THE Plastic Piling CPD presentation Pt 2 Installation of plastic piling
Piling work method statement cm- ms- bw - 002
-
Upload
minh-bui-si -
Category
Documents
-
view
1.487 -
download
22
Transcript of Piling work method statement cm- ms- bw - 002
![Page 1: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/1.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
CAI MEP INTERNATIONAL CONTAINER TERMINAL
METHOD STATEMENT OF PILING WORKS FOR BUILDINGS
Page 1
![Page 2: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/2.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
TABLE OF CONTENTS
1. General…………………………………………………………… 2
2. Scope of Works…………………………………………………... 2
3. Reference Technical Specification ………………………………. 2
4. Reference Drawings……………………………………………..... 2
5. Specification of Piling Machine…………………………………... 2
6. Piling Schedule……………………………………………………. 2
7. Equipment and manpower list…………………………………… 2
7.1. Equipment………………………………………………………… 3
7.2. Labors…………………………………………………………….. 5
8. General Flow Chart Of Piling Work……………………………… 6
9. Piling Procedure…………………………………………………... 7
10. Piling by Diesel Hammer…………………………………………. 8
10.1 Driving Lower Segment PHC Pile………………………………... 8
10.2 Splicing Work……………………………………………………... 9
10.3 Driving Upper Segment PHC Pile……………………………….... 9 11. Pile Driving Record………………………………………………. 10 12. Pile Dynamic Analyzer…………………………………………... 11
13. Quality Control………………………………………………….... 11
13.1. Inspection of Fabrication ……………………………………….... 11
13.2. Inspection of Welding Work……………………………………... 11
14. Safety Control…………………………………………………...... 12
15. Appendixes……………………………………………………….. 13
Page 2
![Page 3: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/3.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
1. General :
This Method Statement for PHC and the solid pile, piling work procedure of
buildings for CAI MEP INTERNATIONAL CONTAINER TERMINAL
PROJECT is to demonstrate the process of driving these piles in compliance with
all the required specifications, standards, and proper construction procedures
governing the pile driving works for the building foundation of the project.
2. Scope Of Works :
Execution and supply of PHC and square solid piles, setting piles location before
driving, driving and all necessary engineering works could be categorized as
follows:
Type of piles are PHC pile type A, (Ø 600 mm, Ø500mm), and 400mmx400mm
solid square piles.
3. Reference Technical Specifications :
Technical Specification: Part 4B, Division 2 – Piling Works for Buildings.
4. Reference Drawing List :
Attached in Appendix B
5. Specification and Certificate of Piling Machine
Specification of piling machine and crane operation certificate:
Attached in Appendix C
6. Piling Schedule :
Attached in Appendix E
Page 3
![Page 4: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/4.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
7. Equipment & Manpower List:
7.1. Equipment to Be Used:
The Equipment to be used for pile driving works is summarized in Table 7.1
Table 7.1 List of Equipment
No Equipment Specification Quantity Capacity
1 Diesel Pile Hammer KOBELCO K35/K25 1 5T
2 Diesel Pile HammerKOBELCO
K35/DELMAG D 251 5T
3 Diesel Pile Hammer HERA3500/D25C 1 5T
4 Diesel Pile HammerKOBELKO K45/KB60
MITSUBISHI MB 701 4.5T,6T,7T
5 Crane Truck Model: LS78 1 35T6 Crane Truck Model: DH 350 1 35T7 Theodolite Japan Made 04 100% precise8 Survey Equipment US Made 1 100% precise9 Automatic Level Japan Made 2 100% precise
TOTAL→ 13
7.2. Labors To Be Deployed:
Labors and/or trades to be deployed for PHC piling work is summarized in
Table 7.2Page 4
![Page 5: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/5.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Table 7.2- List of labors
Description Quantity Remark
Engineer 3
Foreman 3
Piling operator 3
Workers 12
Welders 6
Surveyor 4
Crane operator 2
TOTAL→ 33
8. General Flow Chart Of Piling Work:
General Flow Chart:
Page 5
![Page 6: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/6.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
9. Piling Procedure
PHC Piles D600mm, D500mm and Solid 400mmx400mm will be plant
fabricated and transported to the site by a Trailer truck and by barge. They will be
Page 6
Mobilization of Piling Machine
Delivery of PHC Pile by Barge & Trailer Truck for Building
Lifting the lower segment PHC pile by Crane then mount Diesel Hammer
Driving the lower segment PHC pile
Confirm the bearing capacity by evaluating penetration during driving
Lifting the upper segment PHC pile and Splicing
Driving the upper PHC pile(Middle/Top)
Finish
![Page 7: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/7.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
supported by bedding timbers placed directly under the positions of lifting hooks
(Shown in Figure 1).
Piles will be stored carefully on flat ground within the temporary yard and a
maximum of three (3) layers per stock pile is required.
Pile markings should be carried out to every pile segments to check the rough
penetration per hammer blow. Bottom segment piles will be marked at every 1.0m
pitch, middle segments, and top segments will be marked every 20cm pitch.
Material delivery dockets, receipts and physical inspection report shall be
submitted to the Engineer.
TRUCK CRANE
TRAILER PHC PILE
0. 2L 0. 2L 0. 6L
Figure 1: Transportation of PHC Pile
PHC PILE TIMBER 0. 2L ER
0. 2L 0. 2L
Figure 2: Storage of PHC Pile
10. Piling By Diesel Hammer :
Page 7
Sand Bag Sand Bag
![Page 8: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/8.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
The piles will be driven by diesel hammer. The driving will be stopped after
confirming the bearing capacity. (Shown in Figure 2)
CENTER LINE OF PILE
SURVEYER
TRANSIT/PLUMB BOB
PILE DRIVER
SURVEYER
PILE UNDER DRIVING
DIESEL
HAMMER
G N I V I R D
N O I T C E R I D
TRANSIT/PLUMB BOB
Figure 2: Pile Driving
10.1. Driving Lower Segment PHC Pile:
Crane will lift up the lower segment PHC Pile near the piling machine. The PHC
pile will be held along leader of diesel hammer. Lifting position shall be 0.2L of pile
length. ( lower than cracking moment)
The pile position will be adjusted by moving the leader until its top coincides with
the hammer then mount the cap on the pile top. Before start driving, vertical position
of the pile will be checked carefully by total station or theodolite to confirm its
verticality.
10.2. Splicing Work:
Page 8
![Page 9: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/9.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Prior to splicing, welding surfaces will be cleaned and free from rust, oil, water
and other foreign elements that would affect welded joints.
After driving lower segment, the upper segment will be lifted by piling machine,
set above the lower segment coincide their centers directly and aligned vertically
then fixed the clamp to maintain its alignment. Inclination tolerance shall be
checked by split level, and it should be less than 1.0cm/1.0m)
. Splices will be made by butt welding, using arc welding performed 2G position
and in accordance to WPS (Welding Position Standard) for welding.
Visual and NDT inspection check will be conducted to every welding joint done.
Figure 3
10.3Driving Upper Segment PHC Pile:
Top segment shall be driven after obtaining the PDA test results for correction
factor from Hailey’s formula
Driving will be complete after confirming the sufficient bearing capacity, from
Hailey’ s formula shown below with reference to PDA Test results.
Page 9
PILE DRIVER
DIESEL HAMMER
HELMET
LOWER PILE
1) DRIVING OF LOWER PILE 2) CLEANING OF PILE HEAD 3) SPLICING 4) RESUMING OF DRIVING
UPPER PILE
![Page 10: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/10.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
If it is found that the bearing capacity is still insufficient obtained from
rebound record against design, the pile should be extended and re-driven until the
bearing capacity is reached.
Ru = 9.81 (Ef.MR.H) x MR + e 2 .MP
S+0.5(C1+C2+C3) MR + MP
= A In which:
Ru : Ultimate Resistance, KN
MR: Weight of ram, Kg
H : Drop height of hammer, mm
Ef : Efficiency of fall of hammer
MP: Weight of pile + helmet, Kg
e : Coefficient of restitution [ e = (S+{C₁+C₂+C₃}÷2 x PDA)/(Ef x MR x H) ]
C1: Elastic deformation of pile, mm
C2: Elastic deformation of ground, mm
C3: Elastic deformation of pile head cushion, mm (here C3 = 2 mm).
S : average penetration, in mm per blow for at least the last 10 blows
RP: Correction Factor (RP = S.L.T. / A)
(Use rebound record- Attached Appendix F)
The result of Pile driving and bearing capacity shall be confirmed by the
Engineer and the records of pile installation shall be submitted to the Engineer.
In case the pile tip can not reach the design level due to unforeseen hard layer,
this matter will be reported to the Engineer.
If piles cannot be driven to the design level but has already attained the required
bearing capacity, the driving shall be stopped in accordance to specification and
Engineer’s instruction to avoid buckling or cracking of the pile.
Pile head treatment shall be done after getting Engineer’s approval.
11. Pile Record:
Before final setting of the piles, the rebound shall be recorded.
Page 10
x RP
![Page 11: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/11.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
The pile driving is deemed completed after confirmation of the sufficient bearing
capacity against design. Bearing capacity for all piles will be calculated with
formula.
12. Pile Dynamic Analyzer (PDA)
Pile Dynamic Analysis will be conducted to confirm the pile capacities and to
decide the correction factor of Hiley’s formula. PDA test provides more
information, about Skin resistance distribution, Toe resistance, simulated static
load-settlement relationship, pile integrity, stresses in the pile during the blow.
PDA test shall be conducted by Engineer
13. Quality Control
13.1. Inspection of Fabrication
Before fabrication PHC and square Pile materials such as, cement, sand, gravel,
reinforcing bars, tendon wires and etc, will be inspected on Factory before
fabrication, and finished product will again be inspected before delivery to the site.
The inspection report shall be submitted before piles will be delivered on site.
When PHC and square piles arrives on site/stockyard, these will be inspected
again for its, physical conditions, quantity and quality in accordance with
specification or standards listed below:
- Length tolerance: ±3%
- Outside diameter tolerance: +7mm/-4mm
- Wall thickness tolerance: +unspecified/-0mm
- Cracking: no crack
The quality control and inspection report will be submitted to the Engineer.
13.2. Inspection of Welding Work.
Prior to the welding, the grooved face and its adjacent areas shall be completely
free from oil, paint, oxide, water and all other foreign materials.
Welding rod will be stored in a dry and humid place to keep its required
temperature. Only welding rod approved by the Engineer will be used on the
splicing of pile.
Page 11
![Page 12: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/12.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Piles are jointed with their end plates evenly around its diameter, welding must
be carried out in accordance with manufacture’s instruction and must be checked
before driving resumes. Piles welding splice will be tested by NDT test. Basically
all weld joints shall be tested by NDT but reducing option will be proposed
depending on the quality of test obtained on the previous welded joints. (Refer to
attached form in Appendix F)
(1) Crack Inspection of Welding
There shall be no cracks in or near the weld beads. The inspection shall be carried
out by visual and Non Destructive test (NDT).
(2) Inspection of Bead Surface and Shape
Visual inspection of bead surface and shape shall be done by the process listed
below.
a. Pits on bead surface
Butt joints shall be free of weld pits on the bead surface.
b. Flatness of bead
There shall be no height difference exceeding 3mm within 25mm length of a bead.
c. Undercut
The depth of undercut shall not exceed 0.3mm.
d. Overlap
There shall be no overlap.
During driving, the pile head will be protected by helmet of cast steel or mild
steel fitted closely around the pile. Packing (cushion) timber, covering the head of
pile, will be placed on the pile and will be replaced as often as necessary to prevent
damage to the piles.
14. Safety Control:
Prior to commencement of any activities, the contractor will ensure all safety
work practices and requirements for the different operations and are made
informed and strictly complied at all times.
Page 12
![Page 13: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/13.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
The following steps are strictly checked before and during working.
1. Equipment and machine efficiency checking prior to operation.
2. Grand condition
3. Tool box meeting
15. Appendices:
Appendix A: Organizational Chart
Appendix B: Ref. Drawings List
Appendix C: Specification and Certificate of Piling Machine
Appendix D: Fabrication Schedule
Appendix E: Pile Driving Schedule
Appendix F: Pile Driving & Welding splicing Form
Appendix G: Checklist for PHC Pile Manufacturing
Appendix H: Inspection and Test PLan
Page 13
![Page 14: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/14.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix A: Organizational Chart
Item No Title Numbers Remarks
1 Site Manager 2
2 Engineer/Safety 3
3 Foreman 3
4 Operator 3
5 Welder 6
6 Worker 12
7 Surveyor 4
Total→ 33
Page 14
TOA-TOYO JV
Site Manager
Engineer & Safety
Pile TransportationTeam
Piling Rig-2Team-2
Piling Rig-1Team-1
![Page 15: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/15.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix B:
Ref. Drawing List:
Page 15
![Page 16: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/16.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix C:
Specification and Certificate of Piling Machine
Page 16
![Page 17: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/17.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix D:
Pile Fabrication Schedule
Page 17
![Page 18: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/18.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix E:
Pile Driving Schedule
Page 18
![Page 19: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/19.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix F:
Pile Driving & Welding splicing Form
Page 19
![Page 20: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/20.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix G:
Checklist for PHC Pile Manufacturing
Page 20
![Page 21: Piling work method statement cm- ms- bw - 002](https://reader030.fdocuments.net/reader030/viewer/2022012311/55a33d491a28ab1f7d8b46ff/html5/thumbnails/21.jpg)
Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix H:
Inspection and Test Plan
Page 21