Petrolera Zuata, Petrozuata case
-
Upload
andy-vibgyor -
Category
Documents
-
view
368 -
download
19
description
Transcript of Petrolera Zuata, Petrozuata case
Petrolera Zuata, Petrozuata C.A.
Group #14Anupama Prakash (PGP/17/009)
Anuradha Dhote (PGP/17/010)Sarika Chauhan (PGP/17/044)
Corporate Finance Option
Total Investment = $ 2,424 MnIf only CF is used, investment by PDVSA(49.9%) = $ 1,209 Mn
• PDVSA had given several guarantees to Petrozuata for payment of project expenses, including unexpected cost overruns, prior to completion • This was the first in a series of future deals to be taken up with foreign Oil & Gas companies, for development of Orinoco basin, hence, it was important to
preserve parent’s debt capacity and financial flexibility
Under PF, it was decided that 60% of investment would be sourced from debt, hence – Total Equity Investmnt = $ 975 MnPDVSA’s share(49.9%) = $ 487 Mn
• As we can see, with PF, PDVSA’s investment is significantly lesser, as compared to its investment obligation with CF – this helps to preserve its debt capacity• Sufficient lender protection was ensured under the PF deal structure by putting a time limit (Dec 2001) on project completion – extendable by a finite time.
If this was not met, all debt would become due and payable.• Under PF, PDVSA had the option of getting a higher investment rating for issued bonds, as compared to current country and parent company ratings (B)
There are issues of political risk insurance (PRI) due to which leverage could be costlier, and chances of negative carry due to inflow of large amounts of funds via bonds at the start. However, as PF maintains financial flexibility of parent company, thus putting it in a better position to handle future uncertainties, hence, it can be concluded that project financing is a better funding option.
Project Finance Option
CF and PF as alternative financing models
Operating Risks Involved
Pre-completion risk
• Chances of cost overrun & ensuring funds for project expenses• Sponsors- Conoco & Maraven obliged to pay for project expenses including cost overruns, If any.• Obligations guaranteed by parent companies- DuPont & PDVSA• Severe penalties if sponsors fail to meet these obligations• Incentives to make up for the other party’s shortfall
• Construction All Risk Insurance Policy• Insurance policies to cover physical loss or damage up to $1.5 Billion
• Provision for Contingency in construction budget for upstream, downstream facilities & payment of insurance policies
• Force Majeure• if the project could not be completed with a specified period, all debt will become due and payable
with immediate effect
Post-completion risk• Conoco was not liable to purchase the syncrude
in the case of force majeure• High debt service coverage ratio of 1.35X as the
bare minimum requirement• Break even price was kept quite low so that
operating & financing costs can be recovered even if prices fall to a very low value
• Payment through “cash waterfall system”- • 1st priority- 90 day operating expense
account• 2nd priority- Project’s debt obligations• 3rd priority: Debt Service reserve account
for 6 months• 4th priority: Equity holdersPolitical & Economic Risk• Initial Planning to raise debt from commercial
banks and getting loan guarantees & Country Risk Insurance from agencies like EDC, OPIC & IFC
Tax Rate 34%Asset Beta 0.6Leverage 60%
Cost of Debt 10%
Risk free rate (Rf) 5.60%Market Risk Premium (MRP) 7.00%Country Risk Premium (CRP) 6.67%
Start-up Premium (SP) 2.10%
Return on assets (rA) = Rf+βA*(MRP)+CRP+SP
18.57%Expected Return (Equity) =rA+(1-Tc)*(rA-rD)*(D/E)
27.05%
IRR 25.58% ROA 18.57%
Year Equity Cash Flows Equity Value Debt Value D/E Cost of Equity
1996 ($79,035) $79,035 $0 0.00 18.57%1997 ($1,986) $81,021 1,000,000$ 12.34 88.38%1998 ($550,148) $631,169 1,024,299$ 1.62 27.75%1999 $1,576 $631,169 1,267,280$ 2.01 29.93%2000 $185,047 $631,169 1,450,000$ 2.30 31.56%2001 $225,457 $631,169 1,411,111$ 2.24 31.22%2002 $233,074 $631,169 1,372,222$ 2.17 30.87%2003 $200,600 $631,169 1,333,333$ 2.11 30.52%2004 $218,903 $631,169 1,268,856$ 2.01 29.94%2005 $203,857 $631,169 1,187,614$ 1.88 29.21%2006 $232,620 $631,169 1,086,961$ 1.72 28.31%2007 $229,393 $631,169 977,484$ 1.55 27.33%2008 $238,588 $631,169 849,556$ 1.35 26.18%2009 $226,629 $631,169 755,137$ 1.20 25.34%2010 $216,878 $631,169 669,137$ 1.06 24.57%2011 $216,655 $631,169 567,137$ 0.90 23.65%2012 $262,881 $631,169 449,137$ 0.71 22.59%2013 $242,378 $631,169 401,689$ 0.64 22.17%2014 $251,988 $631,169 348,241$ 0.55 21.69%2015 $260,474 $631,169 252,034$ 0.40 20.83%2016 $250,893 $631,169 134,448$ 0.21 19.77%2017 $376,215 $631,169 75,000$ 0.12 19.24%2018 $320,878 $631,169 75,000$ 0.12 19.24%2019 $301,370 $631,169 75,000$ 0.12 19.24%2020 $276,398 $631,169 75,000$ 0.12 19.24%2021 $292,810 $631,169 75,000$ 0.12 19.24%2022 $217,227 $631,169 -$ 0.00 18.57%2023 $294,578 $631,169 -$ 0.00 18.57%2024 $289,656 $631,169 -$ 0.00 18.57%2025 $289,705 $631,169 -$ 0.00 18.57%2026 $278,074 $631,169 -$ 0.00 18.57%2027 $276,806 $631,169 -$ 0.00 18.57%2028 $274,449 $631,169 -$ 0.00 18.57%2029 $263,604 $631,169 -$ 0.00 18.57%2030 $247,540 $631,169 -$ 0.00 18.57%2031 $250,329 $631,169 -$ 0.00 18.57%2032 $242,937 $631,169 -$ 0.00 18.57%2033 $240,644 $631,169 -$ 0.00 18.57%2034 $226,196 $631,169 -$ 0.00 18.57%
Average 24.31%
Project has IRR of 25.58% for 60% leverage but since debt is being repaid Debt-equity ratio will keep changing.
Cost of equity has been shown for differnent debt-equity ratios which is very high initially. Average cost of equity
comes to be 24.31% which is below IRR
For Fixed Debt-Equity ratio 60%
Expected Returns
Change in LeverageAt 60% leverage, the equity cash flows are such that –
IRR = 26% and Minimum DSCR ratio = 2.08x, against prescribed requirement of 1.35x
For 50% leverage, the advantage of tax shield and lower cost of debt financing reduces. However, the minimum DSCR increases to 2.68x, while IRR suffers and comes down to 23%
For 70% leverage, greater debt impacts minimum DSCR which comes down to 1.91x, however, IRR increases to 29%, giving the project equity investors substantial returns
Advantages• Flexibility to
withdraw as per requirement, matching of cash inflows & outflows
Disadvantages• Short Maturities,
restrictive covenants, small size
• Longer Processing Time• Expensive if PRI is
required
Advantages• Long Maturities,
Fixed Interest rates, Flexible covenants, Available in larger amount
Disadvantages• Can only be raised in lump
sum amount• Results in loss, as funds
can not earn higher return than cost of borrowing (Negative Carry)
Advantages• Advantages similar to
Public Bonds • Can be underwritten
within 6 months
Disadvantages• Less liquid as these
can sold back to only QIBs (Qualified Institutional Buyers)
Rule 144A marketPublic Bond MarketBank Debt
Petrolera Zuata should use combination of Bank Debt & Rule 144A market. Since Rule 144A market offers advantages of Public Bonds, funds can be raised in two or three phases according to funds requirement. At the same time, to ensure liquidity, band
debt can also be taken to make up for the deficit. Going for all the three option will increase the cost of raising fund with no incremental benefit and it is not possible to raise the
entire amount through one instrument only.Hence bank debt and Rule 144A bond market will give Petrolera Zuata ease of raising funds for a longer maturity in large
amount & flexibility to withdraw as per fund deficit.
Sources of Debt
Sensitivity Analysis
Crude Oil Prices• Revenue of the project driven by
market price of Maya crude• Historical data shows that price of
Maya crude has been heavily fluctuating – lowest of $8.14 per barrel recorded around 1986
• During the course of project financing meetings, price of Maya crude was expected to fall from $18.62 to $16 per barrel
• With DSCR of 1.0 (highest forecasted debt service), break even price estimated at $8.63 per barrel
Exchange Rate• Project’s topline would be
affected by exchange rate fluctuations
• Revenues are to be earned in US dollars as against operating expenses that are to be met with local currency of bolivar
• Appreciation of bolivar to increase operating expenses, tax liability, as well as increase pressure on revenues
• Sensitivity analysis can be done by assuming bolivar to become overvalued by 20% to return to PPP
Reserves• Current reserve estimate of
Orinoco belt stands at 21.5 billion barrels
• Planned production level is set at 120000 BPCD
• Sensitivity analysis with lower estimates of reserves will lead to lower production and hence lower realized revenues
• It will also lead to increased capital expenditure for drilling, completion and related oil-well servicing costs
• Impact on project’s topline as well as costs
Sensitivity analysis can also be carried out on other parameters like increased operating costs and substandard upgrader performance.Lower or pessimistic estimates will tend to increase the minimum DSCR requirement based on which the project would be analysed.
Is Investment Grade Rating Possible?• There are good chances for the project bonds to be rated as investment grade despite PDVSA and Venezuela having sub-
investment grade ratings• Possible reasons for an investment grade rating are
Mitigation of risks through well-planned deal structure that entails high debt coverage ratio requirement, strict break-even price threshold and waterfall model payment priority
Positive outlook owing to low operating costs of the project as aginst industry standard – project’s cash operating cost was $3.19 per barrel as against industry median of $8.55
Involvement of sponsor like Conoco which has huge experience in completing large-scale projects of the same nature and whose parent, DuPont, has Aa3 and AA- as credit ratings for its long-term senior unsecured debt
Decision to Invest in the Project:• With the given cash flows and leverage of 60%, the project maintains a minimum DSCR of 2.08x, which is greater than
prescribed 1.35x DSR• Conoco, with a guarantee from DuPont had agreed to purchase the first 104,000 BPCD of Petrozuata’s syncrude for the
35-yr life of the project, based on market price of Maya crude, while, both the parent companies had agreed to severally provide funds to Petrozuata to pay project expenses, including cost overruns -> thus with stable revenues and costs, there are chances of project bonds getting an investment grade rating
• Hence, investing Petrozuata bonds seems like a feasible option
Investment in Project Bonds