PFR -Gondegaon BHATIAenvironmentclearance.nic.in/writereaddata/Online/TOR/17... · 2016. 11....
Transcript of PFR -Gondegaon BHATIAenvironmentclearance.nic.in/writereaddata/Online/TOR/17... · 2016. 11....
-
PRE-FEASIBILITY REPORT
For
NEW UNIT
For
Expansion of 1.5 MTPA Coal Washery to 2.5
MTPA Coal Washery (Total 4.0MTPA after
expansion)
By
M/s Bhatia Coal Washries Limited
At Survey No. 64,65,66,67 Village - Yehsamba (Gondegaon), Tehsil- Parseoni,District- Nagpur (MS).
EIA Consultancy: Pollution & Ecology Control Services (PECS),
Nagpur
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
1
EXECUTIVE SUMMARY
1.0 SummaryoftheProject
S.No. Particulars Description1. NameoftheCompany M/s Bahtia Coal Washeries Ltd.
2. Address
M/s. Bhatia International Limited, AmbikaApartment, Plot No.24, Wardhman Nagar ,Nagpur – 400 008
3. Name of theProjectExpansion of 0.96 MTPA Coal Washery to 2.5MTPA Coal Washery.
4. LocationofthePlantAt Survey No. 64,65,66,67 Village - Yehsamba(Gondegaon), Tehsil- Parseoni, District-Nagpur (MS).
5. CoalWasheryCapacityExisting :1.5 MTPAProposed expansion: 2.5MTPAAfter Expansion : 4.0 MTPA
6. Raw Coal 4.0MTPA
7. SolidWasteGeneration 20 % of Raw Coal
8.Total landrequirement fortheproject
8.28 ha.
9. WashingTechnology Heavy Media Cyclone -WetProcess
10. RawmaterialSources O/C WCL Gondegaon
11.Total Waterrequirement&Source
Total daily Make up water requirement
(including both the phases):550 m3/day
12.TotalPowerrequirement&Source
1000 KVASource:State Electricity Board
13. Workinghours3 shifts daily of 8hr each
330 days a year
14. TotalManpowerTotal:116 persons for each shift.
15 EstimatedCostoftheProjectExisting –7.5CroreProposed Expansion - 15CroreTotalCost–21.5Crore (approx.)
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
2
This Pre Feasibility Report has been prepared for the expansion of Coal Washery Unitover the area
of 8.28Ha.proposed at At Survey No. 64,65,66,67 Village - Yehsamba (Gondegaon), Tehsil-
Parseoni, District- Nagpur (MS) in accordance with the Notification of MoEF S.O. 1533 dated
14thSeptember 2006.
Though any development activity like industry or mining project may cause temporary damage to
land, forest and induce changes in the quality of air, water, flora and fauna of the area, it has
favorable effect of industrialization on social development and progress of the nation. For overall
gain, it is necessary to strike a balance between the two aspects of economy and ecology and ensure
that impacts on the environment are minimized with improvement in socio-economic conditions.
This is better achieved through a well-planned approach of EMP relevant to the area under
consideration.
2. INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION.
i) Identification of Project and Project Proponent
Bhatia International Limited (BIL) is the company of the ‘BCC’ Group. The Group was formed in
the year 1979. The Group will be primarily engaged in trading and supply of imported coal and
indigenous Coal including Meghalaya. The Group has a network of 15 branches all over the
country. It also has agents in different countries for import of coal. The group will be the largest
importer of coal in the trading segment. It will be supplying coal from the various mines of Coal
India Limited as well as imported coal to industrial consumers like cement, Sponge Iron, Fertilizer,
Rayon Steel, Power, Paper, Synthetics, Solvent extraction and many others in Northern, Central,
Western and Southern parts of the country. Leading industries of National and International repute
will be amongst the customers served by the ‘BCC’ Group.
Name : Bhatia International Limited.
Address : M/s. Bhatia International Limited,Ambika Apartment,Plot No.24, Wardhman Nagar , Nagpur – 400 008
Phone : 0712-2680133, 2690115 ( Fax )
ii) Brief description of nature of the project
To meet the enhanced demand of washed coal by power plants, Bhatia International Limited
has Planed to expand the existing 1.5 MTPA to 2.5 MTPA(Total 4.0MTPA after expansion)
washery capacity by HM cyclone technology at Gondegaon. H.M. cyclone washing will be the
technology adopted worldwide for its highest washing efficiency.
Details of area.
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
3
1. Village : (Yesamba)Gondegaon
2. Tahsil : Parseoni
3. District : Nagpur
4. State : Maharashtra
(iii) Need for the project and its importance to the country and or region.
Coal is the most abundant fossil fuel. India is blessed with huge coal reserve,nearly7% of total
coal in the world,85% of this reserve is non- cookingcoal,which caters to the need of
power,cement and sponge iron plants, however most of the reserve are of very low grade coal and
the reserve of good quality coal is fast depleting.
The Coal India Limited and its subsidiaries are the major domestic producers and suppliers of
coal in India. The annual requirement of non-coking coal for various industrial sectors like
power,steel and cements increasing day by day.The reserves of low ash good coal are depleting
and hence in order to fulfill industry’s demand, huge reserve so inferior grade coal are being
mined. Due to higher demand, selective mining is not possible. The average ash in coal, now
being supplied is around37%.Inorderto maintain consistent quality of coal as per the requirements
of various customers of coal, it is necessary to set up coal washing plants in the country.
Based on the above facts, it is felt that washing of coal in the present scenario shall help using
achieving the operational efficiency and better plant performance.Hence,washing of coal is in the
national as well as regional interest.
The use of washed coal has the following advantages:
1. Supply of consistent quality coal can be ensured thereby avoiding
frequent adjustments in putt boiler and minimizing operators
2. Higher the thermal efficiency of boiler and higher steam rate
3. Less wear and tear of the coal grinding mills
4. Lower capital and operating cost for installing smaller ESP
5. Higher productivity and campaign life of DRI kiln
Our proposed Coal Washery unit will generate revenues for the State Government by way of
taxes on coal and benefit the local people by way of direct and indirect employment.
This project is expected to yield a positive impact on the socio-economic environment of the
region .It will also help in sustainable development of this area including further development of
physical infrastructural facilities.
(iv) Demand-Supply Gap
Ministry of coal identified coal washing as an important area aiming at value addition. To reap the
benefits of economics as well as environment, Coal India limited is planning to expand the capacity of
thermal coal.
• Starting from1774,India has a long history of commercial coal mining. Gross coal
resources~286BTofwhich114 BT in proven category. Ash content very high,from 20 to 55% but
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
4
low in sulphur content.
• 20 major coal fields located in east and south eastern quadrant of the country, involving long
distance rail haulages for major consumers.
•The coal production is projected to reach 795MTY in 2016-17and furtherto 1500MTY in 2031-32.
• Current coal demand~770MTand growing @ 6-7% per year to 980 MTin2016-17 and further
to1800MT in 2031-32.
Coal washing and coal beneficiation processes are to be given major thrust in terms of developing
strong research cells for developing better practices, suiting requirements of all the coal fields of
India. Various quality measurements should be put in to place complying with India ISO standards,
or any other globally accepted standards, event the washeries/beneficiation plants operating at
smaller capacities. Apart from such processes, focus must also be given to our mining practices and
stringent norms and practice Should be put in place for better mining practice, so as to avoid
contamination at the beginning level itself.
(v)Imports vs Indigenous production
Imported coals contains much less ash but are costlier as compared to Indian Coal.India has huge
resources of coal and by subjecting the coal to washing ,low ash coal can be obtained at a cheaper
rate than that of the imported coal.The quality of raw materials is key factor for effective plant
operation. Raw coal will be sourced from various mines of WCL like Sasti, Ballarsha and Pauni
mines located in Rajura area.
(vi)Export Possibility
Not envisaged. Entire washed coal will be used in nearby industries.
(vii) Domestic / Export Markets
There is a huge requirement in both domestic and export or high grade washed coal. The coal will be
supplied to nearby industries and thermal power plants as per the demand.
(viii)EmploymentGeneration(DirectandIndirect)duetotheproject
Industrialization uplifts the socio-economic standard of local people surrounding the plant site.
Due to expansion of existing coal washery of 1.5MTPA TO 4.0 MTPA capacity, considerable
employment will be generated.
During the construction phase work will be generated for skilled, semiskilled and unskilled
construction labors. Technical persons will be recruited during the operation phase. It is
estimated to direct employ to116 people of various skills.
3 PROJECT DESCRIPTION
i) Type of project including interlinked and Interdependent project, if any.
-
Pre-feasibility Report for expansion of
The proposed project is coal
various industries especially in thermal power plants for the generation of electricity
ii) Location (map showing general location, specific location, and project boundary &
project site layout) with coordinates.
The proposed area is Private
Figure-1.
1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.
is coal washery project after washing of raw coal the cleaned coal is used in
various industries especially in thermal power plants for the generation of electricity
Location (map showing general location, specific location, and project boundary &
with coordinates.
Private Waste land. The location of proposed project
FIGURE-1: LOCATION MAP
Layout Plan
VC3
Bhatia Coal Washeries Ltd.located
project after washing of raw coal the cleaned coal is used in
various industries especially in thermal power plants for the generation of electricity.
Location (map showing general location, specific location, and project boundary &
project is shown in the
UP
1
432
76
1098
5
R=163mm
T=275mm
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
Source: SOI Toposheet (No. 55 O/3)
Key Map 10 km. radius
iii) Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental consideration gone into should be highlighted.
The proposed expansion of project is at existing project hence no alternate site.
iv) Size or magnitude of operation.
The proposed expansion project will be developed coal washeryunit for the production of
clean coal. The project proposes expansion of 1.5 MTPACoal Washery unit to 4.0 MTPA
Coal Washery unit.
Bhatia Coal Washeries Ltd.Pandarpauni Coal Washery
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
7
v) Project description with process details (a schematic diagram/ flow chart
showing the project layout, components of the project etc. should be
given).
• Raw coal (0-200 mm) at 640 TPH will be fed to BC1 belt conveyor throughtwonos of vibrofeeders
of 320TPH each fitted below 100tonne capacity coal receiving steel hopper. BC1 will discharge
coal to 650 TPH double deck Primary Screen having top deck opening of 50 mm and bottom deck
of 6/13 mm opening.
• The 50 to 200 mm coal will be fed to 8 meter long picking belt (BC2). The extraneous material will
be manually picked and stacked on ground through BC 3 Belt Conveyor.
• The picking belt will discharge the coal to 210 TPH Double Roll Crushers and the crushed coal (-
50mm) will be conveyed through BC4 and the BC5 belt conveyors and screened at secondary
screen of 6/13 mm deck opening.
• The discharge of second deck of primary screen i.e. natural (6/13 to 50 mm) coal conveyed through
BC6 will discharge onto BC7 belt conveyor carrying 6/13-50 mm coal as overflow of secondary
screen.
• The underflow of double deck screen (-6/13 mm) will be fed to BC9 belt conveyor. The underflow
of secondary screen (-6/13mm) will be conveyed through BC8 to be discharged on BC9 and total
coal (-6/13mm) carried by BC9 will be stacked on the fine coal ground stock.
• The BC7 will discharge (6/13 - 50) mm coal to 2 nos. of desliming screen of 240 TPH and the
deslimed coal (6/13 -50 mm) will be fed to 2 nos. of Heavy Media Sump installed on the ground
floor of Washery building. The deslimed coal along with Heavy Media will be pumped to 2 nos. of
1000 mm dia Heavy Media Cyclone.
• The overflow of H. M. Cyclone will be fed to D/R screen (clean) of 150 TPH each. The depulped&
ringed clean coal will be stacked on ground through BC10 belt Conveyor. The tailing of H.M.
Cyclone will be fed to D/R Screen (Reject)_ and the depulped& ringed reject will be stacked on the
ground through BC11 Belt Conveyor.
• The underflow of second compartment of catchpanes of D/R screen (clean) and D/R screen (Reject)
will be collected in the Dilute Media Sump and the media will be recovered by pumping the same
to Magnetic Separator.
• The overflow of Magnetic Separator will be fed to H. M. Sump and the tailing of Magnetic
Separator will be fed to the coal thickener. The overflow of thickener will be clarified water for
recirculation in the plant.
• The underflow of thickener will be discharged to the slurry pond and the settled slurry after being
dried up will be recovered mechanically from slurry pond by JCB.
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
Block Diagram
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
9
vi) Raw material along with estimated quantity, likely source marketing area of
final products, mode of transport of raw material and Finished product.
There is only raw coaland water require in this project. will be available in the Gondegaon
O/C mines of Gondegaon Area of WCL. The washed coal will be dispatched from the
Railway siding.
vii) Resource optimization / recycling and reuse envisaged in the project, if
any, should be briefly outlined.
Rejects generated during coal washing process will be sold to different consumers.
Hence there will be not much area required for storage of the solid waste generation. This
will help in resource optimization and minimisation of waste.
viii) Availability of water its source, Energy / power requirement and source
should be given.
The total daily make-upwater required for the proposed plant will be 550KLD which will be met
through ground water from tube well. Permission will be obtained from CGWA for withdrawal
of water for use inplant. The water balance for proposed 4.0 MTPA coal washery is given in
Table below.
WaterBalanceforproposed4.0MTPAcoalwashery(Unit:KLD)
Purpose
Dailywater
requirement
Effluent
Generation Losses
Makeup
water
requirement
Remarks
Coal washing 7000 6450 550 550
Recycledin
process
Dust suppression 60 0 60 60Plantation 15 0 15 15
Domestic use6 4.8 1.2 6
Discharge in
Septictank &
soakpit
Total 7075 6454.8
626.2
631
Fire fighting (onetime only) 200
Grand total 7275
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
10
ix) Quantity of waste to be generated (liquid and solid) and scheme for their Management
/disposal.
Solid Waste Generation:
About 1.0 MTPA washery rejects will be generated during the coal washing process. The
rejects will be sold to the nearby consumers. There will be not much any storage required
for the coal rejects. No other solid waste is envisaged in the coal washing process.
Wastewater generation:
Total daily water requirement in the proposed coal washery is about 7275 KLD. Out of this,
about 6450 KLD water will be collected as process effluent and will be treated in
thickeners. The treated effluent will be reused in the coal washing process. Remaining
550 KLD water will be lost as coal moisture, evaporation losses and process losses.
The plant will operate on 'Zero Discharge Principal'. There will not be any effluent
discharge from the coal washery plant. All the process effluent generated in the plant will be
treated in thickeners and will be reused in the coal washing process. Domestic effluent from
plant premises will be discharged in septic tanks followed by soak pits.
In view of conservation of water, rainwater harvesting will be carried out in the plant.
Surface run-off from the plant area will be collected in a settling tank through a network of
drains and the water will be used in the process, thereby reducing the drawal of
ground water. Rainwater from roof tops will be collected in a rainwater harvesting tank and
will be allowed to percolate to ground through a scientifically designed rainwater harvesting
system
4 SITE ANALYSIS
i) Connectivity.
The Unit is 20Kms from Nagpur. It is easily accessible throughout the year from Nagpurby Road, by Railway. It enables the speedy and convenient movement of our goods.
• The railway siding is only 3 K.m. away from the factory side
• Nearest Airport is Dr. Babasaheb Ambedkar Airport, Nagpur is 25 kms away
ii) Land use and Land ownership.Land is owned by the Bhatia Coal Washeries Ltd.
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
iii) Topography (along with map).
The area is almost a flatterrain
Satellite Image
iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies
(including area under CRZ), shortest distances from the periphery of the project
to periphery of the forest, national park, wild life sanctuary, eco sensitive areas,
water bodies (distance from the HFL of the river), CRZ. In case of notified
industrial area, a copy of the Gazette notification should be given.
The proposed project land is non agricultural private land. There are no national
parks, wild life sanctuaries, eco sensitive areas within 10 km of the study area. It is
not covered under any forest zone. The study area is not covered under any CRZ.
Key infrastructures are available near by the proposed unit are described below.
Significant features in 10 Km radius (aerial distance) of the project are tabulated below;
Sr. No. FEATURES DETAILS DISTANCE
1.Village (Nearest) Yesamba 1.0 KM (NNW)
No. of villages 20 Within 10 km.
2. River Kanhan River: 3.0kmW
M/s Bhatiya CoalWashries Ltd
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
12
3.Reserved Forest None -
Protected Forest None -
4.National HighwayState Highway
NH 7 (AH 43)None
3.5 km(E)-
5. Major Industries None -
6. Thermal Power Plant None -
7. Mines WCL 1 km (S)
8. Railway Line Yes 6.0 km
9. Archeological Monument None -
10. National Park None -
11. Wildlife Sanctuary None -
12. Interstate Boundary None -
There is no nearest National Park, Wild life Sanctuary in 15 Km radius of the project.
v) Existing Infrastructure.
Kamptee is the nearest hamlet that is approximately at a distance of 5.5 km from
project site. The village is having good infrastructure, viz., electricity, post office and
telephone facility. The water for drinking would be brought in pots and barrels from
the nearby villages. Nearest railway station is Kanhan that is about 6.0 km from the
project site.
vi) Soil classification.
Soil is the most important feature of physiography, the formation of which largely depends
upon the topography rock types and drainage. The cropping pattern in the area is governed by
the thickness of soil mantle, its texture and constancy. The soils of Parseonitehsil is of various
types. Each type covering a well-defined tract which displays cropping pattern of totally
different level.
The soil of the Tehsil is well defined and conductive for growing crops of various kinds. The
numerous varieties of soils known by many local names they are grouped under the following
representative classes. The soil conditions along Parseoniare rich with black cotton Soil and
loams alluvium soil.
vii) Climatic data from secondary sources.
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
13
• The climate Nagpur has tropical wet and dry climate with dry conditions prevailing for most
of the year. It receives an annual rainfall of 1,205 mm (47.44 inches) from monsoon rains
during June to September. The highest recorded daily rainfall was 304 mm on 14 July 1994.
Summers are extremely hot, lasting from March to June, with May being the hottest month.
Winter lasts from November to January, during which temperatures drop below 10 °C
(50 °F).
• Rainfall: The normal annual rainfall (1901-1992) over the district ranges from about 1000
mm to 1200 mm. It is the minimum in the western parts around Katol (985.4mm) and
increases in the eastern direction and reaches a maximum around Umrer (1213.6 mm).
(Source: CGWB report , Nagpur)
• Temperature:The climate of the district is characterized by a hot summer and general
dryness throughout the year except during the south-west monsoon season, i.e., June to
September. The highest recorded temperature in the city was 48 °C on May 19, 2015, while
the lowest was 3.9 °C.
• Humidity: Except during the southwest monsoon season when the humidity is
high (70- 80%) the air is generally dry. The summer months are the driest, with the relative
humidity in the afternoons being about 20%.
viii) Social Infrastructure available.
• Education: Education is a basic requirement for every human being. The governments
should utilize its entire recourses irrational manner to encourage people to become literate to
some extent since educated persons are assets ho help in proper development of the country.
In the Parseoni Tehsil, there are number of primary, middle and Higher secondary school and
colleges.
• Hospital : There are number of Hospital, dispensaries, primary health centre and Sub primary
health centre available in Parseoni Tehsil.
• Transport : The transport facilities in theParseoni Tehsil are well developed and wide spread.
Asian/ national highway link most of the urban areas.
• Communication : Communication facilities go a long way in information collection and its
dissemination in an effective and speedy manner. In the modern society, the roll of the
facilities in the socioeconomic development of the society is very well recognized.
Communication facility help in the flow of information from one place to another in shortest
time, thus helping administration and corporate managers to take crucial decisions relating to
daily functioning of administration and business dealings in shortest possible time. The
importance of developed communication network for the common men judged from the fact
that in rural areas. All communication facility like as phone, fax, printer, scanner, computer
etc are available in Parseoni Tehsil and in nearby urban areas like Kanhan and Kamptee.
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
14
5 PLANNING BRIEF
i) Planning Concept (type of Industries, facilities, transportation etc) Town andcountry planning/ Development authority Classification.
Proposed project activities will be started after getting statutory clearance form related
authorities. The project will be completed in 2016. Further proposed project activities will be
carried out in compliance with all the rules and regulation of statutory authority and provide
the control measure and devices to achieve the standard norms.
ii) Land use planning (breakup along with green belt etc.).
. Thelandusebreakupofplantareaisgivenbelow.ProposedPlantLayOutisgiven.
ProposedLandUsePlan
Sr.No. Particulars Area(Acre) %1 Washeryplant 7.57 37
2 CoalStorageyard 2.86 143 Rejectstorageyard 1.02 54 Greenbelt& Plantationarea 6.75 33
5 Waterreservoir&Rainwaterharvestingarea 1.02 56 Officebuildingandrestshelters 1.22 6
Total 20.44 100.0
iii) Assessment of Infrastructure Demand (physical & social).
The road facility already available will be used and strengthened. The transportation of coal
will be through roads. Power requirement will be 1000 KVA will be met by
Maharashtra State Electricity Board and Water 631 m3/day which will be met through
tubewells.
The labor requirement is 96 (each shift) will be taken from the nearby villages and they will
be trained for the requirement.
iv) Amenities/Facilities.
Facilities are available for drinking water, canteen and toilets.
6 PROPOSED INFRASTRUCTURE
i) Industrial area (processing area).
ProposedPlantwillbecomingupinanareaof8.28 ha.
ii) Residential Area (Non processing Area).
None
iii) Green Belt.
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
15
Local trees proposed for plantation.
iv) Social Infrastructure.
Under Corporate Social Responsibility (CSR) the felt needs of the nearby villages will be
identified and accordingly social infrastructures will be developed.
v) Connectivity (Traffic and Transportation Road/Rail/Metro/Water waysetc.)
The area is approachable from National Highway and Railway.
vi) Drinking Water management (Source & Supply of water)
Drinking Water will be available from nearby villages.
vii) Sewerage System.
Not required
viii) Industrial Waste Management.
The total make up water required for the proposed plant will be 631 m3/day which will
be met through tubewells. The water will be recycled and reused within plant
premises. Process waste water from coal washing will be collected and treated in thickeners
and will be re-circulated in coal washing process. The plant will operate on 'Zero Effluent
Discharge' Principal.
ix) Solid Waste Management.
About 1.0 MTPA washery rejects will be generated during the coal washing
process. The rejects will be sold to the nearby consumers. There will be not much
any storage required for the coal rejects. No other solid waste is envisaged in the
coal washing process.
x) Power Requirement & Supply / Source.
Maharashtra State Electricity Board (MSEDCL).
7 REHABILITATION AND RESETTLEMENT (R &R ) PLAN
i) Policy to be adopted (central/state) in respect of the project affected person
including home oustees, land oustees and landless laborers (a brief outline to be
given.)
None
8 PROJECT SCHEDULE & COST ESTIMATES
i) Likely date of start of construction and likely date of completion(Time schedule for the project to be given.)
The operations shall be carried out after obtaining all statutory permissions as per
the statutory guidelines. The commissioning of the plant is expected by end of
2016.
-
Pre-feasibility Report for expansion of 1.5 MTPA to 2.5 MTPA Coal Washery of M/s Bhatia Coal Washeries Ltd.located
16
ii) Estimated project cost along with analysis in terms of economicviability of the project.
The total cost of proposed Coal Washery project 4 MTPA after expansionestimated as approx. Rs. 36.0 Crores.
Budgetary provision of Rs.1.00 Crores has been made for implementation ofEnvironmental Management Plan.
The project is economically viable considering the project cost, and
environmental cost, and the various community improvement activities planned.
9 ANALYSIS OF PROPOSAL FINAL RECOMMENDATIONS)
i) Financial and social benefits with special emphasis on the benefit to the local
people including tribal population, if any, in the area.
Financial & social benefits with special emphasis on the benefits to the local people
including tribal population if any in the area.
This Coal Washery will provide employment for around 116 people by direct
employment which will include Engineers, Executives, Skilled, Semi- skilled and
Unskilledlabour and indirect employment to more than 120 persons, in contractual
works & transport. The project proponent will extend social welfare activities like
health, education, infrastructure development and environment conservation.