PETRONAS Gas Berhad Corporate Briefing...PGB * Although the Group has more than 50% ownership in the...

42
PETRONAS Gas Berhad Corporate Briefing

Transcript of PETRONAS Gas Berhad Corporate Briefing...PGB * Although the Group has more than 50% ownership in the...

  • PETRONAS Gas BerhadCorporate Briefing

  • PETRONAS Gas Berhad (PGB)

    • Private Limited Company23 May 1983

    • Public Limited Company28 March 1995

    • Listed on KLSE Main Board 4 September 1995

    • PETRONAS owns 60.66% equity

  • PGB

    * Although the Group has more than 50% ownership

    in the equity interests of Kimanis Power Sdn Bhd

    and Kimanis O&M Sdn Bhd, the Group treats these

    companies as joint ventures in accordance with

    Malaysian Financial Reporting Standards. This is in

    consideration that it does not have sole control over

    these investees as strategic and financial decision of

    these investees required unanimous consent by all

    shareholders.

  • GPU

    GTR

  • Customers

    Upstream Processing & Transportation

  • PGU

    Loop

    New Connection

    Gas Processing Plant

    Utilities Plant

    Regasification Terminal

    Power Plant

    Imported Gas

    GPS

    GPK

    UK

    UG

    RGT1

    (2003)

    Kangar

    THAILAND

    Kuala Lumpur

    Segamat

    Paka

    Keppel

  • Location: Sungai Udang, Melaka

    Distance from shore: 3 kilometres

    Capacity: 530 mmscfd/3.8 mtpa

    Length: Approximately 900 metres

    Operated by PGB Subsidiary Regas Terminal Sungai Udang Sdn Bhd

  • Unloading from

    LNGCStorage in FSU Regasification

    Injection into

    Grid

  • Component Fee

    Tariff

    1. Peninsular (RM/GJ)

    Postage tariff for Peninsular

    1.248

    (RM1,277.2M)

    2. Miri (RM/GJ) 1.857

    (RM15.5M)

    3. Bintulu (RM/GJ) 1.147

    (RM1.9M)

  • Revenue (RM million) Profit After Tax (RM million)

    CAGR : 6.3%

    CAGR : 5.4%

  • Total Asset (RM million)Total Equity (RM million)

  • Segment Gas ProcessingGas

    TransportationUtilities Regasification

    Revenue

    Contribution(%)34.1 28.6 23.4 13.8

    Gross Profit

    Contribution (%)31.4 47.2 7.5 13.9

    Gross Profit

    Margin (%)41.6 74.8 14.6 45.3

  • 0

    5

    10

    15

    20

    25

    30

    Lowest share price

    RM14.80

    Highest share price

    RM24.88

    Closing share price

    @ 31 December

    2016 RM21.30

    Market capitalisation

    RM42 billion*Top 10 in FBM KLCI as at 31 December 2016

  • 82

    71

    91

    107 105

    6973

    60

    76

    64

    7771

    ’06 ’07 ’08 ’09 ’10 ’11 ‘111 ’12 ’13 ’14 ’15 ‘16

    Note:

    Financial year 2011 comprises reporting period from 1 April to 31 March.1 For the nine month period ended 31 December 20112 Based on normalised PAT (excluding tax incentives)3 PGB has embarked on a quarterly dividend payment since Q3 FY2014, instead of semi-annually dividend plan in line with practices

    undertaken by some other public listed companies.2

    Dividend declared

    Interim Sen RM Mil

    FY16 1st Interim 14 277.02

    FY16 2nd Interim 14 277.02

    FY16 3rd Interim 15 296.81

    FY16 4th Interim 19 375.96

    Total 62 1,226.81

    82%

    71%

    91%

    107% 105%

    69%73%

    60%

    76%2

    64%2

    77%271%

  • Pengerang Deep Water Terminal

    ( )

    Associated Facilities

    PRPC (Utilities and Facilities)

    Sdn Bhd

    1

    RGT2

    (Regasification Terminal)2

    ASU

    (Air Separation Unit)

    3

    SPV 2

    (Liquid Bulk Terminal)4

    PCP

    (Cogeneration Plant)

    5

    PAMER

    (Projek Air Mentah)6

  • LNG Storage

    Tank

  • Project Cost

    Target commencement

    Estimated at USD858 Million

    Commenced construction in Q2 FY2015

    Target commercial operations

    Q4 FY2017

    IRR At par with IRR of other infrastructure company

    Project mode • EPCC• EPCC Agreement with Samsung C&T Corporation, in

    Consortium with Whessoe Engineering Ltd, Science-TechSolutions Sdn Bhd and Samsung C&T (KL) Sdn Bhd (RM1.5Billion)

    Financing Funded by a combination of equity and debt from therespective parties

    RGTP Tariff (USD)

    Regasification Fee

    Storage Charge

    Tariff

  • Associated Facilities

    PRPC (Utilities and

    Facilities) Sdn Bhd

    RGT2

    (Regasification

    Terminal)

    ASU

    (Air Separation Unit)

    3

    SPV 2

    (Liquid Bulk Terminal)

    4

    PCP

    (Cogeneration Plant)

    PAMER

    (Projek Air Mentah)

    1

    2

    5

    6

    The

    The

    The

    The

  • Linde

    ASU JV Co

    Partnership Linde is:• One of the global leading industrial gases companies• Proven to have the technology and capability for projects

    such as ASU

    Rate of return Above WACC

    Target commissioning Q4 FY2018

    Total Project cost

    USD172M

    51% 49%

    Financing 70:30 Debt: Equity

  • 89.10%

    3.63%

    3.63%

    3.64%

    86%

    90%

    94%

    98%

    102%

    AdjustedCapacity

    NetProduction

    OEE Gap

    100%

    Target production considers internal factors based

    on planned maintenance activities.

    OEE measurement excludes all external factors e.g.

    feedgas composition, feedgas volume, demand, etc.