Patrick Corporation Limited Submission to the IPART Review ......throughput volumes through the Port...
Transcript of Patrick Corporation Limited Submission to the IPART Review ......throughput volumes through the Port...
Patrick Corporation Limited Submission to the IPART Review of the Interface between the Land Transport Industries and the Stevedores at Port Botany
Table of Contents 1. Executive Summary ....................................................................................................2 2. Building on previous studies .....................................................................................5 3. Solutions ....................................................................................................................11 4. Patrick’s Submission ................................................................................................12 5. Improving the efficiency of road freight movements.............................................13
5.1 The logistics chain in Sydney ......................................................................13 5.2 Road Freight Movements ............................................................................13 5.3 Land Side Operations..................................................................................14 5.4 Patrick Land Side Investment......................................................................16 5.5 Interfaces and interdependencies between land side
operations and road freight movements ......................................................18 5.6 The VBS ......................................................................................................19 5.7 Mismatch of Hours.......................................................................................42 5.8 Misaligned incentives along the supply chain..............................................45
6. Improving rail efficiency ...........................................................................................47 6.1 Operational constraints................................................................................49 6.2 Infrastructure constraints .............................................................................51 6.3 Combined Effect ..........................................................................................52 6.4 Rail Access charges at Port Botany ............................................................53
7. Facilitating development of ‘inland ports’ ..............................................................55 7.1 Stevedores' obligations................................................................................56
8. Vertical integration of the supply chain ..................................................................57 8.1 Asciano Businesses ....................................................................................57 8.2 A third stevedore for Sydney .......................................................................61
1
Table of Contents - Figures Figure 1: Sydney Road Transport Charges (Nominal $) 1990/2000 to 2005/2006....................... 12 Figure 2: A side view of the Patrick Rail Mounted Gantry Crane ................................................ 17 Figure 3: VBS Slot Booking Fees from 1999 to 2007 .................................................................. 22 Figure 4: Cost of transporting a container from Port Botany ........................................................ 23 Figure 5: IT related costs via the real time interface between the 1-Stop VBS and Patrick EDI.. 24 Figure 6: Slot time zones............................................................................................................... 26 Figure 7: Slot releases by Patrick .................................................................................................. 26 Figure 8: Patrick VBS Daily Release ............................................................................................ 27 Figure 9: Information gathered by Patrick in relation to truck turnaround times.......................... 29 Figure 10: Proportion of trucks arriving on time for their slots at Port Botany .............................. 33 Figure 11: Arrival times of trucks versus their actual VBS booking slot time................................ 33 Figure 12: Variation of truck arrivals.............................................................................................. 34 Figure 13: Rental rates and charges................................................................................................. 35 Figure 14: Time available to pick up or deliver cargo .................................................................... 40 Figure 15: Truck arrivals per hour January-April 2007 .................................................................. 43 Figure 16: Truck arrivals per day of the week January-April 2007 ................................................ 43 Figure 17: Port Botany TEU throughput projections ...................................................................... 45 Figure 18: Projected increase in train arrivals at Botany Yard 2006-2012 ..................................... 46 Figure 19: FIAB recommendations relating to rail and Patrick's response ..................................... 47 Figure 20: Number of paths for non-passenger trains ..................................................................... 48 Figure 21: FIAB recommendations relating to rail and Patrick's response ..................................... 49 Figure 22: Botany rail move reliability ........................................................................................... 49 Figure 23: Competition between rail and road ................................................................................ 52 Figure 24: Shares of truck container movements at Port Botany .................................................... 59 Figure 25: Truck turnaround times by container ............................................................................. 60
2
1. Executive Summary
All participants in the import/export logistics supply chain, including Patrick, share a common
goal: to lift the productivity and efficiency of the land side interfaces.
Patrick welcomes the independent review of the current land-transport interface at Port Botany
being undertaken by IPART and Patrick appreciates the opportunity to make this submission.
Patrick looks forward to co-operating with IPART, and, in due course, with other stakeholders,
in analysing the issues and assessing the options for dealing with continued growth in
throughput at Port Botany. If unaddressed, Patrick believes that such congestion will hinder
Port Botany as one of Australia's and New South Wales' most important export and import
gateways.
The challenge of securing land side efficiency has long been recognised and debated. In
response, Patrick has invested significant amounts of capital into the Port Botany facility to
secure such productivity improvements.
The IPART Issues Paper has raised a number of issues regarding the land side interface at Port
Botany and Patrick welcomes the opportunity to make comment in response. Salient points
raised in this Submission include:
(a) The current $4 slot booking fee is an insignificant cost compared to the efficiency
and flexibility that the VBS delivers and in light of standard charges for moving a
container in Sydney. The $4 slot booking fee for the VBS has not changed since
April 2003. Patrick is aware that the fee is on charged to end customers and does
not represent a cost to truck operators.
(b) In current dollars, road transport charges have increased 37% per TEU since
1998/1999. In the same time, stevedoring charges per TEU have remained constant.
Furthermore, the average number of containers being transported per Port Botany
truck movement has not changed since 1999.
(c) Patrick is aware that concerns have been expressed from time to time by a small
number of land side operators concerning their perception that Patrick, in its
stevedoring of vessels, gives priority to quayside activities over land side activities.
This is not possible due to the interdependence of the two activities and the fact
they are inextricably linked.
(d) Efficient land side operations go hand in hand with efficient quay side operations.
One cannot exist without the other.
3
(e) Patrick has invested over $200M since 2005 into the Port Botany facility, in the
process enhancing both land side and quayside efficiency. This allowed Patrick to
handle a 35% increase in container throughput and a 20% increase in truck numbers
from February 2006 to February 2007.
(f) The introduction of a Vehicle Booking System has allowed the growth in container
throughput volumes through the Port of Sydney (and hence truck movements) to be
handled efficiently. Truck turnaround times are below what was standard in the
1990s when throughput was a fraction of what it is in 2007. Implementation of
similar Vehicle Booking Systems continue at ports around the world, such as the
Port of Auckland and the Port of Southampton, for example.
(g) Any comparison between Sydney and Melbourne will recognise the efficient road
network around the Port of Melbourne and a smaller number of carriers as
contributors to Melbourne’s perceived efficiency advantage. The inability of
carriers in Sydney to meet booked windows on a consistent basis exacerbates the
difference.
(h) Container dwell time has a direct influence on terminal capacity and the efficiency
of operations. Any market mechanisms to reduce dwell time and encourage the
efficient collection and delivery of containers must be encouraged. Storage charges
are such a mechanism. In the last twelve months, only 2.2% of containers passing
through the Patrick Port Botany facility have incurred storage charges. The majority
of storage revenue arises from long stay containers.
(i) Mismatch of hours will continue to limit efficiency gains throughout the supply
chain. It has been well documented that the stevedores have made the adjustment to
24/7 operation but other supply chain participants have not.
(j) Patrick fully supports the NSW Government’s target of achieving 40% rail share by
2011 for Port Botany’s containers. Patrick has invested heavily to ensure our
operations will meet such a target. However, considerable improvements in rail
infrastructure and operating procedures will be required if this target is to be
achieved.
(k) Modifications to the Botany Yard and duplication of the Botany Freight Line will
contribute to providing greater capacity and capability for increased freight
movement by rail to and from Port Botany.
(l) Patrick is supportive of the FIAB recommendations relating to inland ports in NSW.
Patrick believes that market based solutions will deliver the greatest efficiency,
4
success and sustainability. Patrick believes that the role of Government should be
limited to providing the investment in infrastructure (particularly rail networks) and
making land available for the development of inland terminals. The development
and operation of such terminals should be left to the private sector.
(m) Vertical integration is one way in which the various parties in the supply chain can
work together to drive efficiency. However, there is little vertical integration in the
supply chain in Sydney. Patrick Port Services move fewer than 2% of road
movements into or out of the Port, and truck turnaround data provided to the ACCC
supports the fact that they receive no preferential treatment due to their ownership
structure. Recent restructures within the stevedoring industry will further reduce
vertical integration and enhance transparency.
Patrick believes that the issues facing the efficient movement of freight around Sydney will not
be addressed by focussing solely on the operation of the Vehicle Booking Systems at Sydney’s
container terminals. Instead, increases in container throughput will only be handled by
focussing attention on three key areas:
(a) Improving the efficiency of road freight movement to and from Port Botany;
(b) Improving the efficiency of rail into and out of Port Botany; and
(c) The greater use of inland terminals.
5
2. Building on previous studies
It is important for IPART to utilise the large body of knowledge on the key challenges facing
Port Botany already developed in previous studies. Many of the challenges still facing the
land-transport interfaces at container terminals at Port Botany have been identified in past
reviews. Patrick is keen to see many of those recommended reforms implemented.
This submission draws on the experience that the significant improvements in stevedoring
efficiency and productivity over the past decade have brought to the Port Botany container
terminal operations in suggesting where the solutions can be found for the problems being
experienced in the land-transport interfaces.
Despite many substantial improvements in waterfront and stevedoring efficiency, there remain
significant inefficiencies in the land-transport interfaces at Patrick's container terminal at Port
Botany as a result of a failure of land transport operators to achieve similar improvements.
Patrick has undertaken significant levels of investment to realise its goal of achieving similar
levels of efficiency gain in land side operations that it has achieved in its quay side operations.
Patrick’s crane lift rates are now on par with world’s best practice for similar sized container
terminals.
While this inquiry has its focus on the land-transport interface, and specifically the VBS, the
Terms of Reference and the Issues Paper implicitly recognise that each link in the logistics
chain affects each of the other links. For the chain to reach optimal efficiency, to the ultimate
benefit of the consumers of New South Wales, all of the links must be optimised to work
together.
The Productivity Commission originally identified this in its 1998 Report entitled International
Benchmarking of the Waterfront. It referred to many of the issues still observable today in the
land side interface at Port Botany:
Many of the problems identified in this chapter could be overcome by improved co-
ordination. However, there are few incentives to encourage the numerous
operators to co-ordinate their activities.1
It is only by reviewing the issues affecting the efficiency of all links of the import/export chain
working together that IPART can make recommendations that will materially increase the
efficiency of the land side interface at Port Botany.
1 See Chapter 10 entitled "Port-Land Interface".
6
Throughout the 1980s, 1990s and 2000s there have been numerous reviews which have
considered various aspects of the logistics chain. These reviews have identified issues in
relation to the efficiency and operation of the supply chain, and in particular the land side
interface, and made various recommendations about improvements that could be made.
Many of the issues that have been identified repeatedly by these reviews are still adversely
affecting the logistics chain despite the identification of the problems and the proposals for
reform and solutions.
The main themes that have been repeated throughout these reports include:
(a) Ability to service increased capacity in the future
The major theme throughout these reports is the need to ensure that the logistics
chain is able to deliver adequate capacity into the future to be able to handle
forecast growth and demand.2 There has been significant growth in volumes over
the last several years (in 2005/2006 Sydney processed 1.4 million TEUs, which was
an increase of 7.4% year on year in containerised throughput3) and the forecast
growth and demand over the next two decades will be even more substantial. For
example, it is predicted that by 2025/2026 Port Botany's container throughput will
be between 3.2 million and 4.3 million TEUs.4
(b) The challenge of land side efficiency
It has been widely recognised that an integral part of ensuring that Port Botany can
service this increased volume into the future will be in managing the logistics chain
so that there is efficient transfer of containers between the stevedores and transport
operators5 in order to ensure that this interface does not become a transport
bottleneck.6
2 ACCC Container Stevedoring Monitoring Report No 8 at p 3.
3 ACCC Container Stevedoring Monitoring Report No 8 at p 8.
4 New South Wales Land Side Infrastructure Capability: International Containers, July 2005, Sea Freight Council of New South Wales at p 7.
5 Railing Port Botany Containers: Proposals to Ease Pressure on Sydney's Roads, July 2005, at p 30.
6 ACCC Container Stevedoring Monitoring Report No 8 at p 3.
7
Recommendations of the recent Victorian Competition and Efficiency Commission
Inquiry7 propose solutions to managing port congestion, which are similar to
Patrick’s views and focus on:
(i) improving the efficiency of road freight into and out of the port and in
immediate area;
(ii) increasing the efficiency of rail freight into and out of the port; and
(iii) assisting the development of "inland ports" or intermodal hubs.
(c) The mismatch of hours between participants in the logistics chain
It has been widely acknowledged that the differences in working hours is an
impediment to optimal logistics and has a significant impact on the capacity of the
logistics chain to function effectively.8 This has been recognised by not just the
authors of these reports, but also by the participants in the logistics chain
themselves.
For example, the Seafreight Council ("SFC") found that 42% of respondents to its
survey on Coordination of Working Arrangements thought that changing their own
hours of operation would result in an increase in supply chain efficiency.9
Furthermore, 69% of survey participants indicated that they thought their business
would operate more effectively if other stakeholders in the supply chain changed
their hours of operation.10 However, a large number of those respondents who saw
a benefit for supply chain efficiency from changes to work hours were not prepared
to make a change to their own work hours because of the increased costs that they
would incur.11
In Patrick's view, it should be the responsibility of all participants in the logistics
chain to actively undertake change themselves although this is often not the case.
Previous reports have specifically identified this problem and have stated that: 7 Making The Right Choices: Options For Managing Transport Congestion, Final Report September 2006 at p 323.
8 SFC New South Wales Freight Supply Chain - Coordination of Working Arrangements (Mismatch of Hours) at p 1.
9 SFC New South Wales Freight Supply Chain - Coordination of Working Arrangements (Mismatch of Hours) at p 16.
10 SFC New South Wales Freight Supply Chain - Coordination of Working Arrangements (Mismatch of Hours) at p 21.
11 SFC New South Wales Freight Supply Chain - Coordination of Working Arrangements (Mismatch of Hours) at p 17.
8
The challenge facing the industry is creating the opportunity to work
collaboratively to implement changes that may not directly benefit the
initiator, but would enhance the efficiency of the freight logistics task
overall12
Patrick fully supports this assessment. Patrick has undertaken significant
investment over several years to improve efficiency in the logistics supply chain.13
This includes investment such as the implementation of the VBS, which has been of
significant direct benefit to other participants in the supply chain as well as to
Patrick.
Further improvements in the efficiency of the land side interface will require a
contribution of other participants. Patrick has made a significant contribution to
improving the efficiency of the land side interface, and is continuing to make
significant inroads into the inefficiencies that have been identified as being the
responsibility of the stevedores.
For example, both the Freight Infrastructure Advisory Board ("FIAB") and Sydney
Ports Corporation (“SPC”) have recognised that encouraging the operators of road
and rail to move away from peak periods and a move towards a 24 hours a day, 7
days a week basis will make a major contribution to increasing port efficiency.14
To date, there has been no significant shift to this type of operation by any road or
rail operators.
(d) Lack of coordination between the participants in the logistics chain
In 1992, this issue was identified in the Warehouse to Wharf Report which stated
"the need for more effective coordination and interaction between transport chain
participants".15
It has since been echoed by the SFC in its Import/Export Container Mapping Study,
in which it highlighted "the importance of industry collaboration in relation to
achieving the efficiencies required to meet the increasing pressures on the
12 SFC New South Wales Freight Supply Chain - Coordination of Working Arrangements (Mismatch of Hours) at p 21.
13 ACCC Container Stevedoring Monitoring Report No 8 at pp 22-3.
14 Railing Port Botany Containers: Proposals to Ease Pressure on Sydney's Roads, July 2005, page 31 and Sydney Ports Corporation Logistics Review 2005-06 at p 9.
15 Efficiency of the Interface between Seaports and Land Transport Warehouse to Wharf, April 1992 at p 52.
9
container management task in the future"16 and also in the Productivity
Commission Report in 1998, cited above. The FIAB has also recognised this
problem and noted the ad hoc decision making undertaken by participants in the
logistics chain without due regard to the significant impact that the decision may
have on the operation of the logistics chain.17
Various reforms have been suggested to address these issues, including:
(i) aligning hours of operation;
(ii) developing information technology to transfer information between all
participants in the supply chain;
(iii) undertaking further investigation to improve the efficiency of the
stevedores' land side interfaces;
(iv) greater utilisation of rail transport;
(v) greater utilisation of container staging; and
(vi) developing vehicle booking systems.
Patrick is keen to see many of these reforms and solutions implemented and has,
itself, adopted and implemented many of the recommendations from these reviews
stretching back many years.18 Patrick's efforts in trying to find solutions to the
problems have been recognised in previous reports.
For example, it has been noted that:
(i) unit total revenues for stevedores are 22.4% lower in 2005/2006 than in
1998/99;19
(ii) Patrick increasingly provides services that facilitate the movement of
containers from the wharves to road and rail transport links;20
16 New South Wales Import/Export Container Mapping Study, February 2004 at p 19.
17 Railing Port Botany Containers: Proposals to Ease Pressure on Sydney's Roads, July 2005, page 31 and Sydney Ports Corporation Logistics Review 2005-06 at p 31.
18 Thomas I (1996) The Australian Financial Review, “Patrick to boost Botany capacity”.
19 ACCC Container Stevedoring Monitoring Report No 8 at p.2.
20 ACCC Container Stevedoring Monitoring Report No 8 at p 7.
10
(iii) Patrick has undertaken substantial labour force reforms, improvements in
other workplace arrangements and investment in new technologies and
higher utilisation levels.21 These factors are all referable to the strategies
that have been put in place by Patrick to improve efficiency; and
(iv) Patrick has made substantial capital investment in its container terminal
facilities in the last decade which has been designed to increase the
capacity available in the terminal to allow for growth in throughput over
the next decade.22
Over the last 15 years, Patrick has invested in each of the major factors affecting
capacity, being:
(i) the number of quay cranes that operate at the terminals and the size of
the container storage space;
(ii) modern equipment and facilities for the road and rail interface;
(iii) the efficiency with which the cranes and yard space are utilised;
(iv) the size and skill of the labour force employed at the terminal; and
(v) the stevedores are making continuous efforts to improve the system
including implementing enhanced vehicle booking systems, new
equipment and improved operational procedures.
In Patrick's view, it is now time that all other participants in the logistics chain,
recognise that they, together, with the improvements being put in place by the
stevedores, must make their own contribution to improving the efficiencies in the
logistics chain.
21 ACCC Container Stevedoring Monitoring Report No 8 at p 10.
22 ACCC Container Stevedoring Monitoring Report No 8 at pp 22-23.
11
3. Solutions
Owing to the complexity of the links of the import/export logistics chain, there is no single
panacea for all of the inefficiencies in the chain. However, what is universally accepted is that
in order to minimise the inefficiencies, all of the previous reviews agree, as does Patrick, that
the chain must work together as a co-ordinated whole. If there is mismatch of capacity at any
link of the chain, inefficiency results with an overall detrimental effect on the chain.
Solutions which have been the subject of recommendations of a number of reviews going back
as far as the Cross Report of 1992, would ensure that the whole chain can work together.
Patrick believes that the following measures would have a significant impact and are
deliverable:
(a) Improving the efficiency of road freight movements through the continued use of
existing measures (including the VBS, no show charges and storage charges) plus
other measures aimed at eliminating the mismatch of hours (such as expanding the
hours of operation of carriers and enhancements to the VBS aimed at greater
efficiency from carriers, for example) and addressing misaligned incentives along
the supply chain.
(b) Improving the efficiency of rail into and out of Port Botany. Patrick regards the
achievement of 40% rail modal share as being hampered by constraints outside the
terminal. The difficulties for rail to gain significant modal share are legion. As the
AusLink "Sydney Urban Corridor Strategy" Paper23 notes constraints on rail freight
operations are common to all lines and include limitations on freight rail operators
due to the high volume of passenger services, the limited number of train paths
available and congestion at junctions and restrictive track layouts, to name just a
few!
(c) the greater use of inland terminals away from the scarce and expensive port land
using rail or dedicated land bridging from the ocean terminal to the inland port
where road operators can deliver or pick up the containers. By this means, the
potential of a bottleneck at the ocean terminal can be avoided, containers can be
temporarily stored at a lower cost and there can be greater flexibility for users of the
inland terminals.
23 AusLink, “Sydney Urban Corridor Strategy”, May 2007.
12
4. Patrick’s Submission
This submission addresses in more detail in each of the following sections the areas identified
in the Issues Paper as being of interest to IPART:
(a) Section 5: Improving the Efficiency of Road Freight Movements;
(b) Section 6: Improving Rail Efficiency;
(c) Section 7: The Facilitation of Inland Ports; and
(d) Section 8: Vertical Integration of the Supply Chain.
13
5. Improving the efficiency of road freight movements
5.1 The logistics chain in Sydney
The land-transport interface is one link in an interconnected logistics chain which involves
many players. These players include exporters (suppliers), importers (purchasers), shipping
companies, stevedores, freight forwarders, customs brokers, road transport operators, port
authorities, container depots, rail operators, warehouse operators, government agencies and
facilitators of electronic data interchange.
It is universally accepted that the large number of parties that make up the logistics supply
chain and the interfaces, interrelationships and interdependencies between them make for a
complicated environment. Regrettably, this complexity is often not appreciated by individual
participants in the supply chain themselves, who tend to focus solely upon their task without
consideration of the role their task plays in the whole supply chain.24
This individual task-oriented focus is a significant contributor to the dysfunction and
inefficiency in the supply chain. As a stevedore and terminal operator, Patrick has interfaces
with many of the different participants in the supply chain and is well placed to be able to
provide its perspective as a key participant in and observer of the whole import/export logistics
chain at Port Botany.
5.2 Road Freight Movements
In current dollars, road transport charges in Sydney have increased 37% per TEU since
1998/1999. In the same time, stevedoring charges per TEU have remained constant.
Furthermore, the number of containers being moved per truck movement to the Patrick
facility remains at the same level as it was in 1999.
The land side interface, which itself involves many participants and a wide range of activities,
is one link in the overall logistics chain. In essence, the land side task is to move import
containers from and export containers to the container terminals on behalf of importers and
exporters in order to coincide with ship time of arrival and departure.
As a major link in the supply chain, the majority of carriers have refused to rise to the
challenge of improving work practices. As a result, stevedoring charges per TEU have
remained unchanged since 1999/2000 while road transport charges per TEU have increased
substantially in NSW.25 This is illustrated in the chart below:26
24 Observed by the Freight Infrastructure Advisory Board (“FIAB”) Railing Port Botany's Containers, at p 31.
25 ACCC Container Stevedoring Monitoring Report no 8 at p 2.
14
Figure 1: Sydney Road Transport Charges (Nominal $) 1990/2000 to 2005/2006
5.3 Land Side Operations
Patrick is aware that concerns have been expressed from time to time by a small number of
land side operators concerning their perception that Patrick, in its stevedoring of vessels,
gives priority to the quay side activities over the land side activities. This is not possible
owing to the interdependence of the land side and ocean side activities.
It is undesirable for Port Botany container terminals to be used to store a large number of
export and import containers at the terminal for an extended period of time. The efficiency of
yard operations is directly affected by stack density.27
Management of the terminal requires that the efficiency with which containers are handled at
the land side interface of the terminal matches the efficiency with which containers are
handled at the quayside interface.
The quay side and land side activities are inextricably linked. One cannot be favoured over the
other by terminal management: they must be balanced. The link between the performance of
the quay side and land side operations is immediately apparent: if the terminal does not
manage the efficiency with which containers are moved from the terminal, the ship to shore
operations are affected due to operational constraints arising from congestion in the yard.
26 Data extracted from BTRE, Waterline, Issues 18-41, 1999-2006.
27 Stack density is the average height of containers stacked in the terminal.
Sydney Road Transport Charges (Nominal $)
0
50
100
150
200
250
300
350
400
450
1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
$/TEU
Road Transport Charges
Stevedoring Port Charges
15
The Productivity Commission recognised this relationship between the ability to load and
unload ships and the efficient movement of containers to and from the terminal. For this reason
it is incorrect to claim that land side receivals and deliveries are given a lower priority by
terminals than loading and unloading of ships.28
Associated with the basic task of loading and unloading is container receival, delivery,
clearance and preparation of documentation. The container terminal supplies a facility to store
containers which are in transit. The status of all containers within the terminal at any time are
either pre load or post discharge from a container vessel.
Importers and exporters choose their shipping line. Importers and exporters generally choose
the land-transport operator to transport their containers to and from the container terminals
(“merchant haulage”). A small proportion of container transport is organised by shipping
companies (“carrier haulage”).
The shipping line chooses the stevedore to work its vessels. Individual vessels therefore berth
at the wharf worked by its stevedore. Land transport operators drop off or pick up containers
at a terminal according to the location of the relevant ship.
Wharf side operations are dictated by vessel arrival and departure times. As the shipping lines
work 24 hours, 7 days a week, they require terminals to load and unload containers on and off
vessels on a continuous basis. As noted in the IPART Issues Paper, the contracts that the
stevedores have with the shipping companies require that stevedores meet certain performance
criteria.
28 Supported by the Productivity Commission, International Benchmarking of the Australian Waterfront, at p 176.
16
5.4 Patrick Land Side Investment
Patrick has invested more than $200M in the last three years at its Port Botany facility
enhancing both land side and wharfside capability and efficiency.
From February 2006 to February 2007, such investment allowed Patrick Port Botany to
handle a 35% increase in shipping volumes and a 20% increase in truck numbers at the
Terminal. An increase in rail movements and transhipments also occurred.
Patrick recognises that it has a responsibility to ensure that its stevedoring and terminal
practices are efficient and optimised for their role in the chain. Part of that responsibility is to
ensure that adequate investment has been made in cargo handling equipment and labour to
efficiently manage the land side interface. Patrick has undertaken significant investment at
the Port Botany facility to ensure that the land transport interface does not emerge as a
transport bottleneck.
Patrick’s program of modernising its’ container facilities began in the mid 1990s. Patrick has
invested over $200 million into the Port Botany facility since 2005. As a result, Patrick has
been well placed to handle the unforeseen and significant rise in container throughput in
Sydney in recent years. As Kevin Chinnery stated, this stands in stark contrast to numerous
other Ports around the world:
“The great 2003 – 2005 container shipping boom blew through the supply chain
infrastructure buffer in the world’s most affluent container import markets on the US
West Coast and Northwest Europe … the volume tipped them over into ship queues and
landward congestion”.29
This investment has included reconfiguring and redeveloping the hardstand covering the entire
terminal. This has transformed the layout of the terminal. The investment has also involved the
purchase of two new ZPMC Quay Cranes at Botany, and increased the straddle fleet to 33
machines, with another five new Kalmar Generation Seven straddles due to arrive in July
2007.
Patrick has also invested in five Rail Mounted Gantry Cranes ("RMGs") for the road/rail
interface. RMGs are an ideal mechanism for handling the road and rail interchange while
ensuring maximum efficiency from available ground area. RMGs are used extensively in
overseas terminal operations for this purpose and also in truck to rail intermodal operations.
The handling of the road and rail interface by semi-automated RMGs creates a highly efficient
interface with straddle operations.
29 Chinnery K, “Congestion: Everyone Owns It: Noone Cures It Alone”, Lloyds List DCN, July 21, 2005.
17
The RMGs will be located on a single runway and carry out the positioning and container
movement instructions from the control system. The RMGs will handle rail and staging
between its legs with trucks being handled under a northern cantilever and straddle carriers
being handled under a southern side cantilever, as illustrated below:
Figure 2: A side view of the Patrick Rail Mounted Gantry Crane
Patrick’s investments, in their current form, can further improve efficiency, and the future
investment plans for the Port Botany container terminal will further improve container
handling capacity by the terminal. However, those “nameplate capacity” improvements have
a limit if other parts of the chain are not improved also. The land side operations servicing the
containers cannot remain unchanged. They presently constrain the terminal and will become
more constraining over time as the demand requires higher freight volumes to be handled, the
other parts of the chain are improved and the land side operations remain unreformed. Patrick
is of the view that further investment aimed at allowing increased land side efficiency may not
be realised if the land side operations of other supply chain participants are not reformed in
parallel.
Patrick is committed to working with land side operators who seek a productive dialogue with
realistic objectives in their access to the terminal. Patrick has reached a productive
relationship with land side operators using its terminals in Melbourne, Fremantle and Brisbane.
Patrick believes there is a need for certain reforms to be implemented in order to achieve a
meaningful increase in efficiency in the Port Botany land side interface.
18
5.5 Interfaces and interdependencies between land side operations and road freight movements
Efficient land side operations go hand in hand with efficient wharf side operations. One
cannot exist without the other.
During the loading and unloading of vessels, the task for container terminals is to match the
capacity of the terminal against the capacity of the transport carriers. This allows the volume
of export and import containers being handled at the land side interface to be balanced with the
requirement that vessels be loaded and unloaded in accordance with their scheduled arrival and
departure times.
This capacity management task of terminals involves co-ordination between the stevedores and
the large number of transport operators. The VBS operated by Patrick is one tool in the
capacity management system utilised by Patrick for the land side task.
The tools used by Patrick terminals to assist in the capacity allocation and hence the co-
ordination between participants is as follows:
(a) the allocation of slots through a VBS for the receival and delivery of import and
export containers;
(b) the charging of “no show” fees to discourage transport carriers from not turning up
and also to ensure that carriers do not book more slots than they actually require so
that no capacity is unnecessarily left unused;
(c) the imposition of “storage charges” to ensure that the terminal is not used by
carriers, importers or exporters as a storage facility;
(d) the implementation of paperless processes including the use of PIN numbers to the
transport carriers (for autogate operations) which can be quoted at the gate avoiding
delays in processing paper information; and
(e) allocating stack runs to allow a large volume of empty containers to be moved into
the terminal by carriers at times when the terminal is less busy, such as the evening
and night shifts.
For many years, no co-ordination of vehicles picking up or dropping off containers occurred of
any kind. Containers were handled by a random receival and delivery system – an ad hoc
“first in first served” system. With the large number of transport operators, and the increasing
numbers of containers moving through the ports, this system led to long truck queues as more
trucks arrived at the terminal than the terminal was able to service at one time. This resulted in
19
massive congestion, massive delays and disadvantages to carriers and their exporter and
importer customers alike.
Truck queuing became regarded as a normal part of the logistics chain at ports in Australia.30
This acceptance was evidenced by the level of institutionalisation of the practice of truck
queuing in the establishment of various services for truck drivers in queues (for example,
queuing lanes, toilets, kiosk arrangements) and in the passing on of costs associated with
queuing to importers and exporters.31 This degree of inefficiency and wastage could not
continue as the increasing volume of containers and increased crane rates resulted in pressure
for more efficient land side operations in order to clear the containers.
5.6 The VBS
The introduction of a Vehicle Booking System has allowed the growth in container
throughput volumes through the Port of Sydney (and hence truck movements) to be
managed efficiently. Truck turnaround times are below what was being achieved in the
1990s when throughput was a fraction of what it is today.
The current $4 slot booking fee is an insignificant cost compared to the efficiency and
flexibility that the VBS delivers and in light of standard charges for moving a container in
Sydney. The $4 slot booking fee for the VBS has not changed since April 2003. Patrick is
aware that the fee is on charged to end customers and does not represent a cost to truck
operators.
Implementation of Vehicle Booking Systems continue around the globe, at the Port of
Auckland and the Port of Southampton, for example.32
Prior to the introduction of vehicle booking systems, the random arrivals of trucks meant that
truck turnaround times well in excess of two hours were standard in Australian east coast
ports.33 Truck turnaround times of this magnitude were the standard at a time when volumes
were far below what they are today: for example, 477,000 TEU was the container throughput
for Port Botany in 1990/91. The VBS at Port Botany has delivered an average in gate to out
gate turnaround time of under an hour in an environment of ever increasing trade volume.
30 VTA presentation dated 12/13 February 1991 at p 1.
31 VTA presentation dated 12/13 February 1991 at p 1.
32 Willard A (2006) “Heat is Off” Containerisation International, September, at p.49: “In recent years, congestion has been a major problem for terminals across the world. [This article] … reports on the success of Southampton’s bottleneck solution, the compulsory Vehicle Booking System, a year after implementation”
33 Knowles P, “Truck Queuing: What Operational Changes are Needed” A Presentation to the Waterfront, Ports and Shipping Conference, Sydney, February 12-13, 1991.
20
Patrick introduced a VBS at Port Botany as one tool to reduce truck queues and manage
congestion. The terminals each implemented different VBS systems. While each of the VBS
systems had the same basic purpose, which was to control the rate at which trucks were to
arrive at the terminal to coincide with the terminal’s ability to service those trucks, each
terminal implemented its VBS in a slightly different fashion.
It is widely recognised that the VBS systems introduced by the stevedores have:
(a) significantly reduced truck turnaround times;
(b) reduced the cost of waiting in queues;
(c) minimised truck queues;
(d) allowed containers to be received and delivered more quickly; and
(e) reduced cartage charges to importers and exporters where demurrage was charged
by road transport operators.34
As the Productivity Commission reported when assessing the introduction of VBS in certain
Australian ports:
The systems have significantly reduced truck turnaround times, reduced the cost of
waiting in queues and minimised truck queues. … A VBS also allows containers to
received and delivered quicker. In addition, there is a reduction in cartage charges
if demurrage is charged explicitly by road transport operators. One major
importer in Australia advised that their overall waterfront costs had declined by 30-
40% as a result of a reduction in demurrage charge.35
The VBS portal used by Patrick terminals is one component of the capacity allocation system.
Patrick believes that the VBS system has ensured a much more efficient terminal with benefits
to all carriers and a more even playing field for all carriers by comparison with the ad hoc
random system in use previously.
The role of the VBS in eliminating truck queues was directly observed in Melbourne as a
result of the implementation of key measures recommended by the Final Report of the Joint
Industry Project, 4 July 1990. The massive and immediate effect of the introduction of a
34 Productivity Commission 1998, International Benchmarking of the Australian Waterfront Research Report, at p 177.
35 Productivity Commission 1998, International Benchmarking of the Australian Waterfront Research Report, at p 177.
21
vehicle booking systems is apparent from a comparison of the 1990/1 statistics on truck
turnaround times for trucks to those figures achieved today.36
(a) Cost and price issues
Patrick has always outsourced the VBS function, and today 1-Stop operates a single
system for all Patrick Port Botany users. The 1-Stop VBS is built upon a per
transaction pricing model, which is designed to deliver a fair and equitable system.
Patrick believes that the system offers common access for all carriers and all
carriers are treated equally.
This is the basis upon which the 1-Stop VBS has been built.
36 The additional feature of this report is that the other key measures identified by that report as requiring action by the stevedores and terminal operators have been implemented: greater investment in handling equipment and labour; extended terminal working hours; container documentation pre-preparation; continuous service of trucks and more bulk runs have all been implemented in Port Botany. No change to work practices, investments or systems have been made since then by most truck operators.
22
Date Terminal Operator Costs of VBS & Comments
1992 East Swanson
Dock, Melbourne
GE Not compulsory.
Random slots also available but
priority given to booked slots.
Oct 1994 East Swanson
Dock, Melbourne
Logichip37
June 1999 Port Botany Logichip Terminal moves to a straddle
operation and a VBS is introduced
for the first time at Botany. $3 per
electronic slot booking, $5 per
telephone booking, $50 no show
fee, $10 monthly access fee, $50
registration fee, $20 cancellation
fee.
July 2000 Port Botany Logichip GST introduced on 1 July 2000.
$3.30 per electronic slot booking,
$5.50 per telephone booking, $50
+GST no show fee, $10+ GST
monthly access fee, $50+ GST
registration fee, $20+GST
cancellation fee.
April 2003 Port Botany Logichip $4 (incl. GST) per electronic slot
booking, $8 (incl. GST) per
telephone slot booking, $50 +GST
no show fee, $10 + GST monthly
access fee, $50 + GST registration
fee, $20 + GST cancellation fee.
October
2005
Port Botany 1-Stop $4 (incl. GST) per electronic slot
booking, $8 (incl. GST) per
telephone slot booking, $50 +GST
no show fee, $10 + GST monthly
access fee. No cancellation fees or
subscription fees.
May 2007 Port Botany 1-Stop $4 (incl. GST) per electronic slot
booking, $8 (incl. GST) per
37 All revenue (except for no show fees) paid direct to Logichip.
23
telephone slot booking, $50 +GST
no show fee, $10 + GST monthly
access fee. No cancellation fees or
subscription fees.
VBS Electronic Slot Booking Fees
0
1
2
3
4
5
1999 2000 2001 2002 2003 2004 2005 2006 2007
Dol
lars
Figure 3 – VBS Slot Booking Fees from 1999 to 2007
The $4 slot booking fee for the VBS has not changed since April 2003.
The ACCC reports that VBS revenue paid to the stevedores has increased 224% in
the five years to June 2006 and this figure is widely quoted.38 This figure is
misleading and leads to further misinformation being perpetuated about the VBS.
This statistic ignores the reality that in 2001 VBS slot booking revenue was not paid
to Patrick. It was paid by truck operators directly to Logichip, a third party who
operated and maintained the VBS. Since the introduction of the 1-Stop VBS, slot
booking revenues are paid direct to the stevedore, hence the increase in VBS
revenue that is being paid to Patrick.
Patrick contends that the current $4 slot booking fee is an insignificant cost
compared to the efficiency and flexibility that the web based 1-Stop VBS delivers.
This is especially so when considered in light of standard charges for moving a
container in Sydney.
38 As stated by ACCC at p19 of ACCC Container Stevedoring Monitoring Report No 8, as quoted by IPART at p 46 of Issues Paper.
24
Patrick understands that the following is indicative of the cost of transporting a
container from Port Botany to certain destinations and dehiring the empty container:
From Port
Botany to:
20’
container
VBS % of
Transport Cost
40’
container
VBS % of
Transport
Cost
Minto $395 1.01% $460 0.87%
Smithfield $375 1.07% $430 0.93%
Moorebank $365 1.1% $425 0.94%
Blacktown $380 1.05% $445 0.9%
St Marys $410 0.98% $475 0.84%
Kings Park $370 1.08% $440 0.91%
Hornsby $390 1.03% $455 0.88%
Figure 4: Cost of transporting a container from Port Botany
Furthermore, Patrick is aware that it is common practice for many truck operators to
on-charge a multiple of the $4 VBS booking fee to their end customers (generally in
the range of $10 to $15 per slot)39. Patrick is not aware of a proper cost basis for
the magnitude of the margin charged by truck operators on the slot fee.
(b) The 1-Stop VBS
(i) 1-Stop is a stand alone entity and is a joint venture between Patrick and
DPW (formerly P&O Ports);
(ii) 1-Stop has 22 employees currently, including a Chief Executive Officer,
a General Manager, Project Managers, Sales & Administration staff and
Helpdesk staff;
(iii) 1-Stop outsource and subcontract a significant amount of technical work
relating to improvements and maintenance of the VBS;
(iv) Patrick pays 1-Stop a monthly fee for the provision of the VBS, and in
addition to the monies paid direct by Patrick to 1-Stop;
(v) Patrick also incurs significant IT related costs via the real time interface
between the 1-Stop VBS and the Patrick Electronic Data Interchange
39 See, for example, CLAG, “Application for Authorisation in Respect of Stevedoring Services, Charges & Practices at Port Botany”, December 2005 at p 34.
25
(“EDI”) for both incoming and outgoing information, as illustrated
below:
1 – StopVBS Database
PatrickElectronic
DataInterchange Environment
(“EDI”)
OMS WD OMS ESDOMS FIOMS FRE OMS PB
BillingInterface
VBS Web page
DataWarehouse
Real time interface
EDI Programmer/Developer employedby Patrick to monitor interfaces between 1-Stop & Patrick EDI.
OMS Developer & Project Manager employed by Patrick to monitor internalVBS interfaces: all 2 way traffic
Note: “OMS” is the Patrick Operational Management System
VBS Connection Modules
Figure 5: IT related costs via the real time interface between the 1-Stop VBS and Patrick EDI
(vi) The Patrick EDI feeds into the PeopleSoft billing interface, the
COGNOS Datawarehouse and the Operations Management System
(“OMS”) at Port Botany (and also four other Patrick sites around
Australia being Webb Dock and East Swanson Dock, Fishermans Island
and Fremantle). Messages are then transferred to the straddle cranes via
the Patrick Equipment Control Systems (“EC”);
(vii) Patrick also incurs significant labour costs at Port Botany as a result of
the VBS;
(viii) Patrick also incurs significant managerial expenses at Port Botany; and
(ix) Patrick also incurs significant operational costs at Port Botany over a
situation where there is a random truck queue.
(c) No Show Fees
The $50 no show fee has not changed at Port Botany since the no show fees were
first introduced. This charge has been designed to discourage carriers from
overbooking slots to the detriment of other carriers, and to discourage carriers from
26
not turning up for slots that they have booked. It is intended to provide a
disincentive to scarce slot bookings being wasted through non use and thereby
encourage the efficient use of timeslots. This is in the overall interests of
maintaining effective terminal operations.
However, it is common practice to waive penalties for no shows incurred by any
carriers where the terminal determined that the no show problems were caused by
internal delays at the terminal.
Patrick does not charge for late arrivals. Patrick adopts a flexible approach to slots,
allowing access for trucks that are up to 2 hours outside their slot booking as well as
routinely accommodating trucks that arrive well outside their booked time slot.
(d) Different pricing regimes
While users have expressed a preference for uniformity and coordination by
terminal operators, Patrick does not consider that this is possible in the current
regulatory environment.
(e) Non price access issues
The Patrick VBS is an on line web based system that uses the data available from
Patrick Port Botany as well as the 1-Stop community database. The system’s
booking integrity is maintained by validating the data entered by the carrier either
against container availability (for import containers) and/or vessel availability/cut
off (for export containers). The system provides a system of matching truck arrivals
to anticipated terminal capacity. A carrier needing to pick up or deliver a container
from Patrick Port Botany can make an inquiry via the 1-Stop VBS for the most
appropriate available slot and then book that slot.
More detail on the slot request and allocation process is included below:
(i) The booking process allows for the creation and modification of slot
bookings. A ‘slot’ is a booking made against a time zone. There is a
maximum of one container per slot booking. Each day is divided into 24
time zones from Monday to Sunday as outlined below:
27
Zone Time Zone Time
00 0000 – 0100 12 1200 – 1300
01 0100 – 0200 13 1300 – 1400
02 0200 – 0300 14 1400 – 1500
03 0300 – 0400 15 1500 – 1600
04 0400 – 0500 16 1600 – 1700
05 0500- 0600 17 1700 – 1800
06 0600- 0700 18 1800 – 1900
07 0700 – 0800 19 1900 – 2000
08 0800 - 0900 20 2000 – 2100
09 0900 – 1000 21 2100 – 2200
10 1000 - 1100 22 2200 – 2300
11 1100 – 1200 23 2300 - 0000
Figure 6: Slot time zones
(ii) A booking is thus made against a time zone with each zone having a
designated number of ‘Export (to)’ and ‘Import (from)’ slots. This is
determined by Patrick management and reflect the volume capabilities of
the operation for that particular day.
(iii) Slots are released by Patrick each day, generally for slots two days in
advance:
Day Released Day of Slot
Monday Wednesday
Tuesday Thursday
Wednesday Friday, 0930 release for
Saturday and Sunday
Thursday Monday
Friday Tuesday
Figure 7: Slot releases by Patrick
(iv) Two releases of slots are released daily. The first release is at 0700 and
the second is at 0800. This is to spread the load on the 1-Stop computer
systems and to prevent overload.
28
(v) Carriers are either allocated to the 0700 release or the 0800 release. No
carrier is able to access both releases. The two releases do not give
preference to either carrier group, nor favour the earlier release.
(vi) The current release ratios are included below:
Patrick VBS Daily Release
0700 Release29%
0800 Release68%
Telephone Bookings3%
Figure 8: Patrick VBS Daily Release
(vii) The respective split of slots is determined by historical data. Each slot
release represents the proportion of slots that those carriers have
accessed over the prior twelve months.
(viii) Once the slots are released, carriers request slots based on a ‘first come,
first served’ basis.
(ix) No carrier can see which slots have been allocated other than their own.
(x) The initial allocations last for two hours during which time the carrier
must populate the booking with the container details. Unpopulated slots
are returned to the pool of slots automatically. The carrier which has
booked this slot remains liable to pay for it plus a no show fee unless it is
taken up by another carrier.
(xi) The system operates in real time and carriers can see available slots on
their computer screens as they occur.
29
(xii) It is worth noting that container x-raying was implemented from 2003 in
Australian ports for maritime and port security reasons by the Australian
Government through the Australian Customs Service. This is a
mandatory process and occurs randomly without notice at the direction
of the ACS and overrides all normal container movements. Accordingly,
the VBS portal needs to accommodate ACS priority in order to move
containers to the x-ray facility and back to the terminal. There is only
one transport carrier at each port who holds the ACS contract. The
carrier that holds the ACS contract is given a x-ray login to the VBS and
is able to book x-ray slots through that system. The carriers who have the
x-ray contract with ACS get priority via designated truck grids on the
terminal and by-pass any truck queuing as per arrangements with the
ACS. Currently, in Sydney the contract is held by Patrick Port Services,
who are required to pick up and deliver 50 containers per day from both
Port Botany container terminals. This equates to approximately 200
moves per day and the Customs X-Ray Facility at Port Botany ("CEF")
is open five and a half days per week. This equates to roughly 1200
container movements to and from the terminals per week for x-ray
boxes.
Releases are based on expected terminal capacity, considering the amount of
imports and exports for pick up or delivery, labour and equipment availability and
the time of the week. In Sydney, there is more import related activity early in the
week, as carriers pick up import containers which were discharged over the
weekend. There is a trend towards export activity later in the week as carriers
deliver export containers for weekend loading onto vessels.
Patrick Terminal management recognise that the land side capacity of the terminal
changes on a day to day basis and the practice is to release all available slots for
each hour. If extra capacity becomes available during the day, Patrick will release
more slots into the system and advertise this release via 1-Stop messaging which
will send a message out via email and also to the 1-Stop noticeboard.
(f) Slots and Truck Turnaround Times
A narrow focus on truck turnaround overlooks the reality that there are numerous
stages during the processing of a truck over which stevedores have little control.
The land side efficiency of stevedores however, is often correlated to truck
turnaround times.
30
Currently, Patrick gathers the following times for each truck entering the Port
Botany facility:
Code Description
VBStm VBS time slot booked
In Gate The time the truck enters the In Gate, which is
currently located at the southern end of (the old)
Penrhyn Road. This is when Patrick begins to track
the movements, although the truck may have been
queuing for some time before reaching this point.
Hold The container may be held, for reasons such as
allocation issues or documentation issues.
Hold On
Hold Off
G Pass The Gate Pass is issued and the transaction with the
R&D office is therefore complete. Operationally,
this is the point at which Patrick gains control of the
process. If it is an autogate transaction, assuming
there is no problems the InGate = GPass.
Call Up The BAT number appears on the Call Up Board.
Yd In There is no waiting area at the Patrick terminal so
YdIn = On Lane.
On Lane Truck driver enters a parking bay and reverses into
an empty lane. Driver then walks to a grid box and
scans the bat. This informs the Equipment Control
(“EC”) that a job is available.
Compl The containers are loaded or unloaded and the job
is complete.
OutG The truck exits the terminal.
Total The total amount of time from In Gate to Out Gate.
Figure 9: Information gathered by Patrick in relation to truck turnaround times
As the above shaded areas of the table shows, the stevedore has complete control of
the process only in two steps: from when the truck is On Lane until the job is
complete. At all other steps, there is the potential for the turnaround time to be
affected by circumstances outside of Patrick's control: such as a driver stopping for
31
lunch, a chat or a toilet break. Potentially, drivers can also miss the Call Up or delay
the time until getting On Lane.
As stated above, currently Patrick first recognises a truck when it reaches the In
Gate. Potentially, the truck may have queued for some time prior to this point if
there is heavy congestion at the terminal which may be due to a number of factors,
including yard congestion in the terminal or inclement weather conditions.
Currently, Patrick figures do not include such a figure. However, once the terminal
moves to an automated ingate at the Penrhyn Road roundabout, initiated by the scan
of the MSIC, this data will become available.40
Although each slot is for a duration of one hour, established practice is to allow a
further two hours of grace, meaning that each slot booking provides access to the
terminal over a time period of three hours. If a carrier is still unable to service the
slot within this three hour time frame, carriers can make arrangements with the
Patrick Yard Managers to organise another pick up time and thereby avoid a no
show fee. Since the introduction of the VBS, Patrick Port Botany has never rigidly
enforced one hour time slots, to accommodate the inconsistent arrival patterns of
carriers at Port Botany.
Since the great 2003-2005 container shipping boom, the number of trucks serviced
at the terminal, and hence slots, has increased massively. With the increase in port
throughput has come an increase in vehicle traffic to and from the terminal. Patrick
Port Botany serviced 20% more trucks in February 2007 than it did in February
2006. The load factor per truck41 has not changed since 1999.
(g) Structural Issues
The VBS has allowed Patrick Port Botany to deliver In Gate to Out Gate turnaround
times which have averaged 51 minutes42, despite the considerable and unforeseen
increase in container throughput, and hence vehicles accessing the terminal. This is
in contrast to the situation prior to the introduction of the VBS, where truck
turnaround times were in excess of two hours on average and terminal throughput
was below 50% of what it is today.
40 Patrick perceives real value in a suggestion which has been made that inexpensive and readily achieved realtime webcam video of access roads at Port Botany terminals be webcast to truck operators to allow monitoring of the congestion levels at terminals by carriers allowing staged presentation of trucks accordingly.
41 This refers to the number of containers moved per truck movement to and from the Terminal.
42 This figure represents the average InGate to OutGate time from Jan 1 2004 to June 8 2007.
32
As with most systems, the VBS has shortcomings and there have been continual
improvements made since its introduction including software updates and upgrades
including response to user feedback. 1-Stop currently releases a package of
upgrades and improvements to the VBS every month.
Patrick follows a model of continuous improvement. In Western Australia, a forum
of industry representatives (including Patrick representatives) has been convened to
look into ways to minimise the number of truck movements to and from the Inner
Harbour at Fremantle. The forum has identified certain capabilities both within the
1-Stop technology and the business rules which may assist in the reduction of
traffic. The possibilities for enhancement that have been identified include:
(i) Increasing the number of dual slots in each time zone so that an export
and an import slot is booked at the same time.
(ii) Convert the current dual booking process (one import and one export) to
allow “multi” booking which could mean multiple imports or exports at
the same time.
(iii) Release the “multi” slots earlier than the other slots.
(iv) Establish a “dual” guaranteed slot allocation for carriers who can achieve
certain performance standards.
(v) Create a combined view screen (or appointment scheduler) where
carriers can view and edit bookings to maximise loads and minimise
trips to the terminal.
(vi) Create a port wide backload facility where booking a slot at one facility
can automatically give the option on a slot that will allow the carrier to
backload from the second facility.
Patrick believes that such improvements as those currently being discussed in
Western Australia would also drive a more efficient land-transport interface at Port
Botany. Patrick would ideally like to facilitate and structure a more efficient pick up
and delivery process for import and export containers in Sydney. An impediment to
doing so would be an unwillingness by carriers to work in a constructive manner
with Patrick.
(h) Sydney v Melbourne
33
Any comparison between Sydney and Melbourne will recognise the efficient road network
around the Port and a smaller number of carrier fleets as contributors to a perceived efficiency
advantage in Melbourne. The inability of road operators in Sydney to meet booked windows
on a consistent basis exacerbates the difference.
Given the conditions facing the two Ports, a meaningful comparison of truck
turnaround times and slot release numbers is difficult, as IPART has suggested,
owing to the following factors:43
(i) Melbourne has far higher container throughput than Sydney;
(ii) Sydney moves a higher proportion of cargo by rail (26%) than
Melbourne (17%);
(iii) Sydney has a far higher volume of transhipped containers compared to
Melbourne;
(iv) There is a greater take-up of out of hours and weekend slots in
Melbourne; and
(v) There is a greater balance of import and export trade, meaning there is
not the huge volume of empty containers in Melbourne that characterises
the Sydney trade.
In addition to the above facts, probably the greatest issue facing the land-transport
interface at Port Botany is the failure of carriers to turn up on time for their booked
slot. As previously discussed, trucks in Melbourne carriers are on time for their slot
bookings and do not expect to be serviced outside their one hour time slot unless by
prior arrangements with the Terminal.
The chart below shows the proportion of trucks arriving on time for their slots at
Port Botany (within the one hour booked) on May 21. This was a day where there
was no queuing outside the terminal and an in-gate to out-gate average time of 34.2
minutes.
43 Note issue 9 at p 51.
34
Patrick Port Botany - 21 May 2007
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
12:00
:00 A
M
1:00:0
0 AM
2:00:0
0 AM
3:00:0
0 AM
4:00:0
0 AM
5:00:0
0 AM
6:00:0
0 AM
7:00:0
0 AM
8:00:0
0 AM
9:00:0
0 AM
10:00
:00 A
M
11:00
:00 A
M
12:00
:00 P
M
1:00:0
0 PM
2:00:0
0 PM
3:00:0
0 PM
4:00:0
0 PM
5:00:0
0 PM
6:00:0
0 PM
7:00:0
0 PM
8:00:0
0 PM
9:00:0
0 PM
10:00
:00 P
M
11:00
:00 P
M
Time of Day
% o
f On
Tim
e A
rriv
als
Figure 10: Proportion of trucks arriving on time for their slots at Port Botany
Alternatively, inserted below is data taken from the Patrick Operations Management
System (“OMS”) from 29 May 2007. Again, there was no queuing at the terminal
at this time in the morning. The actual arrival times of trucks is reproduced (under
the “Gate In” column) alongside their actual VBS booking slot time (under the
“VBS Slot” columns):
VBS Slot Gate In VBS Slot Gate In
3:00 4:01 4:00 4:251:00 4:05 3:00 4:270:00 4:06 3:00 4:281:00 4:06 3:00 4:281:00 4:07 3:00 4:303:00 4:08 5:00 4:323:00 4:08 2:00 4:333:00 4:09 5:00 4:333:00 4:10 4:00 4:363:00 4:11 4:00 4:393:00 4:11 4:00 4:463:00 4:12 3:00 4:482:00 4:17 5:00 4:505:00 4:20 4:00 4:572:00 4:22 4:00 4:580:00 4:23 5:00 4:582:00 4:23
Figure 11: Arrival times of trucks versus their actual VBS booking slot time.
35
To illustrate, the first three trucks arriving at the Patrick In Gate after 0400 had
booked a 0300, 0100 and 0000 slot respectively. The above is representative of the
lack of discipline shown by carriers in Sydney regarding VBS slot bookings and, by
contrast, the willingness of Patrick to accommodate arrivals which do not match
their allocated slot times. Activity such as that illustrated in the chart above often
has a flow on effect into the peak dayshift slot booking times, resulting in truck
congestion at the terminal.
Further, the number of actual arrivals per slot demonstrates the variability in actual
arrivals notwithstanding the time of the slot allocated. The data below represents
actual truck arrival numbers presenting at the Patrick In Gate between 0900 and
1000 on days when there was no significant queuing at the terminal. On these days,
the same number of slots were released for the 0900 slot.
The variation of truck arrivals is outlined below:
Date 16 April 2007 17 April 2007 18 April 2007 19 April 2007
Number of trucks
arriving at Patrick In
Gate
42 48 51 79
Figure 12: Variation of truck arrivals
This is in considerable contrast to the experience in Melbourne where truck arrivals
conform to slot time much more closely, allowing the terminals to turn around
trucks without the level of congestion and queuing which often arises due to the
variability of arrivals in Sydney.
(i) Storage Charges
Container dwell time has a direct influence on terminal capacity and efficiency of
operations. Any market mechanisms to reduce dwell time and encourage the efficient
collection and delivery of containers must be encouraged.
Storage charges are such a mechanism. In the last twelve months, only 2.2% of containers
passing through the Patrick Port Botany facility have incurred storage. The majority of
storage revenue arises from ‘long stay’ containers.
Imposition of storage charges is a means to ensure that import containers are
collected from the terminal in an efficient and timely manner. It discourages
36
carriers from using high value terminal land, held under long-term lease by the
stevedore from Sydney Ports Corporation, as a facility to store containers. Port land
is highly valuable and rental rates44 and charges have been rising constantly, as the
chart illustrates:
Figure 13: Rental rates and charges
Storage charges are designed to positively impact import dwell time which has a
large bearing on terminal capacity and efficiency particularly during the peak
season commencing September each year. It is critical that import dwell times
remain at manageable levels. Dwell times have a direct bearing on stack density at a
container terminal. Low stack density has a positive effect on the efficient
facilitation of Australian export trade.
The importance of operational efficiency at Port Botany is illustrated by reference
to problems experienced recently at the ECT Delta Terminal in Rotterdam in The
Netherlands. In February 2007, the ECT refused to accept empty containers due to
a capacity squeeze owing to what port authorities referred to as a “massive increase
in the average time containers spend in the Port”.45
44 As part of the Patrick redevelopment of the Port Botany facility, the Patrick terminal boundary was has been extended at the rear of the Terminal to include the old Penrhyn Road.
45 Roebuck M, “ÉCT Bans Empties to Ease Congestion” International Freighting Weekly, 26 February 2007 at p 3.
Patrick Port Botany 2002 to 2006
41.11%
53.22%
72.61%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Rent Paid to SPC Council Rates Land Tax Payment
% Change in Payment from 2002 to 2006
37
It should be realised that shipping lines also impose strict periods of free-time to
customers and charge detention if containers are not returned to their nominated
depot in time. Patrick’s understanding is that shipping lines generally allow from 7
to 10 days of free-time to import containers which begins the day after vessel
departure (including weekends) and this day is counted as the first day. Quick
turnaround of containers is a pre-requisite to global trade facilitation.
(j) The Relevant Facts About Storage at Patrick
There appears to be a degree of misunderstanding about the significance of storage
charges to the overall costs incurred in the import/export logistics chain.
The facts are as follows regarding Patrick’s operational procedures:
(i) All containers are made available by Patrick systems half an hour after
discharge from a vessel, thereby maximising the free time available;
(ii) Standard practice is to make cargo ‘available’ the day after the vessel has
sailed;
(iii) Patrick’s three free days do not include Sundays and Public Holidays;
(iv) Patrick’s three free days commence from the time the ship is made
officially available; and
(v) This might be up to two days after an individual container has been
discharged and is available for pick up from the Terminal.
Furthermore, in relation to the proportion of containers which incur storage:
(i) From May 2006 to May 2007, approximately 2.2% of total containers
handled at the Port Botany facility incurred storage charges;
(ii) 79.1% of storage revenue is generated from containers that have been on
storage for longer than two days past the three day free period – in other
words, containers that have been in the terminal for longer than five
days; and
(iii) 66.4% of storage revenue is generated from containers that have been on
storage for longer than three days past the three day free period – in
other words, containers that have been in the terminal for longer than
six days.
38
Incorrect assertions have been made by a small number of carriers that storage is
‘fundamentally intended to increase the profitability of the stevedores rather than to
create port discipline and efficiency’46. This is simply incorrect and is denied.
Patrick's incentive is to clear containers as rapidly as possible. The substantial
adverse impact on terminal efficiency when stack density starts to grow far
outweighs the relatively modest gains from storage fees from the 2.2% of containers
that incur storage charges.
Furthermore, this assertion overlooks an agreement made between Patrick Port
Botany and the NSW Road Transport Association (“NSWRTA”), and also
involved Sydney Ports Corporation. In November 2006, in recognition of the record
volumes experienced at Port Botany, Patrick agreed to waive storage charges in
certain circumstances in order to encourage weekend pick ups of import containers.
Patrick does not agree with the contention that ‘delays in access to the port for
container collection by transport operators increase the port storage charges levied
by stevedores’.47 The policy of Patrick management is to co-operate with carriers
and take all reasonable steps48 to ensure that a carrier has access to a container
which is about to incur storage charges.
(k) The effect of the CMR problems on storage revenues in October 2005
The Australian Customs Service ("ACS") published its Cargo Management
Strategy (“CMS”) in 1997. The Cargo Management Re-engineering project
("CMR") was born out of the CMS.
The application and system development for the CMR project included the analysis,
design, development and implementation of the new Integrated Cargo System
("ICS") application. The ICS was implemented in three releases: Release 3,
imports processing, was implemented on 12 October 2005. It had the following
effect:
Problems with the Integrated Cargo System and the Customs Connect
Facility resulted in substantial disruption to the movement of cargo,
46 CLAG, “Application for Authorisation In Respect of Stevedoring Services, Charges & Practices at Port Botany", December 2005 at clause 8.8.
47 IPART (2007), "Review of the Interface between the Land Transport Industries and the Stevedores at Port Botany Issues Paper at p 39.
48 By organising access to a timeslot at the Terminal.
39
particularly sea cargo. Cargo was delayed and Australia’s major ports
congested with containers awaiting clearance and delivery. Industry
stakeholders advised the Australian National Audit Office that the
implementation of Release 3 was extremely stressful and costly, and
extended over many weeks.49
Despite the effect of CMR, when commenting on storage revenue levels the ACCC
recognised that ‘transitional problems’ associated with the ICS “may have been a
contributing factor to higher storage revenues earned by stevedores in 2005-2006’.50
The truth is that the increased storage revenues experienced in 2005-2006 were
purely a result of the ICS introduction. As such, the ACCC quoted figure of a
74.7% rise in storage per TEU since 2001 – 2002 does not properly take account of
the introduction of the ICS which inflated storage revenues for 2005 - 2006.
The pertinent facts are:
(i) Patrick storage revenue per TEU from June 2006 to April 2007 is below
the 2002 – 2003 levels per TEU as quoted in Table 3-iv;51
(ii) Year to date figures referred to above for 2006 – 2007 are only
marginally above 2001-2002 levels;
(iii) The effects of the ICS were evident well into 2006;
(iv) On 9 January 2006, 51% of import containers were ACS held at Patrick
Port Botany;
(v) On 6 February 2006, 45% of import containers were ACS held at Patrick
Port Botany;
(vi) On 24 April 2006, 37% of import containers were ACS held at Patrick
Port Botany. Such figures appear to contradict the claim by ACS that
these problems were largely resolved by late November 2005;52
49 ANAO Audit Report No 24, 2006 – 2007, Customs Cargo Management Re-engineering Report at p 42.
50 ACCC Container Stevedoring Monitoring Report No 8, November 2006 at p 18.
51 Ibid.
52 Ibid at p 19.
40
(vii) The ACCC admits that it is “possible that stevedores incurred some
additional labour and equipment costs during this period as a result of
added congestion within the terminal yards”;
(viii) The truth is that Patrick Port Botany incurred substantial costs
attempting to maintain operations and service levels with yard
congestion at record levels;
(ix) Patrick Port Botany, at our cost, was forced to shuttle entire vessel
import exchanges under bond to facilities off site, as there was no room
available at the Port Botany facility; and
(x) Consolidations and rehandles were continually being undertaken in order
to maintain operations in a yard that was experiencing volumes far
beyond capacity, with a stack density well above the unmanageable
figure of 2.0.
As the Chairman of Shipping Australia at the time pointed out:
…nobody’s preparations proved sound. Customs Integrated Cargo
System didn’t perform; truckers, importers and bankers had no
emergency liaison in place. On the key weekend they all stayed at home.
Only the stevedores and – ironically - Customs itself were visibly doing
anything to deal with the situation.53
The ACCC, IPART and CLAG have not attributed the storage revenue increase
properly to the effect of the ICS introduction. Storage charges have now returned to
pre-ICS implementation levels. This one off rise in storage revenue was abnormal
and should be disregarded when recommending solutions to the long term
inefficiencies which affect the land side interface at the Port Botany container
terminals.
(l) Rationale for Storage
The rationale behind free storage days is allowing the consignee a reasonable
amount of time to organise the clearance of their cargo from the wharves. This
practice stems from the distant past, when the discharge of cargo was a far more
laborious and drawn out process than it is today. In the days before container
shipping, the procedures and processes for clearing cargo through Customs and 53 Phillips M, ‘What's next after the computer crisis and does it look as if we’d be ready for it?” Shipping Australia, November 2005 at p 4.
41
Quarantine was similarly drawn out. The whole system was manual and in broad
terms cargo was not available until the entire cargo on a bill of lading was cleared
and all port and statutory charges were paid.
Four free days of storage had its genesis in these times of lower volume (breakbulk
commodities) and a productivity level commensurate with vessel type and the wide
range of commodities being handled.
Containerisation has now changed the focus of industry endeavours and with
improvements in technology came the ability to load, discharge and transport cargo
far more efficiently . More streamlined procedures and processes for clearing cargo
have also been established, as evidenced by recent ACS and AQIS initiatives.
Since 1 July 2003, four working days of storage (Monday to Saturday including the
day of availability) was changed to three working days (Monday to Saturday
including the day of availability). Patrick has invested substantially in both systems
and infrastructure to enhance terminal access and provide the means for electronic
exchange of data with focus on efficiency and security. Not all in the transport
chain have embraced this opportunity and continue to treat the container terminals
as storage locations for containers rather than temporary r staging locations for
containers in transit. The adoption of increased hours of operation by Patrick has
meant that the absolute time available to pick up or deliver cargo has actually
substantially increased:
Days of Storage R&D Working Hours
Actual Hours Available for Pick
Up or Delivery Early days of
containerisation 4 Mon – Fri Day Shift (7 hrs)
35 hours
Later moved to 4 Mon – Fri
Day & Evening Shift (7 hrs per shift)
70 hours
199954 4 5 days x 3 shifts and Saturday x 2 shifts
136 hours
1 July 2003 3 6 days x 3 shifts 144 hours
June 200755 3 7 days X 3 shifts 168 hours
Figure 14: Time available to pick up or deliver cargo
54 8 hour shifts introduced in September 1998.
55 As discussed above, presently Sundays and Public Holidays do not count in the calculation of the first three working days including day of availability “free days”.
42
5.7 Mismatch of Hours
Mismatch of hours will continue to limit efficiency gains throughout the supply chain. It
has been well documented that stevedores have made the adjustment to 24/7 operations but
other supply chain participants have not.
It is widely recognised that “Sydney roads are already full”.56 Despite this fact, all participants
in the logistics chain except the ships and the stevedores continue to avoid the requirement to
extend their hours of operation. Carriers continue to contribute heavily to peak hour traffic
congestion through their current work practices. They are not assisted by other participants in
the logistics chain such as distribution centres and warehouses. Stevedores work 24/7. No one
else does. This has long been recognised:
Wharf operators contend that they are a 24 hour a day operation. But the
warehouses further down the chain operate for only eight hours each weekday, and
often less. This telescopes freight into congestion peaks.57
During the peak season in 2006, following discussions with the NSWRTA and Sydney Ports
Patrick Port Botany agreed to amend storage charges in order to encourage weekend pick up
and delivery of containers. In the face of Port Botany handling record volumes, this was well
publicised and it was hoped that such incentives would increase truck activity over the
weekend. The change in behaviour was negligible, as the following example reveals:
Illustrative example:
From 4-10 December 2006 Patrick Port Botany serviced over 15 vessels and continued to
experience high container volumes passing through the terminal.
The Terminal recorded an average truck turnaround time of 43 minutes over the course of the
week. The Terminal did not experience material truck congestion at the Terminal at any time
over the week.
Patrick continually advised carriers throughout the week via messages on 1-Stop that strong
volumes were continuing and the Terminal strongly encouraged the utilisation of weekend
slots. The take up is shown in the Table below:
56 Baker J & Clennel A (2007) “Choked Roads to Nowhere – No Remedy in Sight for the City’s Choked Roads” Sydney Morning Herald, 3 May at p 1.
57 House of Representatives Standing Committee on Transport, Communications and Infrastructure (1995) “Warehouse to Wharf: Final Report” at p 5.
43
Shift Number of
Slots Offered
Number of Slots
Taken Up
% Utilisation
Saturday Dec 9
Day Shift
350
124
35%
Saturday Dec 9
Evening Shift
300
0
0%
Sunday Dec 10
Day shift
350
73
21%
Sunday Dec 10
Evening Shift
300
0
0%
It is common carrier industry practise to blame the VBS for not releasing enough slots on a
Monday or Tuesday morning. However, it is impossible to cater for all the potential demand at
these peak times. In this situation, demand will always be greater than supply because there are
thousands of import containers in the Terminal awaiting delivery. The solution cannot be
found, as argued by some carriers, in simply adding more peak time slots.
For example, on the weekend of November 4-5 November 2006, an average of 50 import units
were unloaded per hour from vessels at Patrick Port Botany. However, there was not one
delivery out of the terminal via road or rail after 1200 on the Saturday. This meant that there
were over 3,600 import containers in the Terminal on Monday morning awaiting pick up.
The patterns of truck activity at the Terminal is illustrated in the charts below. The effect of
such behaviour is twofold:
(a) the terminal is hugely congested with import containers early in the week, as it has
filled up over the weekend without an opportunity for congestion to be eased via
road and rail deliveries. Therefore truck turnaround times often suffer due to stack
density and the requirement of countless rehandles to access target containers; and
(b) carriers become frustrated when they are not able to access desired slot times,
generally early morning on a Monday or Tuesday. It is at this time that one will
hear the lament that there are “not enough slots”. This continues to ignore the
reality that there was the possibility of 750 slots being offered the previous day.
44
Patrick Port Botany Jan - Apr 2007
0.00%
1.00%
2.00%
3.00%
4.00%
5.00%
6.00%
7.00%
12:00
:00 A
M
1:00:0
0 AM
2:00:0
0 AM
3:00:0
0 AM
4:00:0
0 AM
5:00:0
0 AM
6:00:0
0 AM
7:00:0
0 AM
8:00:0
0 AM
9:00:0
0 AM
10:00
:00 A
M
11:00
:00 A
M
12:00
:00 P
M
1:00:0
0 PM
2:00:0
0 PM
3:00:0
0 PM
4:00:0
0 PM
5:00:0
0 PM
6:00:0
0 PM
7:00:0
0 PM
8:00:0
0 PM
9:00:0
0 PM
10:00
:00 P
M
11:00
:00 P
M
Time of Day
Truc
k A
rriv
als
Ove
r 4 M
onth
s - %
per
hou
r
Figure 15: Truck arrivals per hour January – April 2007
Patrick Port Botany Jan - Apr 2007
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
18.00%
20.00%
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Day of Week
% o
f Tot
al T
ruck
s
Figure 16: Truck arrivals pes day of the week January – April 2007
Even if 40% of Port traffic is shifted to rail, the trends above must be altered or else truck
congestion will continue to be unavoidable both at the Terminal and on Sydney’s urban
corridors. Offering more VBS slots at peak times on weekdays, or altering the price on the
weekend, is not the answer. Only the spreading of the demand to non-peak weekday and to
weekend times will materially reduce the congestion.
Patrick would be prepared to consider slot rationing in peak times as suggested by the review
by the Infrastructure Implementation Group of the Freight Infrastructure Advisory Board of
45
May 2007.58 As an anti-congestion signal, clearly this would require considerable planning by
all stakeholders. However, in Patrick's view such supply rationing would be less desirable
than addressing the constraints on the land-transport link in the logistics chain described in this
submission.
Patrick therefore fully supports the conclusion of the Infrastructure Implementation Group that
the FIAB recommendation should be implemented, that:
..both rail and road operations [progress] towards a 24 hour a day, 7 day a week,
basis.59
5.8 Misaligned incentives along the supply chain
IPART raises a number of issues related to the industry structure and question whether the
“best economic signals” are being provided.60 The supply chain is a market based solution
being driven by private sector companies and importantly private sector investments.
Although improvements can certainly be made, Patrick regards any regulatory solution as an
undesirable approach when there are a number of market based outcomes readily available,
and which have been recommended in a number of prior reviews.
Although not directly articulated, a concern IPART seem to have is that there is insufficient
competitive pressure on the stevedores to deliver land side operations efficiently. However,
this is far from the true. Patrick’s level of investment in the land side interface, such as the Rail
Mounted Gantry Cranes, is testament to its importance to the overall operation.
It is important to understand that the efficiency of the terminal is indivisible and performance
of the land side operations can not be separated from the overall performance of the terminal.
An inefficient land side operation will increase congestion within the terminal, impact on the
efficiency of resource utilisation including cranes and manpower and ultimately impact on the
ability of the stevedore to service vessels. An efficient land side operation is required to
deliver an efficient service to shipping lines. This was amply illustrated during the Customs
CMR introduction in late 2005.
The shipping lines are the stevedores' contractual customers. Stevedores do have a competitive
choice to make within ports between terminal operators and often also between ports. Shipping
58 At p 16.
59 FIAB recommendation 20 at p 7; The review by the Infrastructure Implementation Group of the Freight Infrastructure Advisory Board report and recommendation, May 2007 at p 15.
60 IPART Issues Paper at p 42.
46
lines choice of stevedore involves a long and detailed tender process, and there has recently
been shifting of volume between the two major container stevedores in Australia.
Shipping lines are driven by the needs of their customers, the importer (or in some cases a
freight forwarder). The importer, for example Target, will be concerned with price and the
certainty and timeliness of delivery of its goods. Land side delivery is a key component of
meeting the shipping lines customers’ needs for certainty and timely delivery. If Patrick’s Port
Botany land side efficiency was low it would be expected that shipping lines would look to
move to another terminal operator and potentially another port. This effect is likely to be
compounded by the fact that land side inefficiency will reduce the efficiency of the terminal as
a whole including the direct service to the shipping lines thereby reinforcing the incentive to
change stevedores.
47
6. Improving rail efficiency
Patrick fully supports the NSW Government’s target of achieving 40% rail share by 2011 for
Port Botany containers. Patrick has invested heavily to ensure our operation will meet such
a target.
However, considerable improvements in rail infrastructure and operating procedures will be
required if this target is to be achieved.
Patrick supports the NSW Government’s target of achieving 40% rail share for Port Botany’s
containers. The enormity of the task is clear when considered in light of continued volume
growth, a forecast of which is illustrated below:
PORT BOTANY (m)TEU THROUGHPUT PROJECTIONSBASED ON 8% GROWTH FROM 2007
1.131.26 1.31 1.28 1.3 1.26 1.2
0.28
0.310.36
0.520.64
0.841.06
0
0.5
1
1.5
2
2.5
2006 (20% RAIL) 2007 (20%) 2008 (21%) 2009 (29%) 2010 (33%) 2011 (40%) 2012 (47%)
RAIL
ROAD
Figure 17: Port Botany TEU throughput projections
In line with above, train arrivals at Botany Yard are likely to have to increase from 14 per day
(currently) to over 30 per day in the next five years to meet demand of 40% modal share, as
illustrated in the table below:
2006 2007 2008 2009 2010 2011 2012
TOTAL PORT THROUGHPUT TEU ( WITHOUT TRANSHIPMENTS) 1,414,797 1,540,000 1,663,200 1,796,256 1,939,956 2,095,153 2,262,765TOTAL PORT RAIL THROUGHPUT 284,369 314,211 354,303 516,808 639,127 840,566 1,059,628TOTAL PORT THROUGHPUT RAIL SHARE 20% 20% 21% 29% 33% 40% 47%
SERVICES PER WEEK 75 80 87 124 148 188 226RAIL THROUGHPUT PER WEEK 5,469 6,043 6,814 9,939 12,291 16,165 20,377TEU PER SERVICE 73 76 78 80 83 86 9075 TEU CAPACITY UTILISATION 49% 50% 52% 53% 55% 57% 60%RAIL OPERATING DAYS PER WEEK 5.5 5.5 5.5 5.5 6.0 6.5 7.0AVERAGE BOTANY TRAINS PER DAY 13.6 14.5 15.9 22.6 24.7 28.9 32.3*AVERAGE SHUNTS PER DAY TO BE MANAGED 75 80 87 124 136 159 178
*INCLUDES BOTANY YARD ARRIVALS AND DEPARTURES
AVERAGE OF 32.3 TRAINS PER DAY ACROSS A SEVEN DAY WEEK MEANS UP TO FORTY ON BUSY DAYS - WEEKEND TRAFFIC WILL TEND TO BE LESS FREQUENT
48
Figure 18: Projected increase in train arrivals at Botany Yard 2006-2012
Patrick moved 24.7% of containers by rail in 2005/2006. Patrick rail volume tends to have a
higher share of export activity than import activity. Patrick’s significant levels of investment in
the land side interface puts Patrick in a position to be able to handle increased rail throughput in
coming years.
FIAB had numerous recommendations relating to rail. Recommendation 20 is reproduced below,
with Patrick’s response alongside:
Recommendation Patrick Response
SPC urgently seek agreement of the stevedores to ensure that state of the art
interfaces are available in respect of Patrick’s operations. Recommended that
interfaces provide for:
Capacity to receive, load and unload
600m push-pull trains.
Patrick has invested in two rail spurs
which are longer than 600m each.
Consolidation of train cargo to single
intermodal destinations
Patrick agrees with this and it would
avoid the requirement for extra
shunting requirements in Botany Yard.
Ultimately, this is dependent on rail
operators, importers and exporters.
Reduced turn around times using
dedicated rail handling equipment
Patrick has invested heavily in state of
the art rail handling equipment to
facilitate improved train turnaround
times.
Progress the implementation of both road
and rail operations towards a 24 hours a
day, seven days per week basis
Patrick currently works 24/7 and
encourages a shift towards longer hours
of operation by other participants in the
supply chain.
Figure 19: FIAB recommendations relating to rail and Patrick's response
Patrick regards the major impediments to achieving 40% rail share as being outside the Patrick
Terminal boundary. The efficiency of our rail interface will allow such volumetric targets to be
49
met by Patrick. In particular, the Patrick terminal at Port Botany will have vastly increased rail
servicing capability when the five RMGs come into operation towards the end of 2007.
It is operational constraints and the parlous state of rail infrastructure in the Botany Yard and
across NSW that are the major impediments to increasing rail’s share of the container volume
to the level desired by the NSW Government.
6.1 Operational constraints
During the morning and afternoon peaks no freight traffics are scheduled on the Metropolitan
Freight Network (“MFN”) which represents a significant operational constraint on freight
movements. While the peak from a passenger viewpoint is of relatively short duration, the
freight curfew for movements with the peak flow is considerably longer as RailCorp requires
the freight service to be clear of the suburban network prior to the passenger peak
commencing. The impact of passenger curfews on metro corridors will make it even more
difficult for freight trains to access metropolitan corridors as passenger train numbers increase
in the future.
The limitations imposed by the curfew constrains movements outside the MFN, as shown
below61 and highlighted by the arrows:
Number of paths for non-passenger trains
012345678
Midnigh
t -2.00
am
2.00a
m-4.00
am
4.00a
m -6.00
am
6.00a
m-8.00
am
8.00a
m - 10.0
0am
10.00
am-12
.00pm
12.00
pm -2
.00pm
2.00p
m-4.00
pm
4.00p
m-6.00
pm
6.00p
m - 8.00
pm
8.00p
m - 10.0
0pm
10.00
pm-12
.00am
Figure 20: Number of paths for non-passenger trains
The management and operation of the Botany Yard and Botany Precinct also represents a
significant operational constraint. Currently, there are over 100 moves per day through Botany 61 From RailCorp Standard Working Timetable.
50
Yard. This is due to the fact that trains need to be split between (potentially) three rail sidings,
as shown in the example below of a standard shunting/wagon placement procedure:
Train arrives Botany Yard > Detach loco and place at rear of train for propelling move (note a
propelling move is where the loco is at the rear of the train and has to be directed by radio
from the front of the train) > Propelling move piloted by second driver in car ahead of train >
Place wagons in P&O Transport Australia rail sidings for loading and unloading and detach >
Exit P&O Transport Australia rail sidings and propel into DP World > Place wagons in DP
World and detach for loading and unloading > Exit DP World and propel into Patrick > Place
wagons in Patrick for loading and unloading.
Note that this procedure is reversed at end of window to reform the train in the Botany Yard.
Figure 21: FIAB recommendations relating to rail and Patrick's response
The impact of the passenger curfew plus the current arrangements at Botany Yard (in addition
to specific operational issues relating to the various rail providers in NSW) combine to impact
the reliability of train arrivals at Botany Yard and therefore Patrick. This is illustrated below:
Figure 22: Botany rail move reliability
Patrick believes that the reliability of arrivals must consistently be at the 90% level if forecast
train volumes are to be handled efficiently. Patrick believes that a sole management authority
for the Botany Yard precinct would assist greatly in achieving this target.
BOTANY RAIL MOVE RELIABILITY
20 DAY ROLLING AVERAGE ON TIME PERCENTAGE
0.45
0.5
0.55
0.6
0.65
0.7
0.75
0.8
0.85
0.9
0.95
1
Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07 Apr-07 May-07
51
Currently, Botany Yard is controlled by a RailCorp management team. Cooks River is
controlled by an additional RailCorp management team. The track outside Botany Yard is
under the control of RailCorp Network Control. Enfield is currently managed by Pacific
National.
In order to increase visibility and improve decision making, Patrick suggests that one
management body would control the Botany Yard, plus the precinct extending to Cooks River,
a set amount of roads at Enfield and the connecting corridors. This would allow decisions to be
based on long term, objective criteria to be taken in the interests of overall efficiency.
Patrick believes that such a measure will assist in allowing growing train volumes to be
managed effectively. There should be ongoing access to a set amount of roads at Enfield as a
spill over and back up facility to the Botany Yard. That way, the Botany Yard capacity can be
optimised. Currently, trains are staying too long in the Botany precinct greatly increasing
congestion.
6.2 Infrastructure constraints
Modifications to the Botany Yard and duplication of the Botany Freight Line will all
contribute to providing greater capacity and capability for increased freight movement to
and from Port Botany.
Following a reform of Botany Yard management and operations, the next most pressing issue
to be addressed is the infrastructure constraints in the Botany Yard and Botany precinct.
Currently, there are pressing infrastructure improvements required in the Botany Yard. Such
improvements include additional cross overs and sidings, motorised points, upgraded
signalling and specified arrival and departure roads.
There also needs to be duplication of the track between the Botany Yard and Enfield. In
conjunction, Enfield must also allocate sidings for Botany trains and this will require
upgrading and remodelling of the current terminal.
Until this occurs, infrastructure constraints in the Botany Yard will continue to act as the
bottleneck stifling achievement of 40% target share.
The Southern Sydney Freight Line (“SSFL”) will be of significant benefit in relation to freight
movements to and from the south west of Sydney. The SSFL should improve access to the
south west Sydney segment of the market which currently accounts for around 16% of the
metro market, but which is expected to grow to about 20%. While this will assist in access to
the area, it should be noted that the principal advantage will be during the morning and
evening curfews. Interstate intermodal services 1500-1800m in length will also be using the
52
corridor. The limited capacity on the SSFL, with only a single passing loop, may become an
issue.
However, the SSFL does little for large areas of Sydney (and the state of NSW) which still
have to compete with the passenger network, or are simply not serviced by freight rail
networks at all. Patrick recognises the need for well considered freight only lines or dedicated
freight paths west and north, as well as to Illawarra and Yennora.
Furthermore, only two metropolitan terminals will have direct access to the SSFL. One of
these, Ingleburn, is yet to be developed as a container handling facility. Yennora and Camellia
will not be assisted by the SSFL, and will continue to be impacted by the constraints of
competing passenger trains.
The problem for rail is that capacity on the main metropolitan networks, especially during the
shoulder and peak, is limited and the costs of providing additional infrastructure for freight is
very expensive.
Additionally, road has easy access to the M4/M2/M7 to service this market in competition with
rail. This reflects the fact that one reason for the rapid recent and projected growth in new
Distribution Centres in certain areas has been their proximity to the greatly enhanced and
expanded freeway/motorway network.
6.3 Combined Effect
The combined effect of the above makes rail extremely unattractive for many freight
movements in Sydney. Rail suffers considerable competitive disadvantages compared to road,
as outlined below. Rail will only become more attractive with a focus on improving and
modernising rail infrastructure in NSW and operational procedures and revised management
structures in the Botany precinct Until then, rail will continue to find competition with road
difficult:
53
Competitive Issue Road Rail
Congestion Congestion around Port and on parts of the urban road network
Congestion in Botany branch & yard and at key points on the rail network
Access to Infrastructure
No restrictions Curfews, and second priority to passenger on most of network. No access during possessions (track maintenance closures)
Flexibility 24/7 Access to collect containers
Restricted to defined track access paths and affected by passenger curfew
Geographical scope Whole metro region Limited to economic distances around inland terminals
System complexity Low – generally “one-off” lift or delivery
High - Botany Yard issues involving the shunts and splitting of trains, competing with passenger networks, track access regimes to name a few
Delivery time Shorter than rail door to door
Rail may have an advantage if customer has multiple boxes which can be carried on one train, but still require multiple truck trips to the final destination
Cost – Back loading
Normally available Variable
Cost - Overall Generally lower cost than rail door to door
Track access charges, double handling/inland terminal costs, and cost of truck delivery to customer
Figure 23: Competition between rail and road
Finally, the fragmented nature of the market means that even a high rail share in this south
west segment will leave substantial share to be found in other parts of the market if the 40%
target is to be reached. The west of Sydney (Penrith, St Mary's, Eastern Creek) remains largely
unserviced. This impacts on areas outside of Sydney (Parkes, Dubbo, Blayney, Bathurst for
example) which enter Sydney from that direction, and are a source for large export volumes of
containerised freight.
Therefore, the other major requirement for improved network capacity, after the SSFL and
Botany lines, is to provide additional pathing to the Western Sydney market between
Parramatta and the Blue Mountains, for example, the emerging Eastern Creek segment.
6.4 Rail Access charges at Port Botany
The payment of a window fee guarantees an exclusive right of entry for a rail operator in
the specified time range. It is based upon a similar principle to a rail access fee which
guarantees an exclusive path.
54
Patrick charges a standard window fee for entry and use of the Terminal siding for all
operators. The charging of such a fee is consistent with operating procedures at other rail
sidings in Sydney and other States in Australia.
The payment of a window fee guarantees an exclusive right of entry for a rail operator in the
specified time range. It is based upon a similar principle to a rail access fee which guarantees
an exclusive path – a window fee buys exclusive internal siding time at the Patrick terminal.
Operational certainty is an extremely important commercial consideration for any rail operator
and the window fee is a mutual commitment on behalf of both the Terminal operator and the
rail operator.
The window fee encourages rail operators to deliver on time performance to the Terminal. On
time performance figures for trains arriving at Port Botany are poor and improvements in on
time performance are essential if modal shift is to occur so as to achieve the 40% rail share
objective.
55
7. Facilitating development of ‘inland ports’
Patrick is supportive of the FIAB recommendations relating to the development of inland ports
in NSW. Patrick believes that market based solutions will deliver the greatest efficiency,
success and sustainability. Patrick believes that the role of Government should be to limited to
providing the investment in infrastructure (particularly rail networks) and making land
available for the development of inland terminals. The development and operation of such
terminals should be left to the private sector.
In principle, Patrick is fully supportive of the FIAB recommendations relating to the
development of inland ports in NSW. Patrick agrees that:
efficient rail movements from Port Botany require efficient intermodal terminals,
located where possible on freight-only rail lines".62
Inland intermodal terminals will deliver economic, social and environmental benefits, in
particular:
(a) Assist in achieving NSW Government goals to reach a 40% rail share;
(b) Improve service levels to importers and exporters by moving wharf interface closer
to demand centres on Sydney’s fringes;
(c) Improved truck productivity;
(d) Decreased traffic congestion and improved traffic flows in ‘near-port’ areas;
(e) Potential for lower road maintenance costs in certain elements of the road network;
(f) Social amenity outcomes;
(g) Fewer greenhouse gas emissions; and
(h) A more sustainable freight and logistics industry better able to cope with anticipated
levels of growth.63
Given the geographical constraints and demographics of cargo movements in Sydney, the
establishment of such intermodal facilities is an immediate priority facing NSW.
62 Review by the Infrastructure Implementation Group of the Freight Infrastructure Advisory Board report and recommendations, May 2007 at p 4.
63 Victorian Freight and Logistics Council (2004) “Industry Intermodal Awareness Program”, VFLC, Melbourne.
56
Patrick supports a recommendation of FIAB and endorsed by the Review by the Infrastructure
Implementation Group, that:
(a) terminals be of sufficient capacity to load full trains either to or from a single
stevedore;
(b) terminals of sufficient size to accommodate on site empty containers parks and
servicing, on site warehousing development, driver facilities, including truck and
trailer parking, rest facilities, an AQIS Inspection in Customs bonded areas;
(c) terminals be available to operate 24 hours a day, 7 days a week to maximise the
return on investment in the sites and utilise the rail network to its maximum
capacity.64
Patrick believes that market based solutions will deliver the greatest efficiency, success and
sustainability. Patrick believes that the role of Government should be limited to providing the
investment in infrastructure (particularly transport networks) and making land available for the
development of inland terminals. The development and operation of such terminals should be
left to industry.
The identified bottle necks which are preventing efficient land side transport of containers will
not be materially addressed by terminal expansion at Port Botany or by the advent of further
container terminal operators. The issues of mismatch in the import/export chain will remain
until the reforms in the land transport operations are implemented. The solutions which
Patrick proposes apply also to containers transported to or from any further terminal which
operates at Port Botany.
7.1 Stevedores' obligations
Under the terms of the Lease for the Port Botany facility between Sydney Ports Corporation
and Patrick, Patrick is entitled to quiet enjoyment of its premises at Port Botany. Patrick is
fully compliant with all obligations relating to the provision of road and rail access under the
terms of its Lease.
64 Review by the Infrastructure and Implementation Group of the Freight Infrastructure Advisory Board report and recommendations, May 2007 at p 11.
57
8. Vertical integration of the supply chain
Vertical integration is one way in which the various parties in the supply chain can work
closely together to drive efficiency. However, there is little vertical integration in the supply
chain in Sydney. Patrick Port Services move fewer than 2% of road movements into or out of
the Port, and the data supports the fact that they receive no preferential treatment due to their
ownership structure. Recent restructures within the stevedores will further reduce vertical
integration and enhance transparency.
IPART raise a number of issues related to vertical integration of the Port Botany supply chain
and seek to asses whether this vertical integration affects the transparency and fairness of the
provision of services in the terminals.
It is important to recognise that vertical integration can deliver significant efficiency benefits
for the supply chain and in many cases is the most appropriate structural solution. However, it
is also important not to overstate the extent of vertical integration in the Port Botany supply
chain, for example 98%65 of the truck movements in Port Botany are associated with non-
stevedore related transport providers.
As IPART notes66 in its Issues Paper there have been a number of changes in the ownership
structure of the Port Botany supply chain. The first section below addresses the changes in
Patrick’s business structure, focusing on the creation of Asciano and describes the current level
of vertical integration. The second section looks at the impact of this vertical integration on
access arrangements in the terminal.
8.1 Asciano Businesses
In December 2006, Toll announced its intention to separate its business into two ASX Listed
entities. This proposal has received regulatory approval and shareholder approval. Asciano
(AIO) was listed on the ASX on June 6, 2007. The chart below summarises the restructure.
Asciano will comprise the Pacific National and Patrick businesses plus the Toll Owens, AAT,
QBH and CCA joint ventures. Toll will retain the remaining companies which mainly
comprise freight forwarding and logistics businesses plus the 63% holding in Virgin Blue.
65 Movements in Patrick’s Port Botany terminal in the calendar year to March 2007.
66 Issues Paper at p 40.
58
The restructure will return Patrick’s level of vertical integration at Port Botany back to the
position prior to Toll’s acquisition of Patrick in early 2006. That is, Toll companies are now
independent of Patrick and in addition to the terminal operations there are only two Patrick
related companies active in the Port Botany supply chain: Patrick Port Services and Patrick
PortLink.
Patrick Port Services offers a range of land based services to shipping lines, freight forwarding
agents, customers brokers, importers and exporters. Its key operations include:
(a) Container parks – container storage and handling;
(b) Container packing and unpacking;
(c) Container transportation to and from Container Parks;
(d) Container repairs, refurbishment and preparation;
(e) General warehousing and bonding; and
Toll Holdings(ASX listed)
Domestic Freight ForwardingLogisticsShippingDistribution and WarehousingInternational ForwardingDefence LogisticsExpress/CouriersAutologistics
Aust
ralia
Toll AsiaAsia
Toll NZ (84.2%)NZ
Virgin Blue (62.8%)VBA
Public shareholders
Asciano Limited Asciano Finance Trust
Stapled structure (ASX listed)
PatrickContainer terminalsPortLinkPort ServicesBulk portsStevedoringToll Owens (50%)
Por
tsR
ail
Public securityholders
Pacific NationalIntermodalBulk
Oth
er
Patrick Autocare JV (80%)AAT (50%)QBH (50%)CCA (50%)
Toll Holdings(ASX listed)
Domestic Freight ForwardingLogisticsShippingDistribution and WarehousingInternational ForwardingDefence LogisticsExpress/CouriersAutologistics
Aust
ralia
Toll AsiaAsia
Toll NZ (84.2%)NZ
Virgin Blue (62.8%)VBA
Public shareholders
Toll Holdings(ASX listed)
Domestic Freight ForwardingLogisticsShippingDistribution and WarehousingInternational ForwardingDefence LogisticsExpress/CouriersAutologistics
Aust
ralia
Toll AsiaAsia
Toll NZ (84.2%)NZ
Virgin Blue (62.8%)VBA
Public shareholders
Asciano Limited Asciano Finance Trust
Stapled structure (ASX listed)
PatrickContainer terminalsPortLinkPort ServicesBulk portsStevedoringToll Owens (50%)
Por
tsR
ail
Public securityholders
Pacific NationalIntermodalBulk
Oth
er
Patrick Autocare JV (80%)AAT (50%)QBH (50%)CCA (50%)
59
(f) Quarantine services.
Port Services employs approximately 700 people in Sydney, Townsville, Brisbane, Melbourne,
Adelaide and Perth.
Patrick PortLink’s main focus is providing rail based land-side logistics and freight forwarding
for importers and exporters between the port, metropolitan container terminals and regional
centres. It key operations include:
(a) Rural rail services to major ports;
(b) Regional Intermodal and “Inland Port” terminals;
(c) Rural Import/Export packing and warehousing; and
(d) Rural distribution services including freight forwarding to support port rail
activities.
PortLink operates across a network of 25 sites throughout south Eastern Australia. It currently
employs about 380 people.
In order to facilitate regulatory approval for the creation of Asciano, Toll and Asciano have
agreed with the ACCC undertakings which include a non discrimination regime covering both
PN and Patrick. The Patrick undertakings focus on non discrimination at the Ports including
Sydney.67 Compliance with these undertakings is independently audited every 6 months.
Vertical Integration and Access Arrangements
IPART68 has stated it will review concerns raised by industry participants that stevedores may
be providing preferential access to their affiliated businesses. The focus of these concerns is
around treatment of affiliates is in the movement of containers by truck. These concerns are
not supported by any cogent evidence.
When looking at issues of vertical integration it is important to understand the relative size of
Patrick Port Services operations at Port Botany. The trucking companies utilising Port Botany
are extremely diversified with the largest customer only having 12% of container movements
and the top 10 customers only making up 33% of total container movements.
67 See http://www.accc.gov.au/content/item.phtml?itemId=785480&nodeId=3a981ab6609cf233f1fb75cdb7d8a734&fn=Fifth%20variation%2020070418.pdf and http://www.accc.gov.au/content/item.phtml?itemId=785515&nodeId=8adc6849bfbe1bfc4cc8355edf3d38d0&fn=Undertaking.pdf
68 IPART Issues Paper at p 40.
60
The figure below illustrates the shares of container movements by truck for the largest ten
transport companies plus Patrick Port Services.
Shares of Truck Container Movements at Port BotanyLargest 10 plus Patrick Port Services
Year to March 2007
Other PPS
Figure 24: Shares of truck container movements at Port Botany
In the year to March 2007, less than 1.5% of truck movements in Port Botany were undertaken
by Patrick Port Services.69 The data above indicates competition among a very large number
of carriers for trucking movements from Port Botany and is in direct contradiction to claims
that vertical integration has been distorting competition in favour of vertically integrated
operators.
Truck turnaround times for the year to March 2007 for the ten largest customers plus Patrick
Port Services at Port Botany show an even distribution. Differences between large and smaller
operators arise because larger operations often have a higher number of containers per truck
and are able to take advantage of stack runs. Patrick’s truck turnaround times are in line with
other larger operators.
69 This excludes the container movements for Quarantine Service contract. These trucks have special access rights in order to meet the contractual commitments to the Quarantine Service.
61
Figure 25: Truck turnaround times by container
Concerns regarding affiliate treatment expressed by industry participants simply do not stand
up to rigorous scrutiny.
8.2 A third stevedore for Sydney
Patrick believes that additional quayside capacity at Port Botany will not overcome the key
challenges facing the land side interface as outlined above. The constraints on the efficient
movement of freight in NSW must be addressed by improvements to the movement of road
freight, investment in rail infrastructure and the establishment of intermodal terminals in NSW.
Land side efficiency issues are not going to be solved by constructing additional quay line at
Port Botany.
Truck Turnaround Times by Container - 10 Largest Customers plus Patrick Port
Services Sydney year to March 2007
0
10
20
30
40
50
60
1 2 3 4 5 6 7 8PPS
9 10 11
Minutes per container