Installation The standard installation is summarized in this section.

Included herein is information on typical installation work flow and installation guide for IDU, ODU, antenna, waveguide installation and cable connection.

Firstly, please refer to the installation flow shown as right diagram

January 13, 2007 NEC Corporation 2007 2

Page 3: Pasolink V4 Installation and Initial Lineup Description

IDU Packing ListEach unpacked component of digital radio system must be checked.

For IDU, we can easily find some relative information from the top panel of IDU, such as:1. Required Power2. System capacity 3. Serial number4. Product date5. Warning6. Caution

January 13, 2007 NEC Corporation 2007 3

Page 4: Pasolink V4 Installation and Initial Lineup Description

ODU Packing List

January 13, 2007 NEC Corporation 2007 4

For ODU we also can easily read some important information such as:1.[ ]G equipment 2. Shift frequency 3. Sub-band4. High/Low 5. Chanel number 6. Frequency point7. Serial number 8. Product date

Page 5: Pasolink V4 Installation and Initial Lineup Description

Identify Different Type ODU

January 13, 2007 NEC Corporation 2007 5

1. 7/8 G ODU 2.Waveguide type ODU

3. Antenna direct mount type ODU(13-52G)

Main different

point

O-ring(attached to wave guide type ODU)

Page 6: Pasolink V4 Installation and Initial Lineup Description

Mounting Bracket Packing List

January 13, 2007 NEC Corporation 2007 6

1 2 3

4 5 No.12345 19'' Rack Mounting Type

DescriptionPole Mounting Coaxial Cable Type (7/ 8 GHz )

Pole Mounting WaveguideType Antenna Direct Pole Mounting Type

Wall Mounting Type

Page 7: Pasolink V4 Installation and Initial Lineup Description

Other Relative Assembly

January 13, 2007 NEC Corporation 2007 7

4

2

3

1

No.

1

2

3

4

7-8g HYB (x1) for 1+1, with N-type coaxial cable connector

13-38G HYB (x1) for 1+1

Desciption

7.5 A Fuse (SMP75) (x 2ea)

Power connector ( Molex Housing M5557-4R) (x lea)Cable termianl (Molex M5556-4T) (x 4ea)

Page 8: Pasolink V4 Installation and Initial Lineup Description

IDU MountingThe installation of procedure for (1+0)IDU mounting is as below:Step 1. Align the IDU to the mount position on the 19-inch rack.

January 13, 2007 NEC Corporation 2007 8

Step 2.Fix each side of IDU to the rack with two screws(M5).

Note*: Normal setting for free space. When free space closed within one rack unit, keep the environmental temperature less than +40C

Step 3.To mount IDU in 19-inch rack, allow space more than 200mm to the rear section and space for one unit to the top and bottom.

Page 9: Pasolink V4 Installation and Initial Lineup Description

IDU MountingThe installation of procedure for (1+1)IDU mounting is as below:Step 1. Align the IDU to the mount position on the 19-inch rack.

January 13, 2007 NEC Corporation 2007 9

Step 2.Fix each side of IDU to the rack with two screws(M5).

Step 3.To mount IDU in 19-inch rack, allow space more than 200mm to the rear section and space for one unit to the top and bottom.

Note*: Normal setting for free space. When free space closed within one rack unit, keep the environmental temperature less than +40C

Page 10: Pasolink V4 Installation and Initial Lineup Description

ODU MountingThere are three types of mounting for the ODU: Pole mounting, wall mounting and 19-inch rack mounting types. The tools for installation are listed in

below Table 1-1.

January 13, 2007 NEC Corporation 2007 10

Electric drill *

ToolsTorque wrench or Monkey wrench

ScrewdriverTape measure*Center punch*

Hammer*

Table 1-1

Caution: How to use small and large O-rings are shown in the following Table1-2.Two(small and large) O-rings are attached in 18-38G Hz band Andre/RFS direct mount antenna. 13/15G band antenna does not have small O-ring(small O-ring is not used for Andrew/RFS direct mount antenna). If the small O-ring is used for ODU direct mount installation, a gap may occur between ODU and antenna for RF interface. This may cause transmit or receive level down.

Page 11: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 11

ANT-------WG/ ODU (18--38GHz BAND)Not used Used

Used Not usedAntenna direct mounting

Waveguide connection

O-RINGSMALL SIZE LARGE SIZE

REMARKSO-Ring OF ATTACHMENT OF ANTENNA

ANT-------ODU

Note: 13/15GHz antenna for direct mount is not possible to connect the ordinary waveguide flanges.

Notes: 1.* Do not use both small O-ring and large O-ring simultaneously.2. Large O-ring size is different with frequency band as follows:

Page 12: Pasolink V4 Installation and Initial Lineup Description

ODU MountingFollowing we will introduce the procedure of pole mounting for different frequency band ODU respectively.1. 7/8 GHz ODU Mounting(Connecting Coaxial Cable)Step 1.Mount the bracket to the pole, point to the opposite station and tighten it with two U-bolts.

January 13, 2007 NEC Corporation 2007 12

Step 2.Mount the ODU on to the bracket and tighten four bolts(M6) at upper and lower parts of the ODU.

Note: The diameter of pole is from 48.5 to 114.5 millimeters.

Page 13: Pasolink V4 Installation and Initial Lineup Description

ODU MountingStep 3. Check that the ODU and the bracket are fixed firmly or not.

January 13, 2007 NEC Corporation 2007 13

Caution: Before connecting the IF cable

between the IDU and ODU, using the circuit tester,

check that the resistance of the IF cable between center conductor and

insulation is more than 100 M Ohm.

Step 4. Connect the Coaxial cable to the RF IN/OUT connector of the ODU. Down the cable fix bracket to fix the Coaxial cable, then tighten the two bolts.

Page 14: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 14

Step 6. Install the Coaxial cables between the antenna and ODU.

(When the wave guide flange is provided to the antenna port, fit the transducer with eight bolts)

Note: Fix the coaxial cable to the pole or member with cable hanger or cable ties after antenna orientation has been completed.

1+0 SystemCaution: Wrap the

coaxial cable connection points

with a self-bonding tape for waterproof.

Page 15: Pasolink V4 Installation and Initial Lineup Description

ODU MountingFor the 1+1 system connection steps similar with 1+0 system.

January 13, 2007 NEC Corporation 2007 15

Using HYB For 1+1 System

1+1 SD SystemNote: Antenna Separation (S)is given by path calculation depending on the system parameter.

Page 16: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 16

2.13-38 GHz Waveguide Connection Pole Mounting Bracket, AssemblingStep 1. Mount the attachment with adapter to the ODU bracket using ten bolts.

Step 2. Loosen eight nuts and remove the two U-bolts from the ODU bracket.

Step 3. Mount the ODU bracket to the pole with two U-bolts.

Page 17: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting3.13-38 GHz ODU Andrew(small/large) antenna direct mounting procedure:

January 13, 2007 NEC Corporation 2007 17

Large size antenna Small size antenna

Step 1. Install the bracket to the antenna pole.

Step 2. Mount antenna to the bracket.Note:1.Figure shows V

polarization 2.Be careful not to damage the O-ring(Antenna)

Page 18: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 18

Step 3. Fix the ODU to the bracket by tightening the M6 screws(four locations).

Step 4. Insert guide pin on the hole of bracket to set the position of screws.

Caution: Align flanges on antenna and ODU correctly, and fix the ODU with four screws.

Page 19: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 19

Step 5. Fix the ODU to the bracket with four screws.

Note: Antenna Separation (S)is given by path calculation depending on the system parameter.

Page 20: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 20

Step 6. For 13-38GHz 1+1 ODU direct mounting antenna system need install Hybrid additionally.

Step 6.1. Fix the bracket and handle to the HYB.

Page 21: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 21

Step 6.2. Check the polarization and fix the HYB to the antenna by tightening the M6(four locations).

Page 22: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 22

Step 6.3. Insert the O-ring to the two ODU ports of HYB.

Step 6.4. Fix the two ODUs with hex screws using the Allen key wrench.

Page 23: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 23

4.Waveguide connection for 1+1 HYB procedure:

Step 1. Assemble the bracket and handle to the HYB.

Page 24: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 24

Step 2. Assemble parts of the pole mounting bracket used to mount to the HYB.

Page 25: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 25

Step 3. Screw the Mount Arm and the Truss with the M6x25 Screw, Flat Washer(x2),Spring Washer(1),Nut, at four locations.

Page 26: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 26

Step 4. Determine centre off set.

Step 5. Fit the guide pin of HYB to the Guide Pin Hole of the Mount Arm.

Note: When either Main or Standby ODU is removed, attach the short plate over the ODU port.

Page 27: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 27

Step 6. Install the HYB onto the bracket with the M6x35 Screw, Flat Washer(x2), Nut(x2), at four positions.

Page 28: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 28

Step 7. Install the HYB to the mounting pole using the M12x200 Screw, Flat Washer, Nut.

Page 29: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 29

Step 8. Adjust direction of the bracket for Waveguide Port of the HYB orientation.

Step 9. Confirm the ODU Type, which is Master or Slave.

Page 30: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 30

Step 10. Install the ODU onto the HYB.

Note: The ODU should be attached by turning the plate marked “V” up position for both Main ODU and Standby ODU.

Page 31: Pasolink V4 Installation and Initial Lineup Description

ODU Mounting

January 13, 2007 NEC Corporation 2007 31

Step 11. Connect the flexible waveguide to the ODU and fix the waveguide to the ODU with four bolts.

Page 32: Pasolink V4 Installation and Initial Lineup Description

Polarization ChangeFor ODU direct mounting type antenna, can refer to the installation manual which is attached to the antenna.(Note: The antenna is

set to V-polarization when shipped from the factory)

As Andrew antenna is example the procedure of change polarization as:

January 13, 2007 NEC Corporation 2007 32

Step 1. Keep the antenna stand horizontally.

Step 2. If you change to H polarization, loosen the four screws with the Allen key wrench and then rotate the Transition hub of feed, keeping the antenna stand horizontal.

Page 33: Pasolink V4 Installation and Initial Lineup Description

Polarization Change

January 13, 2007 NEC Corporation 2007 33

Step 3. Holding the feed with hand, rotate the feed 90 degrees.

Step 4. Check that the aperture part of the Transition hub is rotated by 90 degrees, then fix it with the screws that were loosened in step 1.

Note: When a large and small gasket are included in the antenna package. Please us the large one(The small gasket is not used in antenna mount).

Above procedures descript >1.2M diameter antenna, following will give you brief introduction for small size Andrew antenna how to change the polarization.

Page 34: Pasolink V4 Installation and Initial Lineup Description

Polarization Change

January 13, 2007 NEC Corporation 2007 34

Step 1. Keep the antenna stand horizontally.

Step 2. Loosen six screws with Allen wrench until transition can rotate freely.Note: Do not remove the screw complete from the screw hole. Because of the screw tight is applied, the strength to loosen screw is necessary.

Step 3. Rotate the transition hub 90 degrees until timing pin locates in timing concavity.

Step 4. Tighten six screws when transition hub is located.

Page 35: Pasolink V4 Installation and Initial Lineup Description

Polarization ChangeHybrid polarization change procedure:Step 1. If you change to H polarization, loosen two screws, rotate the Transition hub and put the HYB horizontally.

January 13, 2007 NEC Corporation 2007 35

Step 2. Check that aperture of the connection unit is rotated as shown below, then fix it with the two screws that were loosened in step 1.

Note: The hybrid is set to V-polarization as default.

Page 36: Pasolink V4 Installation and Initial Lineup Description

Polarization ChangeODU polarization change procedure:Step 1.When vertical polarization is required, rotate the ODU so as to go up the plate marked V.

January 13, 2007 NEC Corporation 2007 36

Step 2. When horizontal polarization is required, remove the guide pin fixed on the plate marked with V.

Step 3.Screw in the guide pin removed in Step 2 to the screw hole of the plate marked H.Step 4.Rotate the ODU so as go up the plate marked H.

Note: When the ODU is mounted on to NEC HYB, only V polarization is applied.

Page 37: Pasolink V4 Installation and Initial Lineup Description

Waveguide Connection

January 13, 2007 NEC Corporation 2007 37

1.The connection method of the waveguide type ODU is described in following procedures:Step 1. Mount a waveguide to the ODU, fix the waveguide to the ODU with 4 bolts.

Notes: 1. Use suitable flange adapter between ODU and waveguide depending on the waveguide type.

2. Connection of the waveguide is the same way as ODU is wall mounted or 19-inch mounted.

Page 38: Pasolink V4 Installation and Initial Lineup Description

Waveguide Connection

January 13, 2007 NEC Corporation 2007 38

2.The connection method of the antenna direct mounting type ODU is referred to the following procedures:Step 1. Mount the ODU bracket to the pole with two bolts.

Step 2.Mount the ODU to the ODU bracket with attached 4 bolts.

Page 39: Pasolink V4 Installation and Initial Lineup Description

Waveguide Connection

January 13, 2007 NEC Corporation 2007 39

Step 3.Make sure that the ODU and the ODU bracket are fixed at specified values.

Step 4.Mount the waveguide to the ODU with four bolts.

Page 40: Pasolink V4 Installation and Initial Lineup Description

Frame GroundingThere have very important point is that IDU and ODU frame grounding.Location:

January 13, 2007 NEC Corporation 2007 40

Page 41: Pasolink V4 Installation and Initial Lineup Description

Frame Grounding

January 13, 2007 NEC Corporation 2007 41

For outdoor frame grounding as right diagram:During the on-site installation, please find nearest grounding bus bar for ODU grounding.

Note: * NEC recommends that frame grounding of ODU should be connected to the earth line as NEC’s standard installation.

Page 42: Pasolink V4 Installation and Initial Lineup Description

Cable TerminationThis section we will describe the cable termination such as D-sub connector, IF connector of the L type, IF connector of

the straight type and Molex M5557-4R connector respectively.The necessary tools and materials are summarized in Table 2-2.

January 13, 2007 NEC Corporation 2007 42

Table 2-2 Tools and Material List

Page 43: Pasolink V4 Installation and Initial Lineup Description

Cable TerminationTerminating supervisory cables with D-sub connector making procedure:

January 13, 2007 NEC Corporation 2007 43

Step 1. Strip back the cable sheath, taking care not to damage the braided shield.

Step 2. Fold back the braided shield(do not separate the strands) and trim it as shown.

Step 3. Remove the insulation over a length of 4mm from the end of wire.

Step 4. Insert the cable into the socket contact.

Step 5. Cable should be fitted, so that insulation and bare wire are arranged.

Page 44: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 44

Step 6. Mount the socket contact using a hand crimping tool.

Step 7. Recheck that the wire position is as shown in Step 5 before crimping the contact (see illustration at right).

Page 45: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 45

Step 8. Wind the metallic shield tape on the braided shield.

Step 9. Set the cable into plug case, then fit the cable clamper and two screws.

Step 10. Referring to circle A, fix drain wire with screw.Step 11. Referring to circle B, insert each wire to the specified position, insert the socket contacts into the upper and low row positions while taking care that the socket contacts are inserted the right way round. Finally, fix the plug case with 2 screws.

Page 46: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 46

For D-sub connector pin assignment describe as following table:

CHANNEL NO. CH 8 CH 7 CH 6 CH 5 CH 4 CH 3 CH 2 CH 1

PIN NO. Pin 1 Pin 2 Pin 3 Pin 4 Pin 6 Pin 7 Pin 8 Pin 9 Pin 11 Pin 12 Pin 13 Pin 14 Pin 16 Pin 17 Pin 18 Pin 19

WIRE COLOR Red

Red-White Red-Black Pink

Pink-Blue

Pink-Green

Pink-Black Blue

Blue-Black Purple

Purple-White

Purple-Black

Green-Black

Green-White Yellow

Yellow-Black

Data Input

Data Input Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

CHANNEL NO. CH 8 CH 7 CH 6 CH 5 CH 4 CH 3 CH 2 CH 1

PIN NO. Pin 20 Pin 21 Pin 22 Pin 23 Pin 25 Pin 26 Pin 27 Pin 28 Pin 29 Pin 30 Pin 31 Pin 32 Pin 34 Pin 35 Pin 36 Pin 37

WIRE COLOR

Light-Blue

Light Blue-Blue

Light Blue-Green

Light Blue-Red Orange

Orange-Black

Orange-White Gray

Gray-Black

Gray-Green

Gray-Red Brown Black

Black-White

Light-Green White

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

IDU Traffic IN/OUT(CH1-CH8):

Page 47: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 47

CHANNEL NO. CH 16 CH 15 CH 14 CH 13 CH 12 CH 11 CH 10 CH 9

PIN NO. Pin 1 Pin 2 Pin 3 Pin 4 Pin 6 Pin 7 Pin 8 Pin 9 Pin 11 Pin 12 Pin 13 Pin 14 Pin 16 Pin 17 Pin 18 Pin 19

WIRE COLOR Red

Red-White

Red-Black Pink

Pink-Blue

Pink-Green

Pink-Black Blue

Blue-Black Purple

Purple-White

Purple-Black

Green-Black

Green-White Yellow

Yellow-Black

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

Data Input

CHANNEL NO. CH 16 CH 15 CH 14 CH 13 CH 12 CH 11 CH 10 CH 9

PIN NO. Pin 20 Pin 21 Pin 22 Pin 23 Pin 25 Pin 26 Pin 27 Pin 28 Pin 29 Pin 30 Pin 31 Pin 32 Pin 34 Pin 35 Pin 36 Pin 37

WIRE COLOR

Light-Blue

Light Blue-Blue

Light Blue-Green

Light Blue-Red Orange

Orange-Black

Orange-White Gray

Gray-Black

Gray-Green

Gray-Red Brown Black

Black-White

Light-Green White

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

Data Output

IDU Traffic IN/OUT(CH9-CH16):

Page 48: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 48

IF cables with L-type connector making procedure:Step 1. First fit the tying metal, washer and gasket on the cable.

Step 2. Strip back the cable sheath, taking care not to damage the braided shield, and fit the clamp.

Step 3. Fold back the braided shield(separating the strands of the braid) and trim it.

Step 4. Insert the ferrule.

Page 49: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 49

Step 5. Fit the bush.

Step 6. Cut the aluminum fail and inner insulator away along the bush and remain the inner conductor.

Step 7. Taper the edge of the center conductor using a file as shown in right circle.

Step 8. Cut the aluminum fail and inner insulator away along the bush and remain the inner conductor.

Page 50: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 50

Step 9. Insert the cable into the shell.

Step 10. Tighten tying metal with wrench point by wrench.

Page 51: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 51

IF cables with Straight type connector making procedure:Step 1. First fit the lock nut, washer and gasket on the cable.

Step 2. Strip back the cable sheath, taking care not to damage the braided shield, and fit the clamp A.

Step 3. Fold back the braided shield and trim it.Step 4. Cut away the insulation from the center conductor and fit the clamp B. Be sure not to cut or scratch the conductor while stripping the insulation.

Page 52: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 52

Step 5. Cut the center conductor. Taper the end of the center conductor using a file as shown in the circle.

Step 6. Mount the center contact onto the center conductor.Note: Insert the center contact into insulator(1.5mm)

Step 7. Mount the insulation onto the center contact.

Page 53: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 53

Step 8. Insert the cable into the connector shell.

Step 9. Tighten the lock nut.

Page 54: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 54

Step 1. Remove 3.0 to 3.5 mm of insulation.Power supply cables with Molex connector making procedure:

Step 2. Set the socket contact to the following position onto a hand crimping tool.

Page 55: Pasolink V4 Installation and Initial Lineup Description

Cable Termination

January 13, 2007 NEC Corporation 2007 55

Step 3. Squeeze the handle of the hand crimping tool, insert cable into socket contact.

Step 4. Cable should fit, so insulation and bare wire are arranged.

Step 5. Squeeze the handle of the hand crimping tool until ratchet is released.

Step 6. Insert socket contacts into the power connector till they lock.

Page 56: Pasolink V4 Installation and Initial Lineup Description

Cable and Terminal Connections

January 13, 2007 NEC Corporation 2007 56

Page 57: Pasolink V4 Installation and Initial Lineup Description

Cable and Terminal Connections

January 13, 2007 NEC Corporation 2007 57

Page 58: Pasolink V4 Installation and Initial Lineup Description

Waterproof ProtectionAfter cable connection, must be taken waterproof method in order to protect our equipment resist from raining.

January 13, 2007 NEC Corporation 2007 58

7/8 GHz (1+0) System 7/8 GHz (1+1) System

Page 59: Pasolink V4 Installation and Initial Lineup Description

Waterproof Protection

January 13, 2007 NEC Corporation 2007 59

Page 60: Pasolink V4 Installation and Initial Lineup Description

Initial Lineup

January 13, 2007 NEC Corporation 2007 60

1.Start-up:Step 1. Check that the LINE IN voltage is between +20V to +60V/-20V to -60V with the digital multimeter, before connecting the power connector to

the IDU.Note: The range of DC power input depends on system requirement.

Step 2. Turn on the POWER switch on the IDU.Note: For 1+1 system, when neither No.1 nor No.2 channel is working, first set the OPE SEL switch to the desired (No.1 or No2) position and power on the selected MD Unit or set the OPE SEL switch to neutral(Auto) position and power on both MD units. When either No.1 or No.2 channel is working, perform MAINTE ON condition with the LCT, set the OPR SEL No.1-No.2 switch on the IDU to the working channel side, then, turn on the power switch of the not working channel.

Step 3. Allow equipment to warm up for at least 30 minutes.

Page 61: Pasolink V4 Installation and Initial Lineup Description

Initial Lineup

January 13, 2007 NEC Corporation 2007 61

2.Shut-down:For 1+0 systemStep 1. Turn off the POWER switch on the front of the IDU.

For 1+1 systemStep 1. Perform the setting for MAINT ON condition with the LCT.Step 2. Set the OPR SEL No.1-No.2 switch to the channel position to be on-line.Step 3. Turn off the POWER switch on the channel of off-line.

Note: In 1+1 system, before turn off the POWER switch of No.1 or No.2 channel, perform MAINT ON condition with LCT.

3. Lineup Test:BER measurement cannot be performed on channels which are occupied with LAN signal, therefore change the setting from LAN to 2MB signal

transmission using LCT before the measurement. For BER test required tools as: 1) Digital Multimeter;2) Screwdriver;3) BER Tester;4) Personal Computer.The procedures for BER test between two sites are described for both (1+0) and (1+1) system as follows:

Step 1. Set up as following figure, at station A, the output signal from BER tester (SENDING UNIT),then the input signal mode to BER tester (RECEIVEING UNIT) at station B. Also, can loop up the station B using one BER tester to implement this test.

Page 62: Pasolink V4 Installation and Initial Lineup Description

Initial Lineup

January 13, 2007 NEC Corporation 2007 62

Lineup Test Setup (1+0) System

Page 63: Pasolink V4 Installation and Initial Lineup Description

Initial Lineup

January 13, 2007 NEC Corporation 2007 63

Lineup Test Setup (1+1) System

Page 64: Pasolink V4 Installation and Initial Lineup Description

Initial LineupStep 2. Meter reading of ODU, remove the cap from the RX LEV MON jack.

January 13, 2007 NEC Corporation 2007 64

Step 3. Connect an RF cable with F connectors (Male) to RX LEV MON jack. With the digital multimeter or OW/RX LEV Monitor unit, confirm that the meter indication is as described in table:

Page 65: Pasolink V4 Installation and Initial Lineup Description

Initial Lineup

January 13, 2007 NEC Corporation 2007 65

Step 4. Disconnect RF cable, the digital multimeter or OW/RX LEV MONITOR and reconnect the cap removed in step 2.Step 5. Connect the personal computer to the LA PORT of the IDU using an RS-232C cable.

Note: At the end of LCT operation log out from LCT menu by keying “99” and then exit from the communication software. In case if you have exit from the communication software without logging out from LCT, repeat connecting and disconnecting of the RS 232C cable once to reset.

Step 6.Turn on the power on the PC and press the “CTRL” and “D” keys at the same time

Page 66: Pasolink V4 Installation and Initial Lineup Description

Initial Lineup

January 13, 2007 NEC Corporation 2007 66

Step 7. Press “Enter” key.

Step 8. Press “0” key and “Enter” key.

Step 9. Following display appears.

Step 10. Press the “3” key and “Enter” key, the following appears.For 1+0 System

Page 67: Pasolink V4 Installation and Initial Lineup Description

Initial Lineup

January 13, 2007 NEC Corporation 2007 67

For 1+1 System

Step 11. Press the “1” key and “Enter” key, the following appears.For 1+0 System

For 1+1 System

Step 12. When the Pasolink is in normal working condition, results maybe appeared within the values shown in table:

Page 68: Pasolink V4 Installation and Initial Lineup Description

Initial Lineup

January 13, 2007 NEC Corporation 2007 68

Step 13. Press “99” key to exit.Step 14. Connect the OW/RX LEV MONITOR to the RX LEV MON jack on the ODU.Step 15. Connect headset to the EOW jack on the front panel of the IDU and/or to EOW jack on the OW/RX LEV MONITOR.

Step 16. Press the CALL button switch on the front panel of the IDU, at opposite site, the buzzer on the IDU is activated.Step 17. Check that order wire telephone between sites can be connected by using headsets.

Page 69: Pasolink V4 Installation and Initial Lineup Description

Initial Lineup

January 13, 2007 NEC Corporation 2007 69

Step 18. Set OW switch on the OW/RX LEV MONITOR to ON (OW indicator on the OW/RX LEV MONITOR is turned on).Step 19. Check that order wire telephone between sites can be connected by using headsets.Step 20. Set OW switch on the OW/RX LEV MONITOR to OFF (OW indicator on the OW/RX LEV MONITOR is turned off).Step 21. Disconnect headset from EOW jack on the front panel of the IDU, and/or from EOW jack on the OW/RX LEV MONITOR.Step 22. Disconnect the OW/RX LEV MONITOR from the RX LEV MON jack on the ODU.

Page 70: Pasolink V4 Installation and Initial Lineup Description

January 13, 2007NEC Corporation 2007 70