PHENIX PLANNING

Technical Support Plan for 2006

Don Lynch(updated 3/24/06)

Page 2: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

Major Projects

• Recover from water in dry air system/ MuTr repairs -December ’05 [DONE]• MPC South - [ Detector Insdtallation DONE],

Electronics to be completed by April 1 ‘06• Prepare for Run 6 – [DONE]• RXNP magnet test – [DONE]• Beam Loss Monitor Test – [UNDERWAY COMPLETE BY MAY 1 ’06]• Run 6 – February-June ’06 • HBD Run 6 Installation – Prototype April-May ’06, Engg Run June ‘06• TOF West – Receive/Prep for Install May ’06; Install July ’06• RXNP - DesignMarch-May ’06, Install July ’06• HBD - , Final Aug ‘06• MPC North – Design April- MAy ’06, Install September ’06• Subsystem maintenance, repair, upgrades: TBD• Prepare for run 7 – September-October ’06• Run 7 – November ’06 – June ‘07

Page 3: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

TOF W Installation

TOF W Installation Fixture and

access platform

Ready to install detectors when they arrive. Expected by May 1 2006 Installation scheduled for shutdown 2006.

Page 4: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

TOF W Fabrication

MRPC’s

MRPC’s

Feedthru boards

Page 5: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

½ box with detectors

HV bus

Gas pipe

HV connectors

Holes for Installation/mounting wheels

Gasket

signal cables

TOF W Fabrication

Page 6: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

TOF W Assembly

Page 7: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

HBDGas Supply

HBD electronics rackIn Gas Mixing

House

HBD transparency monitor hutch ready to install instrumentation when it arrives

TOF/HBD Gas Shared Flow

Control Rack. HBD to be single pass

for Run 6

Page 8: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

R134A Gas Bottle Location

Scales to monitor bottle contents

HBD & TOF WGas Systems

Gas PadLocation for CF4 bottles

Page 9: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

HBDElectronics

HBD High Voltage Rack(to be located

on Bridge)

HBD low voltage and signal

electronics rack(installed on east-central

pedestal)

Page 10: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

Gas PadLocation for CF4 bottles

HBDGas Supply

Stainless Gas Lines to top of CM

Piping in IR complete. Flexible lines allow CM to move for maintenance

HBD Gas flow panel Installed. HBD in and out lines are short circuited and now flowing Argon to maintain cleanliness.

Page 11: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

HBD Prototype Gas System

Page 12: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

HBD Support

X, Y, Z adjustments on this side

HBD Support

X, Y

adjustments on this side

HBDMechanical

Support

Page 13: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

HBD Prototype Mounting

Prototype can not use final design mounting due to differences in location of connectors and other basic design differences.

Prototype mounting to be fabricated from fg unistrut.

Page 14: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

MPC Installation

MPC South was installed in Jan. ’06. MPC North scheduled to be installed Sept. ’06.

Page 15: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

MPC Electronics

MPC rack installed without cards. Cards to be installedAs available and as access time is available.

Page 16: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

HBDInstallation/

Access

CM scissor lift table extensions completed Feb. ’06 (extends table 22”

east & west; steps up 8”). Alllows maintenannce and installation access to

new CM detectors.

Page 17: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

CM Lift Table

ExtensionsFirst extension received from Central Shops. Minor modification needed to mount rails. Otherwise works as planned. Was successfully used for DC repairs

Plug lock for lift table. Table is to be operated by authorized techs only. To be locked out when BLM test fixture is installed.

Drift Chamber Repairs

Page 18: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

RXNP Magnet Field Tests

Made from fiberglas unistrut with precision cut angles. To be supported from lower HBD I-beams

PMT’s

Page 19: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

RXNP Magnet Field Tests

Test Completed February ‘06

Page 20: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

RXNP PMT in magnetic field tests

Completed

Page 21: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

Beam Loss Monitors

BLM Stand withBLM’s and Chipmunks

Stripixel sensors and diodes go on this surface

Page 22: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

Beam Loss Monitors

Need to make holders for diodes. 2 size diodes 8 of each for test.

Bare stripixel sensors (2)

Page 23: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

Revised BLM support design

Page 24: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

BLM Test

Page 25: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

BLM Test

BLM Test Installation He Bags

Page 26: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

LN2 Storage Dewar for

BBC

Original Plan As Installed

Page 27: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

LN2 Storage Dewar for

BBC

Page 28: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

LN2 Storage Dewar for

BBC

Page 29: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

20mm thick lead converter

130mm 150mm

outer painting on the converter surfaceor stainless steel case with lead inside

Pb + 2% Sb

R=50mmR=180mmR=330mm

•2cm thick scintillator + 2cm thick lead converter•Enhance RP resolution via adding neutral particles

•fiber light guide• flexibility of mechanical structure.

•12 segments in phi and 2 segments in eta@(1.0, 2.8)•Detector stable against dead channel •help removing auto-correlation effect.

•Hamamtsu fine mesh PMT for light readout•Good dynamic range and work in high field.

•EMCal FEE for electronic readout.• good dynamic range.

RXNP DETECTOR

Page 30: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

RXNP DETECTOR

North and south detectors each with 4 arms to PMT’s

Page 31: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

RXNP DETECTOR

Assembled on benchInto 4 quadrants. Base Plate attaches to Brass nosecone.

Page 32: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

RXNP DETECTOR

Quadrant Assembly

Page 33: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

• CM Crane design• Integration support work for Future Detectors (NCC, SVTX,

FVTX, RPC) (New beampipe)• CM region access stairs• Discretionary improvements to existing equipment

• EC: Fix/replace fibers, Noisy FEM’s in DC, PC, DC water flow interlocks, TEC replace p/s and FEM’s, ARCNET on fiber to all racks?

• WC: Replace bucketless buckets in AGEL racks, noisy FEM’s in DC, PC

• MuTr & MuID: HV repair, troublesome FEM’s, blue logic repairs, MUTR cosmic ray trigger with LL1?

• E F & I: Verify installation of transient suppression in all racks, Bucket maintenance, Fan replacement, Communication testing to UVC HV mainframes, tighten connections on distribution panels, fiber repairs

Additional Shutdown 2006

Tasks

Page 34: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

New Beampipe for Upgrades

A concept discussed between Jan Boissevain of LANL and D. Lynch of BNL. Requires suport built in to NCC and temporary isolating support to move CM.

Page 35: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

CM Region Crane & Cable Routing

Concept

Cable Trays to route cables NCC Detector from Bridge

CM Crane north-south & east-west motions; extended travel east to existing crane coverage

Crane Supports use existing flux return notches

Page 36: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

CM Region Stairs

Something a little more substantial would be nice

Page 37: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

Other Beneficial Work for S/D

2006• DAQ Electronics: Replace/test GL12GTM, STTP’s, blue

logic trigger racks?• Computing: Backups: test reliability, weed out unreliable

hardware and servers, upgrade network• Gas System

– Maintenance and calibration for all components– Subsystem upgrades TBD– New system component installation

Page 38: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

C-A Tasks

Current Tasks

•General run support•New storage trailer (as promised)•Fix roof leaks/mold problems

Tasks for Shutdown 2006

•Install access platforms from EC top north and MMS

•Replace emergency fan louvres•Rewire/add IR ceiling lights on emergency power

•Replace WC sliding platform hoisting cables •Mixing house exhaust fan maintenance

Page 39: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

MOLD Problems

Page 40: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

• Energy Conservation • Clean/organize under the tracks• Move extra I-beams & pipe to storage • Electronics lab (new shelves?)• Clean & organize storage areas:

• Assembly hall • Shelves near transformers• Trailers• Wire

Conservation & Housekeeping

Page 41: PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)

SD 06 Schedule

To Be Determined