pentagon preemption: the 5-sided loss of state energy and power

52
393 PENTAGON PREEMPTION: THE 5-SIDED LOSS OF STATE ENERGY AND POWER Steven FerreyTABLE OF CONTENTS I. Five Applications of Power Preemption ............................................. 394 II. The Inside Game Keeping Power or Generations In-State; ‘Bright Lines’ of Preemption .............................................................. 396 A. Preemption Pentagon Side 1: States Setting Inflated Wholesale Power Rates For Favored In-State Power .................. 397 1. California Feed-in Tariff Confronts the Supremacy Clause .. 397 2. The Inside Story .................................................................... 400 3. The Federal Power Act’s ‘Bright Line’ Between State and Federal Jurisdiction ............................................................... 404 4. The Legal Shift in Power Transactions ................................. 407 B. Preemption Pentagon Side 2: The Geography of New Power ..... 410 1. The New State Offer and Potential Conflict with Federal Steven Ferrey is Professor of Law at Suffolk University Law School, and was Visiting Professor of Law at Harvard Law School in 2003. Since 1993, Professor Ferrey served as a primary legal consultant to the World Bank and the U.N. Development Program on their renewable and carbon reduction policies in developing countries, where he worked extensively in Asia, Africa, and Latin America. He holds a B.A. in Economics, a Juris Doctorate degree, and a Masters degree in Urban and Regional Planning, and was a post- doctoral Fulbright Fellow at the University of London between his two graduate degrees. He is the author of seven books on energy and environmental law and policy, the most recent of which are UNLOCKING THE GLOBAL WARMING TOOLBOX (2010), EXAMPLES AND EXPLANATIONS: ENVIRONMENTAL LAW (6th ed., 2012), and THE LAW OF INDEPENDENT POWER (30th ed., 2013). He also is the author of more than 80 articles on these topics. Professor Ferrey thanks his research assistant, Michael Attisha, for his research assistance with recent case research.

Transcript of pentagon preemption: the 5-sided loss of state energy and power

Page 1: pentagon preemption: the 5-sided loss of state energy and power

393

PENTAGON PREEMPTION:

THE 5-SIDED LOSS OF STATE

ENERGY AND POWER

Steven Ferrey†

TABLE OF CONTENTS

I. Five Applications of Power Preemption ............................................. 394

II. The Inside Game – Keeping Power or Generations In-State;

‘Bright Lines’ of Preemption .............................................................. 396

A. Preemption Pentagon Side 1: States Setting Inflated

Wholesale Power Rates For Favored In-State Power .................. 397

1. California Feed-in Tariff Confronts the Supremacy Clause .. 397

2. The Inside Story .................................................................... 400

3. The Federal Power Act’s ‘Bright Line’ Between State and

Federal Jurisdiction ............................................................... 404

4. The Legal Shift in Power Transactions ................................. 407

B. Preemption Pentagon Side 2: The Geography of New Power ..... 410

1. The New State Offer and Potential Conflict with Federal

† Steven Ferrey is Professor of Law at Suffolk University Law School, and was Visiting Professor of

Law at Harvard Law School in 2003. Since 1993, Professor Ferrey served as a primary legal consultant to the

World Bank and the U.N. Development Program on their renewable and carbon reduction policies in

developing countries, where he worked extensively in Asia, Africa, and Latin America. He holds a B.A. in

Economics, a Juris Doctorate degree, and a Master’s degree in Urban and Regional Planning, and was a post-

doctoral Fulbright Fellow at the University of London between his two graduate degrees. He is the author of

seven books on energy and environmental law and policy, the most recent of which are UNLOCKING THE

GLOBAL WARMING TOOLBOX (2010), EXAMPLES AND EXPLANATIONS: ENVIRONMENTAL LAW (6th ed., 2012),

and THE LAW OF INDEPENDENT POWER (30th ed., 2013). He also is the author of more than 80 articles on

these topics. Professor Ferrey thanks his research assistant, Michael Attisha, for his research assistance with

recent case research.

Page 2: pentagon preemption: the 5-sided loss of state energy and power

394 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

Authority ............................................................................... 410

2. Maryland Inside Regulation .................................................. 412

3. New Jersey Inside Regulation ............................................... 414

4. Comparing Two Most Recent Federal Court

Preemption Decisions ............................................................ 417

C. Preemption Pentagon Side 3: Rights of First Refusal For

Incumbent In-State Power Transmission Companies .................. 419

1. FERC ORDER 1000.............................................................. 419

2. FERC Preemptive Authority ................................................. 421

3. State Refusals to Remove ROFR for In-State Incumbents .... 424

III. The Outside Energy Bar and Preemption of State Power ................... 426

A. Preemption Pentagon Side 4: Excluding Certain Power

Generation Facilities and Their Power from a State .................... 427

1. Wholesale Power Sale Price Constitutional Trip-Wires ........ 427

2. The Constitutional Line on Transmission and Renewable

Power Credits ........................................................................ 430

3. Transmission and Generation of High-Carbon Power ........... 432

B. Preemption Pentagon Side 5: The Rocky Mountain Divide on

Interstate Energy Commerce ....................................................... 435

1. The California Low Carbon Fuel Standard ........................... 435

2. Preemption of California Regulation? ................................... 437

IV. The Five-Sided Pentagon of Preemption ............................................ 441

I. FIVE APPLICATIONS OF POWER PREEMPTION

Orders from the federal courts now are striking state regulation of energy

and climate change technologies as constituting a violation of the U.S.

Constitution. Courts are declaring state regulation preempted under the

Supremacy Clause of the Constitution in five dimensions by constructing a

pentagon of preemption, which blocks some of the most important state

regulation in America.

Power is critically important technology. Electricity is the most

important “power.” Recently, electricity was identified as the second most

important invention in human history,1 with a delivered value of approximately

$375 billion annually in the U.S.2 This level of commerce exceeds the total

amount of corporate income taxes collected in the U.S in any year since the

1. James Fallows, The Fifty Greatest Breakthroughs Since the Wheel, ATLANTIC MONTHLY (Oct. 23,

2013, 7:08 PM), http://www.theatlantic.com/magazine/archive/2013/11/innovations-list/309536/.

2. The average delivered price of all electricity nationwide in 2011 was $0.0966/Kwh, and

$0.1109/Kwh for residential customers. Average Retail Price of Electricity to Ultimate Customers by End-Use

Sector, by State, Year-to-Date through February 2011 and 2010, PUB. POL’Y INST. N.Y. STATE,

http://ppinys.org/reports/jtf/2011/employ/average-retail-price-of-electricity2010-11.htm (last visited Oct. 6,

2014).

Page 3: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 395

creation of the corporate income tax.3 Unique among inventions, electricity

also is essential to operate seven of the other top fifty inventions of all time:

the Internet, computers, air-conditioning, radio, television, the telephone, and

semiconductors.4 Federal courts recently held that the states are legally

preempted from key efforts to regulate the structure of this most essential

aspect of the economy in five aspects.5 This article dissects and analyzes this

pentagon of preemption.

Not only is electricity unique in the modern economy, electric power is

treated differently by U.S. law from all other commerce in the United States,

pursuant to the Federal Power Act6 and the Supremacy Clause of the

Constitution.7 Seven federal courts in the past year, including the Supreme

Court,8 the federal circuit court of appeals,

9 federal trial courts,

10 plus the

Federal Energy Regulatory Commission (FERC),11

have ruled on

constitutional matters applicable to energy or utility regulation, with the vast

majority holding that states are acting unconstitutionally.12

In these cases, state

regulations were found to illegally cross a “bright line rule” established by

federal law and the Supremacy Clause of the Constitution.13

This pentagon of preemption has both “inside” and exterior dimensions:

A state regulatory “inside” game to favor in-state power, and an “outside” bar

to keep certain power outside the state. In the “inside” game, analyzed in

Section II of this article, states have attempted to keep power and its generation

in the state, attempting to:

Force private developers to site new unregulated wholesale power

generation technology inside their states,14

Provide greater financial regulatory incentives for certain power

3. Historical Amount of Revenue by Source, URBAN INST. & BROOKINGS INST. TAX POL’Y CTR. (Apr.

15, 2014), http://www.taxpolicycenter.org/taxfacts/displayafact.cfm?Docid=203.

4. Fallows, supra note 1.

5. See discussion infra Sections II and III (describing state’s attempts at keeping power in-state and

the preemption of state power, respectively).

6. 16 U.S.C. § 824 (2012).

7. See U.S. CONST. art. VI, cl. 2 (“This Constitution, and the Laws of the United States which shall be

made in Pursuance thereof; . . . [S]hall be the supreme Law of the Land; and the Judges in every State shall be

bound thereby, any Thing in the Constitution or Laws of any State to the Contrary notwithstanding.”).

8. Am. Trucking Ass’n. v. City of L.A., 133 S. Ct. 2069 (2013); City of Arlington v. FCC, 133 S. Ct.

1863 (2013).

9. Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 733 F.3d 393 (2d Cir. 2013); Ill. Commerce

Comm’n v. Fed. Energy Regulatory Comm’n, 721 F.3d 764 (7th Cir. 2013); Rocky Mountain Farmers Union

v. Corey, 730 F.3d 1070 (9th Cir. 2013).

10. PPL Energyplus, LLC v. Hanna, 977 F. Supp. 2d 372 (D.N.J. 2013); PPL Energyplus, LLC v.

Nazarian, 974 F. Supp. 2d 790 (D. Md. 2013); Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 838 F. Supp. 2d

183, 233 (D. Vt. 2012); Rocky Mountain Farmers Union v. Goldstene, 843 F. Supp. 2d 1071, 1099 (E.D. Cal.

2011).

11. Cal. Pub. Util. Comm’n, S. California Edison Co., Pac. Gas & Elec. Co., San Diego Gas & Elec.

Co., 132 FERC P 61047 (July 15, 2010).

12. Infra Section II and III.

13. Steven Ferrey, State Wars—The Empire Strikes Back: The Federal/State Constitutional Power

Confrontation, 65 BAYLOR L. REV. 1, 70 (2013).

14. Infra Section II B.

Page 4: pentagon preemption: the 5-sided loss of state energy and power

396 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

production technology in the state,15

and

Set above-market “feed-in” prices for the purchase of certain

renewable wholesale power generated in the state, simultaneously

compelling their regulated utilities and ratepayers to purchase this

more expensive power at these higher prices.16

The exterior state “outside” power bar, dissected and analyzed in detail in

Section III of this article, examines whether it is legally preempted when

certain states regulate:

Attempting to exclude certain power generation technologies from

their states,17

Burdening interstate transport of certain energy resources, while

advantaging in-state identical energy,18

and

Refusing payments for regional power transmission infrastructure to

move out-of-state renewable wind power to their states.19

Section IV draws analogies and conclusions on how the Supremacy

Clause of the Constitution has been the pivotal leverage in recent decisions of

federal courts to block a wide range of state regulation related to this second

most important invention of all time. This article analyzes why and how the

Supremacy Clause aligns federalist power over the U.S. energy future.

II. THE INSIDE GAME – KEEPING POWER OR GENERATIONS IN-STATE;

‘BRIGHT LINES’ OF PREEMPTION

Some states have attempted to promote select in-state power in preference

to other power or power created from other states. States can accomplish this

by manipulating the wholesale price of certain power. The reason for this is

either (a) to provide incentives typically for renewable power or other favored

power development, (b) to cause power generation facilities to locate in the

regulating state as opposed in other states, or (c) to favor in-state energy

production in lieu of the same energy traveling from out-of-state in interstate

commerce.

Each of these has recently been implemented by a different state:

California, New Jersey, Maryland, and Illinois.20

Each state regulation hit

initial legal roadblocks, with some still engaged in on-going litigation.21

15. Infra Section II C.

16. Infra Section II A.

17. Infra Section III B.

18. Infra Section III B.

19. Infra at Section III A.

20. Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 733 F.3d 393 (2d Cir. 2013); Ill. Commerce

Comm’n v. Fed. Regulatory Comm’n, 721 F.3d 764 (7th Cir. 2013); Rocky Mountain Farmers Union v.

Corey, 730 F.3d 1070 (9th Cir. 2013).

21. Entergy Nuclear Vt. Yankee, LLC, 733 F.3d at 393; Ill. Commerce Comm’n, 721 F.3d at 764; Rocky

Mountain Farmers Union, 730 F.3d at 1070.

Page 5: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 397

Preemption analysis pursuant to the Supremacy Clause of the U.S. Constitution

takes center stage in ongoing challenges, and each was declared

unconstitutional either by one of the courts hearing each of these challenges or

by the Federal Energy Regulatory Commission.22

A. Preemption Pentagon Side 1: States Setting Inflated Wholesale Power

Rates For Favored In-State Power

A few states have attempted to set above-market regulated prices for the

mandatory purchase of certain renewable or other wholesale power generated

in the state and compelled to be purchased by their regulated utilities at higher-

than-market prices.23

This went forward despite a robust treatment in the

literature warning states to be careful in setting wholesale rates.24

California,

to date, has been challenged and found to be acting illegally not only recently,

but also in prior similar regulation.25

1. California Feed-in Tariff Confronts the Supremacy Clause

California set inflated prices and terms for certain designated wholesale

power sales to regulated utilities to provide financial incentives for certain in-

state power, excluding eligibility for similar generation of out-of-state power.26

Only the federal government can establish wholesale power prices for power.27

After enacting a feed-in-tariff requiring California state utilities to make

wholesale power purchases at well in excess of market wholesale rates for

power and in excess of avoided costs,28

there was a challenge before the

22. Entergy Nuclear Vt. Yankee, LLC, 733 F.3d at 393; Ill. Commerce Comm’n, 721 F.3d at 764; Rocky

Mountain Farmers Union, 730 F.3d at 1070.

23. CAL. PUB. UTIL. CODE § 399.20 (2013); N. IND. PUB. SERV. CO., SECOND REVISED SHEET NO. 104,

EXPERIMENTAL RATE 665 RENEWABLE FEED-IN TARIFF (2011).

24. See generally Steven Ferrey et al., Fire and Ice: World Renewable Energy and Carbon Control

Mechanisms Confront Constitutional Barriers, 20 DUKE ENVTL. L. & POL’Y F. 125, 142 (2010) (“[T]he

wholesale power buyback rates ‘capture only a fraction’ of the environmental and distributed benefits of

deployment of the technology to society.”); Steven Ferrey et al., FiT in the U.S.A., PUB. UTILS. FORTNIGHTLY

60, 63 (2010) (noting that the states moving forward with FITs will face the long reach of the Constitution,

which controls states acting in a regulatory rather than proprietary manner); Steven Ferrey, Follow the Money!

Article I and Article VI Constitutional Barriers to Renewable Energy in the U.S. Future, 17 VA. J.L. & TECH

89, 114 (2012) (“Attempts by states indirectly or directly to promote higher wholesale energy prices for certain

renewable energy projects have been consistently stricken by the courts and by FERC.”); Steven Ferrey,

Goblets of Fire: State Programs on Global Warming and the Constitution, 34 ECOLOGY L.Q. 835, 840 (2009)

(“Wholesale power cannot enter without penalty . . . .”); Steven Ferrey, Shaping American Power: Federal

Preemption and Technological Change, 11 VA. J. L. & TECH. 47, 49 (1991) (explaining that “[t]he interstate

wholesale power sale is the element of a utility’s operations that triggers federal, rather than state, regulatory

jurisdiction.”); Brian Potts, Regulating Greenhouse Gas ‘Leakage’: How California Can Evade the Impending

Constitutional Attacks, 19 ELEC. J. 43, 44 (2006) (“[B]ecause of these two Constitutional issues, courts are

likely to strike down many or all of their proposals.”).

25. Cal. Pub. Util. Comm’n, S. Cal. Edison Co., Pac. Gas & Elec. Co., San Diego Gas & Elec. Co., 132

FERC P 61047, ¶¶ 64–72 (July 15, 2010).

26. CAL. PUB. UTIL CODE § 399.20 (2013).

27. Infra Section III A 2.

28. FERC Conservation of Power and Water Resources, 18 C.F.R. § 292.304(e) (2014). See also 18

C.F.R. § 292.101(b)(6) (2014) (defining “avoided cost” as “the incremental costs to an electric utility of

electric energy or capacity or both which, but for the purchase from the qualifying facility or qualifying

Page 6: pentagon preemption: the 5-sided loss of state energy and power

398 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

Federal Energy Regulatory Commission as to whether this state regulation

violated the Federal Power Act and the Supremacy Clause of the U.S.

Constitution.29

California argued that its environmental purpose for regulation

should make it exempt from preemption in setting above-market wholesale

feed-in renewable tariff rates for cogeneration facilities of less than 20 Mw and

that environmental costs could be considered to inflate avoided costs.30

The

affected utilities countered that federal law does not allow state regulation of

wholesale sales to achieve state environmental goals, that federal preemption

cannot be avoided based on an environmental purpose of the preempted state

regulation, and states may not, under the guise of environmental regulation,

adopt an economic regulation that requires purchases of electricity at a

wholesale price outside the framework of the Federal Power Act, or if acting

under PURPA, at a price that exceeds avoided cost.31

FERC did not agree that a state may set a state feed-in tariffs, and held

that wholesale generators can receive no more than system-wide avoided cost

for power sales: “even if a QF has been exempted pursuant to the

Commission’s regulations from the ratemaking provisions of the Federal

Power Act, a state still cannot impose a ratemaking regime inconsistent with

the requirements of PURPA and this Commission’s regulations—i.e., a state

cannot impose rates in excess of avoided cost.”32

FERC rejected all of

California’s arguments regarding any environmental rationales for wholesale

rates in excess of limits under federal law or FERC ion.33

After losing before FERC, California moved for FERC rehearing, or in

the alternative a clarification, of this FERC order.34

While FERC dismissed a

rehearing of whether California had authority over federally preempted

wholesale power sale rates,35

FERC did issue a clarification that the avoided

costs determined by states only for a Qualifying Facility (“QF”) selling power

to the utility could be determined with respect to actual costs incurred by the

purchasing electric utility, and reflecting requirements or restrictions imposed

under state law on the technologies eligible, thus yielding different tariffs for

different technologies subject to state law supply mix requirements.36

This

clarified that a state can utilize its long-standing authority to specify what mix

of power generation technologies a regulated utility should procure going

forward.37

Therefore, a state could require that a certain amount of a specific

type of power output required to be procured by a regulated private utility.

facilities, such utility would generate itself or purchase from another source.”).

29. Cal. Pub. Utils. Comm’n, 132 FERC P at ¶¶ 56–72.

30. Id.

31. Id.

32. Id.

33. Id.

34. Cal. Pub. Utils. Comm’n, S. Cal. Edison Co., Pac. Gas and Elec. Co., San Diego Gas & Elec. Co.,

133 FERC P 61059 (Oct. 21, 2010).

35. Id. at ¶¶ 15, 19.

36. Id. at ¶ 20.

37. Id.

Page 7: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 399

FERC turned down California’s argument that avoided cost did not have

to be the lowest cost for procurement of a particular type or technology of

power resource.38

The avoided cost that a utility would be ordered to pay for

wholesale power, subject to state technology supply requirements imposed on

regulated utilities and retail suppliers, would be the cost at which the particular purchasing utility could either itself construct or purchase such type of

power.39

This is still a real limitation pursuant to the Federal Power Act and

the Filed Rate Doctrine applying the Supremacy Clause of the Constitution, as

this PURPA avoided cost cannot exceed the most cost-effective power

purchase avoided by the utility finding the best option for the mandated type of

power to its grid.40

These 2010-2011 FERC opinions regarding California’s feed-in tariff

clarify issues in FERC’s 1995 decision,41

to the effect that different

technologies could be subject to different avoided costs, if and only if the

amount, location, and “ability to sell to the utility” for these technologies is

differentially set forth by state law.42

However, no state with a feed-in tariff

had taken such steps or done such a detailed determination when FERC issued

its 2010-2011 opinions.43

California, in fact, had not justified its feed-in tariff

as even an approximation of avoided cost or as implemented under its

federally-delegated authority under PURPA.44

Instead, it justified its feed-in

tariff “to encourage cogeneration by requiring utilities to sign contracts . . . .”45

The California FERC decision establishes precedent beyond the particular

cogeneration technologies at issue in that law and extends to any state power

feed-in tariffs.46

In its two California decisions, FERC refused California’s

request to agree that facilities interconnected at the distribution level, rather

38. Id. at ¶ 13.

39. FERC Conservation of Power and Water Resources, 18 C.F.R. § 292.304(e) (2014).

40. Cal. Pub. Utils. Comm’n, 133 FERC P at ¶ 31 (citing Southern Cal. Edison, San Diego Gas & Elec.

Co., 71 FERC P 61269, (1995)). This doesn’t mean that a state could not justify avoided cost “adders” to the

base price which utilities would be ordered to pay for wholesale power, but that it must do so more precisely

than picking an arbitrary uniform state value that ignores actual transmission and distribution system costs and

benefits. FERC reaffirmed its prohibition of additions to avoided costs that reflect general environmental

externality bonuses or “adders,” unless they “. . . are real costs that would be incurred by utilities.” Id. A state

could quantify the distinct benefits for transmission, distribution, reliability, capacity, peak-time availability,

line losses avoided for the system, length of commitment, and other factors for specific transmission locations

and nodes.

41. S. Cal. Edison, San Diego Gas & Elec. Co., 71 FERC P 61269, 62078 (1995).

42. Cal. Pub. Utils. Comm’n, 133 FERC P at ¶¶ 28, 30.

43. Id. For example, in the disputed matter, California had added an arbitrary 10% bonus or adder for

all combined heat and power facilities as a non-specific transmission system proxy value “for every kilowatt

hour delivered to the electrical grid . . . at a price determined by the Commission.” Id. at ¶ 4. In the U.S.

transmission and distribution system, the cost savings and value of distributed power is distinct and not

uniform. See Massimo Filippini & Jorg Wild, Regional Differences in Electricity Distribution Costs and their

Consequences for Yardstick Regulation of Access Prices, CTR. FOR ENERGY POL’Y & ECON. (May 2000),

http://www.cepe.ethz.ch/publications/Filippini_lugano.pdf (explaining the regional differences in electricity

transmissions).

44. Cal. Pub. Utils. Comm’n, 133 FERC P at ¶ 5.

45. Id. at ¶ 6.

46. See David P. Yaffe, Are State Renewable Feed-In Tariff Initiatives Truly Throttled by Federal

Statutes After the FERC California Decision?, 23 ELEC. J. 9, 11 (2010) (explaining the consequences of the

California FERC decision on other states).

Page 8: pentagon preemption: the 5-sided loss of state energy and power

400 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

than the transmission level, are beyond FERC’s authority.47

Instead, FERC

reaffirmed that FERC has “exclusive jurisdiction”48

regardless of location

geographically and whether on the transmission or lower voltage system was

not legally relevant to exclusive FERC jurisdiction over all wholesale power

sales.49

2. The Inside Story

State regulation of electric power does not occur ad hoc. As one of the

last regulated industries in the U.S., state regulation occurs by legislation and a

quasi-judicial process at the state public utility commissions.50

In this instance,

California was seeking to subsidize and provide financial incentives for the

development of certain kinds of power development on a distributed basis in

California. Legally, it could have done that with tax subsidies,51

but did not.

California also has adopted renewable portfolio standards52

but wanted to add

additional financial incentives. The feed-in tariff (“FiT”) that California

mandated provided additional subsidies to certain projects without doing so

through the transparent mechanism of a tax subsidy.53

Instead, costs were

invisibly imposed on all utility ratepayers who are required to reimburse

utilities’ power acquisition expenses, which were required to be under the FiT

more than the market price of power.54

In California, it actually was not these affected utilities or their ratepayers

which initiated legal review of this FiT scheme. Rather, it was the state of

California, itself, which initiated review at FERC, attempting to overturn past

decisions holding that California did not have authority to set wholesale

prices.55

California raised several legal arguments as to why existing

precedent did not apply.

First, the California Attorney General, representing the state, argued that

the state mandating that regulated utilities only “offer” to purchase wholesale

power at substantially above wholesale market rates, is different than a

requirement to actually “purchase” the sold power.56

California was not

successful arguing that it was regulating only the buyers of power and not the

sellers of power in the transaction.57

This argument was held unpersuasive by

47. Cal. Pub. Utils. Comm’n, 132 FERC P at ¶ 72.

48. See id. at ¶ 72 (citing FPC v. S. Cal. Edison Co., 376 U.S. 205 (1964)).

49. Id. at ¶ 72.

50. See STEVEN FERREY, ENVIRONMENTAL LAW: EXAMPLES & EXPLANATIONS 579–81 (Wolters

Kluwer 6th ed. 2012) (explaining the regulation of the electricity industry).

51. See STEVEN FERREY, LAW OF INDEPENDENT POWER, Tables 3.13, 3.15, 3.19 (Reuters 2013)

(providing more information on tax subsidies).

52. Steven Ferrey, Threading the Constitutional Needle with Care, 7 U. TEX. J. OIL, GAS & ENERGY L.

59, 116 (2012).

53. See Cal. Pub. Utils. Comm’n, 132 FERC P at ¶ 70 (holding that the CPUS may not, in

implementing the feed-in tariff program, charge rates that are above “the purchasing utility’s avoided cost”).

54. Id. at ¶ 3.

55. Id. at ¶ 4.

56. Id. at ¶ 5.

57. Id. at ¶ 72; see also, Teresa Morton & Jeffrey Peabody, Feed-in Tariffs: Misfits in the Federal and

State Regulatory Regime?, 23 ELEC. J. 17, 20–22 (2010) (discussing the California FiT decision).

Page 9: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 401

FERC.58

It held that FERC’s authority under the Federal Power Act includes

the exclusive jurisdiction to regulate the rates, terms and conditions of sales for

resale of electric energy in interstate commerce, and preempts any state

authority.59

Second, California argued that its environmentally beneficial purposes

should make it exempt from preemption of its authority in setting non-market-

conforming wholesale rates for a state FiT.60

FERC found state purpose to not

permit illegal establishment of FiTs requiring purchases of electricity at

inflated wholesale prices,61

and renewable wholesale generators could receive

no more than fair wholesale market prices under federal law.62

FERC

reiterated that only the federal government can regulate commerce between the

states, and California cannot attempt to regulate commerce outside its

borders.63

This final extra-territorial limitation on California energy regulation

arose again on the fifth side of the preemption pentagon when California

regulated liquid renewable fuels.64

The 2010-2011 FERC articulation of the

total lack of state authority over wholesale power sale policy was nothing new,

but the reemphasis of the basic jurisdictional lines since the beginning of

power and its regulation 75 years ago:

FERC’s [FiT] Order did not create a new policy dilemma; it simply reminded California and the states that the states’ rights to establish policy concerning electric generation resource selection does not include power to impose prices under state law where sale of electricity for resale and any form of interstate transmission are involved.

65

Third, California argued that past judicial and FERC precedent in similar

California matters should no longer apply, because of the new emphasis on

addressing climate change. There was precedent regarding California

decisions fifteen years earlier preempting certain California clean energy

regulation altering wholesale renewable prices. In Independent Energy Producers Ass’n, 36 F.3d 848 (9th Cir. 1994), the California state utility

commission authorized utilities to suspend payment to renewable power-

selling Qualifying Facilities (QFs) if the utility found that the QF did not

comply with federal standards, and substitute a 20% lower, alternative power

58. Cal. Pub. Utils. Comm’n, 132 FERC P at ¶ 72.

59. Id. at ¶ 72; see 16 U.S.C. § 824(d)–(e) (2012) (defining terms); see, e.g., Miss. Power & Light Co.

v. Miss. ex rel. Moore, 487 U.S. 354, 366–69 (1988) (explaining the law in Mississippi).

60. Cal. Pub. Utils. Comm’n, 132 FERC P at ¶ 5.

61. Id. at ¶¶ 17–18. FERC rejected all of California’s arguments regarding generic environmental

rationales for wholesale rates in excess of limits under federal law or set by FERC. Id. at ¶ 70.

62. Id.

63. Id. at ¶ 72. FERC also reaffirmed that since a state cannot add a bonus or “adder” to the tariff that

is not real and actually incurred by the buying utility, a bonus can be supplied “outside the confines of, and, in

addition to the PURPA avoided cost rate, through the creation of renewable energy credits (RECs).” Cal. Pub.

Utils. Comm’n S. Cal. Edison Co. Pac. Gas & Elec. Co. San Diego Gas & Elec. Co., 133 FERC P 61059, ¶ 31

(Oct. 21, 2010).

64. See infra Section III B (discussing the preemption pentagon).

65. Yaffe, supra note 46, at 12.

Page 10: pentagon preemption: the 5-sided loss of state energy and power

402 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

purchase rate.66

In this prior case, the court stated that the rate paid by utilities

for electricity must be determined by calculating the federally-specified

avoided cost that the utility would pay if it had to purchase electricity outside

the renewable QF contract price.67

The court also commented that federal

PURPA full avoided cost rates are the “statutory ceiling.”68

Thus, the federal

wholesale power sale rate could not be altered by state legislation or state

regulatory action.

Going the other direction on power purchase rates—increasing them as

FiTs do, rather than reducing them—raising renewable energy prices as an

incentive to the power producer was previously stricken in California. Fifteen

years before the 2010-2011 case, in Southern California Edison Company, San Diego Gas & Electric,

69 FERC refused to sanction a higher California price for

renewable power supply. The California PUC had ordered two of its investor-

owned and regulated utilities to sign long-term fixed-price contracts with

renewable QF power sellers to purchase electricity at prices that were

competitive with what it cost for the developer move forward on a renewable

energy project, but nonetheless in excess of the utilities’ avoided cost and/or

the price of wholesale power in the market.70

Edison, one of the affected

utilities, had wholesale electricity supply options available for purchase at

$0.04 per kWh or less, while the PUC required purchase of renewable power at

prices as high as $0.066 per kWh.71

After losing before FERC, California

moved for FERC rehearing, or in the alternative a clarification, of this FERC

order.72

Under the filed-rate doctrine, any dispute about these matters may not

be arbitrated by the state, but is reserved exclusively to federal authority.73

Having lost this 1994 decision in the federal court of appeals on a similar

effort by California to establish a wholesale price beyond that allowed by

FERC, the 2010 action by FERC replayed this previously stricken state action.

The California 2010-vintage feed-in tariffs contain a price premium for

renewable power substantially greater than this earlier 1994 50% premium.74

In the recent 2010-2011 California decision, FERC rejected California’s

argument that prior legal precedent no longer applied because California now

sought to address climate change, and made it clear that PURPA does not

permit either the FERC or the states to require a wholesale power purchase rate

which exceeds the utilities’ avoided cost.75

This legal requirement does not

66. Indep. Energy Producers Ass’n v. Cal. Pub. Utils. Comm’n, 36 F.3d 848, 853 (9th Cir. 1994).

67. Id. at 858.

68. Id.

69. S. Cal. Edison, San Diego Gas & Elec. Co., 70 FERC P 61215 (Feb. 23, 1995) (Order on Petitions

for Enforcement Action Pursuant to Section 210(h) of PURPA).

70. Id.

71. Id.

72. Cal. Pub. Utils. Comm’n, S. Cal. Edison Co., Pac. Gas & Elec. Co., San Diego Gas & Elec. Co.,

133 FERC P 61059 (Oct. 21, 2010).

73. Miss. Power & Light Co. v. Miss. ex rel. Moore, 487 U.S. 354, 371 (1988) (“FERC has exclusive

authority to determine the reasonableness of wholesale rates.”).

74. Cal. Pub. Util. Comm’n S. California Edison Co. Pac. Gas & Elec. Co. San Diego Gas & Elec. Co.,

132 FERC P 61047, ¶ 31 (July 15, 2010).

75. 18 C.F.R. § 292.101(b)(6) (1994) (defining avoided cost as “the incremental costs to an electric

Page 11: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 403

apparently change because of environmental or climate change goals: “[a]s the

electric utility industry becomes increasingly competitive, the need to ensure

that the states are using procedures which ensure that QF rates do not exceed

avoided cost becomes more critical.”76

The Ninth Circuit Court of Appeals agreed in deciding a recent California

case.77

The court ruled that Congress did not intend that the scope of FERC’s

jurisdiction over the interstate sale of electricity at wholesale be determined by

a case-by-case analysis of the impact of state regulation on national interests.78

Moreover, while addressing state/local environmental regulation, the Supreme

Court held that federal law is preemptive of state and local law.79

In 2013, the

Supreme Court held that a city in California was preempted by the Federal

Aviation Administration Act of 1994 from imposing additional regulation on

diesel truck emissions for those trucks that accessed the port.80

California’s arguments that its motivations or rationales were entitled to

special status, were not successful before the courts or FERC. In the six

California matters discussed in this section that articulate the borders of federal

and state authority over energy and environmental matters, federal authority

preempted state authority in five of these cases,81

and the sixth was

utility of electric energy or capacity or both which, but for the purchase from the qualifying facility or

qualifying facilities, such utility would generate itself or purchase from another source.”).

76. Cal. Edison Co., San Diego Gas & Electric Co., 70 FERC P 61215 at ¶¶ 61675–76.

77. Pub. Util. Dist. No. 1 of Snohomish Cnty. Wash. v. Fed. Energy Regulatory Comm’n, 471 F.3d

1053, 1066 (9th Cir. 2006). While this decision proceeded on appeal to the U.S. Supreme Court, Morgan

Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty. Wash., 554 U.S. 527 (2008), and

thereafter was remanded to FERC for more clarification, its holding was not overturned before the Supreme

Court: The judgment below is nonetheless affirmed on alternative grounds, based on two defects in FERC’s analysis. First, the analysis was flawed or incomplete to the extent FERC looked simply to whether consumers’ rates increased immediately upon conclusion of the relevant contracts, rather than determining whether the contracts imposed an excessive burden “down the line,” relative to the rates consumers could have obtained (but for the contracts) after elimination of the dysfunctional market. Sierra’s “excessive burden” on customers was the current burden, not just the burden imposed at the contract’s outset. See [Federal Power Comm’n v. Sierra Pac. Power Co., 350 U.S. 348 (1956)]. Second, it is unclear from FERC’s orders whether it found respondents’ evidence inadequate to support their claim that petitioners engaged in unlawful market manipulation that altered the playing field for contract negotiations. In such a case, FERC should not presume that a contract is just and reasonable. Like fraud and duress, unlawful market activity directly affecting contract negotiations eliminates the premise on which the Mobile-Sierra presumption rests: that the contract rates are the product of fair, arms-length negotiations. On remand, FERC should amplify or clarify its findings on these two points.

Morgan Stanley Capital Grp. Inc., 554 U.S. at 528.

78. Fed. Power Comm’n v. S. Cal. Edison Co., 376 U.S. 205, 215 (1964) (“Our decisions have squarely

rejected the view of the Court of Appeals that the scope of FPC jurisdiction over interstate sales of gas or

electricity at wholesale is to be determined by a case-by-case analysis of the impact of state regulation upon

the national interest.”); Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash., 471 F.3d at 1065 (“FERC tempered

this expectation by promising to ‘continue our case-by-case approach’ to granting market –based rate

authority. . . . FERC’s ‘case-by-case approach’ includes ensuring that sellers seeking market-based rate

authority lack, or have sufficiently mitigated, market power and that FERC has a sufficient ‘means of

monitoring the market in which [the seller’s] sales will take place.’”).

79. Cal. Coastal Comm’n v. Granite Rock Co., 480 U.S. 572, 580 (1987) (“[T]he State is free to

enforce its criminal and civil laws on federal land so long as those laws do not conflict with federal law.”).

80. Am. Trucking Ass’n, Inc. v. City of L.A., 133 S. Ct. 2096 (2013).

81. Id.; Morgan Stanley Capital Grp. Inc., 554 U.S. at 545 (“There is only one statutory standard for

assessing wholesale electricity rates, whether set by contract or tariff–the just-and-reasonable standard. The

Page 12: pentagon preemption: the 5-sided loss of state energy and power

404 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

procedurally dismissed, without reaching the merits, because of a lack of

subject matter jurisdiction. Three of the six decisions were rendered by the

U.S. Supreme Court.82

This first side of the preemption pentagon is constructed from more than

75 years of consistent Supreme Court interpretation of the Supremacy Clause83

and the Federal Power Act. A ‘bright line’ demarcates this side of preemption,

with no exceptions, despite California’s arguments, and no case-by-case

analysis of exceptions to the rule. Any regulation of the price or terms of any

wholesale power sales are not within any state power: Even when states

determine avoided cost, states are acting as delegates of federal authority, not

exercising any independent authority over wholesale prices.84

3. The Federal Power Act’s ‘Bright Line’ Between State and Federal

Jurisdiction

This first side of the preemption pentagon is meant by federal law to

establish a ‘bright line’ between federal and state authority regarding energy

regulation. The 2010–2011 California FERC decision conforms with seventy-

five years of authority under the Federal Power Act, which directs FERC to

regulate all interstate electricity transmission and to ensure the reliability of the

national electricity grid.85

The Federal Power Act sections 205 and 20686

empower FERC exclusively to regulate rates for the interstate and wholesale

plain text of the FPA states that ‘all rates . . . shall be just and reasonable. 16 U.S.C. § 824d(a).”); Fed. Power

Comm’n, 376 U.S. at 215 (“We hold that section 201(b) of the Federal Power Act grants the FPC jurisdiction

of all sales of electric energy at wholesale in interstate commerce not expressly exempted by the Act

itself . . . .”); Indep. Energy Producers Ass’n v. Cal. Pub. Utils. Comm’n, 36 F.3d 848, 853–54 (9th Cir. 1994)

(“The structure of PURPA and the Commission’s regulations, reflect Congress’s express intent that the

Commission exercise exclusive authority over QF status determinations.”); S. Cal. Edison Co., San Diego Gas

& Electric Co., 70 FERC P 61215 (1995) (finding that the California program at issue violates PURPA); see

also Cal. Pub. Util. Comm’n., 133 FERC P at ¶ 5 (FERC Order Granting Clarification and Dismissing

Rehearing) (noting that the Federal Energy Regulatory Commission found that the California Public Utilities

Commission’s (CPUC) decision to required California utilities to offer a certain price to CHP generating

facilities of 20 MW or less that meet energy efficiency and environmental compliance requirements would not

be preempted by the FPA, PURPA, or Commission regulations, as long as the program meets certain

requirements).

82. Am. Trucking Ass’n, Inc. v. City of L.A., 133 S. Ct. 2096 (2013); see Morgan Stanley Capital Grp.

Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash., 554 U.S. 527, 545 (2008) (“There is only one

statutory standard for assessing wholesale electricity rates, whether set by contract or tariff – the just-and-

reasonable standard. The plain text of the FPA states that ‘all rates . . . shall be just and reasonable. 16 U.S.C. §

824d(a).”); Fed. Power Comm’n, 376 U.S. at 215 (“We hold that section 201(b) of the Federal Power Act

grants the FPC jurisdiction of all sales of electric energy at wholesale in interstate commerce not expressly

exempted by the Act itself . . . .”).

83. This began with the Supreme Court decision in Pub. Utils. Comm’n v. Attleboro Steam & Elec. Co.,

273 U.S. 83, 90 (1927) (“[T]he paramount interest in the interstate business carried on between the two

companies is not local or either state, but is essentially national in character. The rate is therefore not subject to

regulation by either of the two states in the guise of protection to their respective local interests; but, if such

regulation is required it can only be attained by the exercise of the power vested in Congress[,]” which inspired

the Federal Power Act a few years later.).

84. FERREY, supra note 50, at 4-102.2–4-102.3.

85. 16 U.S.C. §§ 202, 209 (2012); 16 U.S.C. § 824(h) (1935); 16 U.S.C. § 824(a)–(a)(2) (1978), 16

U.S.C. § 797 (2005).

86. 16 U.S.C. § 824d (1978); 16 U.S.C. § 824e (2005).

Page 13: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 405

sale and transmission of electricity.87

FERC case law exerts exclusive

jurisdiction over the “transmission of electric energy in interstate commerce,”

over the “sale of electric energy at wholesale in interstate commerce,” and over

“all facilities for such transmission or sale of electric energy.”88

The U.S. Supreme Court held that Congress meant to draw a “bright

line,” easily ascertained and not requiring case-by-case analysis, between state

and federal jurisdiction.89

When a transaction is subject to exclusive federal

FERC jurisdiction and regulation, state regulation is preempted as a matter of

federal law and the U.S. Constitution’s Supremacy Clause, according to a

long-standing and consistent line of rulings by the U.S. Supreme Court.90

The

rates, terms, and provisions of any wholesale sale or transmission of electricity

in interstate commerce are exclusively within federal jurisdiction and control,

not state authority, under the Federal Power Act, according to U.S. Supreme

Court:91

“FERC has exclusive authority to set and to determine the

87. Pub. Util. Dist. No. 1 of Snohomish Cnty. Wash. v. FERC, 471 F.3d 1053, 1058 (“The

Commission’s jurisdiction covers the ‘transmission of electric energy in interstate commerce and the sale of

such energy at wholesale in interstate commerce.”), remanded to 547 F.3d 1081 (9th Cir. 2008); aff’d in part

and rev’d in part sub nom; Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1, 554 U.S. 527, 557

(2008) (“The Court purports to acknowledge that ‘[t]here is only one statutory standard for assessing

wholesale-electricity rates, whether set by contract or tariff–the just-and-reasonable standard.’”)

88. 16 U.S.C. § 824(b) (2012). The following cases provide examples of the scope of FERC’s

jurisdictional reach: Aquila Merch. Servs, Inc., 125 FERC P 61175, ¶ 17 (2008); Entergy Servs, Inc., 120

FERC P 61020, ¶ 28 (2007); Midwest Indep. Transmission Sys. Operator, Inc., 106 FERC P 61337, ¶ 14 &

n.17 (2004); S. Cal. Edison Co., 106 FERC P 61183, ¶¶ 14, 19 (2004); Virginia Elec. Power Co, 103 FERC P

61109, ¶ 6 (2003); Barton Vill., Inc. v. Citizens Util. Co., 100 FERC P 61244, ¶ 12 (2002); Niagara Mohawk

Power Corp., 100 FERC P 61019, ¶ 17 (2002); Armstrong Energy Ltd. P’ship., LLP, 99 FERC P 61024, 61104

(2002); Progress Energy, Inc., 97 FERC P 61141, 61628 (2001); Cent. Vt. Pub. Serv. Corp., 84 FERC P

61194, 61973–75 (1998); Conn. Light & Power Co. 70 FERC P 61012, 61030, appeal denied, 71 FERC P

61035 (1995); N. Ind. Pub. Servs. Co., 66 FERC P 61213, 61488 (1994); Houlton Water Co. v. Maine Pub.

Servs. Co., 60 FERC P 61141, 61515 (1992); Fl. Power & Light Co., 40 FERC P 61045, 61120-21, appeal

denied, 41 FERC P 61153, 61382 (1987); S. Co. Servs, Inc., 37 FERC P 61256, 61652 (1986); Penn. Power &

Light Co., 23 FERC P 61006, 61018, appeal denied, 23 FERC P 61325 (1983).

89. Fed. Power Comm’n v. S. Cal. Edison Co., 376 U.S. 205, 215–16 (1964) (“Our decisions have

squarely rejected the view of the Court of Appeals that the scope of FPC jurisdiction over interstate sales of

gas or electricity at wholesale is to be determined by a case-by-case analysis of the impact of state regulation

upon the national interest.”).

90. See New England Power Co. v. New Hampshire, 455 U.S. 331, 338 (1982). The Supreme Court

overturned an order of the New Hampshire Public Utilities Commission which restrained within the state, for

the financial advantage of in-state ratepayers, low-cost hydroelectric energy produced within the state: “Our

cases consistently have held that the Commerce Clause of the Constitution, Art. I, § 8, cl. 13, precludes a state

from mandating that its residents be given a preferred right of access, over out-of-state consumers, to natural

resources located within its borders or to the products derived therefrom.” Id. at 338. See also Entergy La.,

Inc. v. La. Pub. Serv. Comm’n, 539 U.S. 39, 47 (2003) (“The filed rate doctrine requires ‘that interstate power

rates filed with FERC or fixed by FERC must be given binding effect by state utility commissions determining

intrastate rates.’. . . When the filed rate doctrine applies to state regulators, it does so as a matter of federal pre-

emption through the Supremacy Clause.”); Miss. Power & Light Co. v. Miss. ex rel. Moore, 487 U.S. 354, 371

(1988) (“FERC has exclusive authority to determine the reasonableness of wholesale rates.”); Nantahala

Power & Light Co. v. Thornburg, 476 U.S. 953, 966 (1986) (“FERC clearly has exclusive jurisdiction over the

rates to be charged Nantahala’s interstate wholesale customers.”); Montana-Dakota Co. v. Pub. Serv. Comm’n,

341 U.S. 246, 251 (1951) (“Section 317 of Federal Power Act in its present form confers on the district court

of the United States exclusive jurisdiction of violations of this Act or the rules, regulation, and orders

thereunder, and of all suits in equity . . . .”).

91. New England Power, 455 U.S. at 340 (“Congress enacted Part II of the Federal Power Act . . .

which delegated to the Federal Power Commission, now the Federal Energy Regulatory Commission,

exclusive authority to regulate the transmission and sale at wholesale of electric energy in interstate commerce,

Page 14: pentagon preemption: the 5-sided loss of state energy and power

406 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

reasonableness of wholesale rates.”92

The Federal Power Act defines “sale at

wholesale” as any sale to any person for resale.93

The Congress in the Federal Power Act “adopt[ed] the test developed in

the Attleboro line [of cases] which denied state power to regulate a sale ‘at

wholesale to local distributing companies’ and allowed state regulation of a

sale at ‘local retail rates to ultimate consumers.’”94

Wholesale rates for sales in

interstate commerce are wholly beyond any state authority.95

If states impose a

rate in excess of avoided cost by either “law or policy,” with avoided cost

being the only wholesale power sale rate that states can set as delegates of

federal authority, the “contracts will be considered to be void ab initio.”96

The

rates, terms, and provisions of any wholesale sale, or transmission of electricity

in interstate commerce, are exclusively within federal jurisdiction and control,

not state authority, pursuant to the Federal Power Act:97

“FERC has exclusive

authority to determine the reasonableness of wholesale rates.”98

The U.S. Supreme Court held that Congress meant to draw a “bright

line,” easily ascertained and not requiring case-by-case analysis, between state

without regard to the source of production.”).

92. Morgan Stanley Capital Grp. Inc., 554 U.S. at 545 (“There is only one statutory standard for

assessing wholesale electricity rates, whether set by contract or tariff–the just-and-reasonable standard. The

plain text of the FPA states that ‘[a]ll rates . . . shall be just and reasonable.’ 16 U.S.C. § 824d(a)”); Miss.

Power & Light Co., 487 U.S. at 371 (“FERC has exclusive authority to determine the reasonableness of

wholesale rates.”); Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash. v. FERC, 471 F.3d 1053, 1066 (9th Cir.

2006) (“FERC’s jurisdiction to determine the reasonableness of wholesale rates is exclusive.”), remanded to

547 F.3d 1081 (9th Cir. 2008).

93. 16 U.S.C § 201(d) (“The term ‘sale of electric energy at wholesale’ when used in this Part means a

sale of electric energy to any person for resale.”); see also 16 U.S.C. § 824d (2012).

94. Fed. Power Comm’n, 376 U.S. at 214.

95. Indep. Energy Producers Ass’n v. Cal. Pub. Utils. Comm’n, 36 F.3d 848, 859 (9th Cir. 1994) (“We

conclude that the CPUC program is preempted by PURPA insofar as it authorizes the Utilities to determine

that a QF is not in compliance with the Commission’s operating and efficiency standards and to impose a

reduced avoided cost rate on that QF.”); S. Cal. Edison Co., San Diego Gas & Electric Co., 70 FERC P 61215

(1995) (“PUPRA expressly directed this Commission, and not the states, to prescribe rules governing QF rates.

PURPA gave the states responsibility for ‘implement[ing]’ the statute and the Commission’s rules. As a result,

a state may prescribe a particular per unit charge only if the process if it uses to establish the per unit charge is

in accordance with the Commission’s rules.”).

96. Conn. Light and Power Co., 70 FERC P 61012 at 61029–30 (1995) (“[I]f parties are required by

state law or policy to sign contracts that reflect rates for QF sales at wholesale that are in excess of avoided

cost, those contracts will be considered to be void ab initio.”).

97. New England Power Co. v. New Hampshire, 455 U.S. 331, 340 (1982) (“Congress enacted Part II of the Federal Power Act . . . which delegated to the Federal Power Commission, now the Federal Energy Regulatory Commission, exclusive authority to regulate the transmission and sale at wholesale of electric energy in interstate commerce, without regard to the source of production . . . . The 1935 enactment was a ‘direct result’ of this Court’s holding in Pub. Utilities Comm’n v. Attleboro Steam & Electric Co., . . . that the states lacked power to regulate the rates governing interstate sales of electricity for resale.”).

98. See Miss. Power & Light Co. v. Miss. ex rel. Moore, 487 U.S. 354, 371 (1988) (“FERC has

exclusive authority to determine the reasonableness of wholesale rates.”); Pub. Util. Dist. No. 1 of Snohomish

Cnty., Wash. v. Fed, Energy Regulatory Comm’n, 471 F.3d 1053, 1066 (9th Cir. 2006) (“FERC’s jurisdiction

to determine the reasonableness of wholesale rates is exclusive.”), remanded to 547 F.3d 1081 (9th Cir. 2008);

Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash., 554 U.S. 527, 545

(2008) (“There is only one statutory standard for assessing wholesale electricity rates, whether set by contract

or tariff – the just-and-reasonable standard. The plain text of the FPA states that ‘all rates . . . shall be just and

reasonable.” (citing 16 U.S.C. § 824d(a))).

Page 15: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 407

and federal jurisdiction.99

Power moves interstate constantly pursuant to

federal law: The U.S. Supreme Court held that “it is difficult to conceive of a

more basic element of interstate commerce than electric energy, a product used

in virtually every home and every commercial or manufacturing facility.100

No

State relies solely on its own resources in this respect.”101

Moreover, the

courts have determined that electrons in interstate commerce cannot be traced,

although we know that they move effortlessly interstate through the very

design of the interconnected interstate transmission system.102

4. The Legal Shift in Power Transactions

An increasing larger majority of U.S. power now proceeds through a

wholesale power sale prior to its ultimate retail sale and disposition,103

thereby

fundamentally altering the legal analysis of what is and is not now

jurisdictional for a state and the federal government to regulate.104

Restructuring and deregulation of the retail electric power sector, commencing

at the state level in approximately 1997, dramatically changed the regulatory

paradigm.105

About one-third of the states restructured prior to the electric

sector problems in California in 2000–2001, whereafter the other two-thirds of

the states retained traditionally structured retail electric sectors.106

99. Fed. Power Comm’n, 376 U.S. at 215–16 (“Our decisions have squarely rejected the view of the

Court of Appeals that the scope of FPC jurisdiction over interstate sales of gas or electricity at wholesale is to

be determined by a case-by-case analysis of the impact of state regulation upon the national interest.”).

100. Fed. Energy Regulatory Comm’n v. Mississippi, 456 U.S. 742, 757 (1982).

101. Id.

102. See Fed. Power Comm’n. v. Fla. Power & Light Co., 404 U.S. 453, 460 (1972) (“[N]one of the

connected electric systems . . . has any control over the actual transfers of power at each point of

interconnection because of the free flow characteristics of electric networks.”); New York v. Fed. Energy

Regulatory Comm’n, 535 U.S. 1, 7 n.5 (2002) (“FERC notes that whether transmission is in interstate

commerce ‘does not turn on whether the contract path for a particular power or transmission sale crosses state

lines, but rather follows the physical flow of electricity . . . . because of the highly integrated nature of the

electric system, this results in most transmission of electric energy being ‘in interstate commerce.’”).

103. ELEC. ENERGY MKT. COMPETITION TASK FORCE, REPORT TO CONGRESS ON WHOLESALE AND

RETAIL COMPETITION MARKETS FOR ELECTRIC ENERGY 10 (2005) (“In the 1970s, vertically integrated utility

companies (investor-owned, municipal, or cooperative utilities) controlled over 95 percent of the electric

generation in the United States . . . by 2004 electric utilities owned less than 60 percent of electric generating

capacity. Increasingly, decisions affecting retail customers and electricity rates are split among federal, state,

and new private, regional entities.”).

104. FERREY, supra note 50 at 591; FERREY, supra note 51, at 5-26–5-28.

105. FERREY, supra note 51, at 149–50.

106. See Steven Ferrey, Sale of Electricity, in THE LAW OF CLEAN ENERGY: EFFICIENCY AND

RENEWABLES 218–19 (Michael B. Gerrard ed., 2011) (“Starting in California, Rhode Island, and

Massachusetts in the late 1990s, several states sought to place their traditional monopoly utilities in the

different position of remaining as power distribution monopolies . . . . restructured retail power markets now

constitute almost one-third of the states’ retail power suppliers. Progress nationwide in this direction was

frustrated by the collapse of the California restructured power market in 2000-2001.”); see also VT. DEP’T OF

PUB. SERV., VERMONT COMPREHENSIVE ENERGY PLAN 2 (vol. 1, 2011), available at http://

www.vtenergyplan.vermont.gov (“Vermont already consistently leads the nation in electric efficiency

investments . . . . We also have, for many of the last 20 years, enjoyed electricity prices that are favorable

compared to our New England neighbors . . . . Nearly half of our electricity supply is currently renewable . . . .

In total, nearly a quarter of Vermont’s energy usage presently is from renewable sources.”). Vermont is the

one state in New England that did not engage in electric sector restructuring or creating an RPS system.

However, ten years later than the 1997–1998 restructuring in New England, Vermont has one of the cleanest

Page 16: pentagon preemption: the 5-sided loss of state energy and power

408 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

Much power generation, and particularly new wind and solar facilities,

are not owned by the retail utilities that deliver power to retail customers, but

instead are owned by independent wholesale market participants.107

The

amount of power wholesaled before it is sold at retail, has shifted from only

5% in the 1960’s to a majority today.108

As noted by the federal courts and

affirmed by the Supreme Court, these independent market participants are the

new competitive reality in power and energy markets:109

When combined with federal preemption law, one crucial result of these energy market regulatory reforms has been ‘a massive shift in regulatory jurisdiction from the states to the FERC.’ . . . The upshot of these federal and state innovations in electricity regulation is that state regulators, despite their continued authority over rates charged directly to consumers, have much less actual authority over those rates than they did [earlier]. Local utilities now obtain power largely through wholesale contracts subject to FERC’s exclusive regulation, rather than through self-generated and transmitted power. . . . Although state regulators formerly took an extremely active role so as to ensure the just and reasonable retail power rates, FERC has exclusive jurisdiction over the wholesale rates that now drive the electric power market and, as a practical matter, largely determine the rates ultimately charged to the public.

110

This entrance of new wholesale power market participants shifts

regulatory jurisdiction from states to FERC. In this newly deregulated

environment in some states, the cost of building and operating facilities is no

longer recovered directly through retail rates.111

Instead, retail customers pay

for the retail distribution utility’s cost of buying wholesale power in a

wholesale transaction, subject to FERC’s exclusive jurisdiction over wholesale

power transactions.112

As a result, much of the traditional state responsibility

portfolios of power and the lowest electricity rates in New England. Power comes from the large Vermont

Yankee Nuclear Power Plant owned by Entergy and importation of power from Canada.

107. See FERREY, supra note 50, at 581–82. This spun generation assets, including nuclear generation,

out into independent ownership not subject to state regulation. Id. The costs of these independent wholesale

power entities are not recovered through state-regulated retail rates, but rather through wholesale rates subject

to FERC’s exclusive jurisdiction. Id. See also 2012 GIS Load Asset Listing, ISO-NE (February 27, 2012),

http://www.iso-ne.com/support/asset_info/index.html (providing data relevant to the area in which this facility

is located).

108. See STEVEN FERREY, THE NEW RULES – A GUIDE TO ELECTRIC MARKET REGULATION 10–11 (2000)

(“In the 1960s, only about 5% of power passed through a wholesale transmission transaction before being sold.

In 1984, 32% of all power that reached end-users had first passed through a sale-for-resale transaction. In the

future, a majority of power will pass through a wholesale transmission transaction before being sold at

retail.”); FERREY, supra note 50, at 587 (“In 1983 about 8[%] of power was sold wholesale prior to being sold

at retail to the ultimate consumer.”).

109. See generally FERREY, supra note 108, at 269–70 (discussing how Congress opened the door to

electric industry competition).

110. Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash., 554 U.S.

527 (2008); Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash. v. Fed. Energy Regulatory Comm’n, 471 F.3d

1053, 1066–67 (9th Cir. 2006); see also, Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 733 F.3d 393 (2d Cir.

2013) (holding that the AEA preempted Vermont’s statutory provisions which required approval from the

legislature to operate a nuclear power plant).

111. FERREY, supra note 51, at 219–20.

112. Id.

Page 17: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 409

for regulating power has now shifted to FERC through its exclusive regulatory

authority over the rates, terms, and conditions of wholesale sales and

transmission of power,113

and to the competitive power market in

approximately one-third of the states.114

The United States Supreme Court has repeatedly held that states are

preempted by the Supremacy Clause of the United States Constitution115

from

directly or indirectly interfering with federal power regulation.116

When

applied to electric power issues, the Supremacy Clause of the Constitution117

is

embodied in the Filed Rate Doctrine, which establishes an absolute line the

states may not cross to regulate electric power.118

The court held that the

Federal Power Act invests the Federal Energy Regulatory Commission with

“‘exclusive authority to regulate the transmission and sale at wholesale of

electric energy in interstate commerce.’”119

The Supreme Court in 1986,120

and again in 1988,121

2003,122

and

2008,123

reaffirmed and enforced the Filed Rate Doctrine as applied through

the Supremacy Clause when states attempted to assert jurisdiction in areas

subject to FERC’s exclusive authority. The 1986 Supreme Court decision

concluded that the Filed Rate Doctrine limitations also apply “to decisions of

state courts.”124

The Filed Rate Doctrine is an absolute prohibition of state

regulation of wholesale power rates, contracts, and terms, which are reserved

exclusively to federal authority: “the filed rate doctrine is not limited to ‘rates’

per se: ‘our inquiry is not at an end because the orders do not deal in terms of

prices or volumes of purchases.’”125

The Supreme Court in 2008 reiterated the

notion that the Federal Power Act created a bright line between state and

federal jurisdiction, with wholesale power sales falling on the federal side of

the line.126

This most recent decision articulated an unbroken line of

113. 16 U.S.C. § 824a-3 (2012); FERREY, supra note 50, at 569.

114. FERREY, supra note 50, at 594.

115. U.S. CONST. art. VI, cl. 2.

116. Fed. Energy Regulatory Comm’n v. Mississippi, 456 U.S. 742, 760–61 (1982), see Sections II and

III (detailing Maryland and New Jersey inside regulation).

117. U.S. CONST. art. VI, cl. 2

118. Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 964 (1986); Miss. Power & Light

v. Mississippi ex rel. Moore, 487 U.S. 354, 371 (1988); Entergy La., Inc. v. La. Pub. Serv. Comm’n, 539 U.S.

39, 49–50 (2003).

119. Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 838 F. Supp. 2d 183, 233 (D. Vt. 2012) (quoting

New England Power Co. v. New Hampshire, 455 U.S. 331, 340 (1982)) (explaining that a state cannot regulate

in areas where proper FERC jurisdiction has been exercised in determining just and reasonable wholesale

rates); see also 16 U.S.C. § 824(b)(1) (2012) (stating that provisions of the statute apply to transmission of

electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce.).

120. Nantahala Power & Light Co., 476 U.S. at 963.

121. Miss. Power & Light Co., 487 U.S. at 372.

122. Entergy La., Inc., 539 U.S. at 50.

123. See generally Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty.,

Wash., 554 U.S. 527 (2008) (explaining that a wholesale electricity rate may be assessed by FERC under a

“just and reasonable” standard).

124. Nantahala Power & Light Co., 476 U.S. at 963.

125. Id. at 966–67; N. Natural Gas Co. v. State Corp. Comm’n, 372 U.S. 84, 90–91 (1963).

126. Morgan Stanley Capital Grp. Inc., 554 U.S. at 527 (citing the separate Supreme Court opinions in

Nantahala, Southern California Edison, and Mississippi Power); Pub. Util. Dist. No. 1 of Snohomish Cnty.,

Wash. v. Fed. Energy Regulatory Comm’n, 471 F.3d 1053, 1066 (2006), aff’d in part and rev’d in part sub

Page 18: pentagon preemption: the 5-sided loss of state energy and power

410 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

Supremacy Clause application barring state regulation:

Congress has drawn a bright line between state and federal authority in the setting of wholesale rates and in the regulation of agreements that affect wholesale rates. States may not regulate in areas where FERC has properly exercised its jurisdiction to determine just and reasonable wholesale rates or to insure that agreements affecting wholesale rates are reasonable.

127

B. Preemption Pentagon Side 2: The Geography of New Power

1. The New State Offer and Potential Conflict with Federal Authority

Some east coast states have been accused of attempting to manipulate

wholesale power prices as a mechanism to cause new projects for power

generation to locate within their states.128

In a traditional regulatory structure,

this would have been within state authority, as there would be no transmission

or interstate wholesale sale of power when utilities constructed the power

generation capacity which they required.129

However, with several states130

having followed Massachusetts’ lead to deregulate retail power sales and to

cause their utilities to divest all of their power generation capacity,131

regulatory authority has shifted. With wholesale acquisition of power now

required for utilities to obtain power resources for customers in these

deregulated and divested states, and power moving in interstate commerce to a

much higher degree,132

the Federal Power Act now substitutes federal

jurisdiction over these wholesale power transactions, divesting state authority.

The “grid” is composed not only of the approximately 4,800

interconnected power generation resources in the United States, but also of the

cable to connect them with consumers, and the hardware to manage them in an

energized instantaneous network.133

The high-voltage transmission network, at

230 kV and higher, comprises 167,000 miles of line in America.134

The

transmission system operates at fifteen different voltage levels.135

PJM

nom.

127. Miss. Power & Light Co. v. Miss. ex rel. Moore, 487 U.S. 354, 374 (1988).

128. See, David Cay Johnston, Enron-Style Price Gouging is Making a Comeback, ALJAZEERA AM.

(May 2, 2014, 4:15 AM), http://www.america.aljazeera.com/opinions/2014/5/new-england-

electricitymarketwallstreetenron.html (illustrating a bias favoring Enron style market manipulation and New

England regulators being captured by corporate and investor interests).

129. FERREY, supra note 108, at 260–63.

130. FERREY, supra note 51, at Section 8.3.

131. FERREY, supra note 108, at 298–301.

132. FERREY, supra note 51, at Section 8.3, p. 8-16–8-17.

133. “What is the Electric Power Grid, and What are Some Challenges it Faces?”, ENERGY INFO.

ADMIN. (Sept. 16, 2014), http://www.eia.gov/energy_in_brief/article/power_grid.cfm.

134. STAN MARK KAPLAN, CONG. RESEARCH SERV., R40511, ELECTRIC POWER TRANSMISSION:

BACKGROUND AND POLICY ISSUES 1-5, n.3 (2009), available at http://fpc.state.gov/documents/

organization/122949.pdf (discussing miles of transmission lines).

135. Craig Cano, Efficiency Should Be Viewed As Key Part of Entire Delivery System, Wellinghoff Says,

ELEC. UTIL. WEEK, Dec. 13, 2010, at 18–19.

Page 19: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 411

operates the “‘largest centrally dispatched power market . . . in the world,’136

covering sixty million customers and 185,000 megawatts” (MW) of power

generation, including all or part of thirteen states including New Jersey and

Maryland.137

See Figure 1. PJM operates pursuant to a tariff approved by

FERC, the “Open Access Transmission Tariff.138

PJM, an ISO, is an FERC-

created and authorized entity,139

managing regional power transmission entities

pursuant to filed tariffs that are approved by FERC.140

Figure 1: MISO and PJM Geographic Service Areas of Independent

System Operator

PJM provides capacity payments for the siting of new power generation

as needed throughout this thirteen state area.141

New capacity payments are

136. PPL EnergyPlus, LLC v. Hanna, 977 F. Supp. 2d 372, 378 (D.N.J. 2013).

137. Id.

138. Id.

139. In the PJM ISO, which serves multiple Eastern states, there are two retail energy markets, a real-

time (spot) and a day-ahead (forward) market. The basis of calculating the electricity price in either market is

Locational Marginal Pricing. PJM’s capacity-market model, the Reliability Pricing Model, was implemented

in 2007 as the successor to its Capacity Credit Market design, as a series of auctions for a delivery year

approximately three years in the future. PJM’s demand curve, the Variable Resources Requirement, defines

the price for a given capacity commitment relative to the applicable reliability requirement, defined for each

constrained Locational Delivery Area. See Amended and Restated Operating Agreement of PJM

Interconnection Inc., PJM (July 14, 2011), http://www.pjm.com/~/media/documents/agreements/oa.ashx

(defining locational marginal pricing and explaining process for an RPM auction); see also ELECTRIC POWER

MARKETS: PJM, FED. ENERGY REGULATORY COMM’N, http://www.ferc.gov/market-oversight/mkt-

electric/pjm.asp (last visited Oct. 6, 2014) (providing overview of PJM’s market description, geography and

RTOs/ISOs, in addition to other company information).

140. Regional Transmission Organizations (RTOs) or Independent System Operators (ISOs) are FERC-

approved and regulated entities which facilitate commercial electricity transfers, through a private corporation

that functions as a tariff administrator. RTOs are responsible for managing both electrical and financial

transactions, including scheduling transmission transactions, dispatching generation, and managing the entire

accounting for the grid capacity and energy charges and transmission fees. FERREY, supra note 51, at Sections

8:10, 10:87, 10:91; FERREY, supra note 108, at 49–50.

141. PPL EnergyPlus, LLC, 977 F. Supp. 2d at 386.

Page 20: pentagon preemption: the 5-sided loss of state energy and power

412 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

awarded to generators by PJM through a bidding process conducted once

annually, approximately three years before the capacity is deemed needed and

will be compensated in capacity payments.142

This three year lag time between

determination and obligation is to allow enough time for any project that is

awarded capacity to get built prior to it being required to be on-line. This

process is overseen by the Federal Energy Regulatory Commission.143

Projects

are separately paid for the actual energy that they produce and sell. PJM

insures “that supply and demand are matched almost perfectly in real time” at

all times.144

PJM “plan[s] expansions to transmission to improve the ability to

transmit energy from where it is generated to serve load.”145

Maryland and

New Jersey, both operating within PJM, each attempted somewhat similar

regulation of energy markets to take advantage of the regional PJM capacity

market payments and have power plants locate within their states.146

The legal

issues presented were similar: Are such state actions regarding the federally

FERC-approved PJM operation, preempted? “It is common ground that if

FERC has jurisdiction over a subject, the States cannot have jurisdiction over

the same subject.”147

The Federal Power Act “delegated to . . . the Federal

Energy Regulatory Commission, exclusive authority to regulate the

transmission and sale at wholesale of electric energy in interstate commerce,

without regard to the source of production.”148

Two 2013 federal court

decisions decided whether, within the PJM interconnection, a state could take

individual incentives by regulation to attempt to cause power plants to exploit

the PJM capacity market and to locate within the state taking such actions.149

2. Maryland Inside Regulation

A dispute in the Federal District Court of Maryland invoked two prongs

of the Constitution.150

It construed Maryland’s requirement for its utilities to

enter long-term “contract for differences” (a form of power purchase

agreements (PPAs)) with certain designated independent power producers

willing to locate new generation capacity constructed in Maryland or the

District of Columbia, as a violation of the Constitution.151

The Maryland

contract for differences (“CfD”) provided that regardless of the price set by the

142. Id. at 388.

143. Id. at 379.

144. Id.

145. Id. (PJM is responsible for the “dispatching” of generation in real time to meet fluctuating demand.)

146. Margaret Ryan, PJM Capacity Market Faces Uprising, BREAKING ENERGY (Dec. 19, 2011),

http://www.breakingenergy.com/2011/12/19/pjm-capacity-market-faces-uprising.

147. Miss. Power & Light Co. v. Miss. ex rel. Moore, 487 U.S. 354, 377 (1988) (Scalia, J., concurring).

148. New Engergy Power Co. v. New Hampshire, 455 U.S. 331, 340 (1982) (citing United States v. Pub.

Util. Comm’n of Cal., 345 U.S. 295, 311 (1953)). See also Nantahala Power & Light Co. v. Thornburg, 476

U.S. 953, 956 (1986) (stating that FERC “has exclusive jurisdiction over interstate wholesale power rates”).

149. See PPL Energyplus, LLC v. Nazarian, 974 F. Supp. 2d 790 (D. Md. 2013), aff’d, 753 F.3d 467 (4th

Cir. 2014) (holding that Maryland’s efforts to regulate utilities were unconstitutional); see also PPL

Energyplus, LLC, et al. v. Hanna, 977 F. Supp. 2d 372 (D.N.J. 2013), aff’d sub nom. PPL Energyplus, et al.

v. Solomon, 2014 WL 4454999 (3rd Cir. 2014) (holding that New Jersey’s fixed prices are unconstitutional).

150. Nazarian, 974 F. Supp. 2d at 796.

151. Id. at 831, 840.

Page 21: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 413

FERC/PJM federally regulated wholesale market, the Maryland utilities would

assure that the Maryland-selected in-state power projects received a guaranteed

price augmented by state funds and fixed by a contractual formula.152

The CfD

contained provisions which enabled the selected supplier to receive its

proposed “contract price” for each unit of energy and capacity sold at

wholesale to PJM in the PJM markets up to a ceiling amount.153

Maryland

ratepayers supply the wedge price between the in-state projects’ winning PJM

bids and the PPA rates. This wedge has some impact in a competitive PJM

bidding process to artificially suppress the capacity payments cleared for all

winning generators.

The successful winning bidders in this in-Maryland energy regulation

countered that while the plant location was geographically limited, an out-of-

state company could compete to build the plant as long as it similarly was

situated within Maryland.154

They argued that the geographic sites of the

commerce was overshadowed by the lack of geographic requirement for the

location of the owner of the facility.155

Congress, in the Federal Power Act of

1935, demarcated a:

‘bright line’ between state and federal authority in the setting of wholesale rates and in the regulation of agreements that affect wholesale rates. States may not regulate in areas where FERC has properly exercised its jurisdiction to determine just and reasonable wholesale rates or to insure that agreements affecting wholesale rates are reasonable.

156

The 2013 federal court decision in Maryland157

determined that

Maryland’s “contract for differences” requiring local utilities to enter into long

term PPAs was an impermissible intrusion of state regulation on regional

wholesale rates, disrupting FERC-approved wholesale power markets.158

Maryland retail utilities, which were required to divest their power generating

facilities, must purchase energy on federally regulated wholesale markets.159

FERC exercises exclusive jurisdiction in this field and has fixed the price for

wholesale energy and capacity sales in the PJM markets at the market-based

rate produced by the auction processes approved by FERC and utilized by

PJM.160

152. Id. at 796.

153. Id. at 891.

154. Id. at 799, 802.

155. Id. at 802.

156. Miss. Power & Light Co. v. Miss. ex rel. Moore, 487 U.S. 354, 371 (1988); see Ark. La. Gas Co.

v. Hall, 453 U.S. 571, 580–82 (1981) (finding that state breach-of contract claim was preempted by FERC’s

exclusive jurisdiction on the grounds that the state court’s interpretation of terms could interfere with FERC

rates).

157. PPL Energyplus, LLC v. Nazarian, 974 F. Supp. 2d 790 (D. Md. 2013).

158. Id. at 834–35. The court was persuaded in part by expert testimony explaining that the CfD went

beyond a mere financing arrangement because it reflected the same factors typically used to establish rates and

dictated the manner in which CPV (the winning bidder) could participate in PJM markets. Id.

159. Id. at 795.

160. Id. at 830. Like the federal court in New Jersey at the same time (see infra at Section III C), this

court cited the preemption holding of Gade v. Nat’l Solid Wastes Mgmt. Ass’n, 505 U.S. 88, 108 (1992).

Page 22: pentagon preemption: the 5-sided loss of state energy and power

414 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

The court assessed whether the CfD state compensation mechanism

impermissibly set wholesale prices for the regulated state utilities’ energy and

capacity power sales into the regional PJM markets.161

The court concluded

that when Maryland manipulates the prices of wholesale power markets, the

utilities and, correspondingly Maryland ratepayers, are directly affected by the

resulting wholesale prices determined on the federally regulated wholesale

PJM markets.162

The Court held the Maryland regulation violates the

Supremacy Clause of the United States Constitution by virtue of field

preemption, but plaintiffs had not proven their additional claim that it violates

the dormant Commerce Clause.163

State action that regulates within this

wholesale power field was void under the doctrine of field preemption.164

“The doctrine of field preemption forecloses state regulation in a field

occupied entirely by the federal government, even if the state’s purpose is

admirable or the state regulation does not conflict with achievement of the

federal scheme. See Arizona v. United States, 132 S. Ct. 2492, 2502

(2012).”165

Based on this principle, Maryland cannot secure the development of a

new power plant by regulating in such a manner as to intrude even indirectly

into the federal field of wholesale electric energy and capacity price-setting.166

Maryland had stated its purpose to cause the construction of sufficient reliable

electric energy for Maryland.167

Maryland is in a highly congested portion of

the regional PJM electric transmission system, which increases the price to

transmit power into the state.168

However, the court held that no rationale

permits a state to cross the ‘bright line’ limiting jurisdiction or “invasion into a

federally occupied field.”169

States cannot dictate the ultimate price received

for wholesale energy and capacity sales in the PJM markets under the Federal

Power Act and the Supremacy Clause.170

3. New Jersey Inside Regulation

Similar to the Maryland in-state requirement for new power generation

capacity, New Jersey had a state law with a similar objective.171

The state of

161. Nazarian, 974 F. Supp. 2d at 830.

162. Id. at 795.

163. Id. at 796.

164. Id. at 840.

165. Id.

166. Id.

167. Id. at 839–40.

168. Id. at 840.

169. Id. at 828–30: Where a state action falls within a field Congress intended the federal government alone to occupy, the good intentions and importance of the state’s objective are immaterial to the field preemption analysis. Field preemption requires the state to ‘yield to the force of federal law . . . notwithstanding that [the state’s action] is constructed upon values familiar to many and cherished by most, and notwithstanding that it may fit neatly within or alongside the federal scheme.’ Id. at 830.

170. Id. at 840.

171. N.J. STAT. ANN. §§ 48:3-98.3 (2011) (repealed 2013).

Page 23: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 415

New Jersey imports a substantial amount of its electricity from other states,

which requires paying more transmission charges to move the power to New

Jersey consumers.172

In 2011, New Jersey enacted the LCAPP program as a

subsidy program with “contracts for differences,”173

to encourage the

acquisition by utilities of the output of 2,000 Mw of new independent

unregulated in-state power projects.174

New Jersey provided selected new in-

state projects financial compensation in the form of a contracts for differences,

and requiring them to obtain capacity payments through participation in the

PJM capacity auction.175

Six hundred eighty Mw of additional generation has

been placed in service in New Jersey since RPM began, some from

reactivations of pre-existing non-operating generation facilities.176

After conducting a competitive bid process with public utilities, the New

Jersey Board of Public Utilities, the state energy regulatory agency, was

directed to enter into standard offer capacity agreements (“SOCAs”), long-

term fifteen-year contracts which guarantee these state selected generating

companies a fixed price for their capacity.177

Winning projects would be

financially “topped off” by state money for winning the federally-approved

PJM capacity reverse auction, which cause the winning project to receive some

of their cash inflow from regional (out-of-state) ratepayers.178

Power generators in the North Atlantic region filed a complaint at FERC

alleging discrimination caused by New Jersey’s statute ordering utilities to sign

long-term contracts only with in-state generation facilities which successfully

bid to receive regional multi-state PJM ISO capacity payments.179

The case

raised field preemption and conflict preemption of the New Jersey LCAPP

CfD proposal,180

where a fixed price from New Jersey for select New Jersey

generators allows such generation effectively to bid below the true cost of new

entry for the regional multi-state FERC-approved PJM auction, and thereby

obstructs the federal goal of a truly competitive auction without selective state

subsidies.181

This was argued to obstruct the federal goal of a competitive

172. Comments on New Jersey Electric Power and Capacity Needs, LS POWER ASSOCIATES, L.P. (July

2, 2010), http://www.state.nj.us/bpu/pdf/energy/LSPower_comments.pdf.

173. N.J. STAT. ANN. §§ 48:3-98.3 (2011) (repealed 2013). After conducting a competitive bid process

with public utilities, the BPU is directed to enter into standard offer capacity agreements (SOCAs), which are

long term fifteen-year contracts which guarantee the state selected generating companies a fixed price for their

capacity.

174. H.R. 3442, 214 Leg., (N.J. 2010).

175. N.J. STAT. ANN. §§ 48:3-98.3 (2011) (repealed 2013).

176. See LS POWER ASSOCIATES, L.P, supra note 172 (stating that of the six thousand Mw retired within

the PJM grid since 2002, one-third of these deactivations of power generation facilities have been in New

Jersey).

177. Id. After the New Jersey BPU selects a generator program, it enters into a standard offer capacity

agreements (SOCA) with the BPU, which obligates the generator to produce a fixed amount of electricity that

is sold to New Jersey retail utilities in return for a fixed price for the power.

178. Id.

179. Mary Powers, PJM Generators File Complaint with FERC Seeking Relief from NJ In-State

Generation Law, ELECTRIC UTIL. WK., Feb. 7, 2011, at 11, 13.

180. PPL Energyplus, LLC v. Hanna, 977 F. Supp. 2d 372 (D.N.J. 2013).

181. After the New Jersey BPU selects a generator program, they enter into a SOCA with the BPU,

which obligates the generator to produce a fixed amount of electricity that is sold to New Jersey retail utilities

in return for a fixed price for the power.

Page 24: pentagon preemption: the 5-sided loss of state energy and power

416 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

auction without selective subsidies for certain in-state capacity resources.182

This caused the regional PJM to guarantee these New Jersey generators a

substantial capacity payment every month at a cost which is passed on not just

to New Jersey electric ratepayers, but to all PJM ratepayers who reside in

many of the thirteen PJM states and Washington, D.C. in the PJM region.183

It

was alleged that this artificially influenced behavior of New Jersey new

generation units also tended to drive down the market-clearing price at the

PJM annual capacity auction, resulting in lower clearing prices and capacity

revenues to all participants than if such state-subsidized entrants had not been

influenced to bid under these circumstances.184

Plaintiffs also alleged a

violation of the Constitution’s dormant Commerce Clause because of state

regulatory in-state “favoritism,” alleging the New Jersey act to be a “blatant

and explicit effort to promote the construction of new generation facilities in

New Jersey.”185

In defense, New Jersey asserted that its LCAPP is a mere planning

measure, with only incidental effect on FERC authority.186

New Jersey

contended that FERC oversight authority is “limited to sales of the actual

physical electricity (or capacity) to a buyer”187

and “[c]ontracts that do not

effect a physical sale of electricity. . . . are not subject to [Commission]

jurisdiction.”188

Even in the absence of field preemption, state law can still be

superseded based on conflict preemption if the state law interferes with a

federal goal.189

There are certain regulatory actions which are only within

federal authority, and which states do not have power to undertake.190

Article

VI, the Constitution’s Supremacy Clause, and the Federal Power Act,191

establish judicially defined “bright line” prohibitions of state regulation of

wholesale transactions in power.192

The 2013 federal district court decision in New Jersey held that the state

was impermissibly regulating wholesale energy prices to promote the

182. PPL EnergyPlus LLC v. Solomon, No. 11-745, 2011 WL 5007972, at *1 (D.N.J. Oct. 11, 2011).

183. Who We Are, PJM, http://www.pjm.com/about-pjm.aspx (last visited Oct. 6, 2014).

184. Solomon, 2011 WL 5007972, at *3.

185. Hanna Northey, Utilities Challenge N.J. Law While Preparing to Reap Its Benefits, E & E

PUBLISHING, LLC (Mar. 2, 2011), http://www.eenews.net/public/Greenwire/2011/03/02/4. Plaintiffs alleged

that because the eligibility requirements, including deadlines, pre-qualification requirements, and other criteria

favored in-state generators, the selection process for LCAPP-sponsored generators favored in-state generators:

All generators selected to participate in the New Jersey LCAPP program were from New Jersey. Id. LCAPP

awarded contracts to Hess Corp., Competitive Power Ventures and NRG Energy. Id.

186. N.E. Hub Partners, L.P. v. CNG Transmission Corp., No. 1-CV-99-0082, 2000 WL 33912020, at *9

(a state regulatory process was field preempted where the result of such process was within federal authority),

rev’d, 239 F.3d 333, 348 (3rd Cir. 2001).

187. PPL Energyplus, LLC v. Hanna, 977 F. Supp. 2d 372, 406 (D.N.J. 2013).

188. Id.

189. See Hines v. Davidowitz, 312 U.S. 52, 67 (1941) (declaring that state law will be preempted if it

“stands as an obstacle to the accomplishment and execution of the full purposes or objectives of Congress”).

190. Id.

191. 16 U.S.C. § 824 (2012).

192. U.S. CONST., art. VI, cl. 2 (“[T]he Laws of the United States . . . shall be the supreme Law of the

Land; and the Judges in every State shall be bound thereby, any Thing in the Constitution or Laws of any State

to the Contrary notwithstanding.”).

Page 25: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 417

construction of new generation facilities in New Jersey.193

The state LCAPP

regulation was held to:

intrude upon the exclusive jurisdiction of the Commission, by establishing the price that LCAPP generators will receive for their sales of capacity. The Court finds that in doing so, the LCAPP ‘places a direct burden upon interstate commerce’ within the meaning of the Attleboro decision. Accordingly, the LCAPP Act invades the field occupied by Congress and is preempted by the Federal Power Act.

194

The court held that conflict preemption “prevents state regulation of, or

influence over, the wholesale price for energy transactions.”195

A government-

imposed price interferes with FERC’s method for the wholesale sale of

electricity in interstate commerce,196

and intrudes upon the Commission’s

authority to set wholesale energy prices through its preferred regional RPM

auction process.197

4. Comparing Two Most Recent Federal Court Preemption Decisions

Despite the similarities of the New Jersey regulation with the

simultaneous Maryland effort to control where power plants are located,198

the

New Jersey federal court disavowed any need to compare the two programs.199

However, the two cases merit some comparison:

Both require eligible projects to locate in-state or in a specified

geographic region

Both require regulated utilities in the state to enter mandatory

contracts to purchase wholesale power

Both utilize state contracts-for-differences as a subsidy mechanism at

a price above market prices

Both require eligible independent power projects to win the PJM

auction for new capacity, and top-off these winning bids by providing

state CfD incentives

This theoretically lowers the winning capacity bids reflecting the

subsidies, extracts some of the compensation for power production

from the regional 13-state PJM market and their ratepayers, and

suppresses the PJM capacity market by virtue of these state subsidies

This causes in-state new power production capacity to win some of the

193. Northey, supra note 185. The complaint also alleged a violation of the Constitution’s dormant

Commerce Clause because it is predicated on in-state “favoritism,” which the court did not find. The utilities

pay a cost equal to the difference between the FERC-approved PJM market clearing price and a contractually

established New Jersey regulatory benchmark price.

194. PPL Energyplus, LLC, v. Hanna, 977 F. Supp. 2d 372, 409 (D.N.J. 2013).

195. Id. at 410 (explaining the Commission has exclusive authority to regulate wholesale prices).

196. Id. at 410.

197. Id. at 406.

198. See supra Section II B 2 (discussing the similarities of Maryland’s and New Jersey’s statutes).

199. Hanna, 977 F. Supp. 2d at 404 (“[T]he Court is not able to discern whether Maryland’s proposal is

sufficiently similar to the LCAPP.”).

Page 26: pentagon preemption: the 5-sided loss of state energy and power

418 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

limited capacity for new projects in the PJM auction, depriving other

projects of a winning bid and capacity payments as part of future

operation, causing many to fail

This influences the location of new power projects through state

subsidies designed to tilt the geographic outcome for winners of the

regional 13-state PJM capacity auction

Maryland and New Jersey had an understandable motive for wanting

more new power production capacity located in-state near their consumers:

This reduces the transmission charges that in-state ratepayers will have to pay

to transmit retail power from generators out-of-state to in-state consumers.200

The state also receives any tax and job benefits of additional development in

the state.201

Since power flows from its point of generation to the nearest point

of retail load or demand,202

having generation in-state proximate to consumers

reduces the risk of transmission problems or insufficient supply at peak times,

increasing power supply reliability.

How did we arrive at this legal landscape? It was Maryland and New

Jersey themselves which elected to require their regulated retail utilities to

divest their power generation capacity in the interests of promoting

competition approximately a decade ago.203

In doing so, they introduced the

necessity of each retail utility purchasing its power from independent

wholesale power generators.204

And in doing so, states shifted their control

over the prior predominately retail energy sales to FERC as the regulator of all

wholesale transactions and of power transmission: “[I]t is difficult to conceive

of a more basic element of interstate commerce than electric energy, a product

used in virtually every home and every commercial or manufacturing facility.

No State relies solely on its own resources in this respect.”205

This shift from

jurisdiction states to FERC was engineered entirely by the states themselves.206

This is not a transfer that can be facilely reversed; the “bright line” jurisdiction

over power has been national law for more than seventy-five years, while the

Supremacy Clause has existed since the genesis of American Constitutional

200. Id. at 411 (“‘[C]ommunity benefit’ points awarded to generators in New Jersey effectively

prohibited out-of-state generators from competing to be eligible generators under the LCAPP Act.”).

201. For treatment of tax aspects of power generation, see FERREY, supra note 51, at Tables 3.13, 3.15,

3.19.

202. Power moves according to Kirchhoff’s Law almost at the speed of light on this energized grid. This

law is also called Kirchhoff’s first law, Kirchhoff’s point rule, Kirchhoff’s junction rule, and Kirchhoff’s first

rule. The principle of conservation of electric charge implies that at any point in an electrical circuit where

charge density is not changing in time, the sum of currents flowing towards that point is equal to the sum of

currents flowing away from that point. People can tap into this energizing service, although technically they

do not purchase a conventional commodity. Steven Ferrey, Inverting Choice of Law in the Wired Universe:

Thermodynamics, Mass and Energy, 45 WM. & MARY L. REV. 1839, 1909–14 (2004); FERREY, supra note 51,

at 10-394.

203. FERREY, supra note 51, at 10-10, 10:12, 10-91.

204. Id. at Section 3-19.

205. Fed. Energy Regulatory Comm’n v. Miss., 456 U.S. 742, 757 (1982).

206. See About Deregulation, MD. GAS & ELECTRIC, (Sep. 9, 2014), http://www.usgande.com/

markets/maryland/EnergyChoice/Deregulation.aspx (discussing Maryland’s choice to voluntarily deregulate).

Page 27: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 419

law.207

FERC has promoted greater competition208

and promoted regional

coordination by ISOs, such as PJM.209

And two separate federal district courts

in Maryland and New Jersey, when confronted with separate challenges to

similar state energy regulation, came to the almost identical conclusion that

this state “inside game” clearly violated the Supremacy Clause.210

This is the

second side of the pentagonal energy preemption.

C. Preemption Pentagon Side 3: Rights of First Refusal For Incumbent

In-State Power Transmission Companies

Can states require that additional power transmission facilities proposed

by a competitive entity actually be turned over and ceded to be built and

owned by incumbent in-state businesses? Incumbents typically are the

traditional utilities in a state, which operate only within that state.211

Several

states are insisting on enforcing state rights of first refusal (“ROFRs”) for

existing in-state monopolies to commandeer any competitive or out-of-state

electric power transmission proposals.212

The high-voltage transmission network was recognized by engineers as

the most important engineering feat of the 20th century.213

Its operation

requires a constant simultaneous balancing of supply and demand on that

system.214

FERC is promoting competition among independent transmission

entities; the conflict where states refuse and recognize only in-state traditional

power entities raises the third side of the pentagon of federal preemption.

1. FERC ORDER 1000

FERC Order 1000 introduced competitive bidding into the construction

process for transmission facilities.215

FERC Order 1000 requires incumbent

transmission providers, utilities, and the regional transmission organizations

(“RTOs”) which manage regional multi-state transmission access to the grid, to

remove rights-of-first-refusal from FERC-approved transmission tariffs.216

207. U.S. CONST., art. VI, § 2.

208. FED. ENERGY REGULATORY COMM’N, FINAL ORDER 888, PROMOTING WHOLESALE COMPETITION

(1996).

209. Transmission Planning and Cost Allocation by Transmission, 76 Fed. Reg. 49,842 (Aug. 11, 2011).

For treatment of ISOs, see FERREY, supra note 51, at 10:87.

210. PPL Energyplus, LLC, v. Hanna, 977 F. Supp. 2d 372, 412 (D.N.J. 2013); PPL EnergyPlus LLC

v. Solomon, No. 11-745, 2011 WL 5007972, at *6 (D.N.J. Oct. 20, 2011).

211. FERREY, supra note 108.

212. Discussed infra at Section II C 3.

213. Mason Willrich, Electricity Transmission Policy for America: Enabling a Smart Grid, End to End,

22 ELEC. J. 77, 77 (2009).

214. FERREY, supra note 50, at 568.

215. Owning and Operating Public Utilities, 76 Fed. Reg. 49,842 (Aug. 11, 2011) (to be codified at 18

C.F.R. pt 35); Transmission Planning and Cost Allocation by Transmission Owning and Operating Public

Utilities, 77 Fed. Reg. 32,184 (May 31, 2012) (to be codified at 18 C.F.R. pt 35); Transmission Planning and

Cost Allocation by Transmission Owning and Operating Public Utilities, 77 Fed. Reg. 64,890 (Oct. 24, 2012)

(to be codified at 18 C.F.R. pt 35).

216. Transmission Planning and Cost Allocation, 77 Fed. Reg. 64,890 (Oct. 24, 2012). For treatment of

this, see RISHI GARG, WHAT’S BEST FOR THE STATES: A FEDERALLY IMPOSED COMPETITIVE SOLICITATION

Page 28: pentagon preemption: the 5-sided loss of state energy and power

420 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

FERC Order No. 1000 addressed the difference between an obligation to build

in one’s transmission zone and a federal right of first refusal: “[W]e do not

believe that [the] obligation [to build] is necessarily dependent on the

incumbent transmission provider having a corresponding federal right of first

refusal to prevent other entities from constructing and owning new

transmission facilities located in that region.”217

FERC directed, in its Notice of Proposed Rulemaking (NOPR) prior to

issuance of its Order 1000, that public utility transmission providers “eliminate

provisions in Commission-jurisdictional tariffs and agreements that establish a

federal right of first refusal for an incumbent transmission provider with

respect to transmission facilities selected in a regional transmission plan for

purposes of cost allocation.”218

This was kept intact when the final FERC

Order 1000 rule was promulgated,219

and in the subsequent FERC Orders

1000-A and 1000-B.220

Failure of RTOs and ISOs to consider and evaluate

independent non-incumbent transmission projects could violate the FERC

Order 890 planning principle of “openness” in transmission planning.221

Order 1000 does not require removal from Commission-jurisdictional

tariffs or agreements references to state or local laws or regulations with

respect to construction of transmission facilities, including, but not limited to

authority over siting or permitting of transmission facilities.222

In terms of

scope, Order 1000 only applies to jurisdictional public utilities, which include

only the investor-owned utilities, and the RTOs which manage them under the

Federal Power Act.223

This would include only approximately less than 200

entities among the approximately 3,000 utilities in the U.S.224

Excluded are all federal government power marketing administrations,225

all rural electric cooperatives226

and membership utility cooperatives,

municipal utilities.227

Additionally all utilities not engaging in interstate

commerce in Alaska, Hawaii, and the majority of Texas within the ERCOT

MODEL OR A PREFERENCE FOR THE INCUMBENT? STATE ADOPTION OF RIGHT OF FIRST REFUSAL STATUTES IN

RESPONSE TO FERC ORDER 1000 AND THE DORMANT COMMERCE CLAUSE (Nat’l Regulatory Research Inst.,

2013) (discussing whether ROFR statutes promulgated by the states are constitutional under the dormant

commerce clause).

217. Nonincumbent Transmission Developers, 76 Fed. Reg. 49,880, 49,887 (Aug. 11, 2011) (to be

codified 18 C.F.R. pt. 35).

218. Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utilities, 136

FERC P 61051, Order 1000 (July 21, 2011).

219. Non-incumbent transmission developer rights must be “consistent with state or local laws.” Id. at

¶¶ 313–317.

220. Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utilities,

Order 1000-A, FERC Stats. & Regs. ¶ 31,132 (May 31, 2012); Transmission Planning & Cost Allocation by

Transmission Owning & Operating Pub. Utilities, 141 FERC P 61044, Order 1000-B (Oct. 18, 2012).

221. Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utilities, 136

FERC P 61051, Order 1000 (July 21, 2011).

222. Id. at 253; Order 1000-A, supra note 220, at ¶ 381.

223. Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utilities, 136

FERC P 61051, Order 1000 (July 21, 2011).

224. FERREY, supra note 50, at 579.

225. 16 U.S.C. § 824(f) (2012).

226. Id.

227. Id.

Page 29: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 421

RTO zone (which does not interconnect with any other states and therefore

technically does not engage in interstate commerce.) are excluded.228

These

slightly less than 200 affected utilities own about 25% of the transmission and

distribution infrastructure, measured as distance of lines, in the U.S.229

2. FERC Preemptive Authority

The Supremacy Clause of the United States Constitution establishes

preemption of federal law over state and local regulation: “[T]he laws of the

United States . . . shall be the supreme law of the land; and the judges in every

state shall be bound thereby, anything in the Constitution or laws of any State

to the contrary notwithstanding.”230

The Federal Power Act creates this

“bright line”231

between state and federal jurisdiction.232

Sections 205 and 206

of the Federal Power Act empower FERC to regulate rates and related terms

for any transmission of electricity in interstate commerce.233

The applicable preemption doctrine under the Federal Power Act also

expressly distinguishes wholesale from retail regulation.234

All transmission

tariffs are exclusively within FERC, rather than state jurisdiction.235

The

Federal Power Act directs FERC to regulate all interstate electricity

transmission and to ensure the reliability of the national electricity grid.236

FERC case law exerts exclusive jurisdiction over the “transmission of

electric energy in interstate commerce” and over “all facilities for such

transmission or sale of electric energy.”237

FERC approves all RTO and

228. 16 U.S.C. § 824(b)(1) (2012).

229. FERREY, supra note 50, at 579.

230. U.S. CONST. art. VI, cl. 2.

231. Id.

232. Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash., 554 U.S.

527, 550 (2008) (criticizing the reasoning of the Ninth Circuit instituting a rate “zone of reasonableness” on

FERC determinations, which would be “a reinstitution of cost-based rather than contract-based regulation.”);

Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash. v. Fed. Energy Regulatory Comm’n, 471 F.3d 1053, 1066

(9th Cir. 2006), aff’d in part and rev’d in part sub nom. Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist.

No. 1 of Snohomish Cnty., Wash., 554 U.S. 527 (2008), vacated, Pub. Util. Dist. No. 1 of Snohomish Cnty.,

Wash. v. F.E.R.C., 547 F.3d 1081 (9th Cir. 2008) (vacating Morgan Stanley Capital Grp. Inc. v. Pub. Util.

Dist. No. 1 and criticizing the reasoning of the Ninth Circuit’s decision, but nonetheless upholding that FERC

has exclusive authority, and responsibility, to review long-term power crises, wholesale market manipulation

by a party to the power sale contract that would negate existing contract protections, and wholesale rates). See

generally Steven Ferrey, Soft Paths, Hard Choices: Environmental Lessons in the Aftermath of California’s

Electric Deregulation Debacle, 23 VA. ENVTL. L.J. 251 (2004) (discussing the California and Western energy

crisis that spawned this litigation).

233. 16 U.S.C. §§ 824d–824e (2012); Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash. v. Fed. Energy

Regulatory Comm’n, 471 F.3d 1053, 1058 (9th Cir. 2006), aff’d in part and rev’d in part sub nom. Morgan

Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1, 554 U.S. 527 (2008).

234. Infra Section III.

235. Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utilities, 136

FERC P 61051 (July 21, 2011) at ¶ 287.

236. 16 U.S.C. §§ 797, 824(a)-(b) (2012).

237. 16 U.S.C. § 824(b) (2012); e.g., the following cases provide examples of the scope of FERC’s

jurisdictional reach. Aquila Merch. Servs, Inc., 125 FERC P 61175, ¶ 17 (2008); Entergy Servs, Inc., 120

FERC P 61020, ¶ 28 (2007); Midwest Indep. Transmission Sys. Operator, Inc., 106 FERC P 61337, ¶ 14, n.17

(2004); S. Ca. Edison Co., 106 FERC P 61183, ¶¶ 14, 19 (2004); Va. Elec. Power Co, 103 FERC P 61109, ¶ 6

(2003); Barton Vill., Inc. v. Citizens Util. Co., 100 FERC P 61244, ¶ 12 (2002); Niagara Mohawk Power

Page 30: pentagon preemption: the 5-sided loss of state energy and power

422 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

Independent System Operator (ISO) terms of service and the financial

tariffs.238

However, FERC does not regulate the construction of transmission

facilities themselves, only economic tariffs for transactions moving power over

them.239

There is a multi-year evolution of the federal regulatory history regarding

greater competition in electric power transmission. Enforcing the Federal

Power Act, the Federal Energy Regulatory Commission (FERC) for a quarter

century has promoted competition in the operation of regulated energy

markets.240

In Order No. 888,241

the Commission established the foundation

for the development of competitive bulk power markets: non-discriminatory

open access transmission service by electric utilities. In Order No. 2000,242

the

Commission encouraged the development of Regional Transmission

Organizations to form “competitive wholesale electric markets,”243

that had to

incorporate non-discriminatory transmission service.244

In Order No. 890,245

Corp., 100 FERC P 61019, ¶ 17 (2002); Armstrong Energy Ltd P’ship, LLLP, 99 FERC P 61024, ¶ 61104

(2002); Progress Energy, Inc., 97 FERC P 61141, ¶ 61628 (2001); Cent. Vt. Pub. Serv. Corp., 84 FERC P

61194, ¶¶ 61973–75 (1998); Conn. Light and Power Co.70 FERC P 61012, ¶ 61030, reconsid. denied, 71

FERC P 61035 (1995); N. Ind. Pub. Servs. Co., 66 FERC P 61213, ¶ 61488 (1994); Houlton Water Co. v. Me.

Pub. Servs. Co., 60 FERC P 61141, ¶ 61515 (1992); Fla. Power & Light Co., 40 FERC P 61045, ¶¶ 61120–21,

reh’g denied, 41 FERC P 61153, ¶ 61382 (1987); S. Co. Servs, Inc., 37 FERC P 61256, ¶ 61652 (1986); Pa.

Power & Light Co., 23 FERC P 61006, ¶ 61018, reh’g denied, 23 FERC P 61325 (1983).

238. FERREY, supra note 108, at 10–11.

239. See generally Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub.

Utilities, 136 FERC P 61051, Order 1000 (July 21, 2011) (stating regulations pertain only to Commission-

jurisdictional tariffs or agreements and does not require removal of references to such state or local laws or

regulations from Commission-approved tariffs or agreements. FERC noted that Order 1000 does not address

the prudence of investment decision nor determine which particular entity should construct any particular

transmission facility, but merely to allow more entities to be considered for potential construction

responsibility).

240. FERC has for twenty-five years attempted to mitigate monopoly transmission power by requiring

certain elements of more competitive open access transmission service as a condition of merger approval.

Utah Power & Light Co., 45 FERC P 61095 (1988). Investment in the transmission grid has lagged

dangerously for decades. See David Raskin, Transmission Policy in Flux, FORTNIGHTLY (May 2013),

http://www.fortnightly.com/fortnightly/2013/05/transmission-policy-flux. In 2005, in the Energy Policy Act

of 2005, Congress gave additional tools to FERC, which provided price incentives and these merchant

transmission entitlements to promote more investment. Id. FERC promulgated Order No. 679, providing

transmission pricing incentives in accordance with new Section 219 of the Federal Power Act. Id.

241. Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission

Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order

888, FERC Stats. & Regs. ¶ 31,036, 61 Fed. Reg. 21,540 (1996), clarified, 76 FERC P 61009 (F.E.R.C.) and

76 FERC P 61347 (1996), reh’g granted, Order 888-A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274,

clarified, 79 FERC P 61182 (1997), reh’g granted, Order 888-B, 81 FERC P 61248, 62 Fed. Reg. 4, 688

(1997), reh’g granted, Order 888-C, 82 FERC P 61046 (1998), aff’d, Transmission Access Policy Study Grp.

v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d, New York v. FERC, 535 U.S. 1 (2002).

242. Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash. v. Fed. Energy Regulatory Comm’n, 272 F.3d

607 (D.C. Cir. 2001); Regional Transmission Organizations, Order 2000, FERC Stats. & Regs. ¶ 31,089

(1999), reh’g granted, Order 2000-A, FERC Stats. & Regs. ¶ 31,092 (2000).

243. Me. Pub. Utils. Comm’n v. Fed. Energy Regulatory Comm’n, 454 F.3d 278, 280–81 (D.C. Cir.

2006).

244. See 18 C.F.R. § 35.34(k)(7) (2000) (outlining the functions the Regional Transmission Organization

must satisfy).

245. Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 72 Fed.

Reg. 12266 (Mar. 15, 2007), reh’g granted, Order 890-A, 73 Fed. Reg. 2984 (Jan. 16, 2008), reh’g granted,

Order 890-B, 123 FERC P 61,299 (2008), reh’g granted, Order No. 890-C, 126 FERC P 61228 (2009).

Page 31: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 423

the Commission amended the Order No. 888 pro forma tariff to require

transmission providers to plan for the needs of their customers on a

comparable basis to planning for their own needs.246

Section 216 by the Energy Policy Act of 2005 directs the U.S.

Department of Energy to study transmission congestion in consultation with

the states, and designate certain transmission-constrained areas as national

interest electric transmission corridors (“NIETCs”).247

Section 216 grants

FERC authority to issue permits to construct transmission facilities in these

NIETCs under certain circumstances.248

FERC implementation hit multiple

suits for failure to adequately assess GHG impacts involving NEPA,249

and

Endangered Species Act challenges regarding failure to assess GHG impacts

could follow.250

A federal appeals court blocked FERC from acting to

“backstop” and granted a federal permit under Section 216 for a new

transmission line where the state had failed for twelve months to act on the

permit.251

As long as the state took some action, including a denial of the

permit, this did not trigger FERC’s Section 216 authority to intercede.252

In

2011, the Ninth Circuit ruled that the DOE failed to properly consult with

affected states in preparing the Congestion Study, as required by section 216,

and failed to consider the environmental effects of designating NIETCs under

the National Environmental Protection Act for corridors in mid-Atlantic and

Southwestern states.253

There are three recognized circumstances in which federal law may

preempt state law:

federal law could explicitly establish the lines for state preemption;254

in the absence of explicit preemption, state law “may be preempted if

it regulates conduct in a field Congress intended the federal

government to occupy exclusively, either because the federal

regulatory scheme is ‘so pervasive’ that a court may infer Congress

246. N.Y. Reg’l Interconnect, Inc. v. Fed. Energy Regulatory Comm’n, 634 F.3d 581, 584 (D.C. Cir.

2011); Order No. 890, ¶ 435.

247. 16 U.S.C. § 824 (2012); Energy Policy Act of 2005, Pub.L. No. 109-58 § 216 Stat. 594 (2005).

248. 71 Fed. Reg. 69,440 (2006), FERC Stats. & Regs. ¶ 31,234 (2006) (describing Order No. 689 made

in 2006, where FERC created a cumbersome, multi-year process for obtaining a federal permit to construct

transmission within a NIETC).

249. Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety Adm., 538 F.3d 1172 (9th Cir. 2008);

Mid–States Coalitions for Progress v. Surface Transp. Board, 345 F.3d 520 (8th Cir. 2003); Border Power

Working Grp. v. U.S. Dep’t of Energy, 260 F. Supp.2d 997 (S.D. Cal. 2003).

250. See, e.g., Pacific Coast Fed. of Fishermen’s Ass’ns v. Gutierrez, 606 F. Supp. 2d 1122 (E.D. Cal.

2008) (regarding the effects a company’s water projects had on endangered salmonid species); Nat’l Res. Def.

Council v. Kempthorne, 506 F. Supp. 2d 322 (E.D. Cal. 2007) (regarding water diversion projects and the

effects the projects would have on the Delta smelt population).

251. In 2007, the PJM ISO approved the construction of the PATH transmission line to move power

within the region through West Virginia, Virginia, and Maryland to constrained population centers along the

Atlantic coast. None of the states cooperated. The economic crisis eased the need for the project and PJM

rescinded its order. Piedmont Envtl. Council v. Fed. Energy Regulatory Comm’n, 558 F.3d 304 (4th Cir.

2009).

252. Id. at 313.

253. Cal. Wilderness Coal. v. U.S. Dep’t of Energy, 631 F.3d 1072, 1079 (9th Cir. 2011).

254. See English v. Gen. Elec. Co., 496 U.S. 72, 78–79 (1990) (“Congress can define explicitly the

extent to which its enactments pre-empt state law.”).

Page 32: pentagon preemption: the 5-sided loss of state energy and power

424 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

left ‘no room for the States to supplement it;’”255

or

state law could clearly conflict with the federal law.256

A state cannot create a conflict or obstacle to federal licensing of

federally regulated energy generation facilities that are within the exclusive

federal authority of a federal agency.257

State law is not allowed to overrule or

supplant federal determinations by adding requirements not consistent with

those in federal law.258

3. State Refusals to Remove ROFR for In-State Incumbents

Notwithstanding this federal FERC prohibition in FERC Order 1000 of

state ROFR, Minnesota, North Dakota, South Dakota, Indiana and Oklahoma

enacted state ROFR statutes, nonetheless.259

Other states have proposed

statutes.260

If there were a state right-of-first-refusal provision, the deck is

effectively stacked against non-incumbents, even if the opportunity to compete

is theoretically open to them through an RTO-administered competitive project

selection process.

In Fall 2012, the Midwest Independent Transmission System Operator

(“MISO”) and a subset of the MISO utility transmission owners made a

compliance filing to FERC containing member state ROFRs, pursuant to the

directives and timing requirements contained in FERC’s Order Nos. 1000,

1000-A and 1000-B.261

In spring 2013, FERC determined that MISO’s

proposed new provision for state or local Rights of First Refusal must be

removed from its tariff filing.262

FERC with regard to a PJM filing held that

nothing in the commission’s regulations allows transmission owners to bar a

non-incumbent transmission developer from cost-based recovery for its

255. See id. at 79 (“in the absence of explicit statutory language, state law is pre-empted where it

regulates conduct in a field that Congress intended the Federal Government to occupy exclusively.”); Entergy

Nuclear Vt. Yankee, LLC v. Shumlin, 838 F. Supp. 2d 183, 218 (D. Vt. 2012).

256. Id.

257. 42 U.S.C. § 2019 (2012); N. States Power Co. v. Minn., 447 F.2d 1143, 1146 (8th Cir. 1971), aff’d,

405 U.S. 1035 (1972).

258. Granite Rock Co. v. Cal. Coastal Comm’n, 480 U.S. 572, 581 (1987); see, e.g., Nat’l Meat Ass’n v.

Harris, 132 S. Ct. 965, 969–71 (2012) (deciding unanimously that federal law prohibits states from enforcing

requirements regarding “premises, facilities and operations” that are “in addition to or different from” those in

federal law).

259. States with either enacted or proposed ROFR laws include: Minnesota – MINN. STAT. § 216B.246

(2012), New Mexico – S.B. 175, 51st Leg., 1st Sess. (N.M 2013), and South Dakota Codified Laws – S.D.

Codified L. § 49-32-19 (2011)).

260. See GARG, supra note 216, at 1 (explaining that states have started passing laws in response to

FERC Order 1000).

261. Transmission Planning and Cost Allocation by Transmission Owning and Operating Public

Utilities, 136 FERC P 61051, Order No. 1000 (July 21, 2011), order on reh’g and clarification, 139 FERC P

61132, Order No. 1000-A (May 17, 2012), order on reh’g and clarification, 141 FERC P 61044, Order No.

1000-B (October 18, 2012).

262. FERC Order On Compliance Filings & Tariff Revisions, Re: Midwest Independent Transmission

System Operator, Inc. and the MISO Transmission Owners, et al., 142 FERC P 61215, ¶ 205 (2013). FERC

directed MISO to strike the following language: “Transmission Provider shall comply with any Applicable

Laws and Regulations granting a right of first refusal to a Transmission Owner.” Id.

Page 33: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 425

transmission facilities.263

This state-federal preemption fight has been recently decided by a federal

court.264

In spring 2013, the Supreme Court rendered a decision on whether

the Federal Communications Commission (FCC) can broadly construe its own

jurisdiction, and whether it is entitled to judicial Chevron deference in this

determination.265

On both issues, the Supreme Court’s answer was yes.266

In

Arlington v. FCC, the majority held that Circuit precedent holding that

Chevron U.S.A. Inc. v. Natural Resources Defense Council, Inc., applies to an

agency’s interpretation of the scope of its own statutory jurisdiction:

“[s]tatutory ambiguities will be resolved, within the bounds of reasonable

interpretation, not by the courts but by the administering agency.”267

There is

no distinction in terms of deference afforded the agency between an agency’s

“jurisdictional” and “nonjurisdictional” interpretations:268

“If ‘the agency’s

answer is based on a permissible construction of the statute,’ that is the end of

the matter.”269

This most recent Supreme Court decision on agency deference

is consistent with recent determinations by FERC about its own scope of

authority on ROFR.270

While the FCC is not FERC, it is a federal utility regulatory agency, and

its relevance to the pending FERC ROFR energy issue is significant. Both

federal agencies operate under federal statutes of similar vintage: The Federal

Power Act of 1935,271

and the Communications Act of 1934.272

The division

between federal and state authority under each of these statutes is similar:

Local authorities approve the siting and construction of cell phone towers and

facilities, subject to federal limitations interpreted by FCC regulation.273

263. 16 U.S.C. §§ 824 (2012).

264. S.C. Pub. Serv. Auth. v. FERC, Nos. 12-1232, 12–1233, 12–1250, 12–1276, 12–1279, 12–1280, 12–

1285, 12–1292, 12–1293, 12–1296, 12–1299, 12–1300, 12–1304, 12–1448, 12–1478, 2014 WL 3973116 (D.C.

Cir. 2014).

265. City of Arlington v. FCC, 133 S. Ct. 1863, 1866 (2013).

266. Id. at 1874–75.

267. Id. at 1868. Under Chevron, the court must first ask whether Congress directly spoke to the precise

question at issue; if so, the court must give effect to Congress’ unambiguously expressed intent. Chevron v.

Nat’l Res. Def. Council, 467 U.S. 837, 842–43 (1984). However, if “the statute is silent or ambiguous,” the

court must defer to the administering agency’s construction of the statute so long as it is permissible. Id. at

843.

268. City of Arlington, 133 S. Ct. at 1871 (“no ‘exception exists to the normal deferential standard of

review’ for ‘jurisdictional or legal questions concerning the coverage’ of an Act.”). “[T]here is no principled

basis for carving out some arbitrary subset of such claims as ‘jurisdictional’.” Id. at 1865.

269. Id. at 1868 (citing Chevron, 467 U.S. at 842). The Supreme Court has afforded Chevron deference

to agencies’ constructions of the scope of their own jurisdiction. See, e.g., United States v. Eurodif, 555 U.S.

305, 316 (2009) (affording Chevron deference); Commidity Futures Trading Comm’n v. Schor, 478 U. S. 833,

844 (1986) (affording Chevron deference).

270. City of Arlington, 133 S. Ct. at 1870–71. See, e.g. Sebelius v. Auburn Reg’l Med. Ctr., 133 S. Ct.

817 (2013) (applying the Chevron framework); Christopher v. SmithKline Beecham Corp., 132 S. Ct. 2156

(2012); National Cable & Telecomm. Ass’n., 534 U.S. 327; United States v. Riverside Bayview Homes, 474

U.S. 121 (1985).

271. 16 U.S.C. § 791, et seq (2012).

272. 47 U.S.C. §151, et seq (2012).

273. City of Arlington, 133 S. Ct. at 1866–67; Rancho Palos Verdes v. Abrams, 544 U.S. 113, 115

(2005).

Page 34: pentagon preemption: the 5-sided loss of state energy and power

426 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

FERC regulates interstate, wholesale, and transmission transactions.274

The

FCC regulates communication utilities, FERC regulates other electric and gas

utilities.275

Since Order 1000 has been upheld by the D.C. Circuit on appeal,276

state

ROFR legislation would then face strict scrutiny, under which legislation does

not usually survive, under a Supremacy or Commerce Clause challenge. This

is the third side of the preemption pentagon which will soon be construed by

the federal courts.

III. THE OUTSIDE ENERGY BAR AND PREEMPTION OF STATE POWER

Not all state energy regulation attempts to provide incentives to certain

in-state power.277

Some states have attempted to disadvantage certain energy

when it would compete in state markets.278

This has manifested in four

regulatory mechanisms:

Banning continued operation of an individual power generation

facility unless it sells its wholesale power to in-state entities at a

significant discount to market rates279

Refusing to treat out-of-state wholesale renewable energy on an equal

basis to in-state wholesale renewable energy280

Banning out of state fuels or their use to generate power in the state281

Disadvantaging out-of-state fuels because of the greater global

warming effect of transporting that fuel a longer distance into the

state282

Does this allow a state to regulate interstate commerce extraterritorially?

Do state environmental purposes overrule the Constitution’s Supremacy

Clause ‘bright line’ on energy? Sides 4 and 5 of the pentagon feature these

constitutional issues.

274. Supra, Section II.B.

275. See generally, Regulatory Agencies, TEX. OFF. PUB. UTIL. COUNS., http://www.opuc.texas.gov/

regulatory%20agencies.html (last visited Oct. 6, 2014) (providing a description of several government

agencies).

276. S.C. Pub. Serv. Auth. v. Fed. Energy Regulatory Comm’n, No. 12-1232, 2014 WL 3973116 (D.C.

Cir. 2014).

277. See THE ELECTRIC ENERGY MARKET COMPETITION TASK FORCE, REPORT TO CONGRESS ON

COMPETITION IN WHOLESALE AND RETAIL MARKETS FOR ELECTRIC ENERGY 25 (2005) (discussing retail

electricity competition and state electric restructuring initiatives).

278. Id.

279. Infra Section III.A.1.

280. Infra Section III.A.2.

281. Infra Section III.A.3.

282. Infra Section III.B. The state regulation to burden out-of-state energy is now propounded in the

furtherance of control of climate change. Id. Distance of travel of commerce requires more use of fossil fuels

to transport the commerce, which increases emissions of greenhouse gases (“GHGs”) with each additional

mile. Id. Therefore, the more distance between the commerce fabrication and consumption, the more effects

on the environment, ceteris paribus. Id. This rationale has been used by California to burden certain energy

fuels that either travel a long distance to California, or are fabricated in the Midwest where more high-GHG

coal is used to make the fuel. Id.

Page 35: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 427

A. Preemption Pentagon Side 4: Excluding Certain Power Generation

Facilities and Their Power from a State

Some states have attempted to either disadvantage or exclude existing

power generation facilities or their power generated from their states.283

Because this is wholesale power in interstate commerce, Constitutional

Supremacy Clause issues are raised. Some states regulation has been

constitutionally stricken.284

1. Wholesale Power Sale Price Constitutional Trip-Wires

Preemption of state power to regulate energy matters and state violations

of the dormant Commerce Clause in 2012 were found by a federal court in a

much-watched case in Vermont.285

As part of its regulation, Vermont

attempted to extract financial concessions from the private power owners as a

condition of a continued license to operate the generating facility in the

state.286

Whether a state can regulate to favor in-state consumer interests,

without fundamentally violating the Constitution’s Supremacy Clause287

is a

fundamental legal issue.

The change at issue involved when an existing statute was fundamentally

altered by Vermont in 2006 immediately after the project owner filed to extend

its federal operating license,288

by adding state amendments to Section 248, by

Act No. 160,289

requiring discretionary approval as a condition for extension

of an existing state energy generating facility operating license,290

from both

the legislature and from the state Public Service Board.291

Prior to these 2006

amendments, under the original Section 231 of the state statute, only the Public

Service Board, a quasi-judicial semi-independent authority, had approval

authority for such extensions through its tightly constrained adjudicatory

process.292

Vermont legislators required Vermont Yankee to provide discounts

283. Infra Section III.A.1–3, B.

284. Infra Section III.A.1–3.

285. Entergy Nuclear Vt. Yankee v. Shumlin, 838 F. Supp. 2d 183, 198–200 (D. Vt. 2012).

286. Id.

287. U.S. CONST. art. VI, cl. 2.

288. Consideration of what would become Act 160, began by the Vermont legislature one week after

Entergy applied to the NRC for a license extension in 2006. Entergy Nuclear Vt. Yankee, v. Shumlin, 733 F.3d

393, 403 (2d Cir 2013).

289. Shumlin, 838 F. Supp. 2d at 198–200.

290. See VT. STAT. ANN. tit. 30, § 248(e)(2) (2008) (Requiring, in Act 160, a legislative vote as a

prerequisite additional step: “[T]he board may commence proceedings under this section and under 10 V.S.A.

chapter 157, relating to the storage of radioactive material, but may not issue a final order or certificate of

public good until the general assembly determines that operation will promote the general welfare and grants

approval for that operation.”). (emphasis added).

291. Id.

292. Shumlin, 838 F. Supp. 2d at 192 (citing VT. STAT. ANN. tit. 30, §§ 11–12 (2008)): At the time the 2002 MoU was signed, the Public Service Board was the quasi-judicial entity bestowed with statutory authority to consider petitions and grant CPGs . . . [and] is required to ‘make . . . findings of fact,’ to ‘state its rulings of law when they are excepted to,’ and its decisions can be appealed to the Vermont Supreme Court, which is required to accord them deference.

Moreover, there is specific precedent as to what constitutes the Board’s public convenience, through a history

Page 36: pentagon preemption: the 5-sided loss of state energy and power

428 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

from the future market-based wholesale price of power to be sold to in-state

incumbent utilities as a requirement for granting a CPG for future operation of

Vermont Yankee as an existing wholesale power generation facility.293

Hearings in Vermont on the PSB agency petition, advancing in an adjudicatory

forum,294

were halted when the state senate voted not to approve or permit

such a new CPG in early 2010.295

Judicial relief was sought by the existing facility owner.296

The federal

trial court ruled that this Vermont regulation of energy violated the Supremacy

Clause in two different regards and was preempted, as well as the dormant

Commerce Clause Constitutional limitations on state energy regulation;

although in one regard one of the preemption claims was not yet ripe.297

On

appeal, the Second Circuit did not disagree with the substantive decision on the

dormant Commerce Clause, but procedurally held the issue also was not yet

ripe for review until plaintiffs actually entered a forced PPA with the state.298

The Second Circuit concurred that it was ripe to find the Vermont statute

preempted on one of the two claims by federal law, and struck the statute as

unconstitutional.299

The state of Vermont could not control sale of power interstate outside of

its origin in Vermont.300

The federal trial court held that the Federal Power

of determinations and orders; See Statues, Rules and Guidelines, VT. PUB. SERV. BD., http://psb.vermont.gov/

statutesrulesandguidelines (last visited Oct. 6, 2014) (listing the Public Service Board’s determinations and

orders).

293. Id.; Complaint ¶ 103, Entergy Nuclear Vt. Yankee, L.L.C. v. Shumlin, 838 F. Supp. 2d 183 (D. Vt.

2012) (No. 11-CV-99).

294. For discussion of administrative law adjudicatory proceedings, see generally FERREY, supra note

50, at 45–48 (stating that proceedings before a state electric energy regulatory agency have the attributes of a

trial to protect all participants. Formal legal rules govern the trial-like process). There is formal presentation of

sworn evidence, cross-examination by counsel, procedural motions, discovery of documents, briefs filed by the

parties, and a decision that must be based on the formal transcribed record and based on the weight of

substantial evidence). Id. at 47–48. Appeal is allowed to the courts based on either procedural issues or a

decision not based on formal substantial evidence. Id. at 48 (contrasting a decision of a state legislature, which

has no such formal legal protections).

295. “Senate Votes to Close Vermont Yankee Nuclear Plant in 2012,” BURLINGTON FREE PRESS (Feb. 24,

2010), http://www.burlingtonfreepress.com/viewart/20100224/NEWS02/100224050/Senate-votes-close-

Vermont-Yankee-nuclear-plant-2012 (The federal NRC had renewed the plant’s federal operating license in

March 2011 for an additional twenty years past its scheduled expiration).

296. Complaint ¶¶ A, B, C, D, Entergy Nuclear Vt. Yankee, L.L.C. v. Shumlin, 838 F. Supp. 2d 183 (D.

Vt. 2012) (No. 11-CV-99).

297. Id.

298. Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 733 F.3d 393, 428 (2d Cir. 2013). There was needed

still: [A] factual record concerning incidental effects of such an agreement on interstate commerce . . . This case therefore does not present a ‘concrete dispute affecting cognizable current concerns of the parties within the meaning of Article III,’ and is therefore not ‘ripe within the constitutional sense.’ . . . However, no [PPA] agreement is before us. Accordingly, the analysis required under the dormant Commerce Clause may not be performed, and so Entergy’s claim is unripe at this time.

Id. at 430–31.

299. Id. at 433.

300. Entergy Nuclear Vt. Yankee, L.L.C. v. Shumlin, 838 F. Supp. 2d 183, 224 (D. Vt. 2012). The court

held: [S]tates are ‘without power to prevent privately owned articles of trade from being shipped and sold in interstate commerce on the ground that they are required to satisfy local demands or because they are needed by the people of the State . . . [a] “protectionist regulation”‘ violating

Page 37: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 429

Act invests the Federal Energy Regulatory Commission with “exclusive

authority to regulate the transmission and sale at wholesale of electric energy

in interstate commerce, and struck state regulation as unconstitutional.”301

The

Vermont federal trial court decision held:

Under the Federal Power Act, 16 U.S.C. § 791a et seq.:

Congress has drawn a bright line between state and federal

authority in the setting of wholesale rates and in the

regulation of agreements that affect wholesale rates. States

may not regulate in areas where FERC has properly exercised

its jurisdiction to determine just and reasonable wholesale

rates or to insure that agreements affecting wholesale rates

are reasonable.302

“[A] state ‘must . . . give effect to Congress’ desire to give FERC plenary

authority over interstate wholesale rates, and to ensure that the States do not

interfere with this authority.’”303

“Under the ‘filed-rate doctrine,’ state courts

and regulatory agencies are preempted by federal law from requiring the

payment of rates other than the federal filed rate.”304

The difference between the Vermont federal district court and the Second

Circuit opinions is one of slight distinction on the procedural ripeness of one

issue presented, prior to that issue being handled by FERC, rather than of

substance:

On the first federal preemption claim in Count 1: Both courts agreed

that the Vermont law was preempted and permanently enjoined its

enforcement as unconstitutional.305

On the second preemption claim in Count 2: “The [trial] court then

held that even if Entergy were to be forced to enter into a new PPA

[power purchase agreement] in violation of the market-based tariff, its

recourse would be to have the agreement reviewed by FERC. The trial

court thus declined to enjoin the defendants on the basis of this

Federal Power Act claim,” and both the district and Second Circuit

courts agreed that this issue was not yet ripe for review since FERC

the Commerce Clause.

Id. at 236.

301. Id. at 236; see also 16 U.S.C. § 824(b)(1) (2012) (discussing Congress’s power to set rates); New

England Power Co. v. New Hampshire, 455 U.S. 331, 340 (1982) (quoting the federal trial court).

302. Shumlin, 838 F. Supp. 2d at 233 (quoting Miss. Power & Light Co. v. Miss. ex rel. Moore, 487 U.S. 354,

374 (1988)).

303. Id. (quoting Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 966 (1986)).

304. Id.. See Entergy La., Inc. v. La. Pub. Serv. Comm’n, 539 U.S. 39, 47 (2003) (“The filed rate doctrine

requires ‘that interstate power rates filed with FERC or fixed by FERC must be given binding effect by state utility

commissions determining intrastate rates.”).

305. Shumlin, 838 F. Supp. 2d at 233. We do not blindly accept the articulated purpose of [a state statute] for preemption purposes. If that were the rule, legislatures could nullify nearly all unwanted federal legislation by simply publishing a legislative committee report articulating some state interest or policy—other than frustration of the federal objective—that would be tangentially furthered by the proposed state law.

Id. (quoting Greater N.Y. Metro. Food Council, Inc. v. Giuliani, 195 F.3d 100, 108 (2d Cir. 1999) abrogated

on other grounds by Lorillard Tobacco Co. v. Reilly, 533 U.S. 525, (2001)).

Page 38: pentagon preemption: the 5-sided loss of state energy and power

430 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

review had not yet occurred.306

On the third preemption claim in Count 3: The trial court found

unconstitutional and issued an injunction “enjoin[ing] Defendants

from conditioning Vermont Yankee’s continued operation on the

existence of a below-market PPA with Vermont utilities.”307

The

Second Circuit did not disagree with the substantive decision on the

dormant Commerce Clause and found preemption likely, but

procedurally held that this issue was not yet ripe for review until

plaintiffs actually entered such a forced PPA with the state.308

The distinction made by the Second Circuit was only procedurally based

on the issue not yet being ripe for review—a final decision on Count 3 needed

to await until there was a PPA entered and there was developed: “a factual

record concerning incidental effects of such an agreement on interstate

commerce. This case therefore does not present a ‘concrete dispute affecting

cognizable current concerns of the parties within the meaning of Article III,’

and is therefore not “ripe within the constitutional sense.”309

The fact that no PPA had been entered made Counts 2 and 3 not yet ripe

procedurally for court decision: “no [PPA] agreement is before us.

Accordingly, the analysis required under the dormant Commerce Clause may

not be performed, and so Entergy’s claim is unripe at this time.”310

2. The Constitutional Line on Transmission and Renewable Power Credits

When dealing with power, can states be compelled to pay for the

infrastructure to move power that they do not want? This infrastructure is not

the power itself, but the transmission infrastructure used to move power in

America. A study by the U.S. Department of Energy forecasts that 39,000

miles of additional high voltage transmission circuits to be constructed in the

next decade.311

Transmission infrastructure is distinct from distribution infrastructure.312

More straightforward approaches to determining what is transmission and what

is distribution was blurred by FERC Order 888, which created a seven-factor

306. Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 733 F.3d 393, 407 (2d Cir. 2013).

307. Shumlin, 838 F. Supp. 2d at 239.

308. See Shumlin, 733 F.3d at 438 (“Vermont argues, however, that the district court erred in issuing an

injunction on the basis of its finding mere intent on the part of the defendants to seek a favorable PPA, and that

the issue was therefore not ripe for judicial review. We agree.”); id. at 430 (“[A] factual record concerning

incidental effects of such an agreement on interstate commerce. This case therefore does not present a

‘concrete dispute affecting cognizable current concerns of the parties within the meaning of Article III,’ and is

therefore not ‘ripe within the constitutional sense.’”).

309. Id. at 430.

310. Id. at 431.

311. NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL, LONG-TERM RELIABILITY ASSESSMENT 23

(Oct. 2010).

312. See generally FERREY, supra note 51, at 5–10 (“The former traditionally is comprised of the higher

voltage copper and aluminum lines, typically operating at above 69 kV. The latter traditionally includes lower

voltage lines, typically operating below 69 kV.”).

Page 39: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 431

test regarding the purpose for which power is moved in individual transactions,

to determine whether it is transmission or distribution.313

The distinction

between transmission and distribution facilities is more than an engineering

question about voltage. It has profound implications for the structure of

preemption.

In a recent decision of the Seventh Circuit Court of Appeals,

314 what was

at issue was clearly transmission infrastructure. Judge Richard Posner,

speaking for the Seventh Circuit Court of Appeals in a unanimous circuit

decision, affirmed the Federal Energy Regulatory Commission’s approval of

the Midwest Independent Service Operator’s (MISO)315

proportionate

customer utility allocation of transmission costs for high-voltage transmission

lines to move renewable wind power to populated areas.316

The petitioning

states raised six challenges,317

each of which was rejected by the Seventh

Circuit Court of Appeals.318

The court dismissal the Tenth Amendment

challenge as “frivolous,” noting that it was “a far cry from the federal

government’s conscripting a state government into federal service.”319

The

court deferred to the federally sanctioned determination of cost allocation.320

For authority for its holding on the respective jurisdiction of state and

federal government to regulate electricity, the opinion relied on a 2012 law

review article on Constitutional energy issues authored by Professor Ferrey.321

The Seventh Circuit declared unconstitutional state regulation limiting state

renewable portfolio standards to in-state generation, as a violation of the

Commerce Clause: “it trips over an insurmountable constitutional objection.

313. Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission

Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order

No. 888, FERC Stats. & Regs. ¶ 31,036, 61 Fed. Reg. 21,540 (1996), clarified, 76 FERC P 61,009 and 76

FERC P 61,347 (1996), on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274,

clarified, 79 FERC P 61,182 (1997), on reh’g, Order No. 888-B, 81 FERC P 61,248, 62 Fed. Reg. 4,688

(1997), on reh’g, Order No. 888-C, 82 FERC P 61,046 (1998); FERREY, supra note 108, at 41–42; FERREY,

supra note 51, at 10–5.

314. Ill. Commerce Comm’n v. Fed. Energy Regulatory Comm’n, 721 F.3d 764 (7th Cir. 2013).

315. Id. at 769 (showing that MISO’s service area extends from the Canadian border, east to Michigan

and parts of Indiana, south to northern Missouri, and west to eastern areas of Montana).

316. Id. at 765 (providing that MISO allocated the costs of the transmission projects among all of the

utilities who draw power from the MISO grid in proportion to each utilities’ overall volume of usage; FERC

approved MISO’s rate design, which led some states to initiate court appeal.)

317. The six challenges were: Does FERC’s approval of the MISO transmission tariff violate the Tenth

Amendment to the Constitution by coercing states into approving all MVPs proposed within their borders?

Are the benefits associated with the transmission projects proportional to the costs imposed? Did FERC have

to conduct an administrative evidentiary hearing during its consideration of MISO’s proposed financing

mechanism? May MISO allocate the total costs of new transmission among the load of member utilities on the

basis of their overall power consumption while allocating no costs to generation? Can MISO allocate costs

associated with the transmission to non-member utilities which are members of PJM ISO? Can MISO allocate

costs to utilities which are leaving MISO? Id. at 772–73.

318. Id. (explaining the rejections made by the Seventh Circuit Court of Appeals).

319. Id. at 772–73.

320. Judge Posner noted that the petitioners failed to provide any estimates of costs and benefits

associated with the new facilities to contradict MISO’s estimated $297 million cost savings. Ill. Commerce

Comm’n., 721 F.3d at 774.

321. Id. at 776; Ferrey, supra note 52, at 59 (having been cited by Seventh Circuit on Constitutional

authority regarding state energy regulation).

Page 40: pentagon preemption: the 5-sided loss of state energy and power

432 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

Michigan cannot, without violating the commerce clause of Article I of the

Constitution, discriminate against out-of-state renewable energy.”322

The

Commerce Clause is another prong of Constitutional contours within which

state regulation must fit,323

which is beyond the scope of this article. The

Supreme Court has denied certiorari for this case.324

3. Transmission and Generation of High-Carbon Power

Section III A1, above, addressed interpretation of preemption when states

manipulate wholesale prices of power sale for power generated within their

states, and Section III A 2, above, addressed Constitutional limits on states

burdening interstate renewable power sales originating from a source exterior

to the regulating state. A combination of both elements comes together when a

state attempts to bar certain types of power generation in the state or import of

certain types of power transmitted into the state. This issue was addressed in

2014 by a federal court in the Midwest.325

Minnesota’s Next Generation Energy Act is a law aimed at reducing

carbon dioxide emissions from large power plants outside the state and banned

the import of foreign coal for power generation or coal-produced power into

Minnesota:326

“no person shall . . . import or commit to import from outside the

state power from” coal production facilities or “enter into a new long-term

power purchase agreement that would increase statewide power sector carbon

dioxide emissions.”327

The law bans Minnesota utilities from importing power

from new coal plants outside the state, and raises the cost of future purchases

of coal power by assigning environmental costs to use of the fuel.328

The Act

prohibits construction of new coal plants in the state and restricts utilities from

creating any more long-term power-purchase agreements for coal-derived

322. Ill. Commerce Comm’n., 721 F.3d at 776. Michigan actually initiated the issue of in-state electric

power discrimination in its RPS program as a demonstration that out-of-state powered transmitted to it was not

recognized as of the same value as in-state electricity, therefore Michigan should not pay a share of power line

tariffs transmitting power from out of state that did not have equal recognition and benefit. Instead of

supporting its position, this assertion caused Judge Posner and the Court to respond to this assertion, even

though it was not the tariff issue before the Court. Id.

323. Id.

324. Ill. Commerce Comm’n v. Fed. Energy Regulatory Comm’n, 721 F.3d 764 (7th Cir. 2013), cert. denied

sub nom. Schuette v. Fed. Energy Regulatory Comm’n., 134 S. Ct. 1277 (2014) and cert. denied sub nom. Hoosier

Energy Rural Electric Co-op, Inc., et al. v. Fed. Energy Regulatory Comm’n., 134 S. Ct. 1278 (2014).

325. North Dakota v. Heydinger, No. 11-CV-3232, 2014 WL 1612331, at *1 (D. Minn. April 18, 2014).

326. 2007 Minn. Laws Ch. 136, art. 5, § 3; MINN. STAT. § 216H.03, subd. 3 (Minnesota-based utilities

operate power plants in west-central North Dakota’s coal-producing region. The power stations are fueled by

nearby lignite mines. The law made exceptions for Minnesota coal projects).

327. MINN. STAT. § 216H.03, subd. 3 (establishing the provision which limits increases in statewide

power sector carbon dioxide emissions).

328. Id. (providing that no person shall “import or commit to import from outside the state power from a

new large energy facility that would contribute to statewide power sector carbon dioxide emissions.”). A “new

large energy facility” is defined as “any electric power generating plant or combination of plants at a single

site with a combined capacity of 50,000 kilowatts or more and transmission lines directly associated with the

plant that are necessary to interconnect the plant to the transmission system.” MINN. STAT. § 216B.2421, subd.

2(1), but excludes facilities that “use[] natural gas as a primary fuel.” MINN. STAT. § 216H.03, subd. 1.

Page 41: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 433

energy from other states.329

The law does not prohibit an extension for

existing contracts with existing coal-fired generation units.330

North Dakota and others sued Minnesota as the statute was a violation of

the dormant Commerce Clause by discriminating against North Dakota’s use

of coal and export of power in interstate commerce.331

North Dakota alleged

that it affects the wholesale price and transmission of power and burdens

interstate power sales.332

The court addressed the balkanization that the

Commerce Clause was designed to prevent.333

The court noted that with the

presence and operation of the Midcontinent Independent System Operator

(“MISO”), the area’s regional transmission organization, the Act can affect

out-of-state entities, including regulatory agencies:

If any or every state were to adopt similar legislation (e.g., prohibiting the use of electricity generated by different fuels or requiring compliance with unique, statutorily-mandated exemption programs subject to state approval), the current marketplace for electricity would come to a grinding halt. Such a scenario is “just the kind of competing and interlocking local economic regulation that the Commerce Clause was meant to preclude.” Healy, 491 U.S. at 337.

334

The court declined to even need or be required to reach the issue of

whether there was undue discrimination in the substance of the Minnesota

statute.335

Instead, the court went directly to the issue that Minnesota acted

extra-territorially in terms of the effects of its regulation on commerce in

electricity originating in other states.336

The Minnesota Federal Court

highlighted precedent of the Supreme Court and many appellate courts

including a prior decision of the Seventh Circuit337

(which was also deciding

the Illinois v. FERC case338

) which used extraterritoriality rationale for aspects

not focused on price regulation.339

Price regulation seemed to be the only

scrutiny imposed by the California federal court in the Rocky Mountain case.340

329. Id. Exemptions were made for the proposed Excelsior Energy integrated gasification combined

cycle (IGCC) plant in northern Minnesota, the Big Stone II coal plant in South Dakota, and the Maple Grove-

based Great River Energy’s Spiritwood Station plant in North Dakota. MINN. STAT. § 216B.1694 (2008) 2009

Minn. PUC LEXIS 6; 2010 Minn. PUC LEXIS 458.

330. MINN. STAT. § 216H.03, subd.7.

331. North Dakota v. Heydinger, No. 11-CV-3232, 2014 WL 1612331, at *4 (D. Minn. April 18, 2014).

332. Id. at *21. Plaintiffs include North Dakota, Basin Electric Power Cooperative, North American Coal

Corp., Great Northern Properties LP, Missouri River Energy Services, Lignite Energy Council, and Minnkota

Power Cooperative Inc. Id. at *13–14.

333. Id. at *22.

334. Id. at *24.

335. Id. at *16.

336. Id. at *16.

337. See Nat’l Solid Wastes Mgmt. Ass’n v. Meyer, 63 F.3d 652, 658 (7th Cir. 1995) (“The practical

impact of the Wisconsin statute on an economic activity completely outside the State reveals its basic

infirmity . . . .”).

338. Ill. Commerce Comm’n v. Fed. Energy Regulatory Comm’n, 721 F.3d 764 (7th Cir. 2013); see

discussion supra Section III.A.2 (discussing the Constitutionality of transmission and renewable power

credits).

339. Heydinger, 2014 WL 1612331, at *17–18.

340. Infra. Section III.B.

Page 42: pentagon preemption: the 5-sided loss of state energy and power

434 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

The Minnesota Federal Court announced the fundamental Commerce

Clause principle that “any attempt directly to asset extraterritorial jurisdiction

over persons or property would offend sister States and exceed the inherent

limits of State’s power.”341

Finding that it had acted clearly to affect

commerce occurring outside the state, the court found this a per se violation of

the Commerce Clause:

The Court finds that Minn. Stat. § 216H.03, subd. 3(2)-(3), violates the extraterritoriality doctrine and is per se invalid and, therefore, the Court need not address whether the statute is discriminatory or fails a Pike analysis. Under the extraterritoriality doctrine, “[t]he Commerce Clause precludes application of a state statute to commerce that takes place wholly outside of the state’s borders.” Cotto Waxo Co., 46 F.3d at 793 (citing Healy, 491 U.S. at 336). In other words, a state statute is invalid “when the statute requires people or businesses to conduct their out-of-state commerce in a certain way.” Id. This is true regardless of whether the commerce has effects within the state, Edgar v. MITE Corp., 457 U.S. 624, 642-43 (1982), and regardless of whether the legislature intended for the statute to have an extraterritorial effect, Healy, 491 U.S. at 336. “The critical inquiry is whether the practical effect of the regulation is to control conduct beyond the boundaries of the State.” Id. (emphasis added) (citing Brown-Forman Distillers Corp. v. N.Y. State Liquor Auth., 476 U.S. 573, 579 (1986)). The practical effect of a statute is evaluated by looking not only at “the consequences of the statute itself,” but also at “how the challenged statute may interact with the legitimate regulatory regimes of other States and what effect would arise if not one, but many or every, State adopted similar legislation.” Id.

342

In the testimony of an expert in the case, “[o]nce the generating facility

injects its output into the interconnected transmission network, the electrons

move according to physical laws, unresponsive to any state law or contract

provisions.”343

Weighing the effect of the Minnesota statute’s extra-territorial

reach on electricity commerce, that by its very nature was unavoidably

interstate, the Minnesota federal court determined that in its basic scope the

Minnesota statute was discriminatory in violation of the most basic elements of

the Commerce Clause, even without more detailed application of a strict

scrutiny or Pike balancing test: “Therefore, in each of those cases, the courts

found that the statute at issue did not require out-of-state parties to transact out-

of-state business according to the regulating state’s terms because the

manufacturers could simply avoid engaging in the prohibited conduct when

transacting out-of-state business.”344

The federal court in Minnesota made a critical distinction between

341. Heydinger, 2014 WL 1612331, at *16–17 (citing Edgar v. MITE Corp., 457 U.S. 624, 642 (1982)).

342. Id. at *16.

343. Id. at *2 (internal citations omitted).

344. Id. at *23.

Page 43: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 435

electricity unavoidably in interstate commerce, and the more controllable

liquid ethanol fuels in commerce in the Rocky Mountain Commerce Clause

litigation345

proceeding at the same time in California:

Because of the boundary-less nature of the electricity grid, the effect of Minn. Stat. § 216H.03’s regulatory scheme on interstate commerce is much different than that of the statutes at issue in Cotto Waxo Co., National Electrical Manufacturers Ass’n, and Rocky Mountain, where the Circuit Courts declined to invalidate the regulations on extraterritoriality grounds. Those cases dealt with the regulation of tangible products (sweeping compounds, light bulbs, and ethanol, respectively) that could be shipped directly from point A to point B.

346

The Minnesota Court treated electricity distinctly from other energy

sources, which it is both in terms of its physics and its status in American

law.347

This is a physical reality not always brought to the attention of courts,

but when it is, the Supreme Court348

and other courts have upheld its

ineluctably interstate nature. The fifth side of the pentagon, did not find such

preemption when dealing with liquid fuels.349

B. Preemption Pentagon Side 5: The Rocky Mountain Divide on

Interstate Energy Commerce

California is accused of attempting to discriminate against interstate

commerce in the transport of certain energy resources, while exempting in-

state transport from an equivalent burden.350

All of this was to address the

energy-related aspects of climate change.351

1. The California Low Carbon Fuel Standard

The purpose of California’s low carbon fuel standard (“LCFS”) is “to

implement a low carbon fuel standard, which will reduce greenhouse gas

emissions by reducing the full fuel-cycle, carbon intensity of the transportation

fuel pool used in California.”352

The LCFS was “designed to reduce

California’s dependence on petroleum” and “to stimulate the production and

use of alternative, low-carbon fuels in California.”353

The LCFS regulates

transportation fuels that are “sold, supplied, or offered for sale in California”

and focuses on the “carbon intensity” of fuels, a metric designed to assess “the

345. See discussion infra Section III.B (discussing interstate energy commerce after the Rocky Mountain

decision).

346. Heydinger, 2014 WL 1612331, at *23.

347. Ferrey, supra note 202, at 1861–84; FERREY, supra note 51 at 2–8; FERREY, supra note 50, at 568.

348. Fed. Energy Regulatory Comm’n v. Mississippi, 456 U.S. 742, 757 (1982).

349. See infra Section III.B (explaining interstate energy commerce after the Rocky Mountain decision).

350. See infra Section III.B.2 (discussion of California regulation of Low Carbon Fuel).

351. See infra Section III.B.2 (discussion of California regulation of Low Carbon Fuel).

352. CAL. CODE REGS. tit. 17 § 95480 (2010).

353. CAL. AIR RES. BD., CALIFORNIA’S LOW CARBON FUEL STANDARD: FINAL STATEMENT OF REASONS

457 (December 2009), available at http://www.arb.ca.gov/regact/2009/lcfs09/lcfsfsor.pdf.

Page 44: pentagon preemption: the 5-sided loss of state energy and power

436 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

amount of lifecycle greenhouse gas emissions, per unit of energy of fuel

delivered, expressed in grams of carbon dioxide per megajoule.”354

The LCFS rule is to reduce the carbon content of transportation fuels sold

in California by 10% by the year 2020 from the year 2010 baseline.355

The

LCFS is a “set of regulations to govern the marketing of gasoline-ethanol

blends sold in California.”356

The goal of LCFS is to reduce carbon intensity

of fuels by 10% by 2020 through regulations requiring providers of gasoline

and diesel fuels to calculate the carbon intensity (CI) of each fuel component,

report such calculations to CARB, and make reductions in order to meet the

carbon intensity standards.357

CARB’s LCFS rule includes the lifecycle GHG

emissions of fuel, including emissions produced during production and

transportation of fuels to California.358

Carbon intensity is not limited to how

much carbon the fuel contains, but also includes the amount of carbon released

in the full fuel cycle including its transportation over distances to California

markets.359

To accomplish this carbon intensity reduction, the LFCS assigns carbon

intensity scores to all covered fuels.360

To lower their carbon intensity scores,

providers may blend low-carbon ethanol into gasoline.361

But even if a

provider blends low-carbon ethanol into their fuel, the provider’s carbon

intensity score also is affected by the other factors of the greenhouse gas

emissions lifecycle, in particular, the location of the commerce and distance

from California markets.362

Corn-derived ethanol produced in the Midwest is

assigned a higher carbon intensity score than chemically similar corn-derived

ethanol produced anywhere in California, regardless of its transportation

within California.363

Thus, a chemically identical ethanol imported from the

Midwest is deemed to have a higher carbon intensity than ethanol produced

anywhere in California, making the Midwest product more expensive for fuel

354. Rocky Mountain Farmers Union v. Goldstene, 843 F. Supp. 2d 1071, 1081 (E.D. Cal. 2011).

355. CAL. AIR RES. BD., supra note 353 at 180.

356. Rocky Mountain Farmers Union v. Goldstene, 719 F. Supp. 2d 1170, 1177 (E.D. Cal. 2010).

357. Id.

358. Id.

359. CAL. CODE REGS. tit. 17 § 95481(a)(38) (2012). The LCFS refers to this inclusive concept as the

“lifecycle greenhouse gas emissions,” which is defined as: aggregate quantity of greenhouse gas emissions

(including direct emissions and significant indirect emissions such as significant emissions from land use

changes), as determined by the Executive Officer, related to the full fuel lifecycle, including all stages of fuel

and feedstock production and distribution, from feedstock generation or extraction through the distribution and

delivery and use of the finished fuel to the ultimate consumer, where the mass values for all greenhouse gases

are adjusted to account for their relative global warming potential.

360. Goldstene, 719 F. Supp. 2d at 1177; Rocky Mountain Farmers Union v. Goldstene, 843 F. Supp. 2d

1071, 1082 (E.D. Cal. 2011). The LCFS does allow for providers to apply for a customized total carbon

intensity value rather than be subject to the assigned default score, which providers in the Midwest have

applied.

361. Goldstene, 719 F. Supp. 2d at 1177. Providers may also buy credits generated from another fuel

provider that has credits in order to meet LFCS standards.

362. Id. at 1178.

363. Id. The carbon intensity calculation does not account for intrastate shipping within the state,

notwithstanding that California is the third largest U.S. state geographically. California’s 770 miles in length

is greater than the distance from ten other states to California. Thus, all fuel, wherever produced in California

and wherever consumed, does not incur a higher carbon efficiency factor for purposes of this regulation.

Page 45: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 437

providers seeking to meet the California fuel standard requirements.

In a case distinct from a somewhat similar suit on the merits by other

parties under Constitutional principles in federal court,364

the largest ethanol

producer in the United States challenged the LCFS rule in California state

court, alleging a failure to comply with the California Environmental Quality

Act (CEQA).365

The California state appellate court held that California had,

in fact, violated CEQA and the California Administrative Procedure Act by

approving the regulation before the required review under CEQA.366

The

California Supreme Court denied a petition from CARB seeking review, and

the agency is required to reopen the LCFS.367

In a prior analogous matter, the

Ninth Circuit held that the public must have an opportunity to comment on

government environmental assessments and environmental Findings of No

Significant Impact at all points in the rulemaking process, pursuant to the

equivalent federal environmental law, NEPA:368

We have determined that an environmental plaintiff was “surely . . . harmed [when agency action] precluded the kind of public comment and participation NEPA requires in the EIS process,” and that this type of “procedural” injury is tied to a substantive “harm to the environment”—“the harm consists of added risk to the environment that takes place when governmental decisionmakers make up their minds without having before them an analysis (with public comment) of the likely effects of their decision on the environment. NEPA’s object is to minimize that risk, the risk of uninformed choice….”

369

However, on Constitutional issues, the litigation was in federal court.

2. Preemption of California Regulation?

Plaintiffs argued that CARB’s LCFS regulations were preempted by

federal environmental law,370

when LCFS closed off California to those

federally grandfathered bio-refineries which would need either to not

participate in the California ethanol fuel market or reduce their carbon

364. Id.

365. Poet, LLC v. Cal. Air Res. Bd., 160 Cal. Rptr. 3d 69, 83 (Cal. Ct. App. 4th 2013). Poet argued that

CARB failed to respond to numerous public comments, that it omitted documents from the rulemaking file,

and that the LCFS will lead to increased GHG emissions, not the reductions it promises. Id. Poet alleged that

CARB’s LCFS rule exceeds the scope of authority delegated to it by the legislature. Id. at 76–77.

366. Id. at 77.

367. Id., rev. denied, S213394 (Cal. Nov. 20, 2013) available at http://www.courts.ca.gov/documents/

minutes/SNOV2013.PDF.

368. Citizens for Better Forestry v. USDA, 341 F.3d 961, 970 (9th Cir. 2003).

369. Id. at 971 (internal citations omitted).

370. Exxon Mobil Corp. v. Env’t Prot. Agency, 217 F.3d 1246, 1255 (9th Cir. 2000). The petitioners

asserted that the 2007 amendment to the Clean Air Act, the Energy Independence and Security Act (EISA),

precluded CARB from its state-level LCFS program. Brief for Plaintiffs at 3, Rocky Mountain Farmers Union

v. Goldstene, 843 F. Supp. 2d 1071 (E.D. Cal. 2011). There is a “savings clause” for states in the Clean Air

Act (“nothing in this act shall preclude or deny the right of any state or political subdivision thereof to adopt or

enforce [any pollution standard] . . . except that such State . . . may not adopt or enforce any standard which is

less stringent than the [federal] standard.” 42 U.S.C. § 7146 (2012).

Page 46: pentagon preemption: the 5-sided loss of state energy and power

438 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

emissions, although not so required by federal law.371

Defendants opposed the

Plaintiffs’ preemption motion not on its merits, but on procedural defenses

based on lack of standing and lack of causation.372

The Defendants argued that

the “farmer plaintiffs” and the “industry plaintiffs” fail to establish standing

even after the court allowed limited discovery regarding this issue.373

The

industry plaintiffs argued that they have individual and associational standing

because the LCFS imposes burdens and requirements that would not be

required without the regulation and it constrains the industry plaintiffs’ ability

to sell corn ethanol to California.374

In a prior determination, the Ninth Circuit held that plaintiffs had

standing to seek injunctive relief to preclude the implementation of a new

policy where the government agency allegedly failed to comply with the

procedural requirements of NEPA and the Endangered Species Act prior to the

promulgation of the policy.375

In the Rocky Mountain case, the court held that

while individual plaintiffs have not provided evidence of individual standing,

but that at least one of the industry plaintiff’s members suffered an actual

injury which established associational standing,376

under the three following

prongs: “its members would otherwise have standing to sue in their own right;

the interests it seeks to protect are germane to the organization’s purpose; and

neither the claim asserted nor the relief requested requires the participation of

individual members in the lawsuit.”377

The defendants argued that the industry plaintiffs do not meet the first and

third prongs because it was not shown that any of the members suffered an

injury, there is no evidence of an actual or imminent injury, and preemption

requires participation of individual members of the lawsuit.378

The court

disagreed with CARB regarding the first prong of the associational standing

371. Rocky Mountain Farmers Union v. Goldstene, 843 F. Supp. 2d 1071, 1094–95 (E.D. Cal. 2011).

Federal objectives were asserted by the plaintiffs to include reducing the United States’ greenhouse emissions,

enhancing energy independence and protecting pre-existing investment in renewable energy. Plaintiffs argue

that Congress struck a balance by not mandating pre-existing bio-refineries to reduce their lifecycle carbon

emissions as outlined in the statute.

372. See id. at 1095 (“[A] plaintiff must show (1) it has suffered an ‘injury in fact’ that is (a) concrete

and particularized and (b) actual or imminent, not conjectural or hypothetical, (2) the injury is fairly traceable

to the challenged action of the defendant, and (3) it is likely, as opposed to merely speculative, that [their]

injury will be redressed by a favorable decision.”).

373. Id. at 109698. The Rocky Mountain Plaintiffs are comprised of “groups that have an interest in

protecting the corn ethanol industry,” including corn growers, users, merchants and marketers of distillers

grain, producers of corn ethanol, and importers of ethanol into California from other states. The Court noted

that rather than take the opportunity in discovery to establish standing, the farmer plaintiffs responded to

Defendants’ interrogatories stating that they are not fuel providers.

374. Id. at 1098.

375. Citizens for Better Forestry v. USDA, 341 F.3d 961, 965 (9th Cir. 2003).

376. Goldstene, 843 F. Supp. 2d at 1099101. Pointing to two specific affidavits that name specific

plants that will be harmed by the LCFS and alleges injuries that have been suffered and therefore the Court

finds the first prong satisfied. Plaintiff Growth Energy had previously submitted evidence to satisfy this

prong. Although they state that the LCFS targets and harms their members, the industry plaintiffs do not

submit any evidence to prove this allegation.

377. Id. at 1099.

378. Id. Neither the court nor the state addressed the second prong of this test because the industry

plaintiffs easily meet this requirement of the organization’s purpose.

Page 47: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 439

test, finding that at least one of the industry plaintiffs’ members suffered an

actual injury and would have the right to sue on its own.379

Similarly, the court

on the third prong held that individual participation of the members is not

needed and therefore it only “raises a pure question of law.”380

Because the state opposed an as-applied preemption challenge while the

plaintiffs opposed a facial challenge,381

the court deferred a decision until

future briefing on these different issues and the standards of review that the

court should use,382

and denied “without prejudice the Rocky Mountain

Plaintiffs’ summary judgment motion related to its preemption claim.”383

Having already found the LCFS illegal on other Constitutional grounds, as

discussed immediately below,384

the federal district court did not need to

resolve this additional claim of preemption, holding that petitioners lacked

standing to raise it.385

The Ninth Circuit stayed the district court’s injunction in April 2012,

pending appeal.386

On appeal to the Ninth Circuit, CARB387

cited Rice v. Santa Fe Elevator Corp., that all preemption analyses must start with the

assumption that the historic police powers of the state are not superseded by a

federal act unless that was clearly the intent of Congress,388

particularly in

areas of traditional state regulation, such as pollution control.389

CARB relied

on the Ninth Circuit’s decision in another environmental case involving

CARB,390

arguing that federal EISA’s savings clauses clearly limit its

preemptive reach,391

citing two separate savings clauses in the EISA.392

379. Id. at 1100. The court points to two specific affidavits that name specific plants that will be harmed

by the LCFS and alleges injuries that have been suffered and therefore the Court finds the first prong satisfied.

Growth Energy has previously submitted evidence that satisfy this prong.

380. Id.

381. Id. at 1102 (“A challenge is facial, as opposed to as-applied, when the ‘claim and the relief that

would follow. . . reach beyond the particular circumstances’ of the plaintiffs.”).

382. Id. at 110203.

383. Id. at 1103.

384. See infra at Section III. B. 3. (discussing preemption in discrimination against out-of-state

commerce.)

385. Goldstene, 843 F. Supp. 2d at 1079.

386. Rocky Mountain Farmers Union v. Corey, 730 F.3d 1070, 1078 (9th Cir. 2013).

387. Brief for Appellant at 3, Rocky Mountain Farmers Union v. Corey, 730 F.3d 1070 (9th Cir. 2013),

(Nos. 1215131, 1215135).

388. Id. at 111.

389. Id. at 112.

390. See Pacific Merchant Shipping Ass’n v. Goldstene, 639 F.3d 1154, 1167 (9th Cir. 2011) (finding air

pollution prevention falls under the broad police powers of the states).

391. Brief for Appellant at 112–13, Rocky Mountain Farmers Union v. Corey, 730 F.3d 1070 (9th Cir.

2013).

392. Id. The first cited savings clause states, “[e]xcept to the extent expressly provided in this Act or an

amendment made by this Act, nothing in this Act or an amendment made by this Act supersedes, limits the

authority provided or responsibility conferred by, or authorizes any violation of any provision of law

(including a regulation), including any energy or environmental law or regulation.” The second cited clause

repeats what the first states; “Except as provided in section 211(o)(12) of the Clean Air Act, nothing in the

amendments made by this title to section 211(o) of the Clean Air Act shall be construed as superseding, or

limiting, any more environmentally protective requirement under the Clean Air Act, or under any other

provision of State or Federal law or regulation, including any environmental law or regulation.”

Page 48: pentagon preemption: the 5-sided loss of state energy and power

440 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

The plaintiffs countered that the Supreme Court of the United States, in

Engine Manufacturers Ass’n v. South Coast Air Quality Management District, invoked Clean Air Act preemption “against rules enacted by a political

subdivision of California that prohibited the purchase or leasing of vehicles

which failed to meet certain emissions requirements.”393

The Court found that

“a state law need not actually interfere with federal law to be considered

‘related to’ the federal law for the purposes of preemption.”394

Conflict

preemption is triggered when a state law actually conflicts with a federal law

and therefore a party cannot comply with both the state and federal law.395

Neither party addressed at the trial level whether the LCFS regulation is

severable.396

The Rocky Mountain plaintiffs alternatively asserted at trial that strict

scrutiny still applies because under the Commerce Clause, one state’s laws

cannot “control conduct beyond the boundary of the state.”397

Defendants

countered at trial that the only effects the LCFS may have on out-of-state

producers are indirect and therefore do not directly regulate outside

California’s boundaries.398

The trial court had found for plaintiffs, identifying

the issue as “whether the practical effect of the regulation is to control conduct

beyond the boundaries of the State.”399

The trial court held that under the

Commerce Clause, states cannot place restrictions on imports “in order to

control commerce in other states.”400

The court held that “this type of

regulation ‘forc[es] a merchant to seek regulatory approval in one State before

undertaking a transaction in another,’ causing the LCFS to ‘directly regulate[ ]

interstate commerce.’”401

In December 2011, the Federal District Court for Eastern District of

California upheld plaintiffs’ argument, invalidating certain parts of the LCFS

rule on Commerce Clause issues and enjoining the rule’s enforcement, as it

“discriminates against out-of-state corn-derived ethanol while favoring in-state

corn ethanol and impermissibly regulates extraterritorial conduct.”402

The

federal trial court reiterated that only the federal government can regulate

393. Paul Liebeskind, It’s Not Easy Being Green: Metropolitan Taxicab Reveals Hurdles Posed by

Federal Preemption to State and Local Environmental Initiavtives, 21 VILL. ENVTL. L.J. 325, 337 (2010).

394. Id.

395. Rocky Mountain Farmers Union v. Goldstene, 843 F. Supp. 2d 1071, 1101 (E.D. Cal. 2011).

396. Id. at 1102 (“Neither party explains sufficiently their position of whether the LCFS is a series of

severable restrictions on dissimilar entities or single, integrated market-based compliance mechanism that

applies to all fuel providers in the California market.”).

397. Id. at 109091. The Rocky Mountain Plaintiffs cited such examples as the LCFS regulating land

use in the Midwest and deforestation in South America rather than solely regulating ethanol carbon emissions

within the borders of California.

398. Id. at 1091.

399. Id.

400. Id. at 1092.

401. Id. (quoting Brown-Forman Distillers Corp. v. N.Y. State Liquor Auth., 476 U.S. 573, 579 (1986)).

If a provider changes its part of the fuels lifecycle, such as changing its transportation mechanism to

California, this change must be submitted to CARB. Id.

402. Id. at 1105. CARB attributed the difference in carbon intensity values to multiple scientific factors

in addition to geographic location factors (emissions related to shipping or transportation of fuel). The court

relied upon a “table” of Carbon Intensity Values generated by CARB. Id. at 1082.

Page 49: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 441

commerce between the states, and California, attempting to regulate commerce

outside its borders, violates exclusive federal authority to regulate interstate

commerce.403

A state cannot, even indirectly, regulate or burden commerce

originating outside of its geographic jurisdiction.404

The court again

distinguished motive from constitutional requirements, holding, “Although

[the] goal to combat global warming may be legitimate, however, it cannot be

achieved by the illegitimate means of isolating the State from the national

economy.”405

On appeal, a split panel of the Ninth Circuit majority reversed this

opinion.406

The Ninth Circuit agreed that the preemption issues were not yet

ripe and remanded for further trial court development of the record on these

issues.407

It reversed the trial court determination on extraterritorial impact of

the LCFS as a violation of the Commerce Clause.408

The opinion determines

that it is acceptable for a state to calculate transportation CO2 in the carbon

emissions index or rating of delivered fuel: “The dormant Commerce Clause

does not require California to ignore the real differences in carbon intensity

among out-of-state” product pathways to California, including the type of

electricity consumed in the region of production and the distance of travel of

the product to California.409

According to the majority, a state environmental

purpose to reduce GHGs emitted in the state is enough to impose such

regulation and any resultant costs on out-of-state commerce.410

IV. THE FIVE-SIDED PENTAGON OF PREEMPTION

Constitutional interpretation is still in motion: Appeals on petitions for

certiorari are now pending after the New Jersey and Maryland LCAPP trial

court cases striking state regulation of locational preferences of new power

generation were upheld by the Third and Fourth Circuits respectively411

, and as

well in the Minnesota matter striking state restriction of use of foreign coal

power.412

Certiorari was denied by the Supreme Court after the Seventh

Circuit decision noting the impermissible state discrimination in state

renewable power credits while upholding federal allocation of regional power

transmission costs.413

The Ninth Circuit opinion on California burdens on

403. Id. at 1084 (citing Shamrock Farms Co. v. Veneman, 146 F.3d 1177, 1179 (9th Cir. 1998)).

404. Southern Pac. Co. v. Ariz. ex rel. Sullivan, 325 U.S. 761, 779–80 (1945) (Arizona imposed length

limitations on out-of-state trains traveling through Arizona, affecting travel from California to Texas, which is

outside the jurisdiction of Arizona’s police power).

405. Rocky Mountain Farmers Union v. Goldstene, 843 F. Supp. 2d 1071, 1088–89 (quoting

Philadelphia v. New Jersey, 437 U.S. 617, 626 (1978)) (internal quotation marks omitted).

406. Rocky Mountain Farmers Union v. Corey, 730 F.3d 1070, 1107 (9th Cir. 2013).

407. Id.

408. Id.

409. Id. at 1093.

410. Id. at 1089–90.

411. PPL Energyplus, LLC, et al. v. Hanna, 977 F. Supp. 2d 372 (D.N.J. 2013), aff’d sub nom. PPL

Energyplus, et al. v. Solomon, 2014 WL 4454999 (3d Cir. 2014); PPL Energyplus, LLC v. Nazarian, 974 F. Supp.

2d 790 (D. Md. 2013), aff’d, 753 F.3d 467 (4th Cir. 2014).

412. North Dakota v. Heydinger, 288 F.R.D. 423 (2012).

413. Ill. Commerce Comm’n v. Fed. Energy Regulatory Comm’n, 721 F.3d 764 (7th Cir. 2013), cert. denied

Page 50: pentagon preemption: the 5-sided loss of state energy and power

442 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

foreign products in interstate commerce regarding renewable fuels did not

receive a majority to rehear the case en banc in the Ninth Circuit,414

and

certiorari was also denied by the Supreme Court.415

The Ninth Circuit opinion is distinct, in that it alone covers energy that is

not electric energy, but tangible liquid fuels whose interstate commerce is

controllable. The opinion, among those seven recent state energy regulatory

decisions covered above, is the only decision upholding the constitutionality of

state regulation of energy.416

The nature of the type of energy regulated by a

state, with electricity occupying a distinct physical and legal space, is a key

constitutional distinction. However, there is also a distinction in application of

the Commerce Clause: the Ninth Circuit majority described discriminatory

access to markets as being an “incentive,”417

where other federal courts and the

Supreme Court find such restriction on commercial access unconstitutional.418

The matters now pending involve American energy, which is essential to

the national economy. Electricity has been identified as the second most

important innovation since the wheel.419

Electric power moves instantaneously

in interstate commerce within the lower forty-eight states,420

and

3,882,600,217 Mwh of electricity was used in 2011.421

Power is unique

compared to other tangible energy sources: A constant simultaneous balancing

sub nom. Schuette v. Fed. Energy Regulatory Comm’n., 134 S. Ct. 1277 (2014) and cert. denied sub nom. Hoosier

Energy Rural Electric Co-op, Inc., et al. v. Fed. Energy Regulatory Comm’n., 134 S. Ct. 1278 (2014). 414. Rocky Mountain Farmers Union v. Corey, 740 F.3d 507 (9th Cir. 2014). 415. Rocky Mountain Farmers Union v. Corey, 730 F.3d 1070, cert. denied, 134 S. Ct. 2875 (2014),

cert. denied sub nom. Am. Fuel & Petrochemical Mfg. Ass’n. v. Corey, 134 S. Ct. 2875 (2014), and cert. denied sub nom. Corey v. Rocky Mountain Farmers Union, 134 S. Ct. 2884 (2014); Jonathan H. Adler, Is the Ninth Circuit Due for Environmental Correction?, VOLOKH CONSPIRACY (June 20, 2012, 10:05 AM), http://www.volokh.com/2012/06/20/is-the-ninth-circuit-due-for-environmental-correction/; Carol J. Williams, U.S. Supreme Court Looks Over 9th Circuit’s Shoulder, L.A. TIMES (June 29, 2009), http://articles.latimes.com/2009/jun/29/local/me-9th-scotus29 (“Experts, including former law clerks, say the Supreme Court justices are more inclined to look over the shoulders of the [Ninth] Circuit judges they suspect of favoring the underdog.”). The Ninth Circuit ruled for environmental groups in five cases appealed to the Supreme Court, and in all of which the Supreme Court reversed the Ninth Circuit. See, Coeur Alaska, Inc. v. Se. Alaska Conservation Council, 557 U.S. 261 (2009) (reversing due to deference given to agencies’ reasonable decisions in continuing their prior practice); Burlington N. & Santa Fe Ry. Co. v. U.S., 556 U.S. 599 (2009) (reversing the Ninth Circuit holding in this case and Shell Oil Co. v. United States); Summers v. Earth Island Inst., 555 U.S. 488 (2009) (reversing in part on the ground of standing); Winter v. Natural Res. Def. Council, Inc., 555 U.S. 7 (2008) (reversing the grant of a preliminary injunction the Ninth Circuit upheld, emphasizing the need for plaintiffs to show irreparable injury absent the injunction).

416. Rocky Mountain Farmers Union v. Corey, 730 F.3d 1070, 1107 (9th Cir. 2013).

417. Id. at 1101.

418. C & A Carbone, Inc. v. Town of Clarkstown, N.Y., 511 U.S. 383, 383 (1994) (“The ordinance

discriminates against interstate commerce, and thus is invalid.”); Dickerson v. Bailey, 336 F.3d 388, 392 (5th

Cir. 2003) (“Texas violates the Commerce Clause by economically discriminating against out-of-state wineries

in favor of its own in-state wineries.”); Cloverland-Green Spring Dairies, Inc. v. Pa. Milk Mktg. Bd., 298 F.3d

201, 210 (3d Cir. 2002) (“The dormant Commerce Clause prohibits the states from imposing restrictions that

benefit in-state economic interests at out-of-state interests’ expense . . . .”).

419. Fallows, supra note 1.

420. New York v. Fed. Energy Regulatory Comm’n, 535 U.S. 1, 16 (2002) (“[T]ransmissions on the

interconnected national grids constitute transmissions in interstate commerce.”).

421. Data is for the most recent year data of 2011. See Table 2.2. Retail Sales and Direct Use of

Electricity to Ultimate Customers, ENERGY INFO. ADMIN., http://www.eia.gov/electricity/annual/html/

epa_02_02.html (last visited Oct. 6, 2014).

Page 51: pentagon preemption: the 5-sided loss of state energy and power

No. 2] PENTAGON PREEMPTION 443

of supply and demand on the utility grid system is required,422

second-by-

second to keep the grid operational.423

A loss of power would disrupt

communication, transport, heating, water supply, and hospitals and emergency

rooms depending on their amount of back-up generation.424

States recently attempted to regulate this unique form of electric energy

as to its:

Place – forcing power generation to locate in the state or leave the

state

Price – Proving a higher price for certain power generated in the state

or requiring utilities and their ratepayers to pay above market prices

for certain power

Regulatory credit value – Providing greater credits for in-state power

or fuel

These state regulations are now a major legal controversy before the

federal courts. Seven federal courts in the past year, including the Supreme

Court,425

the federal circuit courts of appeals,426

federal trial courts,427

and a

recent FERC opinion,428

have decided controversies regarding state energy or

utility regulation, with the majority holding that states have acted

unconstitutionally by crossing into preempted territory. Notwithstanding more

than three-quarter century of Supreme Court and other federal court decisions,

there has been a recent renaissance of state attempts to regulate wholesale,

transmission, and interstate electric markets in a manner which is being held at

least beyond state jurisdiction, and may directly interfere with federal policy

and regulation.

These legal controversies regarding the regulated energy future deployed

five distinct regulatory mechanisms; all were found either at the trial or

appellate levels to be legally preempted under the Supremacy Clause. This

constitutes a somewhat immovable legal structure, with the Supremacy Clause

in place for 225 years, and the “bright line” of the Federal Power Act, in place

since the virtual dawn of widespread use of electric power.429

There is no easy

422. See What the Duck Curve Tells us About Managing a Green Grid, CAL. ISO 1, 2 (Oct. 2013),

http://www.caiso.com/documents/flexibleresourceshelprenewables_fastfacts.pdf (discussing challenges of

balancing supply and demand within energy grid).

423. FERREY, supra note 50, at 568.

424. Michael Bruch et al., Power Blackout Risk, CRO FORUM 12 (2012), https://www.allianz.com/

v_1339677769000/media/responsibility/documents/position_paper_power_blackout_risks.pdf.ts.

425. Am. Trucking Ass’n, Inc. v. City of L.A., 133 S. Ct. 2096 (2013); City of Arlington v. FCC, 133 S.

Ct. 1863 (2013).

426. Rocky Mountain Farmers Union v. Corey, 730 F.3d 1070 (9th Cir. 2013); Entergy Nuclear Vt.

Yankee, LLC v. Shumlin, 733 F.3d 393 (2d Cir. 2013); Ill. Commerce Comm’n., v. Fed. Energy Regulatory

Comm’n, 721 F.3d 764 (7th Cir. 2013).

427. PPL Energyplus, LLC v. Hanna, 977 F. Supp. 2d 372 (D.N.J. 2013); PPL Energyplus, LLC v.

Nazarian, 974 F. Supp. 2d 790 (D. Md. 2013); Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 838 F. Supp. 2d

183 (D. Vt. 2012); Rocky Mountain Farmers Union v. Goldstene, 843 F. Supp. 2d 1071 (E.D. Cal. 2011).

428. Cal. Pub. Utils. Comm’n., S. Cal. Edison Co., Pac. Gas and Elec. Co., San Diego Gas & Elec. Co.,

132 FERC P 61,047, ¶¶ 61,337–38 (2010).

429. Thomas Edison first applied electricity commercially only in 1876 at Wannamaker’s store in

Page 52: pentagon preemption: the 5-sided loss of state energy and power

444 JOURNAL OF LAW, TECHNOLOGY & POLICY [Vol. 2014

detour for a state regulation around the Supremacy Clause.

Philadelphia. Only in the 20th

century did cities become electrified, and as electricity was distributed, the

Federal Power Act was enacted in 1935. See, FERREY, supra note 108, at 264.