Engineering Division 1 PHENIX Vertex Tracker Production Status and Schedule Eric Anderssen, LBNL

description

PHENIX Vertex Tracker Production Status and Schedule. Eric Anderssen, LBNL. Outline. Manpower capabilities, workload, and environment Description of work, by project Generalized production Brief overview of the steps required for each deliverable to better understand scheduled tasks - PowerPoint PPT Presentation

Transcript of PHENIX Vertex Tracker Production Status and Schedule

Page 1: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division 1

PHENIX Vertex Tracker ProductionStatus and Schedule

Eric Anderssen, LBNL

Page 2: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Outline

• Manpower capabilities, workload, and environment• Description of work, by project

– Generalized production– Brief overview of the steps required for each

deliverable to better understand scheduled tasks– General ties to cost estimates’ line items

• Overall Schedule– PHENIX deliverables share resources with both other

projects and separately funded PHENIX deliverables– Integrated schedule and resource availability

• Detailed Discussion of deliverable Milestones by Account Number– Each deliverable is defined in a SOW, discussion will

be by SOW deliverable• Integration with Future Work

– Layer ¾ supports, Station Disk Supports

2

Page 3: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Manpower Team

• Assembled team has extensive experience with similar structures based on ATLAS and ATLAS Upgrade work to date; most have driven the developments of the technologies employed

• Tom, Mario and Greg are direct reports; Dave Uken by contract; Kurt and Rodney by agreement (as required—others are available)

• Availability is negotiated across projects; currently PHENIX has highest priority

Name Function Expertise

E Anderssen Engineer, PISTAR HFT Project Engineer; ATLAS Pixel Project Engineer; Built STAR TPC Field Cages; 20yrs composite structures

Dave Uken Contract EngineerATLAS Pixel Service Panel integration; Tooling for assembly of ATLAS Pixel Components; 4yrs on ATLAS; 20+ yrs product design

Tom Johnson Tech III, LeadLead Tech ATLAS Pixel; Assembly, Installation, Service Termination ATLAS Pixels; All composite deliverables for ATLAS Pixel; 10yrs LBNL

Mario Cepeda

Tech IIILead for ATLAS Upgrade work; 35yrs at LBNL (numerous projects, many for Bevatron Biomed); All composite deliverables for ATLAS Pixel

Greg Klever Tech I Trainee

Kurt Krueger Tech III, matrixed20+yrs race car/motorcycle fabrication; 10yrs at LBNL; Fabricated all bent tube services for ATLAS Pixel; 5yrs ATLAS Assembly

Rodney Post Tech III, matrixedHead of LBNL Optics shop; 30+yrs at LBNL; 7yrs ATLAS Assembly

Page 4: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Strip Pixel Tube Production

• Tubes stored dry after cleaning before bonding• Production rate faster than assembly rate, not on

critical path• Initial yield problem solved—rejects had non-

compliant barb-end bends

4

Page 5: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Strip Pixel Foam Core

• All foam blanks complete• After bonding blanks to bottom

face-sheet, trough for tube is machined

• Assemblies are batched up to this phase to allow more efficient interaction with Shop

5

Page 6: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Ready for Machining

6

Page 7: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Strip Pixel Stave Bond Stations

• 4 bond stations, 2 Long/2 Short, used for every bond operation

• Aim for one operation all tools each day• Rate will drop in half once short staves

are complete• Have been losing Mondays in winter—

tool/table temps below 61F out of tolerance– Facilities looking into re-programming

controller for HVAC

7

Page 8: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Strip Pixel Stave Assembly Status• Status Spreadsheet updates

~weekly and posted• “Percent Complete” is only a

rough metric; ignores rejects• Reports only ‘Assembly’ of the

components• All component and tooling

manufacture is 100% complete• Each box averages~1hr labor

~130hrs total• ETC ~$16k

8

Page 9: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Strip Pixel Tube Production Status

9

• Separate Sheet in previously mentioned spreadsheet

• Nominally for internal tracking rather than reporting—aimed at assuring sufficient tube availability to support stave assembly

• Boxes in first column are ~1hr, remaining boxes thru geometry check ~0.5hr each ~50hrs

• ETC ~$7k

Page 10: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Strip Pixel Stave ETC

• Funds Remaining ~$29k, ETC ~$23k• Burn rates in Dec, Jan feuled by fabrication of parts and tooling• Remaining 180hrs limited by tooling and cure-cycles• 130hrs of assy is critical path, max burn rate ~4hrs/day

~32days remaining.– Batch machining and survey accelerates this some– After completion of Short Staves, rate drops to 2hrs/day

(only 2 tools), balanced with batching…

• Earliest finish 1-April, more likely Mid-April10

Page 11: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Barrel Space Frame Tooling

• Assembly and trim tooling completed late Jan– Will need to modify for shorter support beams

• Lamination tool delivered last rather than first; proved difficult to fabricate

• Lamination tool delivered last week; needs surface work (polish) to remove/round dings from rolling shell

11

Page 12: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Barrel Space Frame Components

Components Required

• 2 Half Shells• 4 Support Beams• 4 Gusset plates

• Gusset plates complete• Support beam plate complete, in

shop for machine to shape– Need to re-program cut-paths after

recent change in design

• Half shell laminates take 1day each to cure, another 2 to trim– First article is used for practice

• Bonded assy is a 1day operation after dry fit of parts

• Expect completion by end of March– Need to schedule work around trips

to BNL—I should be present for final bond and tooling modifications

• Prefer to delay—shell is fragile w/out L4 support or equivalent– May need to design/fab temp

support if required earlier

12

Page 13: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Pixel Layer 1 Support

• 4 total; 2left, 2right• 2 right assemblies complete• 2 left require stave mount bonding• Left-handed blocks bumped to

machine Strip Pixel Stave inserts• Received parts yesterday• 2 bond operations required to

complete• Should be complete early next

week

13

Page 14: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Pixel Layer 2 Supports

• All core-panel assemblies complete

• All blocks bonded onto panel assemblies in one operation

• Also expect completion next week

14

Page 15: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Barrel Space Frame and Pixel Supports

• $37k remaining, ETC ~$25k (need to add mods/reinforcement if required)• This is a ‘Fabrication’ account, i.e. money arrived via Fin, but estimated at

WFO rates. Burn rate is lower due to lower overhead– Included prototype Strip Pixel Staves for ~$15k

• ~160hrs to complete, 112 on critical path (Space Frame), again tooling limited, max ½ time burn rate, 28days for earliest completion

• Earliest Completion April 1 for Space Frame; Pixel supports as noted earlier

15

Page 16: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

Pixel Staves

• 40 acceptable staves complete• $1.5k remains in account after making 2 more

omegas• No more M55J on hand to fabricate more• Sufficient parts to assemble 2 additional

staves, $1.5k barely sufficient• More than 2 requires more material, for

omegas and thermal planes, and machining more mount blocks

• Plan to dry-fit staves still at LBNL onto Pixel Barrel Mounts after their completion next week

• Will send them onto RIKEN shortly thereafter

16

Page 17: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

FVTX Sensor Backplanes• ~2wk delay on initial startup this year

– Material (all) moved offsite over break to mitigate risk of freezer failure during shutdown

– Delayed transfer back until monitoring upgrade was complete

• First test panel delivered 8L/9S wedges– Bag-side of laminate not within flatness spec

• Second test panel complete; wedges being machined– Used caul-plate on bag-side—improved flatness, but part ~100m too

thin (add back removed central 0)– Improve part density (expect more than 8/9)– Expect to ship next week; will finalize interface to DB at that time

• If parts survey flat, will launch production of plate fabrication (2d/plate, ~8plates)– Will machine first plate immediately, but prefer to batch machine rest

in 2 batches after the first plate, (3 batches total, 4 if yield is an issue)

• Assuming successful survey, first production batch ships week of 8-March; remaining batches every 2 wks thereafter as required

• Detailed schedule relies on interface with shop; minimizing batches minimizes uncertainty

17

Page 18: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

FVTX Support Cages• Contract for tooling design in works

– Design changes to support beam need to propagate to model before assembly tooling designed

– Can start on lamination tool, but won’t issue to shop without updated model for verification (due diligence)

• Problem with CN60 order ($20k)– FVTX needs ~6sqm; was in stock last May when originally

quoted– Fabric supplier out of stock on pre-woven material; min

order from Fabric vendor is 50sqm. Costs ~$500/sqm (note vendor supplies Tencate)

– Investigating sharing cost with other programs that will require CN60 (STAR/ATLAS)

– Will investigate buying dry, impregnating only what’s required

• Late May, Early June delivery not unreasonable– Need to propagate in schedule—only got thru wedges in

detail18

Page 19: PHENIX Vertex Tracker Production Status and Schedule

Engineering Division

L34 Support Status

• Same cost model as Pixel Barrel Supports, similar labor cost, increased materials

• Waiting for M55J quote; requested at same time as CN60 quote

• Can likely issue SOW/Estimate by end of week• Work not yet scheduled but understand June

delivery desired • Crude estimate of 8-10wks production duration

from onset of funding

19