Pipe Jacking

49
PIPE JACKING 1 Internet Document Pipe Jacking – Ritchie-Wiki. Available online at http://www.ritchiewiki.com/wiki/index.php/Pipe_Jacking, checked on 2/4/2017. Internet Document Pipe Jacking Association Homepage. Available online at http://pipejacking.org/, checked on 2/8/2017. Internet Document Welcome to Civil and Environmental Engineering at the University of Waterloo. Available online at https://uwaterloo.ca/civil-environmental-engineering/, checked on 2/8/2017. Internet Document Ongoing & Upcoming Trenchless Projects in India (2016). Available online at http://www.indstt.com/trenchless_projects.html, updated on 12/17/2016, checked on 2/8/2017. Reference:

Transcript of Pipe Jacking

Page 1: Pipe Jacking

PIPE JACKING

1

Internet DocumentPipe Jacking – Ritchie-Wiki.Available online at http://www.ritchiewiki.com/wiki/index.php/Pipe_Jacking, checked on 2/4/2017.

Internet DocumentPipe Jacking Association Homepage.Available online at http://pipejacking.org/, checked on 2/8/2017.

Internet DocumentWelcome to Civil and Environmental Engineering at the University of Waterloo.Available online at https://uwaterloo.ca/civil-environmental-engineering/, checked on 2/8/2017.

Internet DocumentOngoing & Upcoming Trenchless Projects in India(2016). Available online at http://www.indstt.com/trenchless_projects.html, updated on 12/17/2016, checked on 2/8/2017.

Reference:

Page 2: Pipe Jacking

2

CONTENTS

• Introduction • Brief History• Methodology• Application• Standards• Equipment/Component• Classification• Alternative methods• Pros & Cons

Page 3: Pipe Jacking

3

INTRODUCTION

• Pipe Jacking is the oldest method of trenchless technology.• Pipes are pushed through the ground behind the shield

using powerful jacks.• Simultaneously excavation takes place within the shield.• This process is continued until the pipeline is completed.• The method provides a flexible, structural, watertight,

finished pipeline as the tunnel is excavated.• Thrust wall is provided for the reaction of the jacks.

Page 4: Pipe Jacking

4

Contd.

Figure 1: Pipe jacking process (a) Jacks are pushing pipe(b) Installation of pipeline under a runway.

(a) (b)Source: www.pipejacking.org Source: www.pipejacking.org

Page 5: Pipe Jacking

5

CONTENTS

• Introduction

• Brief History• Methodology• Application• Standards• Equipment/Component• Classification• Alternative methods• Pros & Cons

Page 6: Pipe Jacking

6

BRIEF HISTORY• First mentioned in 1910, USA by Richardson & Mayo.• In 60s, used in UK and APJA(American Pipe Jacking

Association) is formed.• In 70s, process is industrialized in Japan.• In 80s, developed in Europe. (i) 1800mm dia trenchless pipe is laid for 460m in London,1982. (ii) 560m in water bearing sand and gravel, Byles, 1983.

• Komatsu introduced first fully automated machine in 1975 – IRONMOLE

• Today pipe jacking is remotely operated.

Page 7: Pipe Jacking

7

INDIAN HISTORY• First project is of 3.5km in 1998, Mumbai.• In Cuttack 10km is constructed for sewer using

trenchless method.• Other projects of less than 8km is completed in Goa,

Hyderabad, Kolkata, Delhi, Assam etc.• A total of around 100km is build so far using trenchless

methods so far.Ongoing projects-• 55km of interceptor sewer along 3 major drains for

reduction of pollution in Yamuna river at New Delhi.

Page 8: Pipe Jacking

CONTENTS

• Introduction • Brief History

• Methodology• Application• Standards• Equipment/Component• Classification• Alternative methods• Pros & Cons

8

Page 9: Pipe Jacking

9

METHODOLOGYPLANNING

PROCEDURE

SPECIFIC FEATURE

PROCESS BASED ON SOIL

PIPE JACKING FORCE

FAILURE

SOLUTION

Page 10: Pipe Jacking

10

PLANING• Understand the site history and potential obstructions.• Look at old aerial photos.• Conduct a geotechnical program.• Locate all existing utilities.• Minimize costs.• Develop the best cross section.• Use the right materials.

Page 11: Pipe Jacking

11

PROCEDURE

• The thrust pit and the reception pit are excavated at the required places.

• Then the thrust wall is set up in the thrust pit according to the requirement.

• In case of mechanized excavations, a very large pit is required.

• But in case of manual excavation, a small pit is enough.• Thrust ring is provided to ensure the even distribution of

stress along the circumference of the pipe.

Page 12: Pipe Jacking

12

Contd.• The number of jacks vary upon the frictional resistance of

the soil, strength of pipes etc.,• The size of the reception pit is to be big enough to receive

the jacking shield.• To maintain the accuracy of alignment a steerable shield is

used during the pipe jacking.• In case of small and short distance excavations, ordinary

survey method is sufficient.• But in case of long excavations, remote sensing and other

techniques can be used.

Page 13: Pipe Jacking

13

Contd.

Figure 2a: Pipe Jacking ArrangementSource: http://www-civ.eng.cam.ac.uk

Page 14: Pipe Jacking

14

Contd.

Figure 2b: Labelled arrangement of pipe jackingSource: www.google.com

Page 15: Pipe Jacking

15

SPECIFIC FEATURES• Simple cyclic procedure.• Utilizes thrust from hydraulic jacks to force the pipe forward• Person have to enter in pipe for excavation.• Excavation can be manual or by machine.• Excavation takes place in front of an articulated shield. > Designed for worker safety. > Shield guided with individually controlled hydraulic jacks.• Practically limited to dia. greater than or equal to 1075mm.• Pipe installation process occurs from entrance and exit

shaft.

Page 16: Pipe Jacking

16

Figure 3: Manual and Machine Excavation

Source: www.civil.uwaterloo.ca

Source: www.civil.uwaterloo.ca

Source: www.civil.uwaterloo.ca

Source: www.civil.uwaterloo.ca

Page 17: Pipe Jacking

17

PROCESS BASED ON SOILUnstable soil• Face excavated simultaneously with the jacking operation.• Minimize over excavation and the risk of face collapse.• After pipe jacked into place hydraulic rams are retracted

and another pipe length is installed.Stable soil• Face excavation may precede the jacking operation.• All spoils removed through the inside of the pipe to the

jacking pit.

Page 18: Pipe Jacking

18

PIPE JACKING FORCE• Force on jacked pipe includes: > Pipe dead weight. > Penetration resistance or face pressure. > Soil-pipe friction.• Other forces like: > Curvature forces. > Soil dead load. > Railway or highway live load.• Jacking force must not exceed allowable pipe

compressive strength .

Page 19: Pipe Jacking

19Figure 4: Face Resistance

Source: www.youtube.com

Page 20: Pipe Jacking

20Figure 5: Skin friction and face resistance

Source: www.youtube.com

Page 21: Pipe Jacking

21Figure 6: Total force is greater than permissible limit

Source: www.youtube.com

Page 22: Pipe Jacking

22Figure 7: Force distribution with intermediate jack

Intermediate jackSource: www.youtube.com

Page 23: Pipe Jacking

23

FAILURE• Pipe generally fails from the corner first.• Maximum force is acting at the edges due to: > Uneven distribution of jacking force from one pipe to another. > Unavoidable curvature. > Elastic forces from pressure transfer rings at joints.

Figure 8: Failure of pipeSource: www.youtube.comSource: www.youtube.com

Page 24: Pipe Jacking

24Figure 9: Failure of pipe

Source: www.youtube.com

Page 25: Pipe Jacking

25

POSSIBLE SOLUTIONSolution

Open cut/dig and replace Trenchless

Tunnel & Replace

Jacking Pipe

Tunnel Liner Plate

Slip-lining

Jacking Pipe

Plastic liner

Lining-Rehab

Cured in place

Shotcrete

Page 26: Pipe Jacking

CONTENTS

• Introduction • Brief History• Methodology

• Application• Standards• Equipment/Component• Classification• Alternative methods• Pros & Cons

26

Page 27: Pipe Jacking

27

APPLICATION• Larger Diameter Pipe (1050 mm and up).• Lengths can range from 3 to over 200m.• Sewers, and drainage construction.• Gas and water mains.• Oil pipelines.• Industrial pipelines.• Telecommunication.• Pedestrian subways (access tunnels).

Page 28: Pipe Jacking

CONTENTS

• Introduction • Brief History• Methodology• Application

• Standards• Equipment/Component• Classification• Alternative methods• Pros & Cons

28

Page 29: Pipe Jacking

STANDARDS

29

• BS 6164: 2011 – Code of practice for health and safety in tunnelling in the construction industry.

• BS EN 16191 – Tunnelling machinery safety requirements

Table 1: Standards for pipe jackingSource: www.pipejacking.org

Page 30: Pipe Jacking

CONTENTS

• Introduction • Brief History• Methodology• Application• Standards

• Equipment/Component• Classification• Alternative methods• Pros & Cons

30

Page 31: Pipe Jacking

31

EQUIPMENT/COMPONENT• Jacking Pit.• Jack.• Pipe.• Thrust Ring.• Thrust wall.• Lubricant.• Intermediate Jack.• Cutting-head.• Pressure Transfer Ring etc.

Page 32: Pipe Jacking

32

JACKING PIT• Jacking pit size is function of Length of pipe segments,

Pipe diameter, Shield dimensions, Thrust wall design, Jack size, Pressure rings and Guide rail systems.

• Pit should be shored using Timber or steel piling.• Placement of concrete slab on the floor is recommended.

(a) (b)

Figure 10: Typical Jacking Pit(a) and (b)

Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca

Page 33: Pipe Jacking

33

JACK AND PIPE• Number and capacity of jack is a

function of pipe size, length, skin friction, intermediate jacks etc.

It is suggested to provide even number of jacks.

• Pipe should be light weighted, smooth and strong enough to withstand all the forces.

Figure 11a: Jack

Figure 11b: RCP Pipe

Source: www.civil.uwaterloo.ca

Source: www.civil.uwaterloo.ca

Page 34: Pipe Jacking

34

THRUST RING AND THRUST WALL• Thrust ring distributes force

from jack head to pipe edges equally.

A spacer is optional.

• Thrust wall is provided behind the jack to transfer back thrust of jack to earth and preventing jack to sink.

Figure 12a: Thrust Ring

Figure 12b: Thrust Wall

Source: www.google.com

Source: www.google.com

Page 35: Pipe Jacking

35

LUBRICANT AND INTERMEDIATE JACK

• Lubrication is provided at outer edges of pipe using lubricant injection ports at proper interval.

• Intermediate jack is provided in between the entry and exit shaft. Number of intermediate jack depend on pipe length and jack capacity.

IJ must match pipe diameter.

Figure 13a: Lubricant injection port

Figure 13b: Intermediate JackSource: www.civil.uwaterloo.ca

Source: www.civil.uwaterloo.ca

Page 36: Pipe Jacking

36

CUTTING-HEAD AND PRESSURE TRANSFER RING

• Cutting-head or cutter is located at the front of pipe line. It cuts down the soil ahead using mechanical motion into smaller fragments.

• Pressure transfer ring is used in between of two pipe at joints, it distribute the pressure to succeeding pipe equally. It is made either of cork or synthetic material.

Figure 14b: Pressure Transfer Ring

Figure 14a: Cutter-head

Source: www.youtube.com

Source: www.google.com

Page 37: Pipe Jacking

CONTENTS

• Introduction • Brief History• Methodology• Application• Standards• Equipment/Component

• Classification• Alternative methods• Pros & Cons

37

Page 38: Pipe Jacking

CLASSIFICATION

38

Pipe

Jack

ing

can

be c

lass

ified

on

the

basis

of: Pipe Material

Cutter-head

Excavation Technique

Page 39: Pipe Jacking

39

(a) Reinforced Concrete (b) Vitrified Clay (c) Ductile Iron

(d) Fibreglass (e) Steel (f) Composite

Figure 15: Classification on basis of pipe material(a)-(f)

Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca

Source: www.google.comSource: www.google.comSource: www.hobas.com

Source: www.google.com

Page 40: Pipe Jacking

40

(d) Backacters

(a) Open Face Cutter Booms

(e) Pressurized Slurry

(b) Tunnel Boring Machine (c) Earth Pressure Balance

Figure 16: Classification on basis of Cutter-head(a)-(e)

Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org

Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org

Page 41: Pipe Jacking

41

(a) Manual Excavation (b) Machine Excavation

(c) Conveyer belt Excavation (d) Slurry Excavation

Figure 17: Classification on basis of excavation technique(a)-(d)

Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca

Source: www.google.comSource: www.google.com

Page 42: Pipe Jacking

CONTENTS

• Introduction • Brief History• Methodology• Application• Standards• Equipment/Component• Classification

• Alternative methods• Pros & Cons

0

42

Page 43: Pipe Jacking

ALTERNATIVE METHODS

Trenchless Piping

Non-steering Methods

Steering Methods

43

• Moling/Piercing• Pipe Ramming• Auger Boring• Pipe Jacking

• Micro-tunneling• Horizontal

directional drilling

Page 44: Pipe Jacking

Generic Size and Length• Method Size(inch) Length(ft)

Moling 2” - 12” 150’Ramming 8” - 72” 300’Auger Bore 8” - 60” 250’Pilot Tube 6” - 42” 300’ Pipe Jacking >42” 1,000’Micro-tunneling 12” - 42” 1,500’HDD 2” - 48” 6,500’Tunneling >60” Any length

Table 2: Compatibility of different methods 41

Source: www.pipejacking.org

Page 45: Pipe Jacking

45

(a) Auger Boring (b) Pilot Tube (c) Horizontal Direction Drilling

(d) Micro-tunneling (e) Pipe Ramming

Figure 18: Alternative methods(a)-(e)

Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org

Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org

Page 46: Pipe Jacking

CONTENTS

• Introduction • Brief History• Methodology• Application• Standards• Equipment/Component• Classification• Alternative methods

• Pros & Cons46

Page 47: Pipe Jacking

47

ADVANTAGE• It avoids the excavation of trenches.• Quick set-up, timely finish of projects.• Good quality control and good grade of pipe used.• Can be remotely operated.• Versatile in various ground conditions.• Cost efficient for large length pipe.• Small surface settlements.• Reduces disruption to existing services.• Environment friendly.• Less spoil.

Page 48: Pipe Jacking

48

DISADVANTAGE• Costly for small lengths.• Skilled personal is required.• Dewatering of tunnel path is usually required.• Not feasible for nature of soil changes drastically.• Hard rock/Bed rock or very big boulders should not be

present in the path line.

Page 49: Pipe Jacking

49

CLOSING THOUGHTS• Methods still evolving.• Many hybrid methods emerging.• Will never replace traditional open-cut methods;

however, they complement each other.New idea• To identify potential obstructions we can install a

GPR(Ground Penetrating Radar) at cutting head.