FOLLOWING THE BELOW PPM CHECKS & FINDINGS, CONTRACTOR IS TO REPORT DERIVED
FINDINGS & IMPLEMENT CORRECTIVEACTIONS AS PART OF EACH VISIT, :
DESCRIPTION OF PPM CHECK VISIT 1 # 2 # 3 # 4
POWER
CHECK MAIN POWER TO EQUIPMENT
PERFORM VOLTAGE IMBALANCE CALCULATION (see below)
PERFORM MEGGAR TEST ON ALL COMPRESSOR MOTORS
CHECK CONTACTORS CONTACT POINT AND REPLACE WHERE NECESSARY
CHECK MOTOR AMPERAGE AS AGAINST FLA AND VOLTAGE
CHECK STARTER/ WIRING CONNECTIONS
CHECK STARTER OPERATION
CONTOLS
CHECK CONTROL POWER
CHECK MICROPROCESSOR AND RECORD DATA
CHECK CHILLER SAFETY/ OPERATING CONTROLS
Thermistors and pressure transducers functioning in conjunction with the control system to provide the unit
with the following protections- Loss of refrigerant charge protection, Low water flow detection, Lowchilled water temperature protection, Low and high superheat protection, Low oil protection for each
compressor, Low control voltage to unit protection, Ground current protection for each compressor,Compressors protections against Pressure Overload & Electrical overload. Diagnostic display for all alarms
and set points
REF
RIGERANTCIRCUIT
CHECK REFRIGERANT CHARGE by superheat and sub-cooling temperatures
CHECK EXPANSION VALVE FUNTIONING & STATUS
LOG EVAPORATOR REFRIGERANT TEMP
EVAPORATOR REFRIGERANT APPROACH TEMP
LOG EVAPORATOR PRESSURE
CHECK REFRIGERANT LIQUID GLASS (IF CLEAR )
CHECK FOR ANY LEAK IN REFRIGERANT SYSTEM AND OIL SIDE
LOG CONDENSER REFRIGERANT TEMP
LOG CONDENSER PRESSURE
LOG CONDENSER SUBCOOLER PRESSURE
CHECK FOR RESTRICTION ACROSS DRIER CORES & REPLACE WHERE REQUIRED
CONDENSER LOG ENTERING CONDENSER AIR TEMPERATURE (ON-COIL AIR TEMP)
LOG LEAVING CONDENSER AIR TEMPERATURE (OFF-COIL AIR TEMP)
CHECK CONDENSER FANS FOR CLEARANCE AND ALIGNMENT, BLADES STATUS
LUBRICATE FAN MOTOR BEARINGS ( IF BEARINGS ARE OPEN TYPE)
OIL
LOG OIL LEVEL
LOG OIL PRESSURE
PERFORM OIL ANALYSIS
CHILLEDWATER
LOG CHW FLOW DELTA P
LOG CHW PUMP DELTA P
LOG CHW TEMP
LOG LEAVING CHW TEMPERATURE
LOG ENTERING CHW TEMPERATURE
PERFORM CHW ANALYSIS AND ADVISE RECOMMENDATIONS
-
8/10/2019 Page 07 - Appendix 3 0
3/3
CALIBRATE CHW FLOW SWITCH ( IF NOT ELECTRNIC TYPE )
INSPECT CHW PIPE LINE/ CLEAN STRAINERS
DETECT AND REPORT ANY SIGNS OF CORROSION
CHECK PAINTWORK AND APPLY NEW IF NECESSARY
GENER
AL
REVIEW AND EVALUATE LOG READINGS
CHECK GENERAL OPERATION
The above PPM Checks shall specifically & categorically comprise the below details:
1. Submit the details of No of Compressors failed, complete with Mean Time to Repair & MeanTime between Failures.
2. Status of Filter/Drier core replacement
3. Status of oil test & replacement based on findings4. Status of Expansion valve functioning
5. Additional Refrigerant topping up where identified/applicable
6. Purging where identified/applicable
7.
Based on the previous track history of repeated Compressors failure frequency, performEddy current testing to (once in five years) to detect tube degradation such as pits,
cracks, or wall loss over time & subsequent moisture entry into compressors.8. Submit Maintenance program Accomplished Vs Planned
9. Prevention of Motor overheat by means of internal temperature sensors
10.Prevention of Motor overload
11.Condenser fan & motor replacements status12.Thermistors & Transducers functioning & set-points verification (details are to be
submitted)
13.Assign qualified Maintenance personnel (approval is to be obtained from AccountManager) to identify and initiate PPM works based on the findings from the equipment
history & current status and to carry out Verification & Validation of Maintenance worksis to be carried out.
14.Resource details (Planned Vs Actual site status) are to be submitted15.Method statements are to be submitted