PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities...

19
PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015

Transcript of PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities...

Page 1: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP FY15 PMG

W. Pellico

PIP PMG

March 5th 2015

Page 2: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP FY15 Year to Date

Outline– FY15 activities

• PIP quarterly milestones • Linac• Booster• Project Controls

– FY15 Plans

3/5/2015bp | PIP FY15 Q1+ PMG2

Page 3: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP FY15 Milestones

3/5/2015bp | PIP FY15 Q1+ PMG3

LVL WBS Description Baseline Date

3 1.01.02.03.06.23 Beam shaping technology chosen 10/8/14 10/8/14

3 1.01.02.03.05.33 Linac Notch Final Optical Cavity Certified 2/2/15 10/22/14

3 1.02.01.01.03 Specifications for Anode Power Supply Documented

10/15/14 11/26/14

3 1.01.05.02.02.16 Complete 55 LCW Spare Syst 12/9/14 12/18/14

4 1.01.05.02.01.09 Complete Installation of New Dual Temp System

3/24/15 12/30/14

4 1.01.05.02.01.10 Linac LCW System Complete 11/24/14 12/30/14

3 1.02.03.01.02.05 Booster BPM System, Hardware & Firmware Prototype Design Complete

12/22/14 5/1/15

3 1.01.01.01.02.01.02.09 Prototype Klystron Final Assembly Drawings Complete

12/17/14 3/2/15

3 1.02.03.01.01.03 Booster BPM Specification Complete 12/8/14 3/27/15

3 1.01.02.03.03.20 Linac Notcher (FA) Certify all three stages ready for installation

12/2/14 3/6/15

3 1.02.03.02.01.09 Specifications document for Booster longitudinal dampers complete

12/1/14 3/27/15

Page 4: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP 200 MHz RF Power Systems (WBS 1.1.1)Linac High Level

• Klystron effort – Work has shifted from design to

drafting of the klystron

• Continuing dialogue on hardware specifics

• Continuing discussion on testing at vendor– Looks like this is a viable option– Will not require Fermi to build test

stand

• Long lead-time acquisitions nearly complete

3/5/2015bp | PIP FY15 Q1+ PMG4

Action Date

Preliminary Design Review 4/2/2014

Critical Design Review 7/11/2014

Seal in Drawings Complete 10/6/2014

Final Assembly Drawings Complete

12/17/2014

Seal in Assembly Complete 6/17/2015

Final Dress Complete 7/15/2015

Testing Complete 8/26/2015

Customer Source Inspection 8/27/2015

Package and Ship 9/8/2015

Page 5: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

Activities• 28 cell enclosure design completed

• received enclosure• waiting on vendor to build internal support

structure (4 weeks away)• Gate driver circuit board design/layout done• Designing control cards for both 28 and 54 cell

prototype design• Short circuit testing completed for 9 cell

prototype• Performed corona testing on cells and made

design changes• Selected charging supply manufacturer,

ordered units, will initial use to do thermal analysis of main switching element

• Learning / feed-forward control system work underway

• Proceeding with 54 cell design• Most parts ordered for building 54 cell design,

some have already arrived

3/5/2015bp | PIP FY15 Q1+ PMG5

9 cell timing tests completed• upgrades completed• snubber capacitor (one added)• gate clamp• B-dot coil design• new low inductance stripline

PIP 200 MHz RF Power Systems (WBS 1.1.1)Linac Modulator

Page 6: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP Accelerator Physics (WBS 1.1.2) Linac Laser Notcher

3/5/2015bp | PIP FY15 Q1+ PMG6

Linac Notch Creation (Dave Johnson will give more details)•Started environmental testing of mirrors using test laser•Successfully performed verification test of laser power and optics•Buildup of final laser system got underway

Mirror

Laser Input Port

RFQ

200 MHz Bunched Beam

Page 7: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

Power Distribution

Completed task

LCW distributionCompleted task

Vacuum

Completed task

PIP Linac Utilities (WBS 1.1.5)

3/5/2015bp | PIP FY15 Q1+ PMG7

Oct ‘12

DTL roughing station

Page 8: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP Booster Anode Supplies (WBS 1.2.1.1)

• Anodes to be installed in the FY15 shutdown….– Slower than expected….

• Issues finding vendors that can meet the specifications• Issues with enclosure• Lots of components to test before final install

3/5/2015bp | PIP FY15 Q1+ PMG8

Page 9: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP Booster Bias Supplies (WBS 1.2.1.2)

• Upgrading the west gallery supplies for reliable 15 Hz operations

– Replacing transformers for 15 Hz operation

– Also requires re-plumbing and re-wiring– Adding heat sinks in several areas

• This effort is not as far along as projected, largely due to labor

– 5 out of 10 in west gallery upgraded/tested

– Should not impact initial 15 Hz testing

3/5/2015bp | PIP FY15 Q1+ PMG9

Page 10: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP Booster Cavity & Tuner Refurbishment (WBS 1.2.1.5)

• Since this summer progress continues at an increased pace – Cones for tuners is still a time constraint– TD is used to do some re-work; AD team does majority– New AL cones are now part of the process

• Worked out vendor quality issues• Saves time – but still labor intensive to complete process

• Labor– Another contract tech left!!!!

• New one just hired this week – not sure of status– Will take time to train (typically on the order of 6 months)

• Concern about shutdown – do not want to lose tech/fall behind

• Goal of PIP/AD is to have 17 certified by June 2015– This will allow us to test entire system at 15 Hz– East gallery has had several months of 15 Hz testing

3/5/2015bp | PIP FY15 Q1+ PMG10

Page 11: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

3/5/2015bp | PIP FY15 Q1+ PMG11

Planned installof #17….

A failure of refurbed BRF5 last Tuesday may impact schedule…• No details yet on

what failed

These cavities will never be like new cavities and will have long term operational issues

PIP Booster Cavity & Tuner Refurbishment (WBS 1.2.1.5)

Page 12: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP Booster New Tuners (WBS 1.2.1.6)

• Vendor has now met speciation's for both types of ferrites– Partial orders have been delivered

• buildup of tuner components underway (TD leading effort)

– Second tuner completed…third tuner getting started– Releasing order for more ferrite

3/5/2015bp | PIP FY15 Q1+ PMG12

Page 13: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP Booster New Cavities (WBS 1.2.1.7)

• Splitting into three thrusts:– Rework of Proton Driver cavities and original prototype

• Original cavity (20) installed and operating• Two more (Cavity 21 & 22) work and schedule being developed• Will have 22 stations installed and operating when completed

– Harmonic Cavity System (Perpendicular Bias)• Initial design plan is for injection and transition• Modelling progressing• Building up mock cavity for testing purposes• Plan to order components for full cavity by end of FY15

– Replacement RF system compatible with PIP II (PIP III RCS)• This is on going discussion – hope to settle question soon!• 20 Hz capable

3/5/2015bp | PIP FY15 Q1+ PMG13

Page 14: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP Booster Radiation Shielding (WBS 1.2.2.6)

• TLM system installed in Booster– 8 detectors (each covering 3 Booster periods)– No single detector covers more than 1 expected

“lossy” region• Injection, extraction, collimators, notcher

• Will run series of beam tests in next couple of weeks to characterize system– destructive studies – will impact operations

• ES&H assessment group is working on dosages through the shielding & penetrations– Have done several rounds of test to confirm

assumptions on loss pattern/levels– At least one more scan is planned

3/5/2015bp | PIP FY15 Q1+ PMG14

Page 15: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

BPM • The Booster BPM front end test-stand

is running a Linux/RTAI kernel and the AD/Control's department ACSYS software

– this is the Linux equivalent of MOOC

• Running Linux in a VME crate required some effort to build and test the VME drivers for Linux

• Testing the VME interface to the 250MHz digitizer

Dampers • Several problems encountered with

initial frontend– Lock issues– Card debugging

• Transfer measurements• Phase control work – to match present

system• Compared old and new system

amplitudes and rates of CB instabilities• ACNET software just completed and

now being tested

PIP Booster Instrumentation (WBS 1.2.2.3)

3/5/2015bp | PIP FY15 Q1+ PMG15

• Working on the

BPM control and

readout software

Page 16: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

Transformers• Last transformer to install (East

side)– Will be completed this shutdown

Vacuum• Cabling and associated rack work is

on-going• Tunnel work awaits personnel

availability & will be fill-in work this shutdown

PIP Booster Utilities (WBS 1.2.2.5)

3/5/2015bp | PIP FY15 Q1+ PMG16

Page 17: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP End of Year Budget and Labor Summary

3/5/2015bp | PIP FY15 Q1+ PMG17

AD CD FESS PPD TD0.0

5.0

10.0

15.0

20.0

25.0

30.0

Jan 15 ActsJan Forecast

Dec Actual FTEs = 32.9Dec Forecast FTEs = 28.2

Page 18: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

PIP FY15 Initial Upload (some small differences – will be corrected)

3/5/2015bp | PIP FY15 Q1+ PMG18

CHOOSE OHAP ROLEPI OHAP Category (will fill) AD APC FESS PPD CD TD TOTALFTEs TOTAL FTE 18.99 2.20 0.01 0.00 0.00 3.05 0.00 0.00 24.25

LABOR COST (will calculate)TOTAL LABOR COST $1,923.6 $357.4 $1.2 $0.0 $0.0 $275.9 $0.0 $0.0 $2,558.1 LABOR OH RATE 97.37% 97.37% 54.19% 73.47% 70.00% 87.34% 0.00% 0.00% LABOR OH $1,873.0 $348.0 $0.7 $0.0 $0.0 $240.9 $0.0 $0.0 $2,462.6 M&S (enter)Standard $1,848.5 $1,848.5Pass-Through $0.0Exempt - $ of POs > $500K $2,126.1 $2,126.1Exempt - # OF PO > $500K 2 2TOTAL M&S $3,974.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $3,974.6

M&S OVERHEAD RATES M&S Standard 21.28%M&S Pass-Through 3.00%Exempt - M&S on first $500k $106.4

TOTAL M&S OH $606.2 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $606.2

BUDGET SUMMARYSWF $1,923.6 $357.4 $1.2 $0.0 $0.0 $275.9 $0.0 $0.0 $2,558.1SWF OH $1,873.0 $348.0 $0.7 $0.0 $0.0 $240.9 $0.0 $0.0 $2,462.6M&S $3,974.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $3,974.6M&S OH $606.2 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $606.2TOTAL BUDGET SUMMARY $8,377.3 $705.4 $1.9 $0.0 $0.0 $516.8 $0.0 $0.0 $9,601.4

12,000.0

Over (Under) Guidance (2,398.6)

Adjustments are being planned: Code structure, Some task plans and Labor needs

PIP FY15 budget reduced by 2 million – to 10M working out RLS changes

Page 19: PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

Summary

• Most PIP tasks continue to align to schedule– Refurb rate has greatly improved

• Recent setbacks in labor and RF5 vacuum leak• New Tuners• AL cones

• Recent reviews have gone very well…– DOE PIP & 700 KW Review

• PIP well-defined achievable, etc.- Half of tasks completed - delivering beam improvements- Impressive progress

• Remaining FY15 PIP will be busy – preparing for shutdown and 15 Hz RF cycling…

3/5/2015bp | PIP FY15 Q1+ PMG19