20' - 0" 75' - 0" 10' - 0" 1 0' - 0" 35' - 0" Shed to be Removed Existing Garage Existing Driveway 20' - 0" 75' - 0" 10' - 0" 1 0' - 0" 35' - 0" Shed to be Removed Existing Garage Existing Driveway Scale Project Status Date Drawn by 1" = 30'-0" 5/28/2021 4:00:53 PM S1 Site Plan Concept #2 - Upper Hay Lake - Pearson-Forero Cabin April 29, 2021 Jeff Balmer Impervious Calculation House 1,900 Garage 1,185 Boathouse 120 Deck/Porch 645 Landscaping/Walks 1,000 ?? Driveway 3,850 Total Impervious 8,700 s.f. Lot Size 49,305 s.f. Percent Impervious 17.65 % 1" = 30'-0" 1 Site Plan w Survey 1" = 30'-0" 2 Site Plan w GIS Lower Level Elvation Approx. 1246 +/ - Main Level Elevation Approx. 1256 +/ -
Transcript of Pearson-Forero Concept #2
![Page 1: Pearson-Forero Concept #2](https://reader033.fdocuments.net/reader033/viewer/2022060120/6292bfd0acd66745e81cc893/html5/thumbnails/1.jpg)
20' - 0"
75' - 0"
10' - 0"
10' - 0"
35' - 0"
Shed to be Removed
Existing Garage
Existing Driveway
20' - 0"
75' - 0"
10' - 0"
10' - 0"
35' - 0"
Shed to be Removed
Existing Garage
Existing Driveway
Scale
Project Status
Date
Drawn by
1" = 30'-0"
5/2
8/2
021
4:0
0:5
3 P
M
S1
Site Plan
Concept #2
-Upp
er H
ay L
ake
-
Pea
rson
-For
ero
Cab
in
April 29, 2021
Jeff Balmer
Impervious Calculation
House 1,900Garage 1,185 Boathouse 120Deck/Porch 645Landscaping/Walks 1,000 ??Driveway 3,850
Total Impervious 8,700 s.f.
Lot Size 49,305 s.f.
Percent Impervious 17.65 %
1" = 30'-0"1
Site Plan w Survey1" = 30'-0"
2Site Plan w GIS
Lower Level Elvation Approx. 1246 +/-Main Level Elevation Approx. 1256 +/-