Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26470
RESOLVED That the Design Commission, having considered designs for the reconstruction of
an entrance and loading dock and installation of mechanical equipment, Building 22, Brooklyn
Navy Yard, Brooklyn, submitted by the Brooklyn Navy Yard Development Corporation,
represented by exhibits 6063-MI, MJ & MK of record in this matter, hereby gives to the same
unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26471
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical newsstand, 1180 2nd Avenue, northeast corner of 2nd Avenue and 62nd Street,
Manhattan, submitted by the Department of Consumer Affairs and the Department of
Transportation, represented by exhibits 7343-A, B & C of record in this matter, hereby gives to
the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26472
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical newsstand, 1335 6th Avenue, southwest corner of 6th Avenue and West 54th
Street, Manhattan, submitted by the Department of Consumer Affairs and the Department of
Transportation, represented by exhibits 7344-A, B & C of record in this matter, hereby gives to
the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26473
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical newsstand, 248 West 88th Street, southeast corner of Broadway and West 88th
Street, Manhattan, submitted by the Department of Consumer Affairs and the Department of
Transportation, represented by exhibits 7345-A, B & C of record in this matter, hereby gives to
the same unanimous preliminary and final approval. Commissioner Sheffer recused herself.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26474
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical newsstand, 401 East 149th Street, northeast corner of 149th Street and 3rd
Avenue, Bronx, submitted by the Department of Consumer Affairs and the Department of
Transportation, represented by exhibits 7346-A, B & C of record in this matter, hereby gives to
the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26475
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical newsstand, 572 West 207th Street, southeast corner of West 207th Street and
Vermilyea Avenue, Manhattan, submitted by the Department of Consumer Affairs and the
Department of Transportation, represented by exhibits 7347-A, B & C of record in this matter,
hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26476
RESOLVED That the Design Commission, having considered designs for the rehabilitation of
the Woodhaven Library and adjacent site work, 85-41 Forest Parkway, Jamaica, Queens,
submitted by the Department of Design and Construction, represented by exhibits 1129-U, V,
W & X of record in this matter, hereby gives to the same unanimous preliminary approval.
Preliminary approval is conditioned upon submission of this project for final review and
approval before February 12, 2020.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26477
RESOLVED That the Design Commission, having considered designs for the reconstruction of
the roof, St. Albans Community Library, 191-05 Linden Boulevard, Jamaica, Queens,
submitted by the Department of Design and Construction, represented by exhibits 3679-E, F,
G & H of record in this matter, hereby gives to the same unanimous preliminary and final
approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Ethel Sheffer,
Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26478
RESOLVED That the Design Commission, having considered designs for the construction of a
prototypical planted median, Grand Concourse Boulevard, Phase IV, from East 175th Street to
Fordham Road, Bronx, submitted by the Department of Design and Construction and the
Department of Transportation, represented by exhibits 6105-AC, AD, AE & AF of record in this
matter, hereby gives to the same unanimous preliminary approval with the understanding that
the Percent for Art proposal will be submitted for review before this project returns for final
review. Commissioner Nielsen recused herself.
Preliminary approval is conditioned upon submission of this project for final review and
approval before February 12, 2020.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26479
RESOLVED That the Design Commission, having considered designs for the installation of
prefabricated trailers, Glendale Yard, 69-46 Sybilla Street, Forest Hills, Queens, submitted by
the Department of Transportation, represented by exhibits 6870-V, W, X & Y of record in this
matter, hereby gives to the same unanimous preliminary and final approval with the
understanding that the agency will submit details of the proposed metal screening at the
rooftop HVAC units by June 2018 and prior to construction.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26480
RESOLVED That the Design Commission, having considered designs for the construction of
stairs and planters, 91-30 Van Wyck Expressway, Jamaica, Queens, submitted by the
Department of Transportation, represented by exhibits 7348-A, B, C & D of record in this
matter, hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26481
RESOLVED That the Design Commission, having considered designs for the construction of
stairs, 115 Dooley Street, Brooklyn, submitted by the Department of Transportation,
represented by exhibits 7349-A, B, C & D of record in this matter, hereby gives to the same
unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26482
RESOLVED That the Design Commission, having considered designs for the construction of a
trailhead and parking lot, Arden Heights Woods, Arden Avenue and Arthur Kill Road, Staten
Island, submitted by the Department of Parks & Recreation, represented by exhibits 4796-C, D
& E of record in this matter, hereby gives to the same unanimous preliminary approval.
Preliminary approval is conditioned upon submission of this project for final review and
approval before February 12, 2020.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26483
RESOLVED That the Design Commission, having considered designs for the reconstruction of
a plaza and playground and adjacent site work, Bensonhurst Park, 21st Avenue, Cropsey
Avenue, Bay Parkway, and the Belt Parkway, Brooklyn, submitted by the Department of Parks
& Recreation, represented by exhibits 1652-Z, AA & AB of record in this matter, hereby gives to
the same unanimous preliminary approval with the understanding that the planting bed at the
Cropsey Avenue and Bay Parkway plaza will be restudied.
Preliminary approval is conditioned upon submission of this project for final review and
approval before February 12, 2020.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26484
RESOLVED That the Design Commission, having considered designs for the reconstruction of
a plaza, Doughboy Park, Woodside Avenue and 56th Street, Woodside, Queens, submitted by
the Department of Parks & Recreation, represented by exhibits 3238-Q, R & S of record in this
matter, hereby gives to the same unanimous preliminary approval with the understanding that
a proposal will be submitted for the relocation of the WWI tablets before this project returns for
final review.
Preliminary approval is conditioned upon submission of this project for final review and
approval before February 12, 2020.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26485
RESOLVED That the Design Commission, having considered designs for the reconstruction of
Bridge Park 2, Jay Street, York Street, Bridge Street, and Prospect Street, Brooklyn, submitted
by the Department of Parks & Recreation, represented by exhibits 6266-CK, CL & CM of
record in this matter, hereby gives to the same unanimous preliminary approval.
Preliminary approval is conditioned upon submission of this project for final review and
approval before February 12, 2020.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26486
RESOLVED That the Design Commission, having considered designs for the reconstruction of
the Arthur Ross Nursery Headhouse, Van Cortlandt Park, Van Cortlandt Park East, Major
Deegan Expressway and East 242nd Street, Bronx, submitted by the Department of Parks &
Recreation, represented by exhibits 1960-CX & CY of record in this matter, hereby gives to the
same unanimous preliminary approval with the understanding that the final submission will
include (1) details for the site work, including paths and plantings and (2) all standard required
drawings.
Preliminary approval is conditioned upon submission of this project for final review and
approval before February 12, 2020.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26487
RESOLVED That the Design Commission, having considered designs for the rehabilitation of a
comfort station and a utility building, Betsy Head Park, Dumont Avenue, Thomas S. Boyland
Street, Livonia Avenue, and Strauss Street, Brooklyn, submitted by the Department of Parks &
Recreation, represented by exhibits 781-DG, DH, DI & DJ of record in this matter, hereby gives
to the same unanimous preliminary approval.
Preliminary approval is conditioned upon submission of this project for final review and
approval before February 12, 2020.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26488
RESOLVED That the Design Commission, having considered designs for the reconstruction of
a playground and basketball courts, Patterson Playground, adjacent to P.S. 18, College
Avenue, East 145th Street, Morris Avenue, and East 148th Street, Bronx, submitted by the
Department of Parks & Recreation, represented by exhibits 2594-O, P, Q & R of record in this
matter, hereby gives to the same unanimous final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26489
RESOLVED That the Design Commission, having considered designs for the reconstruction of
a soccer field and baseball field as Phase II of the reconstruction of the Red Hook Recreation
Area, Bay Street, Clinton Street, and Henry Street Basin, Brooklyn, submitted by the
Department of Parks & Recreation, represented by exhibits 2081-BU, BV & BW of record in this
matter, hereby gives to the same unanimous final approval with the understanding that the
waterfront picnic area and plaza will be submitted as a separate project.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26490
RESOLVED That the Design Commission, having considered designs for the reconstruction of
an entrance and adjacent site work, Madison Square Park, Broadway, and 24th Street,
Manhattan, submitted by the Department of Parks & Recreation, represented by exhibits 1945-
CT & CU of record in this matter, hereby gives to the same unanimous final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26491
RESOLVED That the Design Commission, having considered designs for the rehabilitation of a
greenhouse (Palm House), Forest Park, 88th Lane between Myrtle Avenue and Forest Park
Drive, Forest Hills, Queens, submitted by the Department of Parks & Recreation, represented
by exhibits 710-EU, EV & EW of record in this matter, hereby gives to the same unanimous final
approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26492
RESOLVED That the Design Commission, having considered designs for the reconstruction of
Hugh J. Grant Circle and Virginia Park, White Plains Road, Westchester Avenue, and the Cross
Bronx Expressway, Bronx, submitted by the Department of Parks & Recreation and the
Department of Transportation, represented by exhibits 4518-AN, AO & AP of record in this
matter, hereby gives to the same unanimous final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26493
RESOLVED That the Design Commission, having considered designs for the construction of an
operations building, Homeport Pier, 405 Front Street, Staten Island, submitted by the
Economic Dvelopment Corporation, represented by exhibits 6835-AP, AQ, AR & AS of record
in this matter, hereby gives to the same unanimous preliminary approval.
Preliminary approval is conditioned upon submission of this project for final review and
approval before February 12, 2020.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26494
RESOLVED That the Design Commission, having considered designs for the installation of
rooftop HVAC equipment, Engine Company 66, 21 Asch Loop West, Bronx, submitted by the
Fire Department, represented by exhibits 7350-A, B, C & D of record in this matter, hereby
gives to the same unanimous preliminary and final approval with the understanding that the
agency will replace the missing screening panels at the parapet fence prior to sign-off.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26495
RESOLVED That the Design Commission, having considered designs for the installation of
bulkheads, 545 West 52nd Street, Manhattan, submitted by Housing Preservation and
Development, represented by exhibits 7351-A, B, C & D of record in this matter, hereby gives
to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26496
RESOLVED That the Design Commission, having considered designs for the rehabilitation of
the Richmond Hill Community Library, 118-14 Hillside Avenue, Richmond Hill, Queens,
submitted by the Queens Library, represented by exhibits 1495-U, V, W & X of record in this
matter, hereby gives to the same unanimous preliminary and final approval with the
understanding that the landscape reconstruction, including the construction of a reading
garden and ADA path, will be submitted for review by March 2018.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26497
RESOLVED That the Design Commission, having considered designs for the construction of an
ADA ramp and stairs, 40-04 Bowne Street, Flushing, Queens, submitted by the Department of
Transportation, represented by exhibits 7352-A, B, C & D of record in this matter, hereby gives
to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director
Philip Aarons, Laurie Hawkinson, Manuel Miranda, Richard Moore, Signe Nielsen,
Ethel Sheffer, Merryl H. Tisch, Hank Willis Thomas, Shin-pei Tsay, Commissioners
February 12, 2018
CERTIFICATE 26498
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical newsstand, 402 Park Avenue South, southwest corner of Park Avenue South and
East 28th Street, Manhattan, submitted by the Department of Consumer Affairs and the
Department of Transportation, represented by exhibits 4824-J, K & L of record in this matter,
hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before February 12, 2020 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on February 12, 2018.
Justin Garrett Moore
Executive Director