![Page 1: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/1.jpg)
FOLDER 3
1
PENGURUSAN MASA
• Activity Sequencing
![Page 2: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/2.jpg)
2
key planning process for scheduling & estimating..
2
Scope Definition
Create WBS
Activity
Resource
Planning
Activity
Duration
Estimating
Activity Sequencing
Schedule
Development
Cost
Estimating
Cost
BudgetingScope
Management
Time Management
Cost Management
![Page 3: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/3.jpg)
3
Menentukan turutan / hubungan logik di antara aktiviti/kerja
projek
Activity Sequencing
![Page 4: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/4.jpg)
1. Method statements
2. Predecessor
3. Successor
4. Link type
5. Lead time
6. Lag time
7. Task constraint
8. Network diagram
4
Bagaimana Menentukan Susunan Cara
Kerja??..
![Page 5: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/5.jpg)
5
![Page 6: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/6.jpg)
6
Akt. A
Akt. B Successor
Predecessor
2 Predecessor 3 Successor
• Kerja mesti mula / siap
sebelum kerja seterusnya
bermula / siap
• Kerja di mana bermula
/ siapnya bergantung
kepada mula / siap
kerja yang sebelumnya
![Page 7: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/7.jpg)
7
PASANG AIR COND
UJIAN GUNA
Suc : ujian Pre : pasangSuc : guna
Pre : ujian
CONTOH:
![Page 8: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/8.jpg)
8
4.1 FS – Finish to Start 4.2 SS – Start to Start
• Akt. B Tidak Boleh Mula
Sehingga Akt. A Siap.• Akt. B tidak boleh mula
sehingga Akt. A mula
PILING
PILECAP
AKT A
AKT B
PINTU
TINGKAP
AKT A
AKT B
![Page 9: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/9.jpg)
9
4.3 FF – Finish to Finish 4.4 SF – Start to Finish
• Akt. A & B perlu siap
untuk mula Aktviti
seterusnya
• Akt. B tidak boleh siap
sebelum akt. A mula.
Akt. B bergantung kepada
bila mulanya Akt. A
• Sesuai untuk 4M (bahan,
pekerja, mesin, sumber)
MECH.W (A)
ELEC.W (B)T&C
FF Akt. A
Akt. B
![Page 10: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/10.jpg)
1010
Lead Time – awalkan kerja (cth: kerja struktur awal 5 hari)
Lag Time – lewatkan kerja (cth: kerja struktur lewat 5 hari)
Kerja Tanah
Kerja Struktur
+5d Lag time
FS + 5d
-5d Lead time
Kerja Struktur
Kerja Tanah
FS – 5d
![Page 11: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/11.jpg)
i. ASAP : A Soon As Possible (Kaedah penjadualan)Schedule method base on Project Start Date Forward Pass
i. ALAP : As Late As Possible (Kaedah penjadualan)Schedule method based on Project Finish DateBackward Pass
i. SNET : Start Not Earlier Thancth: kerja boleh mula pd 24/8 tetapi sebelum
24/8 tidak boleh buat
ii. SNLT : Start Not Late Thancth: kerja boleh mula pd 24/8 tetapi
selepas 24/8 tidak boleh buat
iii. FNET : Finish Not Earlier Thaniv. FNLT : Finish Not Late Thanv. MSO : Must Start Onvi. MFO : Must Finish On
11
![Page 12: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/12.jpg)
12
![Page 13: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/13.jpg)
13
Kalau ada constraint… tanya kontraktor
kenapa
Akan beri kesan kepada tarikh projek siap
![Page 14: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/14.jpg)
14
Activity On Node (AON)
Aktiviti A Aktiviti B
node
4 Jenis Hubungan1. Finish to Start (FS)2. Start to Start (SS)3. Finish to Finish (FF)4. Start to Finish (SF)
node
![Page 15: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/15.jpg)
15
3
![Page 16: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/16.jpg)
Menambahbaik ‘Link Line’1
2
3
4
![Page 17: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/17.jpg)
Susunan Tatacara Kerja - Predecessor
![Page 18: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/18.jpg)
18
Susunan Tatacara Kerja - Successor
![Page 19: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/19.jpg)
Network Diagram
1
2
3
Untuk pastikan semua predecesor dan sucessor dimasukkan ke dalam setiap aktiviti - kecuali recuring task, start (tiada predesessor) dan finish (tiada sucessor).
![Page 20: PENGURUSAN MASA - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/2/2a/Folder_3-_Activity_Sequencing.pdfBagaimana Menentukan Susunan Cara Kerja??.. 5. 6 Akt. A Akt. B Successor Predecessor](https://reader031.fdocuments.net/reader031/viewer/2022041303/5e1424579752c0414b4edbb0/html5/thumbnails/20.jpg)
Network Diagram