Parallel resources
© beas group 2011 / Page 2
This documentation and training is provided to you by beas group AG. The documents are neither approved nor in any way acknowledged or endorsed by SAP. For SAP Business One, only the documentation and training officially released by SAP shall be binding upon SAP. SAP shall not be responsible for any content of this documentation and training and this documentation and training shall not be binding upon SAP in any way.
The official current SAP Business One documentation and training for SAP Business One is available at http://service.sap.com/sbocustomer/documentation and http://service.sap.com/sbocustomer/training.
© beas group 2011 / Page 3
Requirements for this Tutorial
What you should successfully master
The basics of SAP and be.as Good knowledge of general manufacturing processes
© beas group 2011 / Page 4
Learning Targets
After working through the lesson, you will be able to:
Create and manage parallel resources
© beas group 2011 / Page 5
Agenda
Parallel resources
1: Introduction
2: Tool with same start/end date
3: Parallel resource with the same start/end date
4: Alternative parallel resources
4: Overlapping operations
© beas group 2011 / Page 6
Parallel resourceaIntroduction
What are parallel resources?
Resources, that must be used at the same time.
© beas group 2011 / Page 7
Parallel resource Types of parallel resource
be.as offers the following types of parallel resources:
Tools with the same start and end date.
Parallel resources with the same start and end date, with any degree of utilization.
Alternative parallel resources.
Overlapping work sequences.
© beas group 2011 / Page 8
Parallel resource Tools
Tools are always available 24 hours, there is no shift calendar
To restrain availability use the switch „blocked until“ in the tools master sheet
Tools are only taken into consideration, if capacity planning is activated
© beas group 2011 / Page 9
Parallel resource Tools : setup
Insert tools in the routing in tab „tool“.
Now the routing can be scheduled only at times when the tools are available.
© beas group 2011 / Page 10
Parallel resource Tools : setup a parallel alternative tool
Insert a parallel alternative tool by enabling the switch : defines cycle time“.The expected time is deposited in the tool and transferred to the work sequence when activated.
In the structure view as well as in the APS view you can switch between tools. Automated optimization or tool selection is not possible.
© beas group 2011 / Page 11
Agenda
Parallel resources
1: Introduction
2: Tool with same start/end date
3: Parallel resource with the same start/end date
4: Alternative parallel resources
4: Overlapping operations
© beas group 2011 / Page 12
Parallel resourcesgeneral
Setup the parallel resource in routing: tab “parallel”
With a parallel resources, a work sequence can be processed on multiple resources in parallel. Example: machine and employee or a several machines. Parallel resources as well as the operation itself can be logged on and logged off. All parallel resources always have the same start and end date. Therefore no separate job time or setup time is possible.
The degree of utilization is adjustable, if you set to 50%, with a lead time of 1 hour, the resource will be loaded with 30 minutes.
© beas group 2011 / Page 13
Parallel resourcescapacity check
If the degree of utilization is set to 100% and the resource limits are checked according to resource master sheet, then the operation can only be dispatched at the time, when both the main resource and the parallel resource are available.
If you set a degree of utilization different from 100% or there are more than 1 employe/machine available for this resource, then only the daily capacity is checked. (Check to prevent utilization of more than 100%)
© beas group 2011 / Page 14
Parallel resourcesAPS view
In the APS parallele resources are displayed in the lower domain. To activate: tab „Resource“ - switch „resource“
© beas group 2011 / Page 15
Parallel resourcesdifferent shift schedule
If for the main and the parallel resource different shift schedules are existing, the schedule with the later start date is used.
Example: Main resource (machine) 0:00Operator (employee): 8:00Time is reserved from: 8:00
© beas group 2011 / Page 16
Agenda
Parallel resources
1: Introduction
2: Tool with same start/end date
3: Parallel resource with the same start/end date
4: Alternative parallel resources
4: Overlapping operations
© beas group 2011 / Page 17
Parallel resourcesAlternative parallel resources
Parallel resourcen can also have alternative resources.
Example:
To the machine „1202“ employee group „INJ_INT“ as well as „INJ_EXT“ can be assigned.
To do so, enable the switch „alternative“ at all concerning resources.
© beas group 2011 / Page 18
Parallel resourcesAlternative parallel resources
In the work order, you can select the parallel resource.
Restrictions: you can have an unlimited number of parallel resources and ONE alternative-parallel resource
© beas group 2011 / Page 19
Parallel resourcesAlternative parallel resources: optimization
be.as scheduling function allows to optimize parallel-alternative resources. Enable „optimization“ in the work sequence. Under consideration of existing time reservations, the parallel resource with the shortest lead time is used. For further information see training unit „resource optimization“
© beas group 2011 / Page 20
Agenda
Parallel resources
1: Introduction
2: Tool with same start/end date
3: Parallel resource with the same start/end date
4: Alternative parallel resources
4: Overlapping operations
© beas group 2011 / Page 21
Parallel resourcesOverlapping operations
Usually the following operation starts when the previous one is finished.The overlap limit determines how long after the start of the first operation, the second one can be started in parallel. In the given example, the second operation starts one hour after the first ended.
© beas group 2011 / Page 22
Parallel resourcesOverlapping operations: APS view
In the APS view overlapping is displayed: one hour in this example. Overlapping operations may have different lead time. The following operation can start at the earliest: start date + overlap limit of the previous operation.
If there is no time available for the overlapping operation, the overlapping limit is ignored and the next empty time frame is used.
© beas group 2011 / Page 23
Parallel resourcesOverlapping operations: restrictions
Restrictions:
-Calculation of overlapping operations works only with forward scheduling
-If the lead time (overlapping operation + overlap limit) is shorter than the lead time of the main operation, a correct computation is not possible.
-If capacity limits are taken into account and there are not enough resources available, the overlap limit is ignored.
© beas group 2011 / Page 24
Summary
You can now: Create and manage parallel resources
Thank you for your cooperation!