PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 -...

51
Environmental Monitoring Report Bi-Annual Report Covering the period of January – June 2017 PAK: Jamshoro Power Generation Project Project Number: 47094-001 ADB Loan/Grant Number: L3090/3091/3092-PAK Prepared: July 2017 Prepared by the Jamshoro Power Company Limited (JPCL), with the assistance of Mott MacDonald Limited (United Kingdom) in joint venture with MM Pakistan (Pvt) Ltd (Pakistan), for the Islamic Republic of Pakistan and the Asian Development Bank (ADB). This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Transcript of PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 -...

Page 1: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Environmental Monitoring Report

Bi-Annual ReportCovering the period of January – June 2017

PAK: Jamshoro Power Generation Project

Project Number: 47094-001ADB Loan/Grant Number: L3090/3091/3092-PAKPrepared: July 2017

Prepared by the Jamshoro Power Company Limited (JPCL), with the assistance of MottMacDonald Limited (United Kingdom) in joint venture with MM Pakistan (Pvt) Ltd (Pakistan),for the Islamic Republic of Pakistan and the Asian Development Bank (ADB).

This environmental monitoring report is a document of the borrower. The views expressedherein do not necessarily represent those of ADB's Board of Directors, Management, orstaff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making anydesignation of or reference to a particular territory or geographic area in this document, theAsian Development Bank does not intend to make any judgments as to the legal or otherstatus of any territory or area.

Page 2: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Jamshoro Power GenerationProject(JPGP) Bi-Annual Monitoring Report, Jan-Jun2017

31 July 2017

334014-MML-JPCL-R-00599 JPGP Bi-Annual Monitoring Report, Jan - Jun '17

Page 3: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017
Page 4: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

334014-MML-JPCL-R-00599C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annualenvironmental monitoring report January to June 2017 Final (3).docxMott MacDonald

Mott MacDonaldAl Gaith TowersHamdan StreetPO Box 47094, Abu DhabiUnited Arab Emirates

T +971 (0)2 401 5333F +971 (0)2 627 0734mottmac.com

Jamshoro Power GenerationProject(JPGP) Bi-Annual Monitoring Report, Jan-Jun2017

31 July 2017

Mott MacDonald Limited. Registered inEngland and Wales no. 1243967.Registered office: Mott MacDonald House,8-10 Sydenham Road, Croydon CR0 2EE,United Kingdom 334014-MML-JPCL-R-00599 JPGP Bi-Annual Monitoring Report, Jan - Jun '17

Page 5: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017
Page 6: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

Issue and Revision Record

Revision Date Originator Checker Approver Description0 31.07.17 GC JV TH Final for issue

1 11.06.17 JV JV JV Revised Cover Page

Information class: Standard

This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or beingused for any other purpose, or containing any error or omission which is due to an error or omission in data suppliedto us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to otherparties without consent from us and from the party which commissioned it.

This report has been prepared solely for use by the party which commissioned it (the ‘Client’) in connection with the captioned project. It should not be used for any other purpose. No person other than the Client or any party who has expressly agreed terms of reliance with us (the ‘Recipient(s)’) may rely on the content, information or any views expressed in the report. We accept no duty of care, responsibility or liability to any other recipient of this document. This report is confidential and contains proprietary intellectual property.

Page 7: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

Contents

1 Introduction 11.1 Environmental management 2

2 Environmental monitoring and management 32.1 Environmental monitoring and management overview 32.2 Summary of environmental monitoring during reporting period 3

2.2.1 Lot 1 – Rehabilitation of evaporation ponds 32.2.2 Lot 3 – Municipal solid waste disposal facility 5

3 Actions during the next reporting period 7

Appendices 9

A. Bi-Annual Environmental Monitoring and Management Report; Lot 1Remediation, Rehabilitation of Effluent Ponds, Feb – Jun 2017(SACHAL) 10

B. Bi-Annual Environmental Monitoring Report; Lot 3, Remediation, Jan-Jun 2017 (MAJ&IIC) 27

Page 8: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 1(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

1 Introduction

The Government of Pakistan aims to increase the share of coal-based generation from almostnone in 2016 to 15% over the next few years. In support of this initiative Jamshoro PowerCompany Limited (JPCL) and Genco Holding Company (GENCO), supported by the AsianDevelopment Bank (ADB), is planning a brownfield extension of the Jamshoro Power Station inorder to improve the total plant efficiency and increase the power output from the Plant. Theproject is known as the Jamshoro Power Generation Project (JPGP).

The project site is approximately 20km northwest of Hyderabad, and about 150km northeast ofKarachi in the Sindh Province of Pakistan. The lndus River is about 3.5km east of the powerplant site. Currently there are four fossil fuel-fired electricity generating units installed andoperating at the site (Unit 1 is oil fired and Units 2 – 4 have dual-fuel capability (oil/gas)).

JPGP is proposed to initially comprise of 1x660MW (net) supercritical power plant with facilitiesto expand to 2x660MW plants. The project aims to decrease the existing power shortfall inPakistan and address environmental concerns from the existing oil-fired power units. The newboiler(s) will be designed to utilise imported sub-bituminous coal blended at 80/20 with locallignite as its fuel.

As part of the feasibility study for the project and as required by the ADB an environmental auditwas undertaken of the existing plant. The audit was included as part of the environmental andsocial impact assessment (ESIA) for the 2x660MW supercritical power plant (EnvironmentalImpact Assessment; Jamshoro Power Generation Project; Hagler Bailly Pakistan, October 292013 (the ESIA report)). Section 6 of the ESIA report (Issues Related to Existing Plant andCorrective Actions) identified several items related to the existing plant that require remediationor rehabilitation.

The items that were identified are subject to a loan condition applied by ADB that requires theidentified remediation works to have a signed contract in place prior to commencement of workson the site associated with the new facility (660MW supercritical power plant).

Currently (end of July 2017) JPGP is in the early implementation stage with the followingactivities underway:

(i) Final Technical Proposals for construction and operation of the 2x660MW (gross)supercritical power plant have been received and are under evaluation. It iscurrently envisaged that the Contracts will be awarded by fourth quarter of 2017.

(ii) The following tender packages associated with rehabilitation and remediation ofsome aspects of the existing oil-fired plant have been issued, proposals receivedand contracts awarded:a. Lot 1 – rehabilitation of evaporation pondsb. Lot 2 – rehabilitation of cooling tower/blow-down water drainage channelc. Lot 3 – residential colony municipal waste facility

Work is in progress on these Lots.

(iii) The following tender packages associated with rehabilitation and remediation ofsome aspects of the existing oil-fired plant have been issued and proposals arebeing assessed:

Page 9: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 2(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

a. Lot 4 – hazardous waste disposal facility and hazardous waste collection anddisposal

b. Lot 5 - residential colony municipal wastewater treatment plantc. Lot 6 – remediation of oil contaminated soils – However this work can only be

undertaken once the Power Plant oil transfer polluting process ceases.

This report is the fifth semi-annual environmental monitoring report for the project covering theperiod from January 2017 to June 2017. Subsequent semi-annual reports will be reconfiguredas necessary to reflect activities and available information as the project develops.

1.1 Environmental management

The ESIA study and subsequent ESIA report for the proposed 2x660MW power plant weredeveloped for the Asian Development Bank and include reference to Pakistan nationalstandards and regulatory requirements and international guidelines including ADBs SafeguardPolicy Statement (2009) and the World Bank/International Finance Corporation Environment,Health and Safety Guidelines for Thermal Power Plants (2008) (IFC EHS guidelines).International treaties that Pakistan is a signatory to are also considered.

The EIA report correctly identifies that both Pakistan national environmental quality standards(NEQS) and IFC EHS guidelines will have to be complied with. In operation this means that themost stringent of the NEQA and IFC EHS Guidelines environmental limits/standards/guidelineswill have to be complied with (with the exception of ambient air quality standards where nationalstandards, where they exist, take precedence over IFC EHS guidelines).

A gap analysis with respect to draft bidding documents and technical specifications wasprepared by the PIC and a number of items were identified that were included in the technicalrequirements for the 2x660MW supercritical power plant when the tender documents wereissued.

Page 10: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 3(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

2 Environmental monitoring andmanagement

2.1 Environmental monitoring and management overviewAt the time of compiling this report (July 2017) three work packages were under progress:

· Lot 1– Evaporation pond renovation· Lot 2 – Blow-down channel renovation· Lot 3 – Municipal solid waste disposal facility

Lot 1 and Lot 2 have been awarded to Sachal Engineering Works (Pvt) Ltd (Sachal).Construction environmental management plans have been developed and approved for bothlots. The approved CEMPs include details of scheduled environmental monitoring during theconstruction process. At the time of developing this report work on Lot 2 was on hold whileaccess to the worksites was being agreed with neighbouring landowners. Lot 2 is not reportedfurther in this report; it is anticipated that work will recommence in Q3 2017. Monitoring ofenvironmental parameters for Lot 1 are summarised in this report. The monitoring reportprepared by Sachal is attached as Appendix A.

Lot 3 has been awarded to a consortium of Mian Abdul Jabbar & Co and Indus Construction Co(MAJ ICC). A construction environmental management plan has been developed for Lot 3 andupdates have been requested by the project implementation consultant (PIC). Monitoring ofenvironmental parameters for Lot 3 are summarised in this report. The monitoring reportprepared by MAJ ICC is attached as Appendix B.

It should be noted that this is the first reporting period during which activities have beenundertaken that require monitoring and reporting; as such it is envisaged that feedback will begiven to contractors and information reported will develop over forthcoming reporting periods.

2.2 Summary of environmental monitoring during reporting period

2.2.1 Lot 1 – Rehabilitation of evaporation ponds

Lot 1 involves clearing four existing evaporation ponds of heavy vegetation growth andsediment deposits that have built up over many years of use. Repairs are then to be carried outto any damage to the structure of the ponds and associated infrastructure as necessary to makethe ponds functional. Mechanical excavators, dozers and haulage trucks, tractors and trailersare all used for removing and transporting material. Excavated material is deposited at adesignated site within the JPCL site. The information reported here is extracted from thecontractor’s (Sachal) ‘Bi Annual Environmental Monitoring and Management Report;Rehabilitation of Effluent Ponds. Feb – July 2017’.

The following parameters are monitored and reported:

(a) Ambient air quality(b) Traffic safety(c) Noise Levels(d) Surface water and soil(e) Waste management(f) Cultural heritage management(g) Occupational health and safety

Page 11: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 4(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

Many of the parameters are monitored visually on an ongoing basis and reported qualitatively.Where quantitative data is available it is reported here.

a) Ambient air quality. Taken primarily as dust, visual assessments are made and watersprays are used to control dust levels routinely and in response to observed excessivedust levels. No excessive dust issues have been reported during the reporting period.

b) Traffic safety. Traffic safety is controlled on site by imposing speed limits andinstructions to drivers. Traffic activity is routinely monitored by environment, health andsafety personnel on site. No adverse traffic related incidents have been reported duringthe reporting period.

c) Noise levels. Noise is monitored on site from a health and safety perspective.Monitoring data is reported in Table 3.3.1 and Table 3.3.2 of the contactors bi-annualenvironmental report for Lot 1 in Appendix A. No breaches of the 85dB health andsafety noise limits were recorded during the reporting period. Noise monitoring isreported in Table 1 and Table 2.

Table 1: Noise Level Monitoring during 1st Quarter from Feb 2017 to March 2017

Samplinglocations

GPSCoordinates Date and Time

Average Noise Levelin dB

1 Lot-I CampOffice

E 25.477567N 68.273647

20th March 201709:00 am to 05:00 pm

68.32

2 Dumping areaE 25.471332N 68.272206

25th March 201709:00 am to 05:00 pm

60.08

Source: Bi Annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds. Feb – July2017. Sachal

Table 2: Noise Level Monitoring during 2nd Quarter from April 2017 to June 2017

Samplinglocations

GPSCoordinates Date and Time

Average Noise Levelin dB

1 Lot-I CampOffice

E 25.477567N 68.273647

20th April 201709:00 am to 05:00 pm

68.32

2 Dumping areaE 25.471332N 68.272206

25th May 2017 09:00am to 05:00 pm

60.08

Source: Bi Annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds. Feb – July2017. Sachal

d) Surface water and soil. Samples of surface water and soils from the evaporation pondswere taken and analysed. No exceedances of prescribed standards are reported.

e) Waste management. Solid waste is reported to be collected and disposed of in adesignated municipal disposal site.

f) Cultural heritage management. During excavations, continual observations are made toidentify culturally important artefacts and a ‘chance-finds’ procedure is included in theconstruction environmental management plan (CEMP). Given the nature of the activitieson Lot 1 it is considered unlikely that any culturally important artefacts will be present.

Page 12: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 5(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

g) Occupational health and safety. Health and Safety statistics are recorded and reportedin Sachal’s bi-annual environmental report and are shown in Table 3

Table 3: Monthly Occupational Health and Safety measure recorded at project site

Safety Statistics Feb-Mar Apr-May Jun-JulLTI 0 0 0

TRIR 0.04 0.02 0

Number of days without accident 59 61 36

Number of ill health cases 1 2 0

Overdue preventive open observations 23 21 8Source: Bi Annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds. Feb – July

2017. Sachal

During the next reporting period it is anticipated that Lot 1 will proceed with detailed design ofrepairs to the evaporation ponds and commencement of the repairs.

2.2.2 Lot 3 – Municipal solid waste disposal facility

Lot 3 involves the design and construction of a municipal solid waste facility for the housingcolony, removing municipal waste from the housing colony and depositing in the newlyconstructed facility and capacity building for JPCL employees and colony residents on thehandling and disposal of municipal waste. The information reported here is extracted from thecontractor’s (MAJIIC) Semi-Annual Environmental Monitoring Report; Project Site RemediationPackage (Lott-3). July 2017. The monitoring report prepared by MAJICC is attached asAppendix B.

Lot 3 is in the early stages of development. During the reporting period the following activitieshave been undertaken:

1. Initial segregation of waste has taken place on site2. An awareness programme for residents of the colony has been initiated3. Drinking water quality sampling and analysis has been undertaken with analysis being

undertaken by the Pakistan Council of Research in Water Resources Water QualityLaboratory. All measured parameters were reported as being within acceptable(WHO/EU) limits

4. Groundwater quality sampling and analysis was undertaken by PCSIR Laboratories,Karachi. Both samples recorded elevated E. coli levels with sample 2 taken betweenblocks 12 and 13 recording a level of 1100 CFU/dl. The elevated levels are likely to bedue to the proximity of septic tanks in the colony and may indicate that the septic tanksare leaking. Ground and surface water will have to be handled appropriately duringconstruction of the solid waste disposal facility to avoid adverse impacts on workers,residents of the colony and contamination of soils and groundwater.

5. Toolbox talks have been undertaken for company staff on site. Subjects covered arejungle cutting, proper use of PPE and geotechnical investigations.

As Lot 3 progresses more detailed environmental reporting is expected to be reported.

During the next reporting period MAJICC report that they will undertake the following tasks:

· Awareness programmes

Page 13: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 6(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

· Installation of dustbins· Collection of MSW· Transportation of MSW· Segregation of MSW at site· Drinking and ground water quality monitoring· Air quality monitoring· Noise pollution assessment during excavation work

It is anticipated that Lot 3 will progress to detailed design of the municipal waste disposal facilityduring the next reporting period.

Page 14: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 7(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

3 Actions during the next reporting period

During the forthcoming period (July to December 2017) the following actions are anticipated:

● Financial Bids will be received from bidders for the 2x660MW power plant construction andoperation packages, once the Final Technical bid Evaluation is complete

● Execution of lots 1, 2 and 3 for the remediation/rehabilitation packages will continue on site● Contracts for Lots 4, and 5 for the remediation/rehabilitation packages will be awarded● Lot 6 (bio-remediation of oil contaminated soil) will be awarded subject to cessation of oil

transfer pollution processes

PIC environmental specialists will:

● Respond to queries relating to environmental aspects of the issued bid documents● Review received bids for technical packages for compliance with environmental

requirements● Review received bids for remediation/rehabilitation packages● Assist with selection of the preferred bidders● As appropriate, work with preferred bidders/awarded bidders to establish environmental

management and monitoring plans, programmes and reporting.

The next semi-annual environmental monitoring report will cover the period from July toDeceber 2017 and will be made available by the end of January 2018.

Page 15: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 8(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

Page 16: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 9(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

Appendices

A. Bi-Annual Environmental Monitoring and Management Report; Lot 1 Remediation,Rehabilitation of Effluent Ponds, Feb – Jun 2017 (SACHAL) 10

B. Bi-Annual Environmental Monitoring Report; Lot 3, Remediation, Jan-Jun 2017(MAJ&IIC) 27

Page 17: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 10(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

A. Bi-Annual Environmental Monitoring andManagement Report; Lot 1 Remediation,Rehabilitation of Effluent Ponds, Feb – Jun2017 (SACHAL)

Page 18: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Bi Annual Environmental Monitoring &

Management Report

Project Name: Rehabilitation of Effluent Evaporation Ponds Period: (Feb - July, 2017)

Report prepared by: ATIF HUSSAIN _____________________

Project Manager Lot-I

11

Page 19: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Bi Annual Environmental Monitoring & Management Report

1

Table of Contents

Sr. No. Particulars Page

1.0 Project Description

1.1 Project Description 1

1.2 Project Background

1

1.3 Scope of work 4

2.0 Environmental Monitoring Requirements & Parameters 5

2.1 Environmental Monitoring 5

2.2 Environmental Monitoring during Construction Phase

5

2.3 Project Environmental key personnel 5

3.0 Impact on Environmental Parameters during Construction Phase 6

3.1 Ambient air quality 6

3.2 Traffic safety 6

3.3 Noise Levels 6

3.4 Surface water and soil 10

3.5 Waste Water Management 10

3.6 Cultural Heritage Management 10

3.7 Impact of OHS at Project Site 10

4.0 Mitigation Measures 11

4.1 Air Quality 11

4.2 Water Quality 11

4.3 Noise Level 11

4.4 OHS at Project Site 11

5.0 Picture Gallery 12

12

Page 20: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Bi Annual Environmental Monitoring & Management Report

2

1.1 Project Description The Jamshoro site is about 20 km northwest of Hyderabad, and about 150 km northeast of Karachi. The Indus River flows about 3.5 km east of the site. Highway N-55, also known as the Indus Highway, runs through the site and has immediate access to the national railway, allowing for the easy delivery of equipment, fuel and other materials. The Jamshoro site consists of four (4) existing fossil fired electricity generating units. Unit 1 (U1) is fired by heavy fuel oil (HFO) with an original nominal rating of 250MW. U1 was originally commissioned in 1990. Units 2 to 4 are dual fuel (oil and gas) fired with an original nominal rating of 210MW (each). Units 2 to 4 were commissioned in 1989,1990 and 1991 respectively. Plant effluents from existing plant including boiler blowdown, laboratory waste, plant washing waste water, and water drainage from cooling towers are led to the existing 4 effluent evaporation ponds. These evaporation ponds are now completely filled with sludge, silt and clay along with wild bushes and vegetation growth. The evaporation ponds are to be cleared of wild bushes and vegetation. The existing evaporation ponds and associated channels are to be cleaned. The silt/sludge is to be taken out from the evaporation ponds required levels mentioned in as built/tender drawing and will be dumped to the Water Pre Treatment Area (WPTA) south of Evaporation Ponds within the power plant premises. The discarding of silt and sludge shall comply with the applicable provisions within the EIA.

1.2 Project Background

Plant effluents from existing plant including boiler blowdown, laboratory waste, plant washing waste water, and water drainage from cooling towers are led to the existing 4 effluent evaporation ponds. These evaporation ponds are now filled with sludge, silt and clay along with wild bushes and vegetation growth.

13

Page 21: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Bi Annual Environmental Monitoring & Management Report

3

LOCATION OF THE PROJECT

14

Page 22: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Bi Annual Environmental Monitoring & Management Report

4

1.3 Scope of work

1.3.1 Performance of materials and services

The scope of work under Lot I, includes procurement, transportation, storage,

construction, repair, installation, all detailed survey and geotechnical

investigation, site levelling, and drainage.

1.3.2 Renovation of effluent evaporation ponds

The broad scope of work under this contract shall include but is not limited

to the following:

Removal of all bushes and vegetative growth on existing surface of

Evaporation Pond Area

Sludge and Silt removal from four (4ea) existing evaporation ponds

Disposal Silt and Sludge in accordance with environmental standards

Assessment of damages to the existing evaporation ponds and connecting

channel

Installation of new 12 inch FRP connections at the head end of each pond

for later use

Restoration of evaporation ponds to original conditions (as demonstrated

in the tender (“as built” drawing set)

1.3.3 Design and procurement of various equipment and systems

The Contractor shall carry out the basic and detailed design and engineering as

applicable; finalize the parameters of all equipment and systems. For those

equipment and systems not falling under the Contractor's manufacturing range,

the same shall be procured from reputed sub-vendors. Contractor shall provide

document to prove the capability of sub-vendor.

1.3.4 Transportation, receiving, handling and storage at site

The Contractor shall be responsible for proper transportation of all materials,

equipment and systems from the point of manufacture/ procurement to the

project site and its final location in the plant. It will be the Contractor's

responsibility to develop the shipping and transportation logistics. Similarly, it

will be the Contractor's responsibility to coordinate with necessary departments

such as Imports, Customs, Port Authorities, Roadways, etc.

Upon receipt of equipment and materials at site, the Contractor shall make

arrangements for proper receiving, handling and storage at site. Covered or

indoor storage shall be provided by the Contractor, wherever necessary. In case

use of any hazardous material is envisaged, the Contractor shall make

necessary arrangements duly complying with the applicable laws or regulations

or ordinance or statutes of the Government.

1.3.5 Construction, erection and testing

The Contractor shall follow standard procedures and instructions by the

Employer, if any, for carrying out proper construction, erection and testing of

all the facility. For this purpose, it will be the Contractor's responsibility to

ensure availability of construction machinery, cranes, rigging, scaffolding, tool

for cutting, welding, erection, etc. as may be required.

1.3.6 Commissioning, trial runs and performance guarantee tests

Any pump being provided under the work shall be commissioned and handed

over to the client after trial run.

15

Page 23: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Bi Annual Environmental Monitoring & Management Report

5

1.3.7 General requirements

The items specifically not mentioned in the specification but needed for the

smooth functioning of the equipment/system and plant requirement shall be

deemed included in the scope of Contractor unless otherwise specifically

mentioned under exclusions.

In addition to the scope and services mentioned above, the following general

supplies and services shall be included in the scope of Contractor.

1.3.8 Paints

The Contractor's scope of works includes supply of paints and painting of all

equipment and structures as per the colour scheme to be approved by Employer.

The painting of various components shall comply with the requirement stipulated

in different parts of this specification.

2.1 Environmental Monitoring Requirement & Parameters

The project is committed to monitor and manage its surrounding environment so as to

reduce the negative impacts which may arise from the project activities. To control the

adverse impacts on ambient air quality, traffic safety, noise levels, Surface water and soil,

waste management, cultural heritage management and occupational health & safety of all

personnel on site. The Sachal is regularly monitoring and managing its construction site

by implementing the approved CEMP. The daily, weekly and monthly environmental

inspection records are up to date and have been checked by MML representatives.

Precisely the following pre-determined parameters as indicated below are being regularly

monitored subsequent management program has also taken under consideration for

successful completion of the project.

(a) Ambient air quality

(b) Traffic safety

(c) Noise Levels

(d) Surface water and soil

(e) waste management

(f) Cultural heritage management

(g) Occupational Health and Safety

2.2 Environmental Monitoring during Construction Phase

According to Table 10-2 environmental monitoring in EIA report by ADB, during the

project activities the visual inspections were carried out on daily weekly and monthly

basis to make sure that all above mentioned parameters are on compliance with EIA

and CEMP. The noise level data from the project area is also collected quarterly.

For surface water and soil analysis, the water and soil samples were collected on

different RDs by third party and results of those tests were submitted to MML.

Monitoring and Management

Parameters (Feb 2017 - June 2017)

Ambient air quality

Done with visual inspections

Traffic safety

Implemented and monitored

Noise Levels

Visual inspections and measurements

Surface water and soil

Tests conducted & Submitted

16

Page 24: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Bi Annual Environmental Monitoring & Management Report

6

Monitoring and Management

Parameters (Feb 2017 - June 2017)

waste management

Implemented & Monitored

Cultural heritage management

Visual Inspections

Occupational Health and Safety

Implemented and monitored

2.3 Project Environmental key personnel;

Sr.

No.

Project Key personnel Name of Key

personnel

Telephone No.

01 HSE Officer LOT-I. Atif Hussain 03332401024

02 HSE Supervisor LOT-I Ali Hyder 03023026134

3.0 Impact on Environmental Parameters during construction phase

3.1 Ambient Air Quality

During the construction activities vehicles are carrying employees and tools to the site.

Construction equipment, such as stone (aggregate) crushers is not being used at the site

which could create significant emission of particulate matters. Since rehabilitation of

evaporation ponds would most likely involve significant earth works, increase in particulate

matter in the air from wind-blown dust is also a concern, especially considering the close

proximity of the villages (Local stake holders) to the project site. Ambient Air Quality was

monitored by daily and weekly environmental inspections at site.

3.2 Traffic Safety During project activities vehicle movement is a huge risk to environment as well as the personnel health on site for reducing the risk we put speed limit signs at different roads and drivers are instructed to follow the speed limits strictly. Furthermore, Environmental and health and safety inspections are carried out on regular basis to make sure that the controls are in place and complied properly. 3.3 Noise Levels During project activities, major source of noise is expected to be generated from transport

vehicles which include cranes excavator, trucks, LTVs etc. Regular inspections of all

equipment and vehicles are carried out to make sure the noise levels are below 85 db.

17

Page 25: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

7

Bi Annual Environmental Monitoring & Management Report

Table: 3.3.1. Noise Level Monitoring during 1st Quarter from Feb 2017 to March 2017

Table: 3.3.2. Noise Level Monitoring during 2nd Quarter from April 2017 to June 2017

Sampling

locations

GPS Coordinates Date and Time Average Noise Level in dB

01 Lot-I Camp Office E 25.477284 N 68.273569

20th April 2017 09:00 am to 05:00 pm

65.32

02 Dumping Area E 25.471588 N 68.272076

25th May 2017

09:00 am to 05:00 pm

70.08

To assess the noise generated by different activities and equipment to be used at various

stages of the construction work without proper measures the workers and officers may face

partial or permanent hearing loss. The graphical presentation of noise is depicted in the

following pages of report (Figure-1, 2, 3, 4)

Sampling

locations

GPS Coordinates Date and Time Average Noise Level in dB

01 Lot-I Camp Office E 25.477567 N 68.273647

20th March 2017 09:00 am to 05:00 pm

68.32

02 Dumping Area E 25.471332 N 68.272206

25th March 2017

09:00 am to 05:00 pm

60.08

En

viro

nm

en

tal C

om

plia

nce

Re

po

rt

3rd

Qu

arte

r Mo

nito

ring

data

(sam

plin

g d

ate

; 31

st D

ecem

ber, 2

014)

The

gra

phic

al tre

nds o

f nois

e le

ve

l of fiv

e lo

catio

ns

(Fig

ure

-1); E

ast S

ide

for

one hour

are

pre

sente

d belo

w

dB

100

80

60

40

20

0

dB

18

Page 26: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

8

Bi Annual Environmental Monitoring & Management Report

Noise Level Monitoring during 1st Quarter from Feb 2017 to march 2017

Lot-I Camp Office

Figure 1 Dumping Area

Figure 2

19

Page 27: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

9

Bi Annual Environmental Monitoring & Management Report

Noise Level Monitoring during 2nd Quarter from April 2017 to June 2017 Lot-I Camp Office

Figure 3

Dumping Area

Figure 4

20

Page 28: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

10

Bi Annual Environmental Monitoring & Management Report

3.4 Surface water & soil

The surface water & soil sample were collected from evaporation ponds at different locations.

The samples were collected by third party for analysis and testing and water & soil analysis

report is submitted to MML.

3.5 Waste Management

The solid wastes of domestic nature generated mainly in the labor sheds are regularly being

collected in separate bins and being disposed through municipal cleaners and being

dumping in a designated municipal dumping place. In addition, a small amount of solid

kitchen waste is generated during day time which are also being disposed in methodic way

through municipal cleaner. The environmental and health and safety inspections are carried

out on regular basis to check the compliance.

3.6 Cultural Heritage management During project activities (excavation) and manual digging continual supervision is carried out throughout the project and environmental inspections are carried out regularly. Also chance find procedure is established and implemented as stated in CEMP. 3.7 Impact of OHS at project site

Personal Protective Equipment (PPEs): During project activities, the workers may face minor

injuries due to accidental negligence. The regular provided services are depicted in the

following table-5.

Table-5: Monthly Occupational Health and Safety measure recorded at project site

Safety Statistics Feb-Mar Apr-May Jun-Jul

LTI 0 0 0

TRIR 0.04 0.02 0

Number of days without accident 59 61 36

Number of ill health cases 1 2 0

Overdue preventive open observations 23 21 08

21

Page 29: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

11

Bi Annual Environmental Monitoring & Management Report

4.0 Mitigation measures

4.1 Air Quality

To reduce the generation of dust owing to movement of construction materials

including vehicles, regular water spray are being accomplished at construction site.

Movement of construction debris are being covered while hauled and stored, roads

properly cleaned and water sprayed in order to minimize dust in air. To reduce

generation of dust the stone crusher and batching plant have not been allowed at

construction site.

4.2 Water Quality

The camp is outside the project boundary and from that place possible management

has been ensured to avoid any contamination of any sort around the project boundary.

During the day time, small quantity of office waste is generated (approximately 2kg)

per day which is properly disposed-off through designated municipal corporation

locations.

4.3 Noise Level

Use equipment i.e., designed with noise-control provision;

Route truck traffic away from noise-sensitive areas, where feasible;

Unnecessary vehicle movement has been avoided at project site;

Switch off the engines while remain unused.

4.4 OHS at project site

Personal Safety Equipment (PSE): Use appropriate personal protection equipment,

such as safety boots, helmets, gloves, protective clothing, goggles and ear protection

to comply HSE obligation during construction phase.

22

Page 30: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

12

Bi Annual Environmental Monitoring & Management Report

4.0 Pictures gallery

Speed Limit Signboards on Activity Route

Parking Area

Barricaded Walkways

23

Page 31: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

13

Bi Annual Environmental Monitoring & Management Report

Speed Limit Signboards at Dumping Area

Assembly Point

PPEs Compliance at Site

24

Page 32: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

14

Bi Annual Environmental Monitoring & Management Report

Emergency Drill

PPEs Compliance at Site

Toolbox Talk

25

Page 33: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

15

Bi Annual Environmental Monitoring & Management Report

Site Visit

Water Sprinkling on Activity Route

26

Page 34: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 27(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

B. Bi-Annual Environmental MonitoringReport; Lot 3, Remediation, Jan-Jun 2017(MAJ&IIC)

Page 35: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Jamshoro Power Company Limited

Project Site Remediation Package (Lot-III)

2 X 660 MW Coal Fired Power Project Jamshoro

July, 2017

Semi-Annual Environmental Monitoring Report

28

Page 36: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

29

Page 37: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

1 2 5 4 8

D:\_Thar Coal\Reports to be formatted\Baseline Reports\HK --Draft Baseline Report for Flora and

Fauna.docx 05 October 2012

Semi-Annual Environmental

Monitoring Report

Project Site Remediation Package (Lot-III)

2 X 660 MW Coal Fired Power Project Jamshoro

July, 2017

30

Page 38: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

i

Issue and revision record

Revision Date Originator Checker Approver Description

A July, 2017

Engr Muhammad Safar Korai

Engr. Muhammad Ibrahim

Magsi

Engr. Salem

Ahmed Bhatti

Engr. Abdul Razaque

Domki Submission

31

Page 39: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

2

1. INTRODUCTION 4

1.1. General Information About The Back Ground Of Project 4

1.2. Project Location 5

1.3. Employer (Client) 5

1.4. Engineer (Consultants) 5

1.5. Contractor 5

2. ACTIVITIES THAT HAVE BEEN UNDERTAKEN DURING THE REPORTING PERIOD 6

2.1. Segregation Of Solid Waste At Site 6

2.2. Awareness Program 6

2.3. Water Quality Analysis 8

2.3.1. Drinking Water Quality 8

2.3.2. Ground Water Quality 10

3. COPIES OF ALL ENVIRONMENTAL MONITORING DATA AND CHECKLISTS 11

4. DETAIL OF ANY ENVIRONMENTAL INCIDENTS DURING THE REPORTING PERIOD 12

5. ANY OTHER DOCUMENTS AND RELEVANT DATA 12

6. CONCLUSIONS AND ACTION PLAN FOR THE NEXT PERIOD 13

6.1. Conclusions And Recommendations 13

6.2. Action Plan For The Next Period 13

Contents

32

Page 40: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

3

Abbreviations

ADB Asian Development Bank

GoP Government of Pakistan

ICC Indus Construction Company

JPCL Jamshoro Power Company Limited

JTPS Jamshoro Thermal Power Station

MAJ Main Abdul Jabbar

MSW Municipal Solid Waste

WHO World Health Organization

PIC Project Implementation consultant

33

Page 41: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

4

1. Introduction

1.1. General Information About the Back Ground of Project

The Government of Pakistan (GoP) is planning to set up a super-critical coal fired power plant at

Jamshoro (the ‘Jamshoro Power Generation Project’ or the ‘Project’) to be financed by the Asian

Development Bank (ADB). The power plant will be setup within the premises of the existing Jamshoro

Thermal Power Station (JTPS). The gross generation capacity of the Project will be 660 MW in the

First Stage and 1,320 MW after expansion. The plant will be owned and operated by the Jamshoro

Power Company Limited (JPCL), the implementing agency of the Project.

The JTPS staff housing colony generates an estimated 750 1tons of solid waste annually. As there is

no proper disposal system, the waste is scattered around the colony. There is currently no solid

waste management system in place at the power plant either to manage waste generated in the plant

offices. The waste dumps can be seen in different location of the plant and the colony. There is no

municipal solid waste disposal facility available in the vicinity of the plant where the waste can be sent

for disposal. Aspects resulting from improper solid waste management are:

Contamination of surface and sub-surface soil by leaching from the dumps

Contamination of surface water in case of runoff

Transportation of contamination from leaching to the ground water aquifer

Possible attraction of scavengers to the solid waste dumps

Attraction of pests to the waste dumps resulting in spread of disease vectors

General nuisance and odor.

To overcome these issues, the mitigation measures are required which include:

Collection of waste on daily basis from the colony houses and office premises of the plant

Placement of bins in the key area with proper labelling for the type of waste to be thrown in the bin

and segregation of waste

Awareness campaigns on municipal waste management including segregation, reuse and recycling

A properly designed landfill to cater for the plant needs will be developed.

1 Environmental Impact Assessment of Jamshoro Generation Project by Hagler Bailly Pakistan 2013

34

Page 42: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

5

1.2. Project Location

The JTPS is located north of Jamshoro town in the Jamshoro district of Sindh province, Pakistan. The

power plant is about 10 kilometer (km) northwest of Hyderabad and about 150 km northeast of Karachi.

It is located on N-55, also known as Indus Highway. N-55 is one of the two main highways of the country

which connect Karachi, the main port and industrial hub of the country, with the rest of the country.

1.3. Employer (Client)

Jamshoro Power Company Limited (JPCL), the implementing agency (IA) of the Project.

GENCO Holding Company Limited (GHCL), the parent company of JPCL will be the executing

agency (EA).

1.4. Engineer (Consultants)

Mott Macdonald Ltd in association with MM Pakistan Pvt Limited (The Project Implementation

Consultant)

1.5. Contractor

M/S MAJ-ICC (JV) Bungalow No.C-20, Qasimabad, Hyderabad, Sindh, Pakistan

35

Page 43: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

6

2. Activities that Have Been Undertaken During The Reporting Period

Following activities have been performed from January to June 2017.

Segregation of municipal solid waste at site

Awareness program

Water quality analysis

All these are discussed as under:

2.1. Segregation of Solid Waste at Site

As proposed landfill site has remained as a dumping site of MSW for thermal power house colony since

many years. At site, different components of MSW (such as glass, plastic waste, cloth waste wood

waste etc) have been found that have been segregated according to their nature and stored for further

usage as shown in Figure 2.1.

Figure.2.1 Segregation of different components of MSW

2.2. Awareness Program

Raising awareness about municipal solid waste management is a critical component of effective waste

management. It is important for key stakeholders to be aware of a city’s waste management activities

36

Page 44: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

7

and have a strong understanding of the benefits of proper solid waste management. Following are the

main objectives of awareness program.

To motivate the local people to practice 3Rs (Reduce, Reuse and recycle)

To develop the sense of commitment among people to protect the environment

To imbibe among people the essence of environmental values and ethics and live in harmony with

nature a God’s gift.

Awareness program regarding proper management of MSW was initiated among the residents of the

colony. Followings figures show the awareness regarding benefits of proper management of MSW and

draw backs of improper management of MSW.

(a)

(b)

(c)

(d)

37

Page 45: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

8

(e)

(d)

Figure 2.2 Awareness programs regarding proper management of MSW

2.3. Water Quality Analysis

Drinking and ground water quality were analysed as discussed below.

2.3.1. Drinking Water Quality

Water is one of the most essential elements to health and is so important that human body actually has

a specific drought management system in place to prevent dehydration and ensure survival. Water

might be everywhere, but one must never take it for granted. Water makes up more than two thirds of

human body weight, and without water, we would die in a few days. The human brain is made up of

95% water, blood is 82% and lungs 90%. Water serves as a lubricant in digestion and almost all other

body processes. Our bodies can control over-heating through perspiration from sweat glands in the skin

and from evaporation which produces a cooling effect. Blood is also routed into areas close to the

surface of the skin where it can be cooled and then carried back to the interior of the body. Conversing

in a cold environment, the skin maintains proper body temperature by shunting the blood away from the

exterior surface thereby conserving heat within the body. The movement of water within our cellular

systems also transports vital blood plasma which is 92% made of water. Blood plasma play a critical

role in buffering the body’s pH, circulating antibodies from the immune system, and regulating osmotic

balance which all helps to maintain proper body temperature. In this regard, drinking water quality was

analysed in order to meet international as well as national standard and World Health Organization

38

Page 46: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

9

(WHO) guidelines. Figure 2.3 shows the drinking water quality. At site, clean and fresh water is provided

to every worker. The result regarding water parameter are within the WHO guidelines.

Figure 2.3. Drinking water quality

39

Page 47: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

10

2.3.2. Ground Water Quality

Prior to start any project, it is very important to analyse ground water quality. Figure 2.4 shows the

ground water quality of the site.

Figure 2.4. Ground Water Quality

40

Page 48: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

11

3. Copies of All Environmental Monitoring Data And Checklists

Figure 3.1 and 3.2 represent the copies of all environmental monitoring data and checklist respectively.

(a)

(b)

Figure 3.1. Environmental Monitoring Data

(a)

(b)

(c) (d)

41

Page 49: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

12

Figure 3.2. Environmental Checklist

4. Detail of Any Environmental Incidents During The Reporting Period

Until no any environmental incident like spills, excessive emissions to atmosphere, water quality

contamination have been determined. Each and every thing is smoothly going on. At site pure drinking

water is provided to all workers. At site, all workers are satisfied and environment friendly atmosphere

is provided.

5. Any Other Documents and Relevant Data

At this stage, there is no any other documents and data relevant to the environmental and social

management of the project.

42

Page 50: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

13

6. Conclusions and Action Plan For The Next Period

6.1. Conclusions and Recommendations

During the reporting period, it has been concluded that project activities are environment smoothly

going. Until no any unpleasant event has been occurred. Awareness program initiated and it was

observed that residents of the colony are very much interested in proper waste management system.

Drinking water quality assessment show that water quality parameters were within the range of WHO

guidelines for water quality parameters.

6.2. Action Plan For The Next Period

Following activities would be performed during the next reporting period

Awareness programs

Instalment of dustbins

Collection of MSW

Transportation of MSW

Segregation of MSW at site

Drinking and ground water quality monitoring

Air quality monitoring

Noise pollution assessment during excavation work

43

Page 51: PAK: Jamshoro Power Generation Project · 2017-11-06 · C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017

Mott MacDonald | Jamshoro Power Generation Project 28(JPGP) Bi-Annual Monitoring Report, Jan-Jun 2017

334014-MML-JPCL-R-00599 | 31 July 2017C:\Users\ven71901\Documents\B334014 - Jamshoro\Temp\05 - Semi-annual environmental monitoring report January to June 2017 Final (3).docx

mottmac.com