PAT Picture Guide
Transcript of PAT Picture Guide
-
8/14/2019 PAT Picture Guide
1/58
PAT GuidePAT GuidePAT GuidePAT Guide
Picture Guide to assist in thef PAT/FAT
-
8/14/2019 PAT Picture Guide
2/58
This Document is to be used in accordance with the PAT/ FAT acceptance checklist and
overall Deficiency Lists. It is designed to offer visual assistance to help bridge any languagebarrier with an idea to enhance quality.
Please Note that the Generator PAT checklist has been removed from this guide.
All photos used in this guide were taken on sites deemed ready for PAT by Huawei.
1.0 Site Development
2.0 Records & Documents
3.0 Earth Works
4.0 Site Cleanliness
5.0 Fence (Greenfield )
6.0 Site Development ( Roof top )
7.0 Greenfield/ Roof top ( Indoor ) Brick Room
8.0 Air conditioning ACU
9.0 Greenfield/ Roof top ( Outdoor ) Sun Shelter/ Brick Room
10.0 Tower ( Visual Inspection )
11.0 Electrical
12.0 Electrical Test.
-
8/14/2019 PAT Picture Guide
3/58
MAJOR/ MINOR ITEM DESCRIPTION
CIVIL WORKS
1.0 Site Development
Major 1.1 Layout: Conformity with the Approved Construction Drawing.
2.0 Records & Documents
Major 2.1 As Built drawing reflects the built site.
3.0 Earthworks
Minor 3.1 Grading and Leveling as per indicated in the drawing.
Minor 3.2 Crushed Rock is 100mm deep.(Random locations to be checked)
Major 3.3 Site is free from settlement.
Major 3.4 Compaction has been correctly done in 20cm layers.
Minor 3.5 Access Road Construction 4m wide.
4.0 Site Final Clean
Minor 4.1 General Cleaning (external)
Minor 4.2 General cleaning (internal)
5.0 Fence (Green Field)
Major 5.1 3 strand Barbed wire galvanized (Check quality, connections and Tension of wire)
-
8/14/2019 PAT Picture Guide
4/58
Major 5.6 No holes/gaps in the fence Including underside
Minor 5.7 Fence is aligned, secure and is tensioned correctly.
Minor 5.8 Fence welding is to a good standard.
6.0 Site Development - Greenfield/ Roof Top
Major 6.1Installation of building access steps. (walkways, platforms or ladders should be avail-
able to gain access to the facilities)
Minor 6.2 Site is free from trip hazards.
Minor 6.3 Premises have been returned to original state. (Damaged building etc)
7.0 Greenfield/Roof Top - indoor site (Brick Room)
Major 7.1 Room Lay Out According to Drawing.
Minor 7.2 Porthole or Feeder Entry Location According to Drawing.
Minor 7.3 Cable window glands sealed correctly with clear silicone.
Minor 7.4 Door Location According to Drawing.
Minor 7.5 All door seals are in good order.
Major 7.6 Door and Locks. (Deadbolt and Padlock)
Major 7.7 Door specification is correct. (IP54)
Minor 7.8 Keys handover.
Minor 7.9 Flooring. (Level, Vinyl Installation is Anti Static, No tears )
Minor 7.10 Ceiling Elevation According to Drawing.
Minor 7.11 Cable ladder correct elevation and Alignment.
Major 7.12 Roof structure sealed correctly, Internally and Externally.
-
8/14/2019 PAT Picture Guide
5/58
Minor 7.17 Cable ladder is installed correctly with bond straps at joints.
Minor 7.18 Electrical trunking is installed to a good standard.
8.0 Air Conditioning Unit (ACU)
Major 8.1 ACU are functioning and working efficiently.
Minor 8.2 Serial No. ACU 1:________________________________________
Minor 8.3 Serial No. ACU 2:________________________________________
Minor 8.4 A/C Type, Brand.
Minor 8.5 Overall Installation of package is correct.
Minor 8.6 Check Filter.
Minor 8.7 Check Breaker Location.
Minor 8.8 Correct AC controller holders have been installed inside room.
Minor 8.9 Check Cover and evaporator should be Clean.
Minor 8.10 PVC drain pipe for Air Conditioning/ Fixed every meter/ Drain off point acceptable.
Major 8.11 AC condenser pipes are insulated correctly.
9.0 Greenfield/Roof Top - Outdoor site (Sun Shelter/ Brick Room )
Major 9.1 Overall Installation of package is correct .(Layout)
Major 9.2 Sun Shelter constructed as per drawing.
Major 9.3 Roof sheeting is complete.
Minor 9.4 Sun shelter is rigid.
-
8/14/2019 PAT Picture Guide
6/58
Minor 9.9Brick room internal and external walls are free from damage and are built to a goodstandard.
Minor 9.10 Brick room internal and external paintwork has been finished to a good standard.
Major 9.11 Brick room roof drainage (pipes) has been finished to a good standard.
Major 9.12 Brick room lighting and electrical has been installed.
10.0 TOWER (VISUAL & PHYSICAL INSPECTION)
Major 10.1 Tower height. (as per approved design)
Minor 10.2 Tower Base Plate is filled with Non-shrink grout.
Minor 10.3 Concrete pedestal height. ( Greenfield )
Minor 10.4 Climbing ladder/ fixed to concrete beam/ correct anchor bolts used.
Minor 10.5 Work / rest platform.
Minor 10.6 Cable ladder as per drawing.
Minor 10.7 Cable bridge, cable bridge legs and footings as per drawing.
Major 10.8 TEST: Torque wrench/ Random check of nuts and bolts throughout tower.
Minor 10.9 No missing bolts/nuts/washers.
Major 10.10 Bolts correct size and grade. (8.8 grade)
Major 10.11 TEST: Alignment / verticality. (Tolerance 1:400)
Major 10.12 Lighting arrester .
Major 10.13 Top & bottom Bus Bar.
Major 10.14 Fitting of tower member joints. (Check no gaps between joints)
Major 10.15TEST: Elcometer/ Painting (Random DFT to be measured) and that paint work isfree from damage.
Minor 10 16 Check Antenna mounts (secure installed correctly)
-
8/14/2019 PAT Picture Guide
7/58
11.0 ELECTRICAL
Minor 11.1 Service Entrance Pedestal.
Major 11.2 Mains conduit/ Fixed every meter/ Correct clamps used/ Painted grey/ Sealed to
Minor 11.3 Ceramic spool rack Installed.
Major 11.4 Catenary from EDC pole to landlords roof installed.
Major 11.5 Mains cable secured to Catenary using correct clamps.
Major 11.6 EDC Connection is correct and Glanded into ACDP.
Major 11.7 All electrical fittings - Are secure and functioning. Including, lights, sockets etc
Major 11.8 All external electrical fittings have sufficient IP ratings.
Major 11.9
Cables in panels have lugs fitted/ crimped tightly/ tails are not too long/ attached se-
curely.
Minor 11.10 Cable work in panels have correct individual ID Labels.
Major 11.11 Electrical Panels have correct wiring schematic.
Major 11.12 Lightning surge protection on main panel - SPD.
Major 11.13 DG Socket installed .
Major 11.14 Internal earth bars in panels are connected to main earth ring.
Major 11.15 Circuit breakers correct size.
-
8/14/2019 PAT Picture Guide
8/58
12.0 Electrical Tests (switch board functionality)
Major 12.1 Energize the electrical panel and check operation.
13.0 OB Light Test
Major 13.1 TEST: Cover photo cell and observe that obstruction lamps light up.
14.0 Earthing & Lightning Protection.
Major 14.1 Ground rods installed as per drawing.
Major 14.2Connections between the ground system and the ground rods correct.(2 bolt connec-tion)
Major 14.3 Grounding pits as per drawing.
Major 14.4 TEST: The earth resistance should be less then 5 Ohm. (Record measurement)
Major 14.5 Tower Bus bar properly installed.
Major 14.6 Equipment grounded correctly.
Major 14.7 Tower Legs Grounded.
Major 14.8 Sun shelter steel 'H' beam Grounded.
Major 14.9 Sun shelter Grounded.
Major 14.10 Climb Ladder Grounded.
Major 14.11 Cable Bridge support Grounded.
Major 14.12 Fence Grounded.
Major 14.13 Cable Bridge has bond strap at each joint.
Major 14.14 Grounding strip is fixed every meter using M8 bolts and black rubber spacer washers.
Major 14 15 Grounding strip joints have correct over lap (as per drawing) 100mm bolt to bolt
-
8/14/2019 PAT Picture Guide
9/58
1.0 Site Development.
Check that the newly constructed site
conforms to the construction issue
drawing.
If there are items that are shown on
the drawing but are missing from site,
note them down on thePAT deficiency list.
The picture right, shows theengineer checking that the Surge
Protection Device has been fitted andin the correct location.
2.0 Records & Doc.
Check the As Built Drawings match
the completed works on site.
If there are items incorrectly shown,
or if there are items that are missing
from the As Built Drawing markdown the items using a REDpen.
The drawings must show what has
actually been built on site.
It is important the drawings show
Antenna Heights and Azimuths. If
this is not shown make a note on the
front page of the drawings.
1.0&2.0Records&Documents
-
8/14/2019 PAT Picture Guide
10/58
3.1 Grading & Leveling.
Check that the grading on site
matches what is on the drawing.
Picture 1.Shows a typical site. The
lines drawn help us to see if the
grading is correct. If we compare it to
the drawing below we can see thatthere is not 500mm of flat backfill
before the gradient commences. The
gradient just slopes directly from theBrick Room. This should be noted on
the deficiencies
Picture 2. Shows the actual drawing
dimensions .
Circled, is the ratio that should beused to calculate if the grading on site
is correct.
3.2 Crushed Rock.
Check that crushed rock has been laid
inside Greenfield perimeter fence.
Crushed rock should be laid to a depth
of 100mm.
Check in 5 random locations withinfence that this depth has been main-
tained.
The picture left shows crushed rock
laid around a grounding pit.
2
1
3.0Eart
hWorks
-
8/14/2019 PAT Picture Guide
11/58
3.3 Site Settlement. On Greenfield sites it is important to check atosee if any settlement has occurred.Check: Buildings for cracks, Cable Bridge and Fence Foundation levels. Is the ground around the tower soft?
1 2
3 4Tower Leg
-
8/14/2019 PAT Picture Guide
12/58
4.1 Site Clean External.
Check that the site is clear from anyconstruction rubbish that may have
been left behind.
Cement bags, timber form work, brick
rubble etc.
Picture 1. Shows left over roofsheeting and cardboard on a rooftop
site. Note the poor installation of the
mains conduit on the wall. We can seeit has not been fixed every meter (as
per drawing)
Picture 2. Shows a Greenfield site
with brick rubble and blue PVC pipe
in the background. We can also seethat the backfill has been done poorly
on this site.
4.2 Site Clean Internal.
Check that the inside of the BTS roomis clean from any rubbish or dust.
Is the equipment dusty?
Is there dirt on the cable feeder
window ledge?
Is the vinyl floor clean from dust ,
paint and floor glue?
Check inside the ACDP & SPD
panels, are they free from dust and
metal filings?
A BTS room should be a dust freeenvironment to allow the equipment
1
2
4.0SiteC
leanliness
-
8/14/2019 PAT Picture Guide
13/58
5.1 Barbed Wire Fencing. Check the barbed wire installed around the perimeter fence. Check thejoints (are there any weak points?). Check the tension ( is it tight when pulled by hand? )
Cracked concrete fill
1 2
3 4
5.0Fencing
-
8/14/2019 PAT Picture Guide
14/58
5.1 Barbed Wire Fencing. The pictures above are examples of acceptable barbed wire installations.The arrowed picture shows an end termination. Wire folded over, welded and finished with galvanized paint.
Bolted to brick room wall
-
8/14/2019 PAT Picture Guide
15/58
5.2 Gate Lock.
The pictures on the right show 2different types of gate lock.
Picture 1. Shows one which is
unacceptable. It has been made up on
site not factory made.
It is welded onto the chain link stripnot the fence panel.
Picture 2. Shows a suitable bolt lockwelded firmly onto the middle tube of
the fence panel.
Picture 3. Shows the drop in bolt at
the foot of the Fence Gate. It is just as
important to have a solid concrete
bolting pad as it is to have a secure
lock
5.3 Galvanized Paint.
Picture 1. Shows an acceptable
welded joint with a proper coat of
galvanized paint
Picture 2. Shows a poor weld and bad
paint work See how rust has already
1
1
32
-
8/14/2019 PAT Picture Guide
16/58
5.4 Fence Panel
Connections.The pictures on the right show 2different fence panel to panel
Connections.
Pictures 1 & 2. Show unacceptable
connections. We can see that the bolts
have been left too long in the pictureon the left and too short in the one on
the right. Also they have not been
painted with galvanized paint and havebegun to rust. This also shows they
were a poor quality bolt to begin with.
Picture 3. Shows a good
example of fence panel connections.The panels are tight together and are
spaced with washers. The bolts have
been cropped short and the ends have
been coated with galvanized paint.
5.5 Fence Connection to
Brick Room.
Picture 1. Shows an unacceptable
Fence to Brick Room Connection. Italso highlights many other
deficiencies such as poor
painting of the fence and damage to
the Brick Room wall. If we look even
closer we can see that the nut has not
even been tightened (circled).
Picture 2. Shows an
bl F B i k R
1 2
3
1
-
8/14/2019 PAT Picture Guide
17/58
5.6 Gaps in Fence.
The pictures on the right showunacceptablegaps in the fence
Picture 1. Shows a large gap on the
underside of the fence. The correct
measurement should be 200mm from
fence to backfill. In the far corner themeasurement is over 600mm. Also of
note is the poor fence post grounding
(circled)
Picture 2. Shows a break in the chain
link fence. The arrow is pointing to anunacceptable repair. This leaves the
fence unsecure.
5.7 Fence Tension Correct.
Picture 1. Shows the engineer
pulling on the fence to check its
tension. The fence should not give
way any more than 50mm from itsresting position
1
2
1
-
8/14/2019 PAT Picture Guide
18/58
5.8 Fence Welding.(Poor)
The pictures on the right showunacceptable fence welding.
Picture 1. Shows the chain link being
welded directly onto an internal steel
frame. The large gaps between the
steel and the fence panel are clearlyvisible. As is also the heavy rust.
Picture 2. Shows again large gaps
between the chain link and the fence
panel. The arrow is pointing out there
is no welding at all to the corner of
the Fence.
Chain Link must not be welded
directly onto the fence panel. It must
be threaded NOT WELDED.
5.8 Fence welding. (Good)
Picture 3. On the left shows thechain link threaded with steel rod
The rod welded on the vertical and
horizontal parts of the Fence Panel.
The spot welds should be a minimum20mm long ( arrowed ).
Picture 4. The bottom left shows the
chain link of the fence has been
threaded by steel rod and the rod
1
2
3
-
8/14/2019 PAT Picture Guide
19/58
6.1 Site Access.
Picture 1. Shows blocked access tothe tower. Not only are there large
amounts of furniture stored around the
tower legs but the roof is entirelyclosed over the climbingladder., making access to this towerimpossible .
Also of note is the fact that during a
strike by lightning the entire roof
structure would become live with
electrical current as it is part of the
tower.
Picture 2. Shows that the site is noteasily accessible due to water poolingaround the site. We can see that thebackfill gradient is eroding away.
This a deficiency because it is noteasy to access site through foot or
vehicle traffic. Eventually the water
problem is likely to affect the fence.
6.2 Site Free From Trip
Hazards.The site should be free from obviousTrip Hazards that have been caused
by poor building standards.
Picture 1. Shows the engineer trip-
ping over a Mains Conduit laid acrossa walkway.
Picture 2. Shows the same Conduitfrom a different angle. We can see in
the background that there is more
conduit laid across the walkway.
Why did the Sub-con block thewalkway twice?The Conduit at thefront is unsupported and therefore
bl
1
2
6.0
SiteDevelopment
-
8/14/2019 PAT Picture Guide
20/58
6.3 Landlords Premises.
Once construction has beenCompleted it is up to the sub-con to
reinstate the landlords premises to
their original condition.
Picture 1. Shows the damage caused
by the Sub-con roughly chippingaway the roof tiles to install the cable
bridge. Notice that the Cable Bridge is
missing a bond strap at the joint andthe concrete footings have been left
unpainted
Picture 2. The bottom right shows a
cracked tile that was damaged during
the grounding installation.
Each of these should be marked downas deficiencies for the Sub-con to
repair.
7.1 & 7.2 Room Layout.
Check the room layout against thedrawing . If there are any notable
changes to the room compared to the
construction issue drawing mark it inREDpen on the as built drawing.
If any major items are missing , suchas a smoke alarm or AC Unit mark it
down on the deficiency list.
Also check that the Feeder Cable
entry window ( Item 7.2 ) is as per
drawing. Check size and location
The picture on the left shows the as
built drawing after the engineer has
1
2
oorBrickRoom
-
8/14/2019 PAT Picture Guide
21/58
7.3 Cable Window.
The cable feeder window should besealed to the outside with clear
Silicone. This is to stop any water or
insects from entering the BTS Room.
Check to see if the sealing has been
done neatly without smearing siliconeon the cables. The feeder cables
should be sealed from both sides.
7.5 Door Seals.
The door seals are an important partof the rooms function. They will stop
water and insects from entering the
building.
They also provide an airlock to theoutside so that the air conditionersdont need to work so hard.
Picture 1. Shows the sealant strip isdamaged with 2 large pieces missing.
It also shows there is a fixing screw
missing ( arrowed )
Picture 2. Shows a good door seal.
To check move your hands around the
7.4 Door Location.
This procedure is exactly the same as
Item 7.1 and 7.2.
Also check that the door threshold is
at least 100mm higher than the
ground level on the outside. This is
important to stop water entering the
building in heavy rain.
1
-
8/14/2019 PAT Picture Guide
22/58
7.7 Door Spec. IP 54
The door installed on site should be 1hour fire rated and should meet a
minimum IP Rating of 54.
Check the IP Ratings list at the back
of this guide for assistance .If youare unsure mark in the deficienciesPlease provide certification
The picture top shows a door which
is not IP 54. The door handlespoor
welding show that this is not a factory
made door.
7.6 Door Locks.Check to see that the doors open
and close properly.
Turn the lock. Is it easy to use?
Open and close the door severaltimes. Does it close easily?
When the door is closed. Does it sit
straight in the frame?
Picture 1. Shows an obvious
Deficiency. The entire lockset is
missing. This door has no security
protecting the expensive equipmentinside. This is a major deficiencyand should be fixed immediately.
Picture 2. Shows the engineerchecking a complete lockset.
1 2
-
8/14/2019 PAT Picture Guide
23/58
7.8 Keys Handover.If any keys are to be handed over note it down in the comments. If no keys have been handed over mark it as a fail
in the deficiencies list.
7.9 Flooring.The pictures on the left show a series of common problems.
Picture 1. Shows that there is not enough floor glue on the corner of the tile.
Picture 2. Shows that the flooring has not been completed so that it meets the door threshold.
Picture 3. Shows excessive floor glue (circled ) on the joints of the tiles. This floor also needs a good clean.
21
-
8/14/2019 PAT Picture Guide
24/58
7.10 Ceiling Elevation According To DrawingCheck the ceiling elevation against the drawing ( especially As Built Drawings ) using the same procedure as
items 7.1, 7.2, and 7.4. Also note whether 50mm fiber glass insulation has been installed in the ceiling void.
7.12 Roof Structure Sealed
Check the perimeter of the BrickRoom at high level where it meets the
roof.
All holes should be filled and all gaps
siliconed
Also check on top of the roof
sheeting.
Are the any excess fixing holes that
might leak during rain?
7.11 Cable Ladder.Once again check cable ladder
construction against the drawing.
-Is it the correct height?
-Are the ladder supports well fixed
into the wall?-Is the ladder level?
-Is the threaded rod cropped short?
Picture 1. Shows the engineer check-
ing to see the strength of the supports.
Picture 2. Shows missing nuts and
bolts from ladder fixing brackets.
Picture 3. Shows that the threadedrod has been left too long. It should be
cut approx 5mm after the nut andwasher.
7.13 Int/ Ext Walls Free
From Damage.
This picture
shows a tight seal
to roof and wall
1
2 3
-
8/14/2019 PAT Picture Guide
25/58
7.14 Int/Ext Paintwork
The picture right shows paintworkthat has blistered in the sun (circled ).
It will only be a matter of time before
the paint starts to peel from the walls.
Other areas to check.
Inside the BTS room is there paint on
any equipment, doors, trunking ?
7.16 Internal Bus Bar
Check the Bus Bar is attached firmlyto the wall. Is it in the right place?
Picture 1. Shows the grounding strip
is only attached with 1 bolt (circled).
Picture 2. Shows damage to the wallwhilst installing. Also note within the
picture that there is a missing fixing
bolt (arrowed).
7.15 Fire Extinguisher
The fire extinguisher in the BTS room
should be aDry Powder Type ( Picture 1.). Due
to the electrical nature of a BTS room
Water or Foam type extinguishers are
not acceptable
Picture 2. Shows the engineer ischecking to see that the firing pin is
still intact (circled)
7.17 Cable Ladder with
Bond strapsAll internal cable bridge/ ladder must
be bonded to the main earth ring
21
1 2
-
8/14/2019 PAT Picture Guide
26/58
7.18 Electrical Trunking.
(Poor Installations)
The good installation of electricaltrunking is of high importance. It
carries high volt power that can cause
death if disturbed.
Picture 1. Shows plastic trunking
used to house grounding strip. This isnot acceptable.
Picture 2. Shows trunking which isnot the correct size. It should be large
enough to cover the gland holes thatthe cables go into. The trunking lid
has been roughly chopped to allow
the cable to pass (circled). This is not
acceptable.
Picture 3. Shows the same problemsas picture 2. Also of note is the small
piece of lid that has been stuck onusing silicone. This is not acceptable.
1
2
4
3
Picture 4. Shows 2 different
sizes of trunking butted
together (circled). The end of
the larger piece of trunking is
d d Thi i t
-
8/14/2019 PAT Picture Guide
27/58
7.18 Electrical Trunking
(correct installations)
These pictures show good trunking
installations. Note there are no wires
on show. The trunking fits hard into
the electrical panel.
A panel such as this could house
power between 240415 volts. It is
therefore of upmost importance that
the cables housed in the trunking arewell protected.
Damaging such cables could result in
death.
-
8/14/2019 PAT Picture Guide
28/58
8.1 ACU working Functioning.
The AC Units must be proved to be working. Take the controls from their wall mounted position and test eachindividual unit responds to the controls.
8.4 AC Type (EG. Wall mount) & Brand.
Check the type of AC Unit and the Brand name and note it down on the PAT sheet.
8.2 & 8.3 ACU Serial No. Units 1 & 2.
Check the AC Units for their individual Serial Numbers and note them down on the PAT sheet.
8.6 Check Filters.
Check the filters on all AC units. The
front section of the wall mounted unit
will lift up as shown inPicture 1.
Picture 2. Shows the engineer point-
ing out that the filter is dirty.
The filters should be removed and
8.5 Overall Installation.
The overall installation should match what is shown on the Construction issue drawings. If there are any changes
note them on the As Built Drawings in REDpen. Also note them on the deficiency list.
1
8.0
AirConditioning
-
8/14/2019 PAT Picture Guide
29/58
8.7 Check Breaker
Location.
Open up the ACDP. The breakersshould be directly in front of you.
The picture right shows the correct
size breaker C32Amp (circled).
Notice also that the breaker has been
labeled above. A breaker will be on(live) in the up position. Check
against the drawing.
8.9 Check Condenser
Cover.
Check the covers of the AC Internal
Wall Unit and the External ACCondenser.
Are they fixed to the wall and bracket
correctly?
Are any nuts, bolts or washers
missing?
Are they clean and free of paint
splatter?
Check over the units are there any
h bl h ?
8.8 AC Controllers.
Check that the portable hand held
controllers are in the room and thatthey operate the AC Units in the
room. They should also have the
correct, factory supplied holders fitted
on the brick room wall (pictured).
-
8/14/2019 PAT Picture Guide
30/58
8.10 PVC Drain/ AC Units
Check the entire run of the drain pipe
installation. Has it been clipped every
meter using the correct clips ?
(circled in picture 1.)
Is it draining off into a proper drain?(not onto the landlords roof)
Picture 1. Shows the drain pipe un-
supported at high level (arrowed). The
drain pipe should have been broughtdown the wall.
Picture 2. Shows that the AC unit is
draining onto the landlords roof. Italso shows that flexible hose has been
attached on the end. Why? Thisshould be run into a proper drain.
Picture 3. Unbelievably the sub-con
has attached the AC drain pipe using
cable tie and wire. We can see that the
1
3
2
-
8/14/2019 PAT Picture Guide
31/58
8.11 AC Condenser Pipes.
(Poorly Insulated)
The correct insulation of AC pipe
work is very important and can affect
the life span and the running of the
unit. (see over page for correct insula-
tion)
Picture 1. Shows poorly insulated
pipe work. Notice (circled) that the
unit is not even bolted to the bracket.
Picture 2. Shows condensation
dripping from the pipe work. The unit
will have to work harder to keep the
room cold. The arrow points to a pipe
with just tape no foam insulation.
Picture 3. Shows the same as in pic-
tures 1 & 2 but also notice (arrowed)how the power cables have been runinto the unit. They must be put inside
conduit. Never accept
exposed cables.
1
2
-
8/14/2019 PAT Picture Guide
32/58
8.11 AC Condenser Pipes.
(Correct Insulation)
The picture on the right shows a
correctly insulated unit.
Notice that the pipe work is tightly
bound with foam insulation and ducttape.
The bottom valves have been covered
with a factory supplied cover.
Also of note is the green and yellow
cable (arrowed) which shows the unit
has been earthed.
9.1 Sun Shelter Layout.
( Brick Room Item 9.2 )Check over the drawing and seewhether what has been built on site
matches the drawings.
Picture 1. Shows a Sun Shelter site
where the roof has been built the
wrong way around The roof shouldprovide shelter when the IBBS door is
open. The Sub-con should be made to
turn this shelter around the right way.
Picture 2. Shows a typical sun shelter
built correctly.
Picture 3 Shows the engineer
1
SunShelter/BrickRoom
-
8/14/2019 PAT Picture Guide
33/58
9.2 Sun Shelter/ Brick
Room As Drawing.
Check the constructed brick room
layout against the drawings.
Picture 1. Shows that the Brick
Room has been built without stairsas shown in Picture 2. Why?
Their may be good reason for this
but it should still be noted. So it canbe followed up at an office level.
If there have been any changes to
design there must have been
previous approval to do so.
Also remember to amend the As
built drawings in REDpen to re-
flect this.
9.3 Roof Sheeting
Complete.
Check that the Sun Shelter roofing is
complete. This also includes lookingfor any holes that may have been
made in the roof sheet.
Picture 1. Shows a Sun Shelter with
its roof sheeting complete
Picture 2. Shows incomplete roof
sheeting. This is obvious because we
can still see the roof beam exposed(circled)
21
1
2
-
8/14/2019 PAT Picture Guide
34/58
9.4 Sun Shelter Is Rigid.Check that the Sun Shelter is rigid
(does not sway). The best way to do
this is by hand. If the Shelter is
swaying check the points shown in
the pictures on the right.
Picture 1. Shows a large gap under
the shelters fixing plate. Also notice
that the fixing bolt has not been put in
square. This will stop it from being
tightened to its maximum strength.
Picture 2. Shows 4 areas that should
also be checked.
Are the bolts tight?
Are there any missing bolts?
Are there any missing parts?
Is the bracing correct and tight?
9.5 Paint Finish Is To
Good Standard.
Check over the entire Sun Shelter.
Take you time to note the quality ofthe paint work. The pictures here
show acceptable workmanship with
some minor exceptions. We can see
paint splatter on the landlords roof in
Picture 2. and minor rust showing
through on Picture 3.
CHECK:
Are there any signs of rust ?
Can you see through the paint to the
b l i ?
1 2
-
8/14/2019 PAT Picture Guide
35/58
9.6 Lighting and Electrical.
( IP rating correct )
IP Rating is a system (standard) of
measurement that explains how pro-
tected an electrical item is against an
external environment ( see IP Ratings
Data sheet in the back pages of thisbook ).
The external light fitting of the
projects outdoor sites must have a
minimum IP Rating of IP54. Usingthe IP table we can see that the first
digit relates to dirt and dust and the
second digit relates to water.
We can see that IP 54 means protec-
tion against dust up to 1mm in size
and water that might be splashed on
the electrical item from any direction.
If we look at the differences betweenPictures 1 & 2. it is obvious that pic-
ture 2 is the one not protected against
water & dust.
9.7 Breaker Location.
Check the ACDP and breaker locationagainst the drawing making sure it is
in the correct place.
Note down any differences on the As
Built Drawing and on the deficiencylist
Whilst there check if the breaker is in
the on position and correctly labeled.
9.8 Grounding Bus BarCheck that the Bus Bar has been
installed correctly on the Sun Shelter.
2
1
-
8/14/2019 PAT Picture Guide
36/58
9.9 Brick Room Walls.Picture 1. Check around the Brick
Room taking time to note any damage
to the walls
Whilst you are looking you might try
to notice other problems such as thewarped guards door shown inPicture 2. This shows damagedcaused by a grounding installation
into an indoor site. Repair and paint is
the solution. The grounding installa-
tion is another deficiency in this pic-
9.11 Brick Room Roof
Drainage Pipes.
Picture 1. Shows the correct methodof fitting drain pipes.
Picture 2. Shows the damaged caused
by not having the correct drainage
installed. We can see that water hastravelled through the mortar and tothe outside of the building. Causing
cracking to the outside plaster and
water staining the paintwork.
9.10 Brick Room Int/ Ext
Paint Work.When checking Item 9.9 you should
also be looking at the paint finish ofthe site. The picture on the right
shows water damage which has been
caused by poor roof drainage. (See
Item 9.11. )This is an example of when 3 defi-ciencies need to be written down for
the same problem. Items 9.9, 9.10 &
9.11
9.12 Brick Room Lighting
& ElectricalIt is important to check that the right
electrical fittings have been installed
1 2
1 2
-
8/14/2019 PAT Picture Guide
37/58
10.1 Tower Height.
(as Approved Design)
Confirm that the tower built on site isthe correct type. The As Built
Drawings should have a description of
the tower and height. Check the site
file in the office and cross check the
two. If you do not have the site file
with you, phone to the office and ask.The picture on the right shows the
front page of the As Built drawing
showing the height and type of tower.
10.2 Tower Base Plate
(Non Shrink Grout)
Once the Tower has been built and
leveled there may be a small gap on
the underside of the fixing plates. Thisshould be filled with a non-shrink
grout (not sand cement)
The best product available is made by
a company called SIKA.
Picture 1. Shows a tower leg which
has been grouted neatly. We can see
care has been taken to keep the black
and the red paint separate.
Picture 2. Shows a tower leg beforegrouting. We can also see that theconcrete beam has not been painted
black.
Picture 3. Shows a climbing ladderfixing plate that has been neatly
grouted. It is also a good example of
fixing with the right bolts and good
paintwork.
10.3 Concrete Pedestal
Check the concrete pedestal against
the drawing and make sure it has been
1 2
3
10.0
Tower
-
8/14/2019 PAT Picture Guide
38/58
10.4 Climbing Ladder
Fixed to Concrete Beam.
Check to see that the correct M12fixing bolts have been used to
Secure the climbing ladder to the
concrete beam or pedestal. Many
sites over the project have had the
sub-con finish and leave site without
fixing down the climbing ladder.
Picture 1. Shows an obvious fault
with the entire fixing plate missing
from the climbing ladder.
Picture 2. Shows another example
of a climbing ladder incorrectly
fixed.
We can see that the bolts are too
small and one has actually beenentirely sheared off.
Picture 3. Shows the correct
method of fixing
10.5 Work Rest Platform.Picture 1. Shows an unsupported
work rest platform. There should bean angle bar fitted
(where line has been drawn)to
receive the clip. The clip shown in
this picture is actually doing noth-ing .
Picture 2.Shows a clip fixed the
wrong way around. The top piece
should be fitted underneath.
10.6 Cable Ladder.
(As Per Drawing)Check the cable ladder against the
drawings
1
2 3
ANGLE
BAR
HER
E
1 2
-
8/14/2019 PAT Picture Guide
39/58
10.7 Cable Bridge, Legs
& Footings.
The cable bridge carries the cablework from the BTS equipment to the
tower.
Picture 1. Shows a cable bridge that
has been poorly constructed (circled)
We can see that it has started to bendat the joint.
Picture 2. Shows (unbelievably) a
cable bridge that has been attached
to a climbing ladder with wood andwire.
Picture 3. Shows an unfinished
cable bridge.
It should be built so that it fixes onto
the tower.
Picture 4. Shows a good example ofa cable bridge. Notice that it is well
painted and grounded and has a bond
strap attached at the joint.
10.8 Torque Wrench Test.The torque wrench test is very
important. A random selection ofapprox 15 bolts should be tested
over the tower. Make sure the test
includes all sides .If any bolts failthe sub-con should be made totighten all bolts on the tower.
Pictures 1,2 &3. Show examples
of the torque wrench and the engi-
neers checking bolts.Picture 4. Shows the table of meas-
urements. With grade 8.8 circled.
1 2
3 4
1 2
-
8/14/2019 PAT Picture Guide
40/58
10.9 Tower Missing Nuts
& Bolts.
Missing nuts and bolts could appearanywhere on the tower. The only
way to make sure they are found is
to be very careful to check each
fixing point . You can be sure that
there is at least one missing nut or
bolt on every towerPictures 1 & 2. Show examples of
where missing nuts and bolts might
be located.
10.11 Verticality Test.The verticality test is done using a
theodolite. The tolerances arecalculated using a simple equation
with the maximum tolerance
allowable of 1 in 400. If we use a
15 meter tower as an example thecalculation would be as follows.
1/400 x 1500cm = 3.75cm . This
means that the tower should not
lean any further than 3.75cm over
its entire height.
Picture 1. Shows a theodoliteInstrument.
Picture 2. Shows an engineer with
a theodolite set up ready to test.
10.10 Bolts Grade 8.8.The standard of strength for tower
bolts is grade 8.8. It should be
clearly stamped on all bolt heads.
Picture 1. Shows a bolt head
stamped with 8.8 on the bottom.
Picture 2. Shows a bad bolt. This isnot the correct grade and is not evengalvanized which is why it has
started to rust.
1 2
1 2
2
-
8/14/2019 PAT Picture Guide
41/58
10.12 Lightning Arrester.The lightning arrester (rod ) is likely
to be the first point of contact during a
strike. It is important to check that itis secure and well installed.
Picture 1. Shows the fixing plate thathas been well secured.
Picture 2. Shows a lightning arrester
that has not been fully painted.
Remember to look up.
10.13 Top & Bottom
Bus Bar.
Picture 1. Shows an example of a
good tower Bus Bar installation.
Picture 2. Shows cable work neatly
attached to the bottom Bus Bar. It isimportant to check by hand that the
cable lug bolts are tight.
10.14 Fitting Of Tower
Member Joints.Gaps in tower member joints canaffect the towers strength and over
time could lead to serious problems.
The engineer should use Items 10.8,
10.9, and 10.14 to gain a complete
idea of whether the tower has been
well constructed.
Picture 1. Shows a gap that could be
fixed by tightening the bolt further.
Picture 2. Shows an even moreSevere gap. The paint on the insidethread of the bolt (circled) tells us that
the gap has been there for a long time.
Well before the sub-con painted the
tower.
1 2
1 2
1 2
-
8/14/2019 PAT Picture Guide
42/58
10.15 Elcometer Test
Paint Work Quality.
The towers paint thickness shouldbe tested using an elcometer. With-
out this procedure being completed
a pass cannot be marked down on the
PAT sheet. Check the whole tower
and note any faults on the Def list
Pictures 1 & 2. Show paintwork that
is too thin. When checking the tower
the easiest way to see if paint is thick
enough is to look at the white partsof the tower. Notice also in picture 1the poor line between red and white.
Picture 3. Shows the member sup-
porting the work rest platform has
not been painted properly. (arrowed)
Picture 4. Shows careless
workmanship. The cables will needto be cleaned on this site.
10.16 Check Antenna
MountsPictures 1 & 2. Show two common
problems with the antennas and
mounting brackets. Picture 1 shows
a bolt left loose( circled ) andpicture 2 shows a jumper lead that
has not been tied away properly.
The jumper lead is likely to comeloose over time through exposure to
high winds.
10.17 Concrete Beam
Painted Black
Check to see if the concrete beamsfor rooftop and the concrete foot-
ings for Greenfield sites have had
two coats of black paint to seal the
concrete. Sun Shelter and cablebridge footings should also be
i d
1 2
3 4
1 2
-
8/14/2019 PAT Picture Guide
43/58
11.2 Mains Conduit.The Mains conduit carries a high
voltage cable and therefore must be
secured , marked and protectedaccordingly. Damage to the mains
conduit could result in death. Theconduit must be painted grey toshow that it is different from waterpipes which are blue.
Picture 1. Shows very poor method
of bringing mains EDC power to
site. The cable is not protected andhas been strung up in a temporary
manner over re-barred columns.
What happens to site power if the
landlord decides to add another
story?
Picture 2. Shows an unsealed end ofconduit. It should be sealed with
silicone or rubber compound.
Pictures 3 & 4. Shows poor methods
of fixing conduit. In picture 3 the
sub-con has even used wire. Inset in
picture 1 is a drawing of the correct
clamping method.
1
2 3 4
Picture 5. Shows a mains conduit
that has been cracked before it has
been painted grey. The sub-con
t thi b k ti
11.0
Elecrical
-
8/14/2019 PAT Picture Guide
44/58
11.3 Ceramic Spool Rack
Installed
Picture 1. Shows the constructionissue drawing explaining the use of
the ceramic spool rack and how the
EDC cable should be attached to
the steel wire (catenary). We also
see other details that relate to Items
11.4 & 11.5 on the same drawing.
Pictures 2 & 3. Show the need for
a ceramic spool rack and catenary.
In picture 1 we see that the sub-conneeded to use 2 clips just to holdthe conduit in place due to the
weight of the EDC cable. Picture 2
shows another poor example of a
sub-con just tying the cable to the
balcony railings using old cable.
Both these examples areunacceptable and are both major
deficiencies.
11.4 & 11.5 Catenary &
Clamps.
The cable used to bring the EDCmains power to site is not steel
reinforced so therefore it is not
designed to hold its own weight. In
the hot Cambodian sun it is likely
that the cable will stretch, which isunacceptable. To stop this fromhappening the cable should be sup-
ported by a steel cable (catenary) asshown in the drawing above.
Picture 1. Shows another poor
example of cable work. The cable
has been tied to some re-bar on site
and no care has been taken to
fix the conduit. The correct way is
the way shown on the drawing Eve-
1
32
1
Grey
-
8/14/2019 PAT Picture Guide
45/58
11.6 EDC Glanded Into
ACDP & Other Panels.
Probably one of the most importantitems on the electrical PAT list ( as
explained in Item 11.2) The phase 3
power which enters the site does so
at around 415v, so it is important
that it is supported when entering the
ACDP Panel by a stuffing gland.
Picture 1. Shows the red, yellow,
blue and black phase 3 cables
exposed.
Picture 2. Shows the entire gland
plate missing from underneath of the
ACDP Panel.
Picture 3. Shows a stuffing gland
before it has been fitted into a panel.
Picture 4. Shows a fine example ofgood cable work. The use of glands
on this site also seals the panel from
insects and dust.
11.7 Electrical FittingsIt is important to check the function
and the quality of the electrical
fittings.
-Are the fittings new?
-Are they well attached to the wall?-Do they match the fittings
specified in the site drawings?
-Do they work?
Picture 1. Shows a poor example of
a light installation. Notice that theconduit runs through the electricaltrunking.
Picture 2. Shows the engineer
physically checking the socket face.
This should be done on all sites.
1
4
2
3
1 2
-
8/14/2019 PAT Picture Guide
46/58
11.10 Cable Work ID.Check that wherever possible thecables have been labeled. This will
help the maintenance team in thefuture understand the site better.
Picture 1. Shows cables correctlylabeled from the DG ATS .
Picture 2. Shows the breakers inthe ACDP panel being correctlylabeled.
11 11 Wiring Schematic
11.8 External (outdoor)Fittings Are IP Rated.(See also Item 9.6)Sun Shelter sites in Cambodia aresubject to extreme weatherconditions and it is important that all
outdoor fittings be IP rated
(see Picture 1).The Indoor fitting shown in Picture
2 is not acceptable.See the IP rating guide in this docu-ment for help.
11.9 Cables In Panels.
Picture 1. Shows us 2 types of cableterminations. The black one on theleft has been correctly lugged.
Where as the cable on the right hasnot and has excess copper shownabove the bar.
Picture 2. Shows an earth bar whichhas had too many earth lugs attached
to it. The rule is 1 cable per terminal
1 2
1 2
1 2
-
8/14/2019 PAT Picture Guide
47/58
11.12 SPD Fitted.SPD stands for Surge ProtectionDevice. It protects the equipment
from any power surges that mayhappen using EDC power. It is notnormally fitted on 1+1generatorsites.
The Pictures show examples ofSPDs fitted on site.
11.14 Earth Bar In Panel.
Pictures 1. Shows the earth bar in
the panel not connected. (arrowed)
Picture 2. Shows what the
connection should look like. Theearth cable should be green and
yellow as shown in the picture(arrowed).
11 15 Circuit Breakers
11.13 DG Socket Fitted.
Non generator sites should have aDG socket fitted to the ACDP panel
so that a temporary generator supplycould be connected to Site in theevent of power failure.
Pictures 1 & 2. Show an example ofa DG Socket fitted to an ACDPpanel.
1 2
1 2
-
8/14/2019 PAT Picture Guide
48/58
12.1 Energize Panel.On most sites the power may alreadybe on by the time you come to site todo PAT. If it is not on ask the sub-
con to energize the panel.
The picture on the right shows thesub-con energizing the main breaker.The reason we ask the sub-con toenergize the panel is because heinstalled it and would know if the
panel is ready to be turned on.
14.1 Ground Rods.( As Per Drawing )
Lightning can travel at 220,000 kph
and can cause heat at the strikepoint of up to 30,000 DegreesCelsius. Lightning typically carries
an electrical current of 300 kA.With this in mind we can under-
stand that the grounding system of atower site is extremely important.of which the rods make up a largepart.
Picture 1. Shows a lightning strike
13.1 OB Light Test.The OB light is one of the most im-portant items on the tower. Thesub-con must prove to the PATengineer that the light is working. If
he cannot it is marked as a failed teston the Def List.Whilst checking the light pay
attention to how it has been fitted.Picture 2 shows that the OB lighthas not had all the bolts fitted on the
bracket.1 2
1 2
&
Lightning
13.0
OBLig
htTest
-
8/14/2019 PAT Picture Guide
49/58
14.2 Ground RodConnectionsThere are two type of ground rodconnections that are acceptable.They are shown in pictures 1 & 4.
The grounding strip or cable shouldnever be earth rod.
Picture 1. Shows an earth rod with a
strong 2 bolt connection. The earthpit should look like this.
Picture 2. Shows an earth pit wherethe connections are so poor that wealmost cant see the earth rod.
(circled)
Picture 3. Shows another type of
connection. This is close to beingacceptable but must be connected thesame as in the drawing in picture 4.
Picture 4. Shows the correct way toconnect the grounding strip to theearth rod in picture 3.
14.3 Grounding Pits( As Per Drawing)
There are 2 types of acceptable
grounding as shown in pictures 1& 2.
Picture 1. Shows one type ofgrounding pit. Formed of concrete.
The concrete lid must have a handlebuilt into it.
Picture 2. Shows another type of
grounding pit with a screw topbrass lid. It is important to make the
21
3 4
1 2
-
8/14/2019 PAT Picture Guide
50/58
14.4 TEST:
Earth ResistanceThe earth resistance must meet a
maximum resistance of 5 ohms.Anything greater than this (figure) isa fail.
Picture 1. Shows a resistance meterbeing used by the engineer at PAT.
Circled is the reading of 1.49 ohmsthis is a pass.
Picture 2. Shows the test electrodein the ground. The two testelectrodes should be placed at least10 meters apart and outside the fence
perimeter on Greenfield sites.
Picture 3. Shows a drawing of atypical test set up.
14.5 Tower Bus Bar
Picture 1. Shows a typical drawingof the ground bar plate (Bus Bar).
Picture 2 . Shows cable workattached to the tower Bus Bar. ThePAT engineer should check that theBus Bar is secure, that all cables are
tightly fastened and that the BusBar is the correct type.
14 6 Equipment
3
21
21
-
8/14/2019 PAT Picture Guide
51/58
14.7 Tower Legs
GroundedPicture 1. Shows a typical drawing
of a tower leg connection. It explainsthe two hole connection and the sizeof the grounding strip 30x3mm.
Picture 2. Shows another acceptabletower leg connection. This is a steel
braided cable with a two hole lugconnection.
Picture 3. Shows a good example ofa rooftop tower connection. If welook at other parts of the picture wecan see good examples of other
things, like neat installation, no sharpbends and good paint work to the
concrete beam and other parts.
14.8 Sun Shelter SteelH Beam Grounded
The steel H beam on roof top sites
should be grounded in two placesonly. Its path should travel downonto the main earth ring not to the
Sun Shelter Bus Bar.Picture 1. Shows a poor example of
grounding the steel beam. It has hadtoo many connections made onto it.The connection plates are the wrongsize.Picture 2. Shows another poorexample. This sub-con has used the
1
2 3
2
-
8/14/2019 PAT Picture Guide
52/58
14.9 Sun Shelter
GroundedThe Sun Shelter should be grounded
in much the same way as the steel H
beam. The connection should bemade using two bolts. It should be
separate to all other fixings and itspath should travel down to the mainground ring not to the Sun Shelter
Bus Bar.
Picture 1. Shows a poor connection
made by fixing the ground strip tothe sun shelter leg.
Picture 2. Shows an almost correct
connection but the fixing bolts arenot 100mm apart and the connection
plate is too small.
Picture 3. Shows a good connection.We can see that the bolts are fixed
100mm apart and the rest of thegrounding system is neatly installed.
14.10 Climb LadderGrounded
Check to see that the climb ladder
has been correctly connected to thegrounding system.
Picture 1. Shows a goodconnection to the climbing ladder
but is unacceptable for otherreasons. We can see that the cablehas been bedded into the concretepedestal. Also the climbing ladder
has not yet been fixed and the con-crete has not yet been painted black.
21
3
21
-
8/14/2019 PAT Picture Guide
53/58
14.10 Cable Bridge
Support GroundedThe cable bridge support legs should
be grounded in at least 2 places..Picture 1. Shows a good example ofa rooftop leg connection with the 2
bolts spaced 100mm apart.
Picture 2. Shows a good Greenfield
leg connection. Notice that the sub-con has painted the concrete footingthe wrong colour. It should be black
not white.
Picture 3. Shows a poor connection.We can see that the fixing point has
the bolts too close together. Also wecan see other problems such as the
support has only 1 leg and there isdamage to the landlords roof.
Picture 4. Shows a very poor choice
of connection by the sub-con. Thisentire connection will have to beremoved and redone.
14.11 Fence GroundedThe fence around the perimeter of aGreenfield site should be groundedin 6 places. Once in each corner andonce on each of the gate posts.
Picture 1. Shows a typical fencelayout for a Greenfield site. Thegrounding points have been circled
to show where to find theconnections.
Picture 2. Shows an incorrectconnection. It should have a two
bolt lug and we can see that it is
21
21
3 4
-
8/14/2019 PAT Picture Guide
54/58
14.12 Cable Bridge Bond
Strap At Each Joint.To make sure that the cable bridge is
bonded properly it must have a bondstrap at each individual joint.
Pictures 1 & 2. Show good exam-ples of the correct way to bond acable bridge together. The connec-
tions are bolted and the cable has thecorrect lugs attached. The paint hasbeen scratched away to give a better
bond to the cable bridge. The onlything the sub-con could do betterhere is to re-paint the cable bridgeafter making the connection.Picture 3. Shows an unacceptablebond connection. Only the version
above is correct. Also notice that theconnection plates are wrong and thattoo many have been used in a shortdistance. If we look closely we can
see that there is actually no need forthe connection plate circled, to bethere at all.
14.13 Strip Fixed EveryMeter With Black Rubber
Spacer Washers.Due to the massive power of a
lightning strike it is important tomake sure the ground strip is fixedsecurely.
Picture 1. Shows a correct connec-tion. The strip is fixed using an M8bolt tightly fitted with a black rub-ber washer underneath.Picture 2. Shows an incorrect ver-sion of picture 1 The strip should
21
21
3
-
8/14/2019 PAT Picture Guide
55/58
14.15 GroundingConnection Plates.
Another means of connecting jointsis using connection plates. Thesemust be a minimum size of
150x150mm to allow for the100mm spaced bolts.
Picture 1. Shows that the sub-conhas used this method to get over amistake. There is simply no need
for this type of connection. It is afail and should be removed and
14.14 Ground Strip Joints
Have Correct OverlapA grounding installation should have
the minimum amount of connectionspossible.
Picture 1. Shows a good example ofan over lapped connection. The boltsare spaced neatly apart at 100mm
intervals.Picture 2. Shows a failed connec-tion. No welded joints are allowed.
We can see why as the joint hasalready begun to rust.Picture 3. Shows another failed con-nection. This time the bolts are too
close together. We can also seeunused fixing holes (circled) in the
strip.Picture 4. Shows another failed con-nection. This one fails because of thedifferent sizes of grounding strip
used. Also we can see the strip hasbeen fixed down incorrectly using ascrew instead of a bolt.
1 2
43
21
-
8/14/2019 PAT Picture Guide
56/58
14.16 Grounding Strip
Down Building.The grounding installation must be
fixed every meter and in the case ofrooftop sites that includes down theoutside of the building.Picture 1. Shows one method ofcontainment. Sometimes it is notpossible to fix down the side of the
building so the grounding strip is runinside PVC conduit.Picture 2. Shows a good example. It
also shows the correct overlap andhas been done neatly.Picture 3. Shows the grounding stripreaching the pit. This picture has
been shown to highlight the poormethod of connection.
Picture 4. Shows an unacceptableinstallation. The grounding strip hasjust been left hanging down the sideof the building. This is where the
method shown in picture 1 shouldbe used.
14.17 Other Metal Parts.Other metal parts can mean twothings. Are there any more metallicitems on site that should begrounded? Also, are there any metal
parts that have been connected tothe grounding system that shouldnthave been?
Picture 1. Shows an example of adangerous installation. In the event
of a lightning strike this wholemetal roof would become live.Picture 2. Shows a similar problem
as in picture 1 This time it is the
1
3 1
2
1 2
-
8/14/2019 PAT Picture Guide
57/58
14.18 No Sharp Bends
Any bends in the ground strip should
be smooth and round not flat. Checkall bends at PAT.
Picture 1. Shows a bend that is tooflat. This is a fail and will have to bere-done.
Picture 2. Shows a good example ofa nice smooth bend . We can also see
that it has been bolted correctlyusing M8 bolts and black rubberspacer washers.
Picture 3. Shows an example of avery bad flat bend. This could cause
the ground system to fail.
Picture 4. Show a good example ofa smooth bend. This is the ideal
installation.
1 2
3 4
15.0 Other Items Not
Shown On PAT List.Some deficiencies that occur on sitedo not actually have an Item numberon the PAT list. They are still defi-
ciencies and should be marked downaccordingly.Picture 1. Shows a window to the
guards room built on the outside wallof the compound. This is a securityrisk.Picture 2. Shows the solution to the
problem in picture 1. Security barsh b fi d Ch k h
1 2rItems
-
8/14/2019 PAT Picture Guide
58/58
RevisionA24/0
6/09
1.0 & 2.0 Records & Docouments