People FirstSystem Upgrade
OverviewMarch 22, 2010
![Page 2: People First System Upgrade Overview](https://reader036.fdocuments.net/reader036/viewer/2022082818/56812f08550346895d94a673/html5/thumbnails/2.jpg)
© 2008 Convergys Corporation. All rights reserved.
System Upgrade Overview
Page 2
![Page 3: People First System Upgrade Overview](https://reader036.fdocuments.net/reader036/viewer/2022082818/56812f08550346895d94a673/html5/thumbnails/3.jpg)
© 2008 Convergys Corporation. All rights reserved.
System Upgrade Overview
Page 3
Major functional enhancements to be delivered with SAP upgrade
Communication and Training are critical to minimize disruption
System testing and UAT sign-off to be complete prior to upgrade
Risk Assessment and Contingency Planning Payroll processing Contingency Plan is a return to existing system Multiple mock upgrades will be completed prior to “live”
upgrade
![Page 4: People First System Upgrade Overview](https://reader036.fdocuments.net/reader036/viewer/2022082818/56812f08550346895d94a673/html5/thumbnails/4.jpg)
© 2008 Convergys Corporation. All rights reserved.
Offline Window
Effort to resize the downtime window to date, we have: Setup separate environment Conducted mock runs for the upgrade Worked with BASIS team to tune payroll cluster conversion Engaged with SAP to leverage their expertise in reducing the cycle
Conclusion: 5 Business Day Window
Plan for offline window is illustrated below (orange is validation window)
![Page 5: People First System Upgrade Overview](https://reader036.fdocuments.net/reader036/viewer/2022082818/56812f08550346895d94a673/html5/thumbnails/5.jpg)
© 2008 Convergys Corporation. All rights reserved.
Upgrade Process - Summary
Page 5
Detailed SAP Upgrade schedule (hour/minute) Validated through mock upgrades Communicated to all participants
Aggressive Management Frequent status reporting (scheduled calls) Open conference bridge for issue reporting and resolution 24 x 7 work schedule during upgrade
Upgrade Facts The People First database is approximately 1.6 terabytes 338 unique assignments/enhancements delivered with upgrade Approximately 700 transports (programming changes)
![Page 6: People First System Upgrade Overview](https://reader036.fdocuments.net/reader036/viewer/2022082818/56812f08550346895d94a673/html5/thumbnails/6.jpg)
© 2008 Convergys Corporation. All rights reserved.
Validation Summary
Page 6
System validation Spot check to ensure business functionality is operational DMS and Technical teams to collaborate
Contingency for unplanned events Payroll processing Contingency plan (return to existing system)
Post “go-live” support
![Page 7: People First System Upgrade Overview](https://reader036.fdocuments.net/reader036/viewer/2022082818/56812f08550346895d94a673/html5/thumbnails/7.jpg)
© 2008 Convergys Corporation. All rights reserved.
QuestionsQuestions
Page 7