Page 1
NFS DW Reporting Awareness Items
December 2011
Page 2
Reporting Awareness Items
Item Refer to:
WBS Structure Differences between PTA and DW See page 3
Timing of Accounting Information See page 4
Current Values and Month End Close Filters See page 5
PTA Awareness Items See page 8
Page 3
WBS Structure Differences
WBS # PTA DW
00000 Construction - Building Construction - Building
00000 Construction - Onsite Construction - Onsite
00000 Construction - Offsite Construction - Offsite
00000 Construction - Unique Construction - Unique
98200 IT Equipment IT Equipment
91000 Professional Fees Professional Fees
91500 Built in Equipment Builtin Equipment
90000 Land/Building Purchase/Disposition Site Acquisition
95500 Imaging Equipment Imaging Equipment
99000 Recharges Proj Mgmt Recharge
97000 Artwork & Plants Artwork/Plants
98000 IT Cabling & Labor IT Cabling + Labor
93000 Contingency Contingency
94000 Construction Escalation Escalation (Constr.)
94000 Equipment Escalation Escalation (Eqpt.)
95000 Equipment Moveable Equipment
92000 Owner's Misc. Misc. Owner's Cost
96000 Furnishings Furnishing
99500 Tenant Improvement Allowances Offset for TI Allowance
Page 4
Timing of Accounting Information
Timing of Accounting Information should be taken into account when creating or interpreting reports. Data which comes from Accounting systems to the NFS DW through PTA will be 2 days old when displayed in the Reports.
Example:Day 1: Accounting commitment and expenditures are loaded into PTA on a nightly basis.
Day 2: Accounting commitment and expenditures are then loaded from PTA to the NFS Data Warehouse.
The timing of the nightly loads should be taken into consideration when creating and reviewing reports. The NFS DW team will be working on incorporating data directly from the accounting systems in future phases.
Page 5
Current Values and Month End Close Filters
1. Since the NFS Data Warehouse retains historical values, while creating ad-hoc reports please add “Current Value” Filter to the Query Filter Pane when using Objects from the following classes:
Project Cost Sheet Values Project Revisions Values Contract Values Invoices Values Schedule Values Acct Expenditures Values Account Commits Values See page 8 for the “Current Value” Filter
2. The “MEC” filter has been created for easy Month-End-Close reporting. This will only apply to Project Cost sheet and Contracts Classes. See page 9 for “MEC” Filter
Page 6
“Current Value” Filter
Add “Current Value” Filter to Query Filter Pane as shown.
Page 7
Month End Close (“MEC”) Filter
Add “MEC” Filter to Query Filter Pane as shown.
Page 8
PTA Awareness Items
These items only impact only PTA.1. The “Current Budget Authorized to Spend” shows authorized dollars,
but these dollars have not been approved to spend for QI projects (Place holder projects).
2. The PTA NFT report shows the rollup project target budget whereas the DW NFT report shows the project target budget. As a result the forecast variance (target budget – current forecast) will differ.
3. The PTA CQE report will show a 0 amount for original budget, when in fact there is an actual amount in the project. The DW CQE report shows the actual amount as expected.
4. The PTA CME report will show some service areas as REG. The DW CME report will show the correct service area name.
5. In PTA’s NFT report, projects that are Cancelled or Final Closeout phase and the expenditure and target budget are $0, the project is omitted from the report. The DW NFT report will include these projects.
6. Vendor Evaluations created prior to May 2, 2011 are not available in the DW. Prior to this date, evaluation data was not required in PTA.