Partnership to Advance Clean Energy-Deployment
(PACE-D)
Technical Assistance Program
PACE-D TA Action Plan for the State of Karnataka
April 28, 2014
2
1. Karnataka’s developmental and climate change challenges and the role of
clean energy interventions
2. Gap analysis for clean energy deployment (policy, regulatory, institutional and
programmatic)
3. PACE-D TA Program’s role in accelerating clean energy deployment
4. Matrix of policy, regulatory, programmatic and institutional initiatives and
interventions for clean energy development and deployment
5. Proposed technical assistance activities under the PACE-D TA Program
Presentation Overview
KARNATAKA’S DEVELOPMENTAL CHALLENGES
&
THE ROLE OF CLEAN ENERGY INTERVENTIONS
3
4
Karnataka is a vibrant state but is currently faced
with a number of demographic & economic challenges
Total Population:
61.1 million
57.04 % of population
located in rural areas
319/ sq. km population
density
Per capita income
2011-12: Rs 69493 /
year (Lowest among
the southern States in
India)
Peak electricity
requirement 2012-13
10,124 MW
(Peak met : 8761 MW)
Peak Deficit: 13.5%
Total no. of districts 30
4 revenue divisions, 49
subdivisions, 176 talukas
and 747 revenue circles
Geographical
spread
(190,498 sq. km)
Source: Census 2011, CEA, PIB, Discom ARRs, dept of Agri,Ktka
Gross Cropped area
130.62 L ha
Only 32.7% irrigated
Total GDP: 522,650
Rs. Crore (FY13)
Agriculture contributes
just 17% of state GDP
.
Installed thermal /Hydro
capacity: 25.5%/33%
Installed renewable
capacity: 35.5%
Total number of rural
households 7,864,196
13%
of all households do
not use electricity/ solar
as main source of
lighting
5
Energy Imperative
• Limited in-state fossil fuel resource availability.
• Significant Hydro capacity in the energy mix (~33%)
• Peak demand of 10124 MW in FY 2012-13
• Peak demand expected to be 18403 MW in FY 2021-22 and Peak demand deficit of to continue for next 5 years*
• Increased dependence on short-term power purchases by ESCOMS (~19% for FY 13). Cost is 30-35% higher than Avg. power purchase cost.
• RE potential > 18800 MW (excl. Solar) & installed capacity > 4300 MW
• EE potential in the state is 7900 Mn Units (2009) and the realized potential is negligible
Priorities
• Energy Access
• Demand Supply Gap
Reduction
• Reducing dependence on
short term power purchase
• Energy Security
• Stimulating investments
• Balanced growth of all
types of RE sources
Development Challenges
• Issues related to Coal linkage & environmental restrictions hinder further Thermal and Hydro capacity addition in the State.
• High population growth rate, Projected growth rate (2011-21) 15.60 % over decade
• Per capita electricity consumption low in comparison to other high-growth States in the country (925 kWh)
• High proportion of Agri. Consumption (~20 Lakh IP sets and nearly 30% of total electricity consumption in 2012)
• Due to significant shortages, the supply availability is constrained in rural/semi-urban areas
The energy scenario contributes to state’
challenges- which can be addressed through clean energy
development
The state envisions
energy access for all
& to provide 24x7
power supply by 2020
and to be self reliant
ANALYSIS OF CLEAN ENERGY DEVELOPMENT INITIATIVES AND
GAPS IN KARNATAKA
6
7
Karnataka :
Clean Energy Vision for the State
State Energy Department Vision
To provide 24 HRS power supply to ALL by the year 2020
Committed to make Karnataka self reliant
Improving efficiency of electricity companies
Encouraging development of renewable energy
Implementing energy conservation measures.
KREDL Vision
To harness green and clean renewable energy
sources in the state for environment benefits and
energy security. To initiate energy efficiency
measures in all sectors for sustainable growth.
8
There is a already an institutional structure in place
in Karnataka for clean energy deployment in the state
Karnataka
Electricity
Regulatory
Commission(State
Electricity
Regulatory
Commission)
Government of Karnataka (Policy, Planning, Budget)
Energy Department(Policy and Planning)
Karnataka
Renewable Energy
Corporation
Limited (KREDL)
KP
CL
(Gen
erat
ion)
KP
TC
L(T
ran
smis
sio
n)
BE
SC
OM
(Ban
gal
ore
)
Discoms
ME
SC
OM
(Man
gal
ore
)
HE
SC
OM
(Hu
bli
)
GE
SC
OM
(Gu
lbar
ga)
CE
SC
OM
(Ch
amu
nd
esh
war
i)
PCKL (Power Procurement)
INTERVENTION MEASURES
RE measures : policy, regulatory, program & institutional level
EE measures : policy, regulatory, program & institutional level
GAP ANALYSIS
Policy and regulatory gap analysis
Fund and resource requirement analysis
Institutional gap analysis and identification of priorities through consultation
AS-IS ANALYSIS
Analysis of RE /EE policies and ongoing programs
Review of target setting and business planning process
Organizational structure review and SWOT Analysis
9
To understand the makeup of the clean energy sector
in the state and identify the key gaps, the following approach was adopted
10
Policy
Regulation
Programmatic
Institutional
• Governed by Regulatory
framework specified by
KERC
• FiT, RPO, OA Rules and
REC regulations in place
• Grid connectivity
framework formulated
• Tariff related directives
issued for DSM
• KREDL
• KERC
• DISCOMS/PCKL
• ULBs/PWDs/Municipal
• Institutional
Coordination with
Central Institutions –
MoP, MNRE, BEE
• Comprehensive RE
policy (2009-14)
• Solar policy 2011
• Karnataka
Semiconductor Policy
• Directives for energy
efficiency
• KSECF
• Mandatory use
of Appliances
and equipment
(SWH, CFL, Ag
pump sets
• ECBC (draft)
• RE programs: Grid
connected RE
facilitation and
allocation- (~4070 MW)
• Successful solar bidding
for 200 MW of projects
• Focus on MNRE funded
programs- RVE, SWH,
Solar Agriculture Pump,
Solar Lantern
• EE programs –targeting
different consumer
categories in Bangalore
& 3 regional office.
Karnataka has already taken a number of
steps for developing the clean energy landscape in the state
11
ST
RE
NG
TH
SO
PP
OR
TU
NIT
IES
WE
AK
NE
SS
ES
TH
RE
AT
SA strong institutional
implementation framework at KREDL is required for
scaling up of RE and EE deployment
- Organization with around 17 years of experience;
- Experience of implementing RE & EE programs as SNA & SDA;
- Six technology specific divisions with division heads of requisite qualification
- Profitable Entity (Net profit of more than INR 140 million in 2012-13)
- Basic physical infrastructure in place
- Current organizational structure not amenable to
meet developmental objectives
- Lacks qualified/ experienced, committed &
motivated staff (long term continuity of resources
& visibility of career path)
- Inadequate knowledge management , systems,
processes & protocols
- Limited initiation of self sustaining and revenue
generating programs
- Lacks systematic capacity building and training
mechanisms
- Limited exposure to new markets/ ideas
- Huge untapped potential for RE and EE
- Develop business models for creation of new
markets for RE & EE technologies including
solar thermal applications.
- Develop sector specific EE plan
- Restructuring of organization to meet
development objective and sustaining
outcomes;
- Need to develop ecosystem for RE & EE
deployment through strategic partnerships.
- Partial or complete withdrawal of external
funding/subsidy support shall affect financial
stability of KREDL
- Issues related to potential environmental
clearance issues in the Western Ghats may
hinder RE capacity addition in the State;
- Potential evacuation bottleneck for renewable
energy projects
- Ability to mobilize funds to cater to
developmental goals of the organization
SWOT ANALYSIS
(KREDL)
12
ST
RE
NG
TH
SO
PP
OR
TU
NIT
IES
WE
AK
NE
SS
ES
TH
RE
AT
S
Similarly, a strong regulatory institutional
framework is critical for clean energy ecosystem development
- Fairly advanced regulatory framework for renewable energy
- Established infrastructure
- Experienced senior staff
- Proactive, dynamic leadership
- Pool of key staffs to handle RE issues Trainned through RE seminars frequenlty
- Longer control period for FIT
- No long term, progressive RPO trajectory;
- REC framework is not conducive for OA
transactions
- Regulatory framework for DSM in Karnataka yet to
evolve
- No dedicated cell for RE/DSM/EE activities
- Compliance monitoring & enforcement for CPP/OA
users to be put in place
- Opportunity to create competition in RE space
- Devising guidelines for net metering & enabling conducive framework for rooftop PV
- Opportunity to develop a regulatory framework for off-grid RE development
- Opportunity to develop a regulatory framework for DSM
- Managing increasing penetration of variable RE
generation
- Pending litigations for enabling competitive
framework
- Implementation challenges for RPO enforcement
for CPP/OA transactions.
- Striking balance between long-term goal and short
term cost implications due to RE/EE interventions
SWOT ANALYSIS (KERC)
13
Regulation
Programmatic
• Existing RE policy due
for expiry in FY 2014
• Off – Grid RE policy
• Comprehensive Energy
Security and Energy
Efficiency Policy
• Focus required for
nurturing ecosystem
(mfg., finance, R&D,
skill development)
• Long term action plan
for utilization of KSECF
• Competitive bidding
framework for RE in
Karnataka
• Net Metering
framework
• Regulatory framework
DSM
• Rules and regulations
for EE programs
(ECBC)
• Procedures and
Systems for program
management
• Solar thermal programs
for industrial and
commercial sectors
• Green fund - Non-
operational
• Subsidy driven
programs than market
driven ones
• High impact Sectors
specific EE programs
• Project management
cell (KREDL)
• DSM &RE cell (KERC)
• Ecosystem
development for RE/EE
sector through strategic
partnerships
• Developer database/
knowledge
management (KREDL)
• HR Policy for continued
motivation
• Skill sets to cater to
new roles of the
organization
KREDL, GOK
KERC, KREDL
KREDL
KERC
Policy
Institutional
However significant gaps still exist in the policy,
regulatory, programmatic & inst. framework for
clean energy development
ANALYSIS OF CLEAN ENERGY DEVELOPMENT OPTIONS AND
GAPS IN RAJASTHAN
14
CLEAN ENERGY OPTIONS, INTERVENTION OPPORTUNITIES AND NEXT STEPS
15
Clean Energy Priorities Energy
access
Demand
Supply gap
reduction
Reducing
dependence on
short term
power
Energy
security
Stimulate
investments
Balanced
growth of all
type RE
Utility scale RE generation √ √ √ √On site RE generation
(Large & Small
Institutional) √ √ √ √
Increase use of Solar
Energy for thermal
application√ √ √ √ √
Micro-grids (Off grid) √ √ √ √Small household based
systems √ √ √ √
Energy Efficiency (All
sectors) √ √ √ √
Accelerating RE and
EE deployment in Karnataka can help the state
meet its multiple challenges
16
Policy Regulation Institution ProgramFurther Scaling up/
Market Mode
Onsite Generation
• Solar Roof top policy
• Interconnection /net metering framework
• Gross metering framework
• Technical standards
• Building Bye laws
• Retail Tariff rebates
• Supply/Service Network
• Skilled Manpower
• Monitoring & Certification agencies
• Resource database/ Generation tracking
• Program Identification, design, development and deployment framework
• Institutional capacity building support for RE
• Market enablers (PPP, RESCO based business models)
• Solar City programs
• Fiscal Incentives
• Domestic SPV(1kW/5kW)/ lighting programs
• RESCO support program
• Govt/ Institutional Segment (Hospitals, Hotels, Edu. Inst.)
• Commercial Establishment
• Industrial Establishments
• Municipal (Streetlight & water pumping)
• Urban systems (commercial, domestic)
A number of opportunities exist for scaling up of
clean energy deployment one such opportunity
has been elaborated below as a sample
17
The state has a relatively high level of development of grid connected
renewable energy (predominantly Wind & Cogen) - however the state
needs to address the key challenges associated with:
1) Energy security & access; 2) Demand supply gap; 3) Reduction in dependence
of short term power 4) Balanced growth of all types of RE
Replicable,
Scalable &
Sustainable
Market &
Eco-system
Transformation
Accelerated
Deployment
Guiding Principles for Prioritisation Matrix
Framework for prioritization of intervention
options for clean energy deployment
18
Policy
• Inputs to finalize new Solar Policy & formulation of policy for promotion of decentralized solar rooftop and solar thermal applications
• Support for revision in comprehensive RE policy for next control period;
• Development of comprehensive energy security and energy efficiency policy;
• Support to design energy access through off-grid RE policy;
Institutional & Capacity Building
• Design and implementation of outcome focused organizational structure of KREDL;
• Support for design and roll-out of a competitive bidding framework for grid-interactive RE
• Support for design and development of high impact sector specific EE programs
• Support in program identification, design, development and deployment for solar thermal applications
• Support in design and roll-out of a capacity building program to build awareness of RE/EE amongst district level officials and representatives
Implementation Support
• Support for implementation of ECBC
• Support for implementation of new policies
• Support in creation and operationalization of “Green Fund” mechanism for State
• Support in development of inter-linkages with other State department programs for RE/EE deployment
Support proposed by
PACE-D TA Program to KREDL
19
Regulatory framework for
RE
• Assistance in formulation of Net-metering Framework
• Development of concept paper for competitive bidding in RE
Regulatory framework for
EE
• Demand Side Management Workshop
• Assistance in development of DSM regulations
• Assistance in development of guidelines such as Cost-Benefit Analysis (CBA) and Evaluation, Monitoring and Verification (E,V & V) of DSM Programs
• Assistance in development of action plan for implementation of Demand Response program in Karnataka
Organizational structuring &
capacity enhancement
• Development of Institutional structure for DSM related activities
Support proposed by
PACE-D TA Program for KERC
20
1. Finalisation of PACE-D TA Action Plan for the state of Karnataka
2. Constitution of counterpart teams for specific modules by KREDL
3. Meetings and consultation with KERC
4. Initiation of Technical Assistance activities
Next Steps
21
Thank You
For more information please access
www.pace-d.com
22
Back Up Slides
The peak demand in Karnataka at the end of tenth five year plan is 6253 MW. This
has increased to 10124 MW in FY 2012-13. However the state was able to meet
only 8761 MW during FY 2012-13 resulted in to the peak deficit of 1363 MW.
23
Source: CEA
In FY 2012-13 Karnataka was able to meet only 57044 MU however energy
requirement was 66274 MU.
24
Source: CEA
Projection of Energy Requirement and Peak Demand of Karnataka
25
Source: CEA
26
Karnataka depends significantly on Short
term Power sources
Short term power purchase costlier than average power purchase cost by 30-35%
Excessive Dependence on short term power procurement presents an opportunity for
adoption of DSM /Demand Response / EC measures and use of Energy efficient
technologies
Need to explore development of Pumped Storage/Energy Storage systems
3.8
4
4.2
4.4
4.6
4.8
5
5.2
0
2000
4000
6000
8000
10000
12000
FY-11 FY-12 FY-13
Av
g.
Ra
te f
or
Pu
rch
ase
(R
s./
kW
h)
Sh
ort
te
rm p
urc
ah
se (
MU
)Short-term energy purchased (MU) Average rate of purchase(Rs/kwh)
KPCL Thermal, 12914, 23%
KPCK Hydel, 9996, 17%
State Share of CGS, 11619,
20%
IPP Thermal, 6184, 11%
Renewables, 5425, 10%
Short term, 11046, 19%
Energy Mix by ESCOMS- 57184 MU (FY13)
Source: KERC website
State RE policy framework -Salient
Features
27
Renewable
Energy
Policy of
Karnataka,
2009-14
Renewable Energy Policy of Karnataka, 2009-14
Date of Issuance January 19, 2010
Target Installation4200 MW additional capacity with accumulative Renewable Energy capacity addition of 6600
MW by 2014.
Policy Mandate
Development, propagation and promotion of Renewable Energy sources and
Technologies.
Acceleration of identification, development and implementation of new Renewable
Energy projects.
Encourage the industries, in addition to sugar industry, with cogeneration potential to
set up co-gen plants expeditiously.
Provision of "single window" service for technical consultation, sources of finance and
project clearance.
DescriptionState
Potential
Installed
(till
Mar-09)
Target during
policy period
(2009-14)
Achieved during
policy period
(2009- Nov,13)
Cumulative
Achieved
*(till Nov-13)
Issues / Remarks
MW MW MW MW MW
Wind 13236 1368 2969 971 2339
Non commissioning of earlier alloted projects by developers whose
allocation got cancelled eventually; AD benefit removed by MNRE;
Longer control period with no tariff revision
SHP 3000 416 600 320 736 Environment & Forest Clearance issues in Western Ghats
Cogen 1500 535 281 591.55 1127 Mid-term correction of tariff Rs.3.59 per kWh to 3.90 per kWh;
Biomass 1000 81 300 9.5 91Low tariff deterring investors to develop biomass projects in
Karnataka
Waste to
Energy 135 0 50 0 0
No standard norms for tariff, tariff determined on project specific
basis; only limited project experience country-wide; local resistance
Total 18871 2400 4200 1892 4292
RE Source-wise Potential and Achievement - Karnataka
Source: KREDL website, RE Policy document
State RE policy framework -Salient
Features
28
Solar Energy Policy of Karnataka, 2011
Date of Issuance July 1, 2011
Target Installation 350 MW up to 2015-16
Policy Mandate Allocation of solar projects under state policy and national solar mission
200 MW capacities to be installed for procurement by Discoms through competitive
bidding.
Unlimited capacity through captive power plants and sale to third party
100 MW capacity under Renewable Energy Certificate Mechanism
50 MW maximum under Bundling Scheme
Target
achievement
Successful bidding of 80 MW of Solar (20 MW Solar thermal and 60 MW Solar PV
under Solar Policy 2011
Successful bidding of 130 MW of Solar PV in the State
Solar Policy
GOK is in the process of review of State Solar Policy
Solar
Achievement
(Nov-13)
10000
24
Potential
Installed
Solar Potential Vs Installed (MW)
Source: KREDL website
2004 2005 2006 2008 2009
2012 2013
Wheeling &
Banking
allowedFIT for RE
Standard
PPA for RE
Discussion
Paper-WTE
WTE
– FIT terms
Standard Agreement
(Wheeling & Banking)
FIT – Solar demo Project
APPC-FY12
APPC-FY13
Banking for
Solar
Wheeling & Banking
extension
APPC-FY14
FIT-Solar
FIT-wind
2010
FIT Solar
FIT for RE
(2nd Ctrl prd)
Green Tariff
- HT
Evolution of RE Regulatory
Framework in Karnataka
Source: KERC website
30
• Time of Day (ToD) has been made mandatory for all HT installations whose contract
demand is more than 500 kVA;
• Optional ToD tariff is also introduce for HT & LT consumers whose contract demand is
less than 500 kVA,
• For HT consumers, surcharge of Rs. 0.03/unit consumed will be levied for every
reduction in power factor by 0.01 below 0.90 lag,
• For LT consumers (Commercial), surcharge of Rs. 0.02/unit consumed will be levied
for every reduction in power factor by 0.01 below 0.85 lag,
• Directed distribution utilities in the state to conduct energy audit at the distribution
transformer level,
• Directed distribution utilities to adopt high voltage distribution system for agricultural
loads which results in the reduction of line losses and power theft,
• Installation of electronic timer switches for street lights, for switching on and off at
the required timings
• To adopt “Bachat Lamp Yojna” of Bureau of Energy Efficiency;
• To prepare time bound action plan for implementation of above mentioned DSM
programs;
DSM/EC related directives issued by KERC
Summary of RE Programs of KREDL
Programme Focus Mode
Wind resource monitoring
program
Solar Units at Nemmadi
Kendra
District Level Energy
Parks
GOK-Solar rooftop
Yogene
Other Solar Off-grid
programs
Resource
assessment
80% by C-WET and
20% by KREDL
Solar Power packs for IT Infrastructure in Govt.
Offices
50% Revenue Dept of State, 30% MNRE, 20%
KREDL
Energy Parks in
Engineering Collages
75% for Ist park in
district, 50% for 2nd
For captive domestic
consumption
50% subsidy -30%
MNRE-20% KREDL
SWH, Solar Pumps,
Solar Lanterns
CFA available from
MNRE
Apart from the mentioned programs, wind, solar and biomass program operational as per the policy
framework for these technologies
32
Most of the programs initiated targeting Municipal sector.
Agricultural sector offers highest energy saving potential. No specific programs initiated targeting Ag. sector.
Energy savings potential in domestic sector is 20% (1.24 BU). Belaku Yojna program is expected to save
around 0.15 BU. Need to develop domestic sector specific energy savings plan to tap this potential.
Energy savings potential in commercial sector is 20% (0.25 BU). KREDL is in the process of finalization of
ECBC. There is a need to initiate programs targeting existing buildings.
KREDL has initiated EE programs
amounting to capital outlay of >185 million rupees
Sector (No of
Programs) EE and EC Initiatives Fund Outlay
Agriculture No Program initiated -
Commercial (1) Training and Capacity building of ECBC 3 Lakh
Residential (2)
Belaku Yojana Scheme- Replacement of incandescent lamps with CFL 10 Crores
LED Village Campaign 13.78 Lakhs
Industrial (1) Workshop on Notified PAT scheme for DCs -
Municipal (21)
Energy audit programs in various govt buildings 1.15 Crores
LED lighting programs in various towns in the state 5.05 Crores
Energy Efficient pumps in various government hospitals 0.75 Crores
Awareness &
Outreach Promotional awareness 1.03 Crores
Source: KREDL Annual Report
• KREDL: Established in 1996 as SNA & mandated to perform role of SDA from 2004
• Vision: To harness green and clean renewable energy sources in the state for
environment benefits and energy security. To initiate energy efficiency measures in
all sectors for sustainable growth.
• Profit making organization with Net profit of INR 140 Mn (FY13) and reserves of
over INR 732 Mn (FY 13)
• Headquarter at Bangalore and 3 regional offices (Hubli, Mysore & Gulbarga)
• 8 Divisions, 6 Technology Divisions (Human resource strength of 63)
MD,
KREDL
Wind HydroBiomass
& CogenSolar Off Grid EE&DSM
Regional
Offices
Admin
KREDL- brief profile
33
34
RE/EE Policy: Needs
Sl. No. Policy Status/Requirement
1 Existing RE Policy 2009-
14
Due for expiry in FY 2014
Inaction may cause policy vacuum for RE technologies and EE
where no visibility of long term policy regime exist
2 Karnataka Solar Policy,
2011
Deals only with Utility scale Solar generation.
Policy level interference required for promotion of small scale &
distributed Solar generation in the State.
3 Off-Grid RE Policy Policy focus for promotion and proliferation of off-grid RE
technologies (other than Solar) is lacking
No Policy for onsite generation and consumption like net-
metering, rooftop installation etc.
Essential from the perspective of Energy Access in the State
4 Policy framework for EE No comprehensive policy framework for EE in the State –
Necessary to reduce reliance on short term power procurement
and for bridging growing demand supply gap.
5 Long term Integrated
Energy Policy
Required for ensuring energy access, energy security in the
State
35
Institutional : Needs (1/3)
Organization Structure review
Restructuring to meet development objectives and sustaining outcomes
Focus on ecosystem development, deployment mechanisms and shared services
Human Resource
Need for qualified/ experienced, committed & motivated staff
Lack of qualified/experienced manpower for management, administration & deployment of programs
Lack of continuity of permanent personnel at senior management cadre impacting commitment
Lack of incentives and career path impacting motivation
Comprehensive HR policy need to be put in place
Knowledge Management
Protocols & database for state-wide resource potential, sectoral GHG emissions,
RE installed capacity & generation, EE/EC measures, land banks, beneficiaries,
developers, manufacturers, R&D initiatives
36
Institutional: Needs (2/3)
Procedures and Systems
Procedures & Systems for Effective Operations
Management & Financial Controls
HR Policies & Practices
M&V and Impact Assessments
Communication Strategy and Systems for awareness and outreach
Capacity Building
Capacity Building to design, facilitate & contract, administer/monitor grid interactive and off-
grid projects for energy access
Exposure to external environment/best practices – domestic/international
Capacity Building & Training on aspects of technology, technical, regulatory, legal,
commercial, contracts, DPR preparation, financial modeling, database development &
management, communication & outreach, knowledge management systems/processes.
37
Institutional: Needs (3/3)
Ecosystem Development
Ecosystem development for RE/EE sector through strategic partnerships for R&D
promotion, skill development, communication & awareness creation
38
Policy Regulation Institution ProgramFurther Scaling up/ Market
Mode
Grid Connected RE • Transmission/ Evacuation Planning
• Project Allotment/Allotment Load/ Resource framework
•Review of Solar policy
• Long term RPO target/trajectory• Enforcement framework• Conducive Open access & pricing framework• Guidelines for Competitive Bidding framework;
•Rationalization of Biomass tariff
• Institutional capacity building for RE
•Inter-linkages with other State department programs for clearances and deployment
• Pilot/ Demo : Smart grids, Storage
•Roll out of Competitive bidding for Wind
• Grid Integration Framework
•Promotion of wind Open Access;
Onsite Generation (Large & small Inst.)
• Solar Roof top policy • Interconnection /net metering framework• Gross metering framework• Building Bye laws• Retail Tariff rebates
•Program Identification, design, development and deployment framework•Resources database/generation framework• Institutional capacity building
• Market enablers (PPP, RESCO based business models)• Solar City programs•Domestic SPV(1kW/5kW)lighting programs;•Fiscal Incentives;
• Govt/ Institutional Segment (Hospitals, Hotels, Edu Inst.)• Commercial Establishment• Industrial Establishments• Municipal (Streetlight & water pumping)•Urban systems (commercial, domestic)
Increase Use of SolarThermal Applications
• Solar Thermal (to be included in Solar Policy)
• Rebate and incentive measure
•Mandatory targets
•Program Identification, design, development and deployment framework
•Institutional capacity building
•Market assessment•Pilot/demo projects for different targeted categories;•Market enablers (RESCO, business models);•Awareness & Outreach programs
• Commercial (cooling, hot water & cooking)
•Industrial (cooling, hot water & cooking)
•Institutions (Solar cooking system)
•Cold storage chain
Multiple intervention opportunities exist for scaling
up of clean energy deployment – Part I
Wind
SHP
Biomass
Solar
39
Policy Regulation Institution ProgramFurther Scaling up/ Market
Mode
Micro Grids
• Off grid policy framework• Guidelines for rural micro grid development
• Technical Standards• Connectivity and pricing framework
Standard configurations for systems• Program Identification, design, development and deployment framework
• Business models for PPP• Agri pumpset program
• Rural local bodies/ Panchayats• Telecom
Household based systems
• Off grid policy framework • Retail Tariff rebates •Product financing support program• Program Identification, design, development and deployment framework• Akshay Urja Shop network
• Empanelment of suppliers/grading of suppliers• Standard procurement guidelines/ rate contracts• Product based commercial distribution models
• Microfinance & product based commercial distribution models• Outreach/ Awareness/ Publicity
Energy Efficiency
• Energy Security and EE Policy framework
• DSM regulation/ guidelines• ECBC rules/regulations•Feasibility of creation of green fund and its regulatory framework
• Cell/institutional structure/resources (Utility/ regulator/SNA)• M & V framework• Program Identification, design, development and deployment framework•Institutional strengthening for ECBC
• Local research/ High impact EE sector programs• Funding DSM/ EE programs options• Outreach awareness (ECBC/DSM)
• Domestic• Commercial• SME sector
Multiple intervention opportunities exist for scaling
up of clean energy deployment – Part II
2638
3523
3063
1869 1815
1401
0
500
1000
1500
2000
2500
3000
3500
4000
FY 2010-11 FY 2011-12 FY 2012-13
Total Revenue PAT
40
Other income
39%
Income from power generation
14%
Development facilitation fees
47%
Financial performance analysis of KREDL
Figs in INR Lakhs
Source: KREDL Annual Report for FY12-13
41
RE Potential and Achievement in
Karnataka (as on Nov 2013)
There is huge untapped RE potential in the State:
Also, there is need for balanced growth of all type of RE in the State
Excluding Solar, the State has a RE Potential of around 18700 MW
*Solar Potential considered as 10000 MW; Total excludes Solar potential and Achievement
Potential, 18736*
Installed Capacity*,
4292.5
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
Wind Small Hydro
Biomass Solar* Cogen Total
Cap
acit
y M
W
Source: KREDL
42
Observation
I. Significant reduction (~37%) in income from Infrastructure Development
facilitation fees from FY 12 to FY 13 Income from DPR processing fee for wind reduced from INR 120 Mn (FY12)to INR
33.5 Mn (FY13)
II. Significant increase (~76%) in operating expenses from FY 12 to FY 13 Contribution towards capital schemes (Nemmadi Kendra-INR 55 Mn) charged as a
revenue expense in FY 13
Financial Performance of KREDL
FY 2010-11 FY 2011-12 FY 2012-13
Total Revenue 263.8 352.3 306.3
Total Expense 71.6 88.3 155.9
Net Profit(After Tax) 186.9 181.5 140.1
0
50
100
150
200
250
300
350
400
Financial performance of KREDL ( all fig in INR Mn)
-13%34%
23%
77%
0 100 200 300 400
FY 2010-11
FY 2011-12
FY 2012-13
178.3
231.4
145.5
35.3
41.2
42.2
50.1
79.6
118.5
Revenue Components
Infrastructure development facilitation fees
Income from power generation
Other income
(INR Mn)
Source: KREDL Annual Report for FY 13, FY12, FY11
43
Finally the off grid RE space has started
to open up on the back of new ways
market development initiatives
Programs for Farmers
• Tamil Nadu: Plans to distribute 5 HP solar pumps in 2013-14
• 80% subsidy (MNRE, RashtriyaKrishi Vikas Yojana )
• Punjab: Plans to install 500 solar pumps in 2013-14
• 70% subsidy (MNRE, state)
• Priority to farmers opting for diverse crops e.g. sugarcane, cotton, maize, soybean, oilseeds, pulses
Market Mode for SPV Plants
• 10000 rooftop Project in Kerala
• Total capacity: 10 MW (1 kWpcapacity plant each)
• Bidding for supply of 1 kW solar systems (min bid Rs 1.77 L/kW) with 5 yr AMC
• Identification of beneficiaries completed and implementation of program started
• Gandhinagar rooftop PV Prog.
• 5 MW (1 MW private roofs and 4 MW govt. building roofs)
• Min Rs 3/kWh green incentive to roof owner
• Power off take by Torrent Power
Social Solar
• SunEdison’s pilot in Meerwaravillage (MP)
• 14 kW solar powered micro grid for 400 residents, 60 homes
• Local community volunteers to help manage and safeguard the power system, tracking payments, resolving issues
• Gramateller Indi: Low power consumption, Solar powered ATM
• Vortex engineering, an IIT Chennai incubated startup providing installation services for such ATMs in rural and semi urban India\
• Potential for 6 lakh such rural ATMs
44
Regulations / Tariff Orders (TO) for RE
FIT order for RE Technologies (Wind, Mini-
Hydel, Biomass, Bagasse)
Control period: 18.01. 05 – 31.12.09
FIT order for RE Technologies (Wind, Mini-
Hydel, Biomass, Bagasse)
Control period: 01.01. 05 – 31.12.14
Solar Energy TO dated July 13, 2010
Control period: 13.07.10 – 01.04.13
Solar Energy TO dated October 10, 2013
Control period: 01.04.13 – 31.03.18
Wind Energy TO dated October 10, 2013,
Control period: 10.10.13 – 10.10.18 ( 5 years
as mentioned in Order )
Wheeling and Banking charges Order dated
July 11, 2008
Control period: 11.07.08 – 10.07.13 (later
extended to 31.03.2014)
KERC(NCE)Regulations, 2004 dated 27
September, 2004
KERC (Power Procurement from Renewable
Sources by Distribution Licensee and
Renewable Energy Certificate Framework)
Regulations, 2011
FIT – RE FIT – RE – Case specific
Standard PPA approval
Standard Wheeling and Banking Agreement
Wheeling and Banking Charges Discussion Paper on RE issues
(WTE, Solar, Wheeling-Banking)
Green Energy Tariff for HT consumers
Dispute Resolution involving RE issues
RPO
REC
APPC
RE Pricing framework in Karnataka
45
KERC has not been revising and updating
the FiT regularly – leading to less capacity
addition and regulatory uncertainty
• Wide variation in capital costs across states in
2009 which started coming down after CERC
developed a FiT – states started benchmarking
their process to this process
• Earlier SERCs were dependent on cost data
furnished by the developers or cost details of
projects submitted to state nodal agencies/
IREDA
• Karnataka has the lowest capital cost than what
has been assumed by CERC, and other states.
• Its FiT is second lowest in compare to CERC,
RERC, MERC and GERC.)
Comparative analysis of Wind pricing across states
46
*(additional Solar RPO target of 0.25% during these years)
• Stagnant RPO targets since 2008-09. Progressive increment in RPO targets would be necessary to
provide impetus to RE industry
• Technology specific RPO targets would be useful for balanced growth of all types of RE sources
within State.
• Long term visibility of RPO trajectory beyond FY 2013-14 is necessary
• Lack of suo-moto regulatory initiative on RPO compliance monitoring and enforcement
• No RECs allowed on open access RE
ESCOMs
RPO
Target
(FY 09 to
FY13)
RPO target Achievement by ESCOMs
2008-09 2009-10 2010-11 2011-12* 2012-13*
BESCOM 10% 11.29% 11.96% 11.63% 10.37% 8.60%
GESCOM 7% 8.82% 9.94% 8.00% 10.97% 8.22%
HESCOM 7% 10.86% 10.27% 9.78% 8.43% 8.59%
MESCOM 10% 11.58% 11.49% 6.44% 14.34% 10.89%
CESC 10% 9.63% 9.21% 13.43% 12.09% 10.75%
RPO framework in Karnataka-
Implementation challenges
47
DSM Initiatives MERC DERC CSERC GERC KERC
Creation of DSM Cell in SERCs √ - - - -
Tariff related directives (ToD, PF etc.) to
promote DSM
√ √ √ √ √
Recovery of DSM related cost through
ARR
√ √ √ √ √
Directed distribution utilities to undertake
DSM related activities
√ √ √ - √
Directed distribution utilities for creation of
DSM cell
√ √ - - -
Development of state specific DSM
Regulations
√ √ - √ -
Capacity building/training/outreach and
awareness
√ - - - √
Comparative Analysis of DSM initiatives
by various SERCs
KERC is yet to develop state specific regulatory framework for large scale
deployment of DSM in the state of Karnataka
48
Approach for RPO Compliance Reporting Framework Development
Step 1 RPO
Reporting Cell
Step 2 Form /
Format DesignStep 3 Reporting
Framework Design
Step 4 Manual for
Obligated EntitiesStep 5 Development
of a Web ToolStep 6 Compliance
Reporting to RERC
Cell structure, role
and responsibilities
of members
Formats for RPO
compliance data
collection from OEs
Protocol for data
collection and M&V,
process for OE (CPP/OA)
accreditation, list of OE
and updating the OE list
RPO information
manual for OEsQuarterly reporting
to RERC
RPO Compliance Reporting Framework
TA support activities proposed for KREDL
49
Inputs to finalize new Solar Policy & formulation of policy for
promotion of decentralized solar rooftop and solar thermal applications
Task
Objective
Scope of
Work
Provide inputs in finalization of the draft solar policy of the State and
circulate draft Solar Policy
Provide comments on the draft Policy prepared in-house with specific
focus on promoting decentralized/distributed solar generation, solar
thermal applications and enabling business models thereof.
Review existing clauses in the draft solar policy of the State, (viz. targets,
Promotion routes- Grid & Off-grid, implementation mechanism, role &
responsibility of various agencies etc.)
Suggest additional clauses for promoting rooftop solar power installation
and off-grid solar installations
Deliverables Submission of comments on draft policy to KREDL for consideration of the
State Energy department thereof
Discussion with KREDL / Energy Department for finalization of policy
Activities for TA support – KREDL
TA support for revision in comprehensive RE policy for next Control Period
Task
Objective
Scope of
Work
Assist KREDL in development of Comprehensive RE policy in the State for the
new control Period
Comprehensive Review existing RE policy in the State
Review of capacity addition targets and achievements.
Analysis of key learning during the existing control period and latest
technological/market development to be incorporated in the new policy
Development of draft contours for comprehensive RE policy;
(objective, vision, title and enforcement, scope of policy, technologies covered, technology specific
potential & targets, finance aspects, roles and responsibilities of various stakeholders, nodal
agency, roadmap for the implementation, monitoring and verification framework etc., )
Activities for TA support – KREDL
Deliverables
Background/discussion paper on comprehensive RE policy;
Draft Comprehensive RE policy document;
Support in stakeholder consultation workshop to finalize Comprehensive RE policy
Development of Energy Security and EE Policy for Karnataka State
Task
Objective
Scope of
Work
Assist KREDL in development of Energy Security and EE policy for the state of
Karnataka
Review of legal and policy frameworks for EE in India and developments in
Karnataka;
Review of international EE policies and its frameworks;
Defining the need for state specific EE security & EE policy framework;
Development of draft contours for proposed EE Security & EE policy framework;
(vision and mission for long term development, objective and scope of the policy, sectors to be
covered, sector specific potential and targets, financing aspects, roles and responsibilities of
various stakeholders, fiscal & statutory intervention measures for EE deployment, roadmap for the
implementation and monitoring and verification framework etc., )
Activities for TA support – KREDL
Deliverables Background/discussion paper on comprehensive EE Security and EE policy;
Draft policy on Energy Security & EE
Support to design Energy Access through Off-Grid RE policy (for KREDL)
Task
Objective
Scope of
Work
Assist KREDL in development of off-grid RE policy for accelerated
deployment of distributed generation projects in Karnataka
Study of as is scenario of energy access and analyzing the scope existing for energy
access through off-grid networks in the State
Identifying respective requirements of rural (off-grid) and urban areas (stand alone
rooftops, etc.)
Analysis and selection of off grid RE technologies to be implemented.
Analysis on the funding schemes available, both state and central.
Undertake a detailed research on conversion of schemes from subsidy mode to
market mode.
Deliverables
Concept paper on off-grid RE policy;
Draft Off-grid policy document;
Support in stakeholder consultation workshop to finalize Off-grid RE policy
Activities for TA support – KREDL
54
Support for design & implementation of outcome focused organization
structure for KREDL
Task
Objective
Scope of
Work
Assistance in design & implementation of outcome focused organization structure
for KREDL
Review existing organization structure of KREDL
Highlighting the weak links in the present organization structure
Highlighting scope of possible improvements in the organization structure
Suggesting modification based on expected outcome or role to be played by KREDL
in promotion of growth of RE and EE in future
Suggesting modifications in order to strengthen the team structure and reviewing
responsibilities of technical and non-technical staffs in KREDL
Deliverables Revised Organization Structure for KREDL
Revised roles and responsibility chart for each level of staff
Facilitate rollout of the revised organizational structure
Activities for TA support – KREDL
Roll-out of a competitive bidding for grid-interactive RE (for KREDL)
Task
Objective
Scope of
Work
Assist KREDL for rollout of competitive bidding for RE in Karnataka
Analysis of guidelines of RE competitive bidding finalized for the State
Assistance in identification of RE technologies and specific capacity (with scope of
phasing) for competitive procurement
Assistance in preparation/vetting of bid documents
Assistance in bid process management
RFQ process
Pre-bid meeting and clarifications
Evaluation of bids
Selection of successful bidders
55
Deliverables Comments / Review of bid documents drafted by KREDL
Bid Process Management support
Activities for TA support – KREDL
56
Assistance in development of high impact sector specific EE programs
Task
Objective
Scope of
Work
Assist KREDL in development of energy savings plan to tap the energy savings
potential for high impact sectors (Commercial)
1. Data Collection
Desk research to collect information about commercial sector and consumption profile;
Data collection from ESCOMs & select commercial segments;
2. Data Analysis
Identification of energy consumption trend in commercial sector;
Development of baseline for commercial sector
Identification of potential energy savings measures;
3. Review of existing initiatives in Karnataka and national initiative in commercial
sectors
4. Development of Energy Savings Plans
Recommendation for implementation of EE programs;
Implementation plan for identified programs;
Possible options for sourcing of funds for identified EE programs
Deliverables Energy savings action plan document for commercial sector
Activities for TA support – KREDL
Support in Program Identification, design, development and deployment for
solar thermal applications (for KREDL)
Task
Objective
Scope of
Work
Assist KREDL in identification, design, development and deployment for
various programs for promoting solar thermal applications
Study of as is scenario/achievement of existing solar thermal programs in
the State
Identifying respective requirements of Industrial, Commercial, Domestic,
rural and urban solar thermal applications
Analysis and selection of solar thermal applications to be implemented.
Analysis on the funding schemes available, both state and central.
Program identification, design, development and deployment for solar
thermal applications
Deliverables Report on Identified programs, design-development-deployment
mechanism for solar thermal applications in the State
Activities for TA support – KREDL
58
Support in design and roll-out of a capacity building program to build
awareness of RE/EE amongst district level officials and representatives
Task
Objective
Scope of
Work
To support KREDL in capacity building program to build awareness of RE/EE
amongst district level officials and representatives to increase outreach of KREDL
Understanding the training requirements of district level officials and representatives
Identification of general & specific RE and EE areas in which capacity building is
required
Assistance in preparation of annual training chart focusing the following:
Suggesting topics of training to cover need, ways and means of promoting RE &
EE and significance of coordinated effort in RE & EE promotion
Suggesting districts from various parts of the State where training programs can
be conducted on a rolling basis such that participation of officials of all districts
in the State can be ensured
Frequency of conducting such training programs
Deliverables Draft Annual Training Calendar for capacity building of RE/EE amongst district level
officials and representatives
Facilitate implementation of the Annual Training Calendar
Activities for TA support – KREDL
59
Support in Institutional Strengthening for ECBC Implementation (KREDL)
Task
Objective
Scope of
Work
Support to KREDLL for institutional strengthening for effective implementation of
ECBC in the state of Karnataka
Development of understanding of current level of ECBC adoption and implementation
in the state;
Identification of current capacity to enforce and administer ECBC in their jurisdictions;
Identification of technical skills required for compliance checks and inspections;
Development of targeted institutional strengthening training and capacity building
programs for KREDL and other government organizations;
Deliverables Capacity building programs for ECBC implementation
Activities for TA support – KREDL
60
Support in implementation of new policies
Task
Objective
Scope of
Work
Support in implementation of new policies
PACE-D TA will assist KREDL in implementing the new policy introduced under this
program as:-
• New Solar Policy & formulation of policy for promotion of decentralized solar
rooftop and solar thermal applications
• Integrated RE policy for next Control Period
• Energy Security and Energy Efficiency Policy
Deliverables Support to KREDL in implementation of New Solar Policy & policy for promotion of
decentralized solar rooftop and solar thermal applications
Support to KREDL in implementation of RE policy for next Control Period
Support to KREDL in implementation of Energy Security and Energy Efficiency Policy
Activities for TA support – KREDL
61
Support to KREDL in establishment & operationalization of green energy fund
Task
Objective
Scope of
Work
Support to KREDL in establishment of green energy fund by levying green energy
cess to industrial and commercial consumers
Review and analysis acts and provisions of similar initiatives of various states for
establishment of green energy fund;
Review of Karnataka Electricity (Taxation on Consumption ) Act 1959 and subsequent
amendments to find out the provisions of establishment of Green fund;
Development of draft framework and guidelines for establishment of green fund;
Assistance in stakeholder consultation
Finalization of framework and guidelines of green energy fund
Deliverables Draft framework and guidelines for establishment of green energy fund;
Stakeholder consultation;
Final framework and guidelines for establishment of green energy fund;
Activities for TA support – KREDL
62
Support to KREDL in development of inter-linkages with other State department
programs for RE/EE deployment
Task
Objective
Scope of
Work
Support to KREDL in establishing inter-linkages with other State department
programs for RE/EE deployment in the State
Review of budget allocation and utilization of various state departments in deployment
of RE/EE
Review of RE/EE programs implemented by other state departments
Identification of funds with various other State departments and channeling the same
for deployment of RE/EE programs of KREDL ensuring effective utilization of funds
Design of effective channel between KREDL and other departments for tracking
availability of funds, linking same with appropriate RE/EE programs of KREDL and for
supporting implementation of such programs
Deliverables Report to KREDL on inter-linkages with other State department programs for RE/EE
deployment
Assistance in identification of other State department funds for RE/EE deployment
Activities for TA support – KREDL
TA support activities proposed for KERC
63
64
Assistance in formulation of Net-metering Framework
Task
Objective
Scope of
Work
Assist KERC in developing concept paper on Net Metering Framework for
Karnataka
Review and analysis of model guidelines by FOR
Identification of key stakeholders and their roles and responsibilities
Identification of Key issues and challenges to be addressed for implementing net
metering
Design of interconnection scheme with focus on timeline, charges, certification,
agreement, dispute resolution
Guidelines on development of rooftops for utilities
Cost-benefit analysis covering impact assessment on Utilities and various consumer
categories
Deliverables A comprehensive concept paper on Net Metering framework with focus on rolling out
guidelines for implementation, interconnection, energy accounting of such system
Activities for TA support - KERC
Development of concept paper for competitive bidding in RE (for KERC)
Task
Objective
Scope of
Work
Assist KERC for development of a concept paper of competitive bidding for
RE in Karnataka
Study of Statutory and regulatory framework for competitive bidding for RE in India
Analysis of key design considerations for introduction of competitive bidding in RE
Analysis of various competitive bidding models under Case-1 or Case-2
Analysis of case studies of projects conceived under both case 1 and case 2 and the
respective fallout.
Analyzing Role of KERC, nodal agency, project developers and utilities for enabling
competition under both Case 1 and Case 2.
65
Deliverables Draft concept paper on competitive bidding to KREC for consultation
Assistance during stakeholder consultations
Activities for TA support - KERC
KERC – Demand Side Management Workshop
Task
Objective
Scope of
Work
Assisting KERC in conducting Demand Side Management Workshop
Assist KERC in organizing a workshop for the DSM based on the national and
international experience.
Discussion on regulatory framework for DSM, best practices in DSM and innovative
financing mechanism adopted, during Workshop
Findings of the workshop will be used to identify the areas of technical assistance
required for the state of Karnataka for the large scale deployment of DSM/EE
programs.
Activities for TA support - KERC
Deliverables Concept note and agenda for the workshop
Identification of stakeholders and sending them invites;
Organize and conduct the workshop
Preparation and submission of DSM workshop report
KERC – Development of DSM Regulations
Task
Objective
Scope of
Work
Assisting KERC for development of DSM Regulations
Review and analysis of model DSM Regulations developed by FOR
Review of experience and analysis of DSM Regulations implemented by other
SERCs;
Development of contours of proposed DSM Regulations;
Development of draft DSM Regulations for the state of Karnataka
Finalization of DSM Regulations through stakeholder consultation;
Activities for TA support - KERC
Deliverables DSM regulations for the state of Karnataka
68
KERC – Development of guidelines such as CBA and E,M & V
Task
Objective
Scope of
Work
Assistance to KERC in development of guidelines such as CBA and E,M & V of
DSM programs
Review of FOR and other SERCs guidelines
Identification of criteria and defining the costs and benefits of DSM programs;
Analysis of framework for development of baseline database;
Establishment of criteria for engaging agency for third party evaluation;
Development of draft guidelines / manuals on CBA and E,M &V
Stakeholder consultation on draft guidelines;
Finalization of guidelines addressing necessary comments of stakeholders
Deliverables Guidelines on cost-benefit analysis of DSM programs
Guidelines on Evaluation, Monitoring & Verification of DSM programs
Activities for TA support - KERC
KERC – Development of action plan for implementation of DR programs in Karnataka
Task
Objective
Scope of
Work
Assistance in development of action plan for implementation of DR
programs in Karnataka
Development of DR discussion paper (includes lessons learnt from national and
international DR programs and viable approaches for state of Karnataka)
Development of action plan for pilot DR scheme for the state of Karnataka
(program scope, target audience, overall program design, identification of suitable
hardware & software technology, incentive/penalty mechanism, sector specific load
curtailment options, baseline establishment methodology and M&V aspects etc.)
DR awareness workshop
Deliverables DR discussion paper (Lessons learnt from national and international DR programs
and viable DR approaches for Karnataka)
Action plan for DR implementation in Karnataka
DR awareness workshop
Activities for TA support - KERC
70
KERC - Development of Institutional Structure for DSM related Activities
Task
Objective
Scope of
Work
Assisting KERC in development of institutional structure for DSM related activities
and development of targeted institutional strengthening programs
Development of understanding of various DSM related activities to be performed by
KERC
Identification of key competencies requirement for the DSM cell
Review of existing institutional structure of KERC and identification of institutional
capacity and skill sets needed for DSM implementation
Identification of training needs and capacity building requirements of the proposed
DSM cell
Development of draft strategy paper on the institutional structure for DSM
Discussion with KERC on the draft strategy paper
Finalization of strategy paper in consultation with KERC
Deliverables Strategy paper for institutional structure for DSM related activities
Activities for TA support - KERC