Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris,...
-
Upload
clarissa-oliver -
Category
Documents
-
view
220 -
download
2
Transcript of Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris,...
Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho
Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho
Presented by
Dean E. Harris, P.E., CH2M HILL
Project DescriptionProject Description• Current alignment is
through the City
• Realignment will provide a non-stop route for through traffic
• WGI is completing roadway and structural design
• CH2M HILL is responsible for geotechnical and structural design
Sand Creek BywaySand Creek Byway
Project FeaturesProject Features
• Project features include two interchanges, a smaller bridge crossing a city street, and numerous MSE walls
• Community is sensitive to appearance and function
• Community supports the project
Sand Creek CrossingSand Creek Crossing
Geotechnical ExplorationsGeotechnical Explorations
• Piezocone (CPTu) was the primary method of subsurface exploration
• Maximum depth of CPTu soundings of 80 m
• Soil borings were advanced adjacent to many soundings to collect samples.
• Other testing included vane shear testing and shear wave velocity tests
Cone rig and barge in Sand Creek
Typical Soil ProfileTypical Soil Profile
• Upper 10 m: Medium stiff sandy silt to clay, N = 9 to 15 blows per 0.3 m
• 10 to 39 m: Very soft to soft clay with thin layers of loose to medium dense sandy silt,
N = 0 to 5 blows per 0.3 m
• 39 to 67 m: Alternating soft to mediumsilt and clay, N = 7 to 13 blows per 0.3 m
555
565
575
585
595
605
615
625
635
0 5 10 15
QT (MPa)E
leva
tio
n (
m)
0 100 200 300 400
FS (kPa)
Corrected TipResistanceFriction Resistance
Pore Pressure (kPa)
0 1000 2000
Hydrostatic
Excess PWP
0 20 40 60
Water Content (%)
Natural Water Content
LL - PL Range
Pile Loading TestPile Loading Test
• Axial compression loading test on a 0.41 m (16 in) steel pipe pile, driven to a depth of 45 m, with PDA and CAPWAP analysis
• Pile was instrumented at 8 levels, with vibrating wire gauges on sister bars, and 2 telltales; concrete-filled
• Osterberg Cell (O-Cell) used at the head of the pile, with steel reaction frame
Pile driving with APE D36-32
Piezometer Response During and After Pile Driving
0.0
10.0
20.0
30.0
40.0
50.0
0 1 10 100
Elapsed Time (Days)
Ex
ce
ss
He
ad
(m
)
Depth = 30 m
Loading System
Loading test
0
500
1000
1500
2000
2500
0 10 20 30 40 50
Movem ent (m m )
Lo
ad (
KN
)
Head O-Cell
Toe Mvmnt
Load-Movement Curves from Loading TestLoad-Movement Curves from Loading Test
Findings from Loading TestFindings from Loading Test
• Plunging failure occurred at movement of 11 mm
• Analysis considered pile residual load
• For clay layer, = 0.1, Nt = 6
Condition Capacity (kN)
End of Initial Driving 260
Restrike (after 24 hours setup)
980
Static Loading Test (50 days after driving)
1900
0
5
10
15
20
25
30
35
40
45
50
0 500 1000 1500 2000
Load (kN)
Dep
th (m
)
Residual Load
Interpreted Load
Probable Distribution of TrueLoad
Strain Gauge PlacementStrain Gauge Placement
Neutral Plane AnalysisNeutral Plane Analysis
Interpretation of Gauge LoadInterpretation of Gauge Load
0
5
10
15
20
25
30
35
40
45
50
0 500 1000 1500 2000
Load (kN)
Dep
th (m
)
Residual Load
Interpreted Load
Probable Distribution of TrueLoad
Summary and ConclusionsSummary and Conclusions
• Pile Setup is a major factor affecting construction and estimated capacity
• Instrumentation is necessary to extrapolate the pile testing data to other pile lengths
• Residual load effects are significant in interpreting capcity