaking the Surveys and may be removed on

request. Please note, the majority of Surveys will not require ground disturbance on your Land. However,

minor excavation of the Land will be required during geotechnical investigations which are necessary to

assist Beach in designing the pipeline to safely cross watercourses and major roads.

Name and Address of Person or body engaged to carry out the survey

Beach will be engaging subcontractors to conduct the surveys outlined in Attachment 1 of the Notice. At the

time of this Notice, Beach is in the process of selecting the preferred subcontractor[(s)] to undertake the

Surveys. Subcontractor details will be made available to you once finalised. Subcontractors will be made

aware of their commitment and responsibility to comply with quality management and health, safety and the

environment requirements, to ensure impacts to Land are minimized.

Map of the proposed route of the pipeline or the pipeline corridor

A map of the proposed pipeline route over the Land is included with this Notice as Attachment 2 and shows

the following:

• the relevant part of the Land over which the survey is proposed to be made; and

• the location of that Land including the allotment and section numbers, parish and municipal names and

the boundaries of adjacent Lands relating to the proposed survey.

Page 74: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

NOTICE OF INTENTION TO ENTER LAND FOR SURVEY

Notice Template Rev 0 Page 3 of 5

Consent to enter Land

Beach will take all reasonable steps to enter into agreement with each landowner and occupier to enter the

Land and conduct the Surveys. Beach is committed to clear and transparent communications during these

discussions to ensure you have an appropriate understanding of the requirements of the surveys. If no

agreement is reached on one or more parcels of Land, Beach may apply to the Minister for consent to enter

your Land within 14 days after issuing the Notice of Intention to Enter Land.

Signature of authorised person of the Proponent Lattice Energy Limited

Name:

Date:

Position:

Page 75: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

NOTICE OF INTENTION TO ENTER LAND FOR SURVEY

Notice Template Rev 0 Page 4 of 5

Attachment 1 – Surveys

Name of Survey Description of Survey activities

Terrestrial and aquatic

ecology

Assessment of isolated areas to be undertaken to determine significant flora and

fauna in terrestrial and aquatic (Port Campbell Creek) ecosystems, to manage

environmental impacts of the construction and operation of the pipeline. Access to

these areas will be obtained by light vehicle where appropriate. No ground

disturbance is necessary. The survey will occur within the mapped targeted survey

area displayed in the Notice of Intention to Enter Land for Survey previously provided

to you.

Cultural Heritage A small team of 4-5 people will assess the relevant areas via foot to manage impacts

of the construction and operation of the pipeline to land and artefacts of cultural

significance. Ground disturbance may be required at more isolated locations where

teams will hand dig shallow holes. Access to these areas will be obtained by light

vehicle where appropriate. Representatives from Eastern Maar may be present if they

wish to attend. The survey will occur within the mapped targeted survey area

displayed in the Notice of Intention to Enter Land for Survey previously provided to

you.

Soil conductivity A small team of 2-3 people will assess the relevant areas by foot or in a light vehicle,

accessing discrete locations of the Property to measure electrical conductivity of soil.

Data collected will be used to inform the pipeline design. The reading is made using a

small hand-held probe inserted approximately 20cm into the ground. The survey will

occur within the mapped targeted survey area displayed in the Notice of Intention to

Enter Land for Survey previously provided to you.

Hydrology survey If a river or stream crosses the proposed pipeline route, a small team of 2-3 people

will assess the relevant areas by foot or in a light vehicle to determine and record river

or stream conditions. The area to be inspected will extend up to 50m upstream and

50m downstream of the ‘proposed pipeline route’ outlined in the Notice of Intention

to Enter Land for Survey previously provided to you.

Survey location Survey locations are to determine the positions of underground service utilities

(underground infrastructure), which is then required to inform the design of the

pipeline and prevent damage to service utilities where surveys are undertaken using

mechanical equipment to break ground in a discrete area. A metal detector and a

water jet are used to confirm the locality of the underground infrastructure. Any

wastewater created from these surveys is collected in a wastewater tank through a

vacuum system. Areas disturbed during this Survey will be reinstated at the

completion of the Survey.

The survey will occur within the mapped targeted survey area displayed in the Notice

of Intention to Enter Land for Survey previously provided to you.

Geotechnical Geotechnical surveys are required to assist Beach in designing the pipeline to safely

cross rivers and major roads. A geotechnical investigation will include surface

exploration and subsurface exploration of a site, using a vehicle mounted drill rig

(4WD or truck) to establish boreholes measuring 10 to 15cm in diameter and up to

20m in depth and/or the use of a narrow probe to test soil layers and confirm soil

stability at discrete locations.

In some instances, a PVC pipe will be positioned into the hole to keep the hole open

and allow for the soil permeability to be tested. The PVC pipe will be removed at the

end of the 12 month Survey period unless you allow it to remain for use in the

construction period.

Sample drill cuttings are taken to be analysed and the remaining cuttings will be

placed back into bore holes during back-filling and restoration. Survey vehicles used

may vary in size.

The geotechnical Survey will occur within the Survey Area shown on the map outlined

in the Notice of Intention to Enter Land for Survey previously provided to you.

Page 76: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

NOTICE OF INTENTION TO ENTER LAND FOR SURVEY

Notice Template Rev 0 Page 5 of 5

Name of Survey Description of Survey activities

Feature survey A small team of 2-3 people will assess the relevant areas by foot or in a light vehicle,

using surveying technology to develop a digital three dimensional image of physical

features that the pipeline may effect (terrain, trees, building outlines, dams, water

courses etc). These measurements and images may be taken from anywhere within a

distance of 100m of the proposed pipeline route (shown in the Notice of Intention to

Enter Land for Survey previously provided to you). Surface scans may be taken to

confirm position of existing underground pipelines. Pegs may be placed in the ground

at fence-lines and at other distinct locations (which will be removed at the end of

construction or beforehand on request).

Attachment 2 - Map of the proposed pipeline route

[Map – to be inserted]

Page 77: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

54 of 56

Appendix D Draft Notice of Pipeline Corridor

Page 78: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Beach Energy Limited | ABN 20 007 617 969

Level 8, 80 Flinders Street Adelaide, South Australia 5000

GPO Box 175, Adelaide, South Australia 5001

T +61 8 8338 2833 | F +61 8 8338 2336

beachenergy.com.au

Notice Template Rev 0 Page 1 of 2

NOTICE OF PIPELINE CORRIDOR

Pursuant to Section 27 of the Pipelines Act 2005 and Regulation 7 of the

Pipeline Regulations 2017

Day Month 2019

Ref: BPT / [◌]/19

By Post / Express Post / Courier / Email

ENTERPRISE PIPELINE PROJECT

Lattice Energy Limited (“Lattice”) a related body corporate of Beach Energy Limited (“Beach”) is the pipeline

proponent – Lattice’s contact details are:

Attention: Enterprise Pipeline Project

c/o Beach Energy Limited

Level 8, 80 Flinders Street, Adelaide SA 5000

Enterprise Pipeline Project Hotline – 1800 797 011

Project Contact - Community Relations Manager Victoria – [email protected]

To: [landowner name]

Land: Volume xxx Folio yyy being rrrrrrr (the “Land”)

Address: [Address]

Status: [Landowner/Occupier]

Re: NOTICE OF PIPELINE CORRIDOR

In accordance with Section 27(1) of the Pipelines Act 2005 (the “Act”), and Regulation 7 of the Pipeline

Regulations 2017 (the “Regulations”), I, Lattice Energy Limited, a member of the Beach Energy Limited group

of companies (“Beach”) (ACN 007 845 338) of Level 8, 80 Flinders Street, Adelaide SA 5000, is considering

applying for a licence to construct and operate a pipeline over the following Land:

Description of the land (see attached sketch showing the relevant part of the land) and title particulars

A copy of a plan showing the pipeline corridor is attached to this Notice.

The proposed pipeline will consist of a 200-300mm diameter production pipeline, accompanied by a 50-

100mm diameter MEG line, both approximately 12km in length. The proposed new pipeline would run from

Page 79: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

NOTICE OF PIPELINE CORRIDOR

Notice Template Rev 0 Page 2 of 2

the onshore Enterprise drill site near Port Campbell, joining into existing easements housing the Otway

pipeline, and then connecting to the existing gas processing facility, the Otway Gas Plant, both of which are

operated by the Proponent. If the Enterprise joint venture determines the project is commercially viable, the

proposed pipeline will be constructed and used to flow the raw gas for processing at the nearby Otway Gas

Plant, the processed gas will then supply to the East coast gas market.

The selection process for the final pipeline route will consider many factors, including project requirements,

existing easements, landowner considerations, options to minimise environmental and cultural impact,

geotechnical considerations and land tenure for both the construction and operational phases.

*Information regarding the proposed pipeline, including the processes that will be followed for obtaining

required approvals and details of how Lattice Energy Limited, a member of the Beach Energy Limited group

of companies proposes to consult with you is also attached.

*Information regarding the proposed pipeline, including the processes that will be followed for obtaining

required approvals and details of how Lattice Energy Limited, a member of the Beach Energy Limited group

of companies proposes to consult with you was given to you with the notice of intention to enter land for

survey issued on: [insert date that written notice of intention to enter land for survey was given to owner or

occupier under section 19 of the Act]

[*delete the statement that does not apply]

Signature of authorised person of the Proponent Lattice Energy Limited

Name:

Date:

Position:

Notes:

1. A pipeline corridor is a corridor of land within which a pipeline is proposed to be constructed under the Pipelines

Act 2005. The final route of the proposed pipeline within the corridor is subject to consultation and approval under

the Pipelines Act 2005.

2. Under section 27(3) of the Pipelines Act 2005 this Notice lapses after 12 months from the date of this Notice, unless

the Minister administering that Act, extends that period in writing.

Page 80: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

55 of 56

Appendix E Regulatory Approvals

Statutory approval and licencing for the Project components will need to be considered under the

following legislation:

Level of Government Legislation

Commonwealth

legislation

• Aboriginal Torres Strait Islander Heritage Protection Act 1984

• Environment Protection and Biodiversity Conservation Act 1999.

• Native Title Act 1993.

• Navigation Act 2012.

• Civil Aviation Act 1988.

Victorian State

legislation

• Aboriginal Heritage Act 2006.

• Aboriginal Lands Act 1991.

• Catchment and Land Protection Act 1994.

• Country Fire Authority Act 1958.

• Crown Land (Reserves) Act 1978.

• Climate Change Act 2010.

• Dangerous Goods Act 1985.

• Environment Effects Act 1978.

• Environment Protection Act 1970.

• Flora and Fauna Guarantee Act 1988.

• Fences Act 1968.

• Gas Safety Act 1997.

• Heritage Act 1995.

• Land Act 1958.

• Land Acquisition and Compensation Act 1986.

• Local Government Act 1989.

• National Parks Act 1975.

• Occupational Health and Safety Act 2004

• Pipelines Act 2005 and Pipeline Regulations 2017 (Vic).

• Planning and Environment Act 1987.

• Road Management Act 2004.

• Traditional Owner Settlement Act 2010.

• Water Act 1989.

• Wildlife Act 1975

Page 81: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Pipeline Consultation Plan

Enterprise Project - Victoria

Released on 13/09/2019 - Revision 0 - Status Issued for Approval

S4700AN718451

56 of 56

Appendix F Sample Monthly Consultation Report

Page 82: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

A XX XX XX XX XX

Revision Date Reason for Issue Prepared Checked Approved

Beach Energy Stakeholder Consultation

Report

Enterprise Pipeline Project

Date of report: XX/XX/2019

Consultation period: XX/XX/2019 - XX/XX/2019

stephanie.eggleston
Typewriter
Report Template Rev 0
Page 83: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline - Stakeholder Engagement Log (Consultation Period: XX - XX)

Engagement Topic Events (occurance) Events (percentage) Engagement topics Events (occurance)

Survey Access Phone - In

Property Access Phone - Out

Land Access Agreement SMS - In

Complaint SMS - Out

Operations Email - In

Property Management Plans Email - Out

Amenity Impacts Letter - In

Project Impacts Letter - Out

Project Information Meeting – Stakeholder site

Project Schedule and Timing Meeting – Beach site

Engagement Process Meeting - Neutral site

Communication Materials Meeting – Group event

Regulations Total events:

Other

Total events:

stephanie.eggleston
Typewriter
Report Template Rev 0
Page 84: Pipeline Consultation Plan - Beach Energy · Appendix A Checklist of requirements for a consultation plan 50 Appendix B Information Sheets 52 Appendix C Sample Notice of intention

Enterprise Pipeline - Stakeholder Engagement Log (Consultation Period: XX - XX) Cells in Orange need to be searchable / reportable, so the data needs to be consistent

Engagement Topic Asset Stakeholder Name (last, first) Stakeholder Type Engagement Method Engagement date Engagement

Time

Description Summary Stakeholder Comments Beach Response

Survey Access Project - Enterprise

Pipeline

XXXX Landowner Letter 29/10/2019 2:00pm Posted Notice of Intention to Enter Land for Survey. Notice of Intention to

Enter Land for Survey.

Survey Access Project - Enterprise

Pipeline

XXXX Landowner Meeting – Stakeholder

site

15/11/2019 11:30am Confirm access and any changes to conditions prior to survey commencing. Confirm access and any

changes to conditions

prior to survey

commencing.

Land Access Agreement Project - Enterprise

Pipeline

XXXX Occupier/Tenant Phone - Out 15/01/2020 3:30pm Called to ask if he had received the agreement re Stock crossings. Left a

voicemail and asked him to return my call.

Stock crossings.

Complaint Project - Enterprise

Pipeline

XXXX Landowner Meeting – Stakeholder

site

1/12/2020 9:00am Beach representative visited landholder at site to address dust complaint. Dust complaint.

stephanie.eggleston
Typewriter
Report Template Rev 0