PFR For Proposed Expansion
Slum Rehabilitation Scheme of
“Shree Saibaba Nagar SRA Co-
Op. Hsg. Soc. (Prop.)” at
Dhobighat, Satrasta, Mumbai” By
M/s. Omkar Realtors Projects Pvt.
Ltd.
9th November ,
2017
Proposed SRA Scheme
By M/s. Omkar Realtors Projects Pvt.Ltd
Pre-
Feasibility
Report
(PFR)
Submitted to
Expert Appraisal Committee (EAC), MoEF& CC, Delhi
Environmental Consultant
Building Environment (India) Pvt. Ltd
Dakshina Building, Office No-401,4th Floor,
Beside Raigard Bhavan, Sakal Bhavan Rd,
Sector 11, CBD Belapur,
Navi Mumbai, Maharashtra 400614
Telefax: 022 4123 7073/2757 8554
Web: www.beipl.co.in
Submitted by
Omkar Realtors Projects Pvt.Ltd.
Omkar House, Off Eastern Express
Highway, Opp. Sion-Chunabhatti Signal,
Sion (E). Mumbai 400 022
B- +91 22 66254100
F- +91 22 24034066
http://www.beipl.co.in/
PFR For Proposed Expansion Slum Rehabilitation Scheme of “Shree Saibaba Nagar SRA Co-Op.
Hsg. Soc. (Prop.)” at Dhobighat, Satrasta, Mumbai” By M/s. Omkar Realtors Projects Pvt. Ltd. 2017
1
BE/ToR-Omkar_Expn.Dhobighat /017/003 Rev.00
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY 3
i. Power Requirement: 5
ii. Water Requirement: 5
iii. Manpower Requirement: 6
iv. Wastewater Management: 6
v. Solid Waste Management 6
vi. Noise 6
a. Environmental Attributes 7
b. Air Dispersion Modeling 7
2. INTRODUCTION 8
3. PROJECT DESCRIPTION 9
i. Location Details 9
ii. Connectivity: 10
iii. Details of Alternative Site Considered 10
iv. Project Area Details 10
v. Process Details 10
vi. Flow Chart Showing Project Layout 10
vii. Power: 10
viii. Water: 11
ix. Manpower: 11
x. Raw Material Requirement 11
xi. Waste Management/ Disposal 11
4. SITE ANALYSIS 12
i. Connectivity 12
ii. Land form and Land Use 12
iii. Land Ownership 12
iv. Existing Land Use Pattern 12
v. Existing Infrastructure 12
vi. Soil Classification 12
vii. Climate data secondary source 12
viii. Social Infrastructure Available 12
5. PLANNING BRIEF 13
PFR For Proposed Expansion Slum Rehabilitation Scheme of “Shree Saibaba Nagar SRA Co-Op.
Hsg. Soc. (Prop.)” at Dhobighat, Satrasta, Mumbai” By M/s. Omkar Realtors Projects Pvt. Ltd. 2017
2
BE/ToR-Omkar_Expn.Dhobighat /017/003 Rev.00
i. Planning Concept - SRA Project 13
ii. Population Projection - On completion of the project, total population is expected to be
16417 Nos. 13
iii. Land use planning - As per the DP Plan the site is under commercial and residential
zone. 13
iv. Amenities or facilities 13
6. PROPOSED INFRASTRUCTURE 14
i. Residential area – 14
ii. Commercial area – 14
iii. Green belt – 14
iv. Drinking water Management 14
v. Sewerage System 14
vi. Industrial Waste Management 14
vii. Solid Waste Management 14
viii. Power Requirement and Supply 15
7. REHABILITATION AND RESETTLEMENT PLAN 16
8. PROJECT SCHEDULE AND COST ESTIMATES 17
PFR For Proposed Expansion Slum Rehabilitation Scheme of “Shree Saibaba Nagar SRA Co-Op.
Hsg. Soc. (Prop.)” at Dhobighat, Satrasta, Mumbai” By M/s. Omkar Realtors Projects Pvt. Ltd. 2017
3
BE/ToR-Omkar_Expn.Dhobighat /017/003 Rev.00
1. EXECUTIVE SUMMARY
M/s. Omkar Realtors Projects Pvt.Ltd. has proposed an expansion of SRA Scheme on plot
bearing C.S.No. 1(pt) , 2(pt) and 3(pt) of Lower Parel Division in G/South Ward at G.B. Sakpal
Marg and Babu Kamlakant Singh Marg, Dhobighat, Satrasta, Mumbai-400011 for Shree
Saibaba Nagar CHS ( Prop.) & other 7 Societies. The project location on Google is shown
below in Figure 1.1 and Layout in Figure 1.2.
Figure 1.1: Project Location
Figure 1.2: Project Layout
The total cost of the project estimated is 1000 Cr. The project site comes under Municipal
Corporation of Greater Mumbai (M.C.G.M). As per the Draft GDCR 2034, the development
allowed on this plot as per regulation No.13.2 & 13.3 is C-R i.e. Commercial & Residential.
The DP plan is shown below in Figure 1.3.
PFR For Proposed Expansion Slum Rehabilitation Scheme of “Shree Saibaba Nagar SRA Co-Op.
Hsg. Soc. (Prop.)” at Dhobighat, Satrasta, Mumbai” By M/s. Omkar Realtors Projects Pvt. Ltd. 2017
4
BE/ToR-Omkar_Expn.Dhobighat /017/003 Rev.00
Figure 1.3: DP plan
The project will be developed on total plot area of 42,542.79 sq.mt. After deducting
reservations, the effective net plot area comes about 27,696.68 sq.mt.The total Built-up area
planned on the site is 4, 17,835.01 sq. mt. The project involves construction of rehab & sale
buildings. Their details are given Table 1.1
PFR For Proposed Expansion Slum Rehabilitation Scheme of “Shree Saibaba Nagar SRA Co-Op.
Hsg. Soc. (Prop.)” at Dhobighat, Satrasta, Mumbai” By M/s. Omkar Realtors Projects Pvt. Ltd. 2017
5
BE/ToR-Omkar_Expn.Dhobighat /017/003 Rev.00
Table 1.1: Project Description
Details Description
Total Plot area 42542.79 sq.mt.
Deductions 14846.11 sq.mt.
Net Plot area 27696.68 sq.mt.
Total Plot area 42542.79 sq.mt.
Permissible FSI 4
FSI consumed 162790.64 sq. mt.
Non FSI 255044.37 sq. mt.
Total Construction B.U.A 4,17,835.01 sq. mt.
Rehab Bldgs.
Rehab Bldg. No. 1 Gr. + 42nd Upper Floor
Rehab Bldg. No. 2 GR + 28th (Pt.) Floors.
Sale Building No. 1 (Tower 1, Tower 2 & Tower 3)
Tower 1 Basement + Gr.+ 1st to 6th Podium + 7th & 8th
Amenity Floor + 9th Service Floor +10th to 79th
Upper Floor
Tower 2 Basement + Gr.+ 1st to 6th Podium + 7th & 8th
Amenity Floor + 9th Service Floor + 10th to 40th
Upper Floor
Tower 3 Basement + Gr.+ 1st to 6th Podium + 7th & 8th
Amenity Floor + 9th Service Floor +10th to 40th
Upper Floor
Project Infrastructures
i. Power Requirement:
Electricity will be sourced from Local Authority.
ii. Water Requirement:
Construction Phase
Total water requirement estimated is 150 KLD. The water demand will be met by local
authority and water tankers.
Operation Phase
Rehab:
Source: MCGM /Recycled water / RWH / tanker
Total Water Demand: 1939.00 KLD
Domestic: 1284.00 KLD
Flushing: 642.00 KLD
Gardening: 8.00 KLD
Car Washing: 5.00 KLD
Sale:
Source: MCGM /Recycled water / RWH / tanker
Total Water Demand : 529.00 KLD
Domestic: 342.00 KLD
PFR For Proposed Expansion Slum Rehabilitation Scheme of “Shree Saibaba Nagar SRA Co-Op.
Hsg. Soc. (Prop.)” at Dhobighat, Satrasta, Mumbai” By M/s. Omkar Realtors Projects Pvt. Ltd. 2017
6
BE/ToR-Omkar_Expn.Dhobighat /017/003 Rev.00
Flushing: 171.00 KLD
Gardening: 8.00 KLD
Car Washing: 8.00 KLD
iii. Manpower Requirement:
Construction Phase
During the construction phase about 500 persons will be deployed on the site from nearby
places. Influx of these people was temporary in nature.
Operation Phase
On completion of the project, residents will occupy their property. Total population is expected
to be 16417.
iv. Wastewater Management:
Rehab Buildings: Total 1733.00 KLD of wastewater will be generated from the project site.
After recycling treated sewage will be used for flushing, gardening & car washing.
Sale Buildings: Total 461.00 KLD of wastewater will be generated from the project site. After
recycling treated sewage will be used for flushing, gardening & car washing.
v. Solid Waste Management
Construction Phase
During the construction phase, soak pits and septic tanks will be provided for disposal of waste
water. Temporary sanitary toilets will also be provided during peak labor force.
Operation Phase
Solid waste generated from the project will be segregated at source.
Rehab:
The total quantities of solid waste that will be generated in the project will be 6159 Kg/day.
Out of which 2529 Kg/day will be non-biodegradable and 3631 Kg/day will be biodegradable.
Sale:
The total quantities of solid waste that will be generated in the project will be 1639 Kg/day.
Out of which 673 Kg/day will be non-biodegradable and 966 Kg/day will be biodegradable.
Biodegradable waste will be treated in OWC. Non Bio-degradable waste will be handed over
to authorized local vendor for recycling.
vi. Noise
The construction noise localized, intermittent in nature. This has subsided with the completion