PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

25
PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP

Transcript of PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Page 1: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

PAPER TOWER COMPETITION

Dr. rer. nat. Christiane Gresse von Wangenheim, PMP

Page 2: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Exercise: Paper Tower Competition

Group exercise in groups with 6 participantes.

Instructions:

Objective is to build a paper tower of at least 60 cm height using only the materials provided. Your tower must be free of any outside support (e.g. cannot be fixed on the floor, wall, or a team member). The tower must be able to withstand a moderate breeze (as blown by the teacher).

Only projects completed on time with the tower fully built according to the requirements will be considered in determining the winner. Projects also need to have properly completed the performance report.

The criteria (with equal weights) to determine the winning team are:

Largest number of SPIs and CPIs ≥ 1 in all stages

Lowest total cost

Beauty (to be evaluated subjectively by a vote of all students)

Page 3: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Phase Expected result Duration

0. Project planning Project plan 15 min

1. Design Documentação do projeto da torre 3 min

Monitoring & control Register of used resourcesPerformance report

3 min

2. Construction Tower with 20 cm of height 3 min

Monitoring & control Register of used resourcesPerformance report

3 min

3. Construction Tower with 40 cm of height 3 min

Monitoring & control Register of used resourcesPerformance report

3 min

4. Construction and test Tower with 60 cm of height 3 min

Monitoramento & controle

Registro de despesasRelatório de desempenho

3 min

Phases of the exercise

Important: No technical activity may me executed during monitoring & control.

Page 4: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Phase 0. Project planning

Select a group member as project manager, with the following responsibilities: Coordinate the revision and completion of the project plan. Register used resources Coordinate monitoring & control

Plan the human resources, assigning group member to roles: Principal Engineer and engineers: design, construct and test the

tower. Auditor : controls the correct execution of the exercise by supervising

another group. Plan the required resources and complete the cost baseline. Analyze risks and, if necessary, acquire protections.

Duration: 15 minutes

Page 5: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Material (and costs)

Material Paper sheet: $ 2

Paper clip: $ 1

Piece (approx. 5 cm) of tape: $ 5 (pieces can only be used as one piece)

Scissor: $ 20

Tape measure: $ 20

Only these materials can be used.

Human resources Cost of 1 min. of a human resource is $ 10.

Page 6: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Risk analysis

Identify potential risks and decide for which one preventive actions should be taken.

Acquire risk preventions for those identified.

In case, the risk actually happens, the prevention will protect your project against the impact.

Risk Prevention costLack of human resources $ 25

Lack of material $ 25

Requirement changes $ 25

Changes of deadline $ 25 Unexpected need of conformity to standards

$ 25

Page 7: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Phase 1. Design

Discuss how you will construct the tower.

Document the result in form of a schematic drawing.

Important: During this phase, no construction activity may take place.

Page 8: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Monitoring & control

Register any usage of resources used in this phase. Monitor the performance calculating SPI and CPI.

Earned Value ManagementPV – Planned Value: Cost planned for the scheduled activities to be completed

until the current date.

AC – Actual Cost: Cost spent on the performed activities until the current date.

EV – Earned Value: Planned cost of performed work.

SPI – Schedule Performance Index: SPI = EV/PV

CPI – Cost Performance Index: CPI = EV/AC

Page 9: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Monitoring & control

80% $ 180 $ 180

EA= Progress * PV = 80% * $ 180 = $ 144

$ 144

SPI= EA/PV= $ 144/$ 180 = 0.8

CPI= EA/AC = $ 144/$ 180 = 0.8

0.8 0.8

Page 10: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

PHASE 2. Construction

Construct a tower with 20 cm height.

Register any material and human resources used.

Page 11: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Monitoring & control

Register any usage of resources used in this phase. Monitor the performance calculating SPI and CPI.

Page 12: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

PHASE 3 ...

.. Continue to construct the tower until at least 40 cm of height.

Page 13: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

PHASE 4 ...

.. Complete the construction of the tower and test the tower.

Page 14: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Everything OK? Any question?

Everybody ready?

Page 15: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Phase 0. Project planning

Select the project manager. Plan the human resources, assigning group member to roles:

Principal Engineer and engineers: design, construct and test the tower. Auditor : controls the correct execution of the exercise by supervising

another group. Plan the required resources and complete the cost baseline. Analyze risks and, if necessary, acquire protections.

Duration: 15 minutes

Page 16: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Phase 1. Design

Discuss how you will construct the tower.

Document the result in form of a schematic drawing.

Duration: 3 minutes

Important: During this phase, no construction activity may take place.

Page 17: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Monitoring & control

Register any usage of resources used in this phase. Monitor the performance calculating SPI and CPI.

Duration: 3 min.

Important: During this phase, no construction activity may take place.

Page 18: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Phase 2. Construction

Construct a tower with 20 cm height.

Register any material and human resources used.

EVENT: Your principal engineer suffered an accident and cannot participate in this phase. Groups, who acquired the prevention for the risk of lack of human

resources, nothing changes. For all others, the team member assigned as principal engineer does

not participate (comes to the front of the room). Yet, the cost of these members is still registered as a used resource.

Duration: 3 min.

Page 19: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Monitoring & control

Register any usage of resources used in this phase. Monitor the performance calculating SPI and CPI.

Duration: 3 min.

Important: During this phase, no construction activity may take place.

Page 20: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Phase 3. Construction

Construct a tower with 40 cm height.

Register any material and human resources used.

EVENT: Your client just called you to inform you that the rules of the competition have been changed, now requiring the construction of a tower of at least 70 cm of height. Groups, who acquired the prevention for the risk of requirement

changes, nothing changes continuing with the requirement to construct a tower of 60 cm of height.

All other groups now have to construct a tower of at least 70 cm of height.

Tempo: 3 min.

Page 21: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Monitoring & control

Register any usage of resources used in this phase. Monitor the performance calculating SPI and CPI.

Duration: 3 min.

Important: During this phase, no construction activity may take place.

Page 22: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Phase 4. Construction

Construct a tower with 40 cm height.

Register any material and human resources used.

Duration: 3 min.

Page 23: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Monitoring & control

Register any usage of resources used in this phase. Monitor the performance calculating SPI and CPI.

Duration: 3 min.

Important: During this phase, no construction activity may take place.

Page 24: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Finished!

Acceptance criteria: Free standing paper tower of at least 70 (60) cm of height which

withstands a light breeze.

Correct and complete performance reporting.

The winner is: Largest number of SPIs and CPIs ≥ 1 in all stages

Lowest total cost

Beauty (to be evaluated subjectively by a vote of all students)

Page 25: PAPER TOWER COMPETITION Dr. rer. nat. Christiane Gresse von Wangenheim, PMP.

Licença

Atribuição-Uso Não-Comercial-Compartilhamento pela Licença 2.5 Brasil

Você pode: - copiar, distribuir, exibir e executar a obra - criar obras derivadas

Sob as seguintes condições:Atribuição — Você deve dar crédito ao autor original, da forma especificada pelo autor ou

licenciante. Uso Não-Comercial — Você não pode utilizar esta obra com finalidades comerciais. Compartilhamento pela mesma Licença — Se você alterar, transformar, ou criar outra obra

com base nesta, você somente poderá distribuir a obra resultante sob uma licença idêntica a esta.

Para ver uma cópia desta licença, visite http://creativecommons.org/licenses/by-nc-sa/2.5/br/ ou mande uma carta para Creative Commons, 171 Second Street, Suite 300, San Francisco, California, 94105, USA.