Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris,...

29
Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL

Transcript of Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris,...

Page 1: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho

Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho

Presented by

Dean E. Harris, P.E., CH2M HILL

Page 2: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Project DescriptionProject Description• Current alignment is

through the City

• Realignment will provide a non-stop route for through traffic

• WGI is completing roadway and structural design

• CH2M HILL is responsible for geotechnical and structural design

Page 3: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Sand Creek BywaySand Creek Byway

Page 4: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Project FeaturesProject Features

• Project features include two interchanges, a smaller bridge crossing a city street, and numerous MSE walls

• Community is sensitive to appearance and function

• Community supports the project

Page 5: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.
Page 6: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Sand Creek CrossingSand Creek Crossing

Page 7: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Geotechnical ExplorationsGeotechnical Explorations

• Piezocone (CPTu) was the primary method of subsurface exploration

• Maximum depth of CPTu soundings of 80 m

• Soil borings were advanced adjacent to many soundings to collect samples.

• Other testing included vane shear testing and shear wave velocity tests

Page 8: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.
Page 9: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Cone rig and barge in Sand Creek

Page 10: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.
Page 11: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Typical Soil ProfileTypical Soil Profile

• Upper 10 m: Medium stiff sandy silt to clay, N = 9 to 15 blows per 0.3 m

• 10 to 39 m: Very soft to soft clay with thin layers of loose to medium dense sandy silt,

N = 0 to 5 blows per 0.3 m

• 39 to 67 m: Alternating soft to mediumsilt and clay, N = 7 to 13 blows per 0.3 m

Page 12: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

555

565

575

585

595

605

615

625

635

0 5 10 15

QT (MPa)E

leva

tio

n (

m)

0 100 200 300 400

FS (kPa)

Corrected TipResistanceFriction Resistance

Pore Pressure (kPa)

0 1000 2000

Hydrostatic

Excess PWP

0 20 40 60

Water Content (%)

Natural Water Content

LL - PL Range

Page 13: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Pile Loading TestPile Loading Test

• Axial compression loading test on a 0.41 m (16 in) steel pipe pile, driven to a depth of 45 m, with PDA and CAPWAP analysis

• Pile was instrumented at 8 levels, with vibrating wire gauges on sister bars, and 2 telltales; concrete-filled

• Osterberg Cell (O-Cell) used at the head of the pile, with steel reaction frame

Page 14: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Pile driving with APE D36-32

Page 15: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.
Page 16: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Piezometer Response During and After Pile Driving

0.0

10.0

20.0

30.0

40.0

50.0

0 1 10 100

Elapsed Time (Days)

Ex

ce

ss

He

ad

(m

)

Depth = 30 m

Page 17: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Loading System

Page 18: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Loading test

Page 19: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

0

500

1000

1500

2000

2500

0 10 20 30 40 50

Movem ent (m m )

Lo

ad (

KN

)

Head O-Cell

Toe Mvmnt

Load-Movement Curves from Loading TestLoad-Movement Curves from Loading Test

Page 20: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.
Page 21: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Findings from Loading TestFindings from Loading Test

• Plunging failure occurred at movement of 11 mm

• Analysis considered pile residual load

• For clay layer, = 0.1, Nt = 6

Page 22: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Condition Capacity (kN)

End of Initial Driving 260

Restrike (after 24 hours setup)

980

Static Loading Test (50 days after driving)

1900

Page 23: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

0

5

10

15

20

25

30

35

40

45

50

0 500 1000 1500 2000

Load (kN)

Dep

th (m

)

Residual Load

Interpreted Load

Probable Distribution of TrueLoad

Page 24: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Strain Gauge PlacementStrain Gauge Placement

Page 25: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.
Page 26: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Neutral Plane AnalysisNeutral Plane Analysis

Page 27: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Interpretation of Gauge LoadInterpretation of Gauge Load

Page 28: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

0

5

10

15

20

25

30

35

40

45

50

0 500 1000 1500 2000

Load (kN)

Dep

th (m

)

Residual Load

Interpreted Load

Probable Distribution of TrueLoad

Page 29: Pile Testing and Evaluation for the Sand Creek Byway, Sandpoint, Idaho Presented by Dean E. Harris, P.E., CH2M HILL.

Summary and ConclusionsSummary and Conclusions

• Pile Setup is a major factor affecting construction and estimated capacity

• Instrumentation is necessary to extrapolate the pile testing data to other pile lengths

• Residual load effects are significant in interpreting capcity