Pershing Hill Elementary School Burn Pit Stockpile

Removal Project

1

Page 2: Pershing Hill Elementary School Burn Pit Stockpile Removal Project 1.

Burn Pit and Stockpile July 2009

Stockpile

Burn Pit

Page 3: Pershing Hill Elementary School Burn Pit Stockpile Removal Project 1.

Soil Transport Route

Pershing Hill ES

CSL

Temporary Staging Area

Approved

Page 4: Pershing Hill Elementary School Burn Pit Stockpile Removal Project 1.

Geotechnical Boring Plan

RED CIRCLES

Arsenic Detections• 2.2 ppm – 3.3 ppm

Above EPA RSL for residential and industrial

Diesel Range Organics300 ppmAbove Residential

GREEN CIRCLE

Storm Water Control FeatureDioxin and Furan Detections

Page 5: Pershing Hill Elementary School Burn Pit Stockpile Removal Project 1.

Geoprobe Boring

Locations

Geoprobe Boring Location Map

Samples collected from the Burn Pit bottom (20 to 24 feet bgs)

•All results detected dioxins/furans

Page 6: Pershing Hill Elementary School Burn Pit Stockpile Removal Project 1.

Soil Stockpile Sampling

10 samples collected throughout the soil stockpile – Dioxin/furan test results consistent with Burn

Pit test results

Page 7: Pershing Hill Elementary School Burn Pit Stockpile Removal Project 1.

Data Summation

Dioxins/Furans– EPA analysis of dioxin/furans shows no risk high enough to warrant

any action

Arsenic– Arsenic levels above EPA RSL, but generally consistent with Ft.

Meade and regional background levels

Diesel Range Organics– Above state criteria

Page 8: Pershing Hill Elementary School Burn Pit Stockpile Removal Project 1.

8

Precautionary Measures

• Move Burn Pit stockpile to permitted location at the Closed Sanitary Landfill – engineering controls in effect

• Stockpile currently covered• Post stockpile testing• Dump trucks to be covered• Soil screened for hydrocarbons and placed into 2 stockpiles

Page 9: Pershing Hill Elementary School Burn Pit Stockpile Removal Project 1.

Short-term Project Schedule

• Mobilization this week• Site preparation work at the school – 2 days• Sediment controls at Landfill• Hauling commence ~ March 31, 10• 3 weeks of hauling• Two stockpiles re-tested for disposal purposes

9

Page 10: Pershing Hill Elementary School Burn Pit Stockpile Removal Project 1.

Army Contact Information

U.S. Army Garrison Fort George G. Meade

Directorate of Public Works - Environmental Division

2212 Chisholm Avenue, Suite 5115

Fort Meade, Maryland 20755-7068

Michael (Mick) Butler

Environmental Division Chief

Office: 301.677.9188

[email protected]

Paul V. Fluck, P.G., REP

Installation Restoration Manager

301.677.9365 - direct

240.429.8228 - cell

301.677.9001 - fax

[email protected]