PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance...

26
PETROKEMYA (SABIC) Control Loop Performance Monitoring and Assessment Presentation at KFUPM Monday, 24 th November 2008 by Khalid T Al Ruwaili Khalid T . Al-Ruwaili Manager, Control System Department Petrokemya, SABIC Petrokemya Olefins-III v

Transcript of PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance...

Page 1: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

PETROKEMYA (SABIC)Control Loop Performance p

Monitoring and Assessment

Presentation at KFUPMMonday, 24th November 2008

byKhalid T Al RuwailiKhalid T. Al-Ruwaili

Manager, Control System DepartmentPetrokemya, SABICPetrokemya Olefins-III

v

Page 2: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Contents …Contents …Introduction …The incident …Study objectives …Study findings …S l ti & D i iSolution & Decision …Project implementation …Benefits …

2

Page 3: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Introduction …Introduction …When it comes to performance of Control Loops in Process Industries, it is said that the day plants were built, it started to go , y p , gbad. With continuous operation, wear & tear, material variation, seasonal changes and changes in process characteristics plantsseasonal changes, and changes in process characteristics, plants drift away from their optimal performance. Most industries realize it only after a big process upset or

d ti lproduction loss.

3

Page 4: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

The incident …The incident …In Olefins-II, the VHP to HP steam-let-down valve PV-8660 had problems since plant startup. So, Operations kept the valve in p p p , p pMANUAL mode, as its performance in AUTO mode was not satisfactory. When the Process Gas Compressor (BK-0201) tripped on 31stWhen the Process Gas Compressor (BK-0201) tripped on 31st December 2004, VHP Steam demand came down, and because PV-8660 got stuck at 20%, HP steam header pressure dropped. This reduced turbine speed of BFW pump and caused lack of BFW andreduced turbine speed of BFW pump and caused lack of BFW, and in turn eight (8) millisecond furnaces tripped.Olefins-II plant was down for 16 hours, and total production loss was

i l t t 3680 t i t f th l (SR 5 851 200)equivalent to 3680 metric tons of ethylene (SR 5, 851,200).

4

Page 5: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Study objectives …Study objectives …Main objectives of the CSD survey were,

To study the reasons for performance-deterioration ofTo study the reasons for performance deterioration of control loops over a period of time, due to which control loops in various plants of Petrokemya were kept in MANUAL mode and not in their DESIGN MODE ofMANUAL mode, and not in their DESIGN MODE of operation.To develop a system and apply the latest hardware /

ft t l t t d it d i thsoftware tools to study, monitor, and improve the performance of critical control loops, on a continuous basis.

5

Page 6: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Study findings …Study findings …Control Loops working alright, but may deteriorate anyway …Change in the process characteristicsChange in the process characteristics …Operations prerogative …Control Valve problems …Inadequate control scheme design …Other reasons …

6

Page 7: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Study findings (cont) …C

ateg

ory

Description Controllers status

VCM

Pla

nt

PVC

Pla

nt

PPS

Plan

t

lyet

hyle

ne

Ole

fins-

I

Ole

fins-

II

Ole

fins-

III

Util

ities

Ove

rall

C V P P

Po

O O O

1Controllers apparently working alright but may deteriorate anyway

Auto 279 470 87 0 532 829 989 159 3345deteriorate anyway

2 Change in process characteristics Manual 9 5 9 0 16 21 2 5 67

3 Operations prerogative Manual 25 26 12 0 20 464 101 7 655p p g

4 Control Valve problems Manual 3 4 4 0 8 3 4 2 28

5 Inadequate design Manual 8 4 0 0 0 3 47 3 65

7

Total per Plant 324 509 112 0 576 1320 1143 176 4160

Loops on Auto: 3345 (of 4160) Loops on Manual: 815 (of 4160)

7

7

Page 8: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Control Loops working alright but …Control loops are tuned during plant initial commissioning …PID parameters are set based on experience

Control Loops working alright but …

PID parameters are set based on experience …Problematic control loops are tuned through trial and error …Plants may run for their lifetime with sub-optimal controls …Control valves become mechanically deficient …

Flow control valve does 1 - 2 million reversals/year …Valve packing frequently over-tightened to prevent emissionsValve packing frequently over tightened to prevent emissions …

Causes valve stiction and control loop cycling …Process characteristics change with time …

Equipment fouling, wear, modifications …Even well-tuned control loops develop problems …

8

Page 9: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Control Loops working alright but (cont) …

Alarm LimitAlarm LimitLimit of OperabilityLimit of Operability

Reduction in benefits

Lowering of set point to maintain safety margin

Lowering of set point to maintain safety margin

Reduced Profit – Running further from ConstraintsIncreased Maintenance Costs – Equip & Valves CyclingIncreased Operator Loading Alarms Intervention reqd

Variability increases over time

Variability increases over time

9

After optimization 2 – 3 years later

Increased Operator Loading – Alarms, Intervention reqd.

Performance decreases over time

9

9

Page 10: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Control Loops - symptoms of poor performance …

Excessive varianceOscillatory behaviorDisclosing events– Increased alarm frequency

O t i t ti

Excessive Variance

– Operator intervention– Loops placed in manual mode– Controller output saturation

Oscillatory Behavior

Frequent alarmsOperator interventionPID T i h

Poor Control Loop Service

PID Tuning changesLoop in manualOutput runs into limits

10

Page 11: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Change in the Process Characteristics …

Compared to the original design, process characteristics change with time. Plant modifications, equipment wear & tear or fouling and varying plant loads, contribute to deterioration in the performance of control loops.For example,

Plants are modified, debottlenecked, or added with new equipmentIn VCM plant, guided wave radar level instruments were identified and successfully used as a replacement for obsolete and problematic displacer type level instruments. In Olefins I nearly 56 VORTEX flow meters are installed in place ofIn Olefins-I, nearly 56 VORTEX flow meters are installed in place of Orifice plates in furnace dilution steam flow meter applications, to overcome problems like, frequent plugging of impulse tubing with coke particles, and unstable & oscillating flow measurement.

11

Page 12: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Operations prerogative …

Over a period of time, plant operating personnel develop opinion on some control loops that there will be problems irrespective of the actions they take. Or, the Operators do not keep some control loops in their designed MODE of operation due to other reasons.For example,

In PVC plants, 15 Poly Reactor pressure control loops are in MANUAL mode, against their designed AUTO mode, to avoid releasing VCM to atmosphere.

12

Page 13: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Control Valve problems …

HysteresisStictionNonlinear Installed Characteristic

HysteresisNonlinear Installed CharacteristicOversized Control Valve These problems cannot be solved through tuningthrough tuning

Stiction

Non-linear characteristic

Oversized valve

13

Page 14: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Inadequate Control Scheme design…

Process units or equipment are provided with inadequate control schemes to control them, or inadequate field instrumentation to measure the required process variables.When it comes to performance of control loops, it becomes very difficult to judge, whether adequate control schemes are provided in the first place. For example,

When we compare three ETHYLENE plants in Petrokemya, which were built at different times, the number of control loops and field i t t i h th l l t k t i i i ifi tlinstruments in each ethylene plant kept increasing significantly.

14

Page 15: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Solution & Decision …

In the first phase of the project, we decided to go in for the following,Control Loop Performance Monitoring and Assessment packageControl Loop Tuning packageControl Loop Tuning packageAlarm Management System (AMS) package

And, in the second phase, we plan to go in for the following,Plant wide Advanced Process ControlPlant-wide Advanced Process ControlReal-Time Optimization

15

Page 16: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Project implementation (Olefins-II) …

We decided to implement the project in Olefins-II first. We prepared Invitation-To-Bid (ITB) documents and sent them to renowned Automation Companies. After technically and commercially evaluating the proposals, we selected the solution offered by Honeywell for Olefins-II.Deliverables,

Loop ScoutOperTuneAlarm ScoutAdvanced Alarm Management (AAM)Alarm Configuration Manager (ACM)Alarm and Event Analysis (AEA)User Alert (UA)Loop Scout Server, Advanced Alarm Management (AAM) Server

PowerEdge 1800, Xeon 3.0 GHz , Dual CPU, SATA Raid-5 hard disk

16

Page 17: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Project implementation (VCM) …

Then we moved on to Vinyl Chloride Monomer (VCM) plant. This time, we selected Process Automation Systems (PAS) after technically and commercially evaluating the proposals from renowned automation companies.Deliverables,

ControlWizardTuneWizardAlarm Analysis Module Alarm Documentation and Rationalization (D&R) module Automatic Data Update (ADU) module Real Time Alarm Management Application PlantState Suite Server

DELL tower, Xeon 3.0 GHZ , Dual CPU, 4GB SDRAM memory, 73 GB Raid-5 hard disk

17

Page 18: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Project implementation (VCM) …

Clients

Internet

Business LAN

Clients

External Firewall

Process Control Network

Controller Performance,Controller Tuning,

Alarm ManagementServers

Internal Firewall

OPC DA Server Clients

DCS

18

Page 19: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Project implementation (VCM) …

ControlWizard Treemap Performance Display provides a visual overview of loop

Assessment Details viewer shows data used for analysis, lists statistics, and provides p p

performance, loop importance, and draws attention to problem areas.

y , , pcorrective actions

19

Page 20: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Project implementation (VCM) …

Assessment Details viewer shows data used for analysis, lists statistics, and provides

Advanced Assessment Details viewer provides autocorrelation, impulse response, y , , p

corrective actions. p , p p ,and power spectrum plots, as well as detailed results of performance analyses .

20

Page 21: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Project implementation (Olefins-III) …

Too many alarms causing nuisance Many alarms were disabled (process safety)History Module (HM) of Honeywell DCS overflowingHistory Module (HM) of Honeywell DCS overflowing Difficult to retrieve alarm history of last few hours12 % - “BADPV” alarms

“Null” reading for fraction of a secondNull reading for fraction of a second.Mainly temperature alarms/defective thermocouple

30 % - “OFFNORM” alarms Change of state Deluge valvePump seal leakBurner scanner failure

21

Page 22: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Project implementation (Olefins-III) …

55 % - “PVHI” and “PVLO” alarmsProcess value exceeding high/low alarm limitsWrong selection of alarm limitsWrong selection of alarm limitsPoor controller tuningVarying feedstock

Controllers were tuned by HoneywellControllers were tuned by HoneywellAlarm limits were corrected based on feedstock“Dead bands” were created to allow for process swing“Time delay” was provided for process swing.“Bad PV” alarms were removed for temperatures

22

Page 23: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Project implementation (Olefins-III) …

NU

M

42

Olefins-III

MB

ER O

F A

42Journey from OverloadedWorkstation to “Robust" A

LARM

S P

Workstation

ER H

OU

RR

% PLANT UPSET

23

Page 24: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Benefits …

Continuous monitoring of all loopsAutomatic assessmentNon-invasiveNon invasiveProvides an overview of all loops

Prioritization of maintenance effortsProblem identification & diagnosisProblem identification & diagnosisScheduled reportingMaintain Advanced Process Control benefits

Typically, 40 - 70% of savings from APC projects are achieved by optimizing the performance of control loops

Reduce frequency & severity of abnormal situationsPoor performance of control loops contribute to 30% of preventable/unplanned plant downtime

24

Page 25: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Benefits (Cont) …

In Olefins-III, We achieved 93% reduction in total alarms per day (from 52,000 to 4,000 for 4 workstations). )We moved from "overloaded" workstation to "robust" workstation. We achieved this within 7-weeks of installing the system.Operators are now able to concentrate on process related issues Ope ato s a e o ab e to co ce t ate o p ocess e ated ssuesbetter than before.Nearly 95% of control loops run in their designed MODE.We achieved stable operation of C2-splitter and overallWe achieved stable operation of C2 splitter, and overall production increase of 3% (Capacity of the plant is one (1) million-tons-per-year of ethylene).

25

Page 26: PETROKEMYA (SABIC) Control Loop Performance Monitoring …€¦ · Control Loop Performance Monitoring and Assessment ... With continuous operation, ... Deluge valve Pump seal leak

Thank You

Any Questions?

Khalid T. Al-Ruwaili Manager, Control System Department

26