Phosphorus Removal: Advanced Chemical Dosing using Real ...
Transcript of Phosphorus Removal: Advanced Chemical Dosing using Real ...
Phosphorus Removal:
Advanced Chemical
Dosing using Real Time
Control (RTC) systems
Stuart Ainsworth RTC Optimisation Specialist
SWIG workshop November 26th, 2014
I. Chemistry of P removal
II. General Site Characteristics
III. P-RTC compared to existing methods
IV. Equipment Reliability / Suitability
V. Case Studies
2
Chemistry of Phosphorus Removal
Clear link between molar ratio and % removal ortho P
Jar tests limitations
Mixing important but NOT as critical as clean water applications
Knowing the concentration of ortho P is very important for accurate dosing!
11/12/2014 HACH LANGE 3
0 10 20 30 40 50 60 70 80 90 100
Mo
lar
Ra
tio
% Ortho P Removed
Ferric P Removal Efficiency vs. Aluminium
Ferric Sulphate Real Resultsat Burscough
Ferric Sulphate Jar test
Aluminium Sulphate Jar Test
I.
Ferric Sulphate Removal at
WwTW
Validated results from alternative WwTW & chemical supplier
Good Correlation
11/12/2014 HACH LANGE 4
R² = 0.9958
R² = 0.9579
0 20 40 60 80 100
Mo
lar
Ra
tio
% Removal
Validation check of Precipitation Chemicals
Ferric Sulphate 12.5%
Aluminium Sulphate 5.4%
I. Chemistry of Phosphorus Removal
I. Chemistry of P removal
II. General Site Characteristics
III. P-RTC compared to existing methods
IV. Equipment Reliability / Suitability
V. Case Studies
5
There is NO credible link between flow and
load (when considering all conditions).
Flow paced dosing systems are NOT in
control!
Establishing an effective storm suppression
dose is very difficult.
11/12/2014 HACH LANGE 6
There is a credible link between time and
load BUT there are very significant variations
in load for any given time.
Profiled dose systems do not take into
account “load to be removed”.
Profiled dose not account for profile changes
due to changing flow conditions.
II. General Site Characteristics
Based on real data from
typical domestic catchment
(P.E. circa 30K)
Note: minimum & maximum
concentrations very close
Slight increase in flows can
lead to extended “no-dose”
events
True load profile is much
more dynamic than typical
fixed profile dose systems
11/12/2014 HACH LANGE 7
II. General Site Characteristics
Less load is required to be
removed for any rain event.
The molar ratio required is
reduced through lower %
removal requirement.
Real time control can exploit
this for chemical savings.
Real time control focus on
load peaks.
11/12/2014 HACH LANGE 8
II. General Site Characteristics
Demonstrates the problem
of when to reinstate
“normal” conditions after
storm suppression dose.
Shows how static profiled
dose can be unsuitable.
Much wider dynamic range
to accommodate peak
minima & maxima.
11/12/2014 HACH LANGE 9
II. General Site Characteristics
Scope of Presentation
Chemistry of P removal
General Site Characteristics
P-RTC compared to existing
methods
Equipment Reliability / Suitability
Case Studies
11/12/2014 HACH LANGE 10
P-RTC compared to existing methods
The correct amount of precipitant is added at the correct time
True site chemical efficiency is taken into account
Establishing an effective storm suppression dose is very difficult. This is automatically
controlled with P-RTC
11/12/2014 HACH LANGE 11
Realtime flow
(flowmeter)
Measured [orthoP]
orthoP % removal
Molar ratio Fe:orthoP
Precipitant Flow rate
orthoP target
“Beta” curve
Load to be removed
Standardized software for P-Elimination (open / closed-loop)
11/12/2014 HACH LANGE 12
waste water
precipitationagent
Dosing
pump
Precipitation Process
QPrecPO4-P
X
Qprec
PO4-Pload
Q
PO4-P
Degree of elimination
waste water
Precipitationagent
Dosing
pump
Precipitation Process
QPrec PO4-P
Set point
Qprec
PO4-Pload
X
Q
Advantage
High process control
Set point
w = Limit - cSS · cP,SS - safety
Requirements
PO4-P and flow [Q] online measurements
Advantages
Immediate reactions to load changes
Easy to adjust
Set point
Biological P-elimination to be considered
Requirements
PO4-P and flow [Q] online measurements
Scope of Presentation
Chemistry of P removal
General Site Characteristics
P-RTC compared to existing
methods
Equipment Reliability / Suitability
Case Studies
11/12/2014 HACH LANGE 13
Instrumentation Features
11/12/2014 HACH LANGE 14
Proven method for ortho P analysis
***** Exclusive use of “TMS” filter system – game
changer on crude sewage analysis! *****
Very secure “fall back” position based on bespoke load
analysis / look up table as part of the commissioning
process.
Suitable for all chemical application points / treatment
stages.
Opens the opportunity to comply with ultra low P and
metal consents using conventional dosing.
Simple to Retro-fit
11/12/2014 HACH LANGE 15
Completely integrated solution
Standardised system
No. Task Status
1. Definition of control algorithm ✓ Done
2. Programming of control
algorithm ✓ Done
3. Implementation on hardware ✓ Done
4. Testing of software and
hardware ✓ Done
5. User interface ✓ Available
6. User manual ✓ Available
7. Backup stages ✓ Available
8. Communications interface ✓ Available
9. Setting of the plant-specific
parameters
During
commissioning
Standardized hardware for P-Elimination
11/12/2014 HACH LANGE 16
Flow
Precipitant
dosing
PHOSPHAXsc
On-line analyzer
SC1000
parameterization WTOS module
(P-Module)
Standardized hardware for P-Elimination
11/12/2014 HACH LANGE 17
Flow
Precipitant
dosing
PHOSPHAXsc
On-line analyzer
SC1000
parameterization WTOS module
(P-Module)
PLC
SCADA
12.11.2014 HACH LANGE 18
Standardized Software for P-Elimination
Inlet sample preparation - Key to sustainable measurement
19
Scope of Presentation
Chemistry of P removal
General Site Characteristics
P-RTC compared to existing
methods
Equipment Reliability / Suitability
Case Studies
11/12/2014 HACH LANGE 20
21
Population 17,000 pe
Flow 800 m3/hour Maximum
Consent limit 2mg/l annual average
Effluent average concentration 0.8 mg/l
Coagulant Ferric sulphate
Max. dose rate 198 l/h
Dose rate 30 l/h fixed speed by hand
Open loop control system: Northwest UK
22
Savings:
20,000 £/ year 30 l/h
16,5 l/h
45%
red.
Before
RTC
After
RTC
ROI 14 months
Open loop control system: Northwest UK PO4-P concentration
Closed-loop control system: wwtp Flieden, GERMANY
11/12/2014 HACH LANGE 23
Size 15,000 pe
Ptot limit 2.0 mg/l
Dosing point Inflow aeration
Precipitant FeCl3
Ø dosing rate 6.5 l/h based on daily lab measurement
Characteristics Exceeding limit due to seasonal load peaks from juice
production
Target Maintain effluent limit Ptot
11/12/2014 HACH LANGE 24
0
1
2
3
4
5
6
7
8
10.02.2011 15.02.2011 20.02.2011 25.02.2011 02.03.2011
Pd
os [
l/h
] &
Q
[(m
³/h
)/1
00
]
0
0,2
0,4
0,6
0,8
1
1,2
1,4
1,6
1,8
2
PO
4-P
[m
g/l]
Pdos Qin/100 PO4-P
Closed-loop control system: wwtp Flieden, GERMANY
minimum dose
11/12/2014 HACH LANGE 25
Safe process control
Reduced precipitant consumption by 60% (7,000€/y)
Simple installation
6.5 l/h
2.6 l/h
Before With RTC
60%
7.000 €
reduced
Closed-loop control system: wwtp Flieden, GERMANY Results
Summary: P-RTC compared to existing methods
The correct amount of precipitant is added at the correct time
True site chemical efficiency is taken into account
Dosing can stop immediately when rainfall dilution allows
Protection against
overdosing and metal noncompliance
alkalinity issues
extreme flow events (extended dry periods)
Opens up the opportunity to comply with more stringent Consents
11/12/2014 HACH LANGE 26
Thank you.