P5: UJ56 Relocation Study Contributions from BE -ABP -ASR -BI -CO DG -RP EN -CV -EL -MEF -STI GS...

49
P5: UJ56 Relocation Study Contributions from BE -ABP -ASR -BI -CO DG -RP EN -CV -EL -MEF -STI GS -SEM -ASE IT -CSPH -CMX TE -CRG -EPC -MPE 09/06/2010 1 [email protected]

Transcript of P5: UJ56 Relocation Study Contributions from BE -ABP -ASR -BI -CO DG -RP EN -CV -EL -MEF -STI GS...

[email protected] 1

P5: UJ56 Relocation StudyContributions from

BE -ABP -ASR -BI -CO

DG -RP EN -CV -EL -MEF -STI

GS -SEM -ASE

IT -CS PH -CMX TE -CRG -EPC -MPE

09/06/2010

[email protected] 2

Project overview and scope

Current knowledge:→ Expected levels of radiation in UJ56 are known→ Shielding along the LHC side of the tunnel will not provide a long

term solution to avoid single event upset in the electronics systems installed in the UJ56

→We cannot wait until the second long shutdown (~2014) without major risks to the electronics

→ Relocation of equipment has to be considered

Purpose of study:→ Identify what can be done during the next shutdown in 2012→ Identify potential showstoppers

09/06/2010

[email protected] 3

What equipment is at risk?

09/06/2010

Gnd floor:Infrastructure electronics for EN-EL,EN-CV and GS-ASE

S Maridor EN-MEF

[email protected] 409/06/2010

Power converters

24 racks

What equipment is at risk?

S Maridor EN-MEF

[email protected] 5

→ First attempt – build a shielding wall on the tunnel side of the UJ56→ Initial assessment made in 2009 and presented on Feb 9th 2010.

09/06/2010

Is there any quick fix?... No

Shielding Effectiveness:

- Ground floor: ~10

- First floor: ~2Without shielding With shielding

© R. Versaci et al.

[email protected] 6

→Goal: Find a permanent solution to relocate the electronics currently in the UJ56 during the 2012 shutdown

→Limitation: For some equipment the cable length is critical (compensators)

→Priority: Racks located on the first floor should be taken care of first since they are the most vulnerable

→Asset: CMS has offered to assist in finding space in its experimental area

→Synergies: Opportunity to improve accessibility to equipment during operation

09/06/2010

Introducing the relocation effort

[email protected] 709/06/2010

Proposal

→Move sensitive equipment from 1st floor and GND floor→Use the UJ561 personnel galley as much as possible

→ Choice of escape route for CMS/LHC personnel to be revisited

→Use parts of the USC55 when needed→Use UL55 Bypass tunnel when needed

[email protected] 809/06/2010

Scenarios

→Common approach: use the UJ561 and USC55 S4→ 3 options for the CMS escape route

→Scenario A: use space UL55 bypass tunnel in addition→Scenario B: use space in USC55 control room in addition

S4 CTRLUJ561

UL55

[email protected] 909/06/2010

Investing the space in UJ561

→Step 1: Assess what pieces of equipment need to move

All power converters17 racksSome racks will stay, others will be merged or eliminated

[email protected] 1009/06/2010

Investing the space in UJ561

→Step 1: Assess what equipment needs to move

5 Components of the safe room targeted for relocation in the UJ561

[email protected] 1109/06/2010

Investing the space in UJ561

→Step 2: suggest a layout

Philippe Orlandi, JC Guillaume, N Dos Santos [EN-EL]

Equipment organised by cable lengthlimitations

New safe room

Rack AreaPower converters

Evacuating the UJ561 might require new openings to the Bypass

[email protected] 1209/06/2010

Investing the space in UJ561

RQX.R5

RTQX2.R5

RYCA01-02

GYPOS 01 à 03

DYPG01 & 02CYCIP01

CYNET01EYC01 à 03

EYU01 – EYP01

RYMCB01 à 05

RYLB01RYLC01RYSC01

→Step 3: Assign location to equipment

Philippe Orlandi, JC Guillaume, N Dos Santos [EN-EL]

[email protected] 13

→Remarks:→ If adequately equipped, UJ561 could be accessible

through the USC55 at all times→Sectorisation scheme would have to be revisited→Space left between the power converters and the wall

is ~1m. →Cooling will require demineralised water→Ventilation scheme would include fan coils with a

chilled water link→New cable tray capacity will have to be found→ Cable ducts to be created using coring techniques

→ Impact on the CMS escape route to be assessed09/06/2010

Investing the space in UJ561

[email protected] 1409/06/2010

Insertion of service ducts through coring

Cooled cablesCtrl cables

DC Power cables

Bottle neck Ø=350mmL<12m

From 1st floor

[email protected] 1509/06/2010

Alternative to study for water cooled cablesLength ~ 15m, Ø=350mmSimilar jobs were done between UA and RA

UP56UJ56

1st floor

2nd floor

Insertion of service ducts through coring

If excavation could start from bypass:Better for scheduleAllows work in UP56 in parallel

[email protected] 16

→Feasibility studies will have to be carried out by GS-SEM→ Impact on neighbouring equipment to be assessed→ Impact on overall schedule to be assessed

09/06/2010

Insertion of service ducts through coring

[email protected] 17

→3 options should be considered1. Keep the CMS escape route going through the UJ561

- Presence of flammable material- Small clearance between equipment and wall ~1m- Escape route would go through a safe room No need for civil engineering Identical to existing path

09/06/2010

CMS escape route – Option 1

[email protected] 18

→3 options should be considered2. Use the UL55 Bypass as escape route

- More complicated and longer escape path- Less favourable for ALARA (breezing of potentially

activated air) Limited need for civil engineering work No need to enter the UJ561

09/06/2010

CMS escape route – Option 2

[email protected] 1909/06/2010

CMS escape route – Option 2

J Bos PH-CMX

New blast door

[email protected] 20

→3 options should be considered3. Create a new escape gallery Width >1.2m Height=2.3m

- Civil engineering work required for ~ 3 months- Insertion in PM56 to be defined Shorter and safer escape route Fully compliant with standard emergency routes

09/06/2010

CMS escape route – Option 3

[email protected] 21

UXC55

USC55

Pillar WallUPX56

Shelter

PM56

09/06/2010

UP56

UJ561

UJ561?

A

BC

UJ56

3 routes considered at firstOnly limited tooling can be used

CMS escape route – Option 3

[email protected] 2209/06/2010

CMS escape route – Option 3.a

Formal request from CMS to consider a different position for the junction galleryThe new gallery should not introduce any risk to compromise the classificationof the USC55 as a non designated area

Meeting with DG-RP (S Roesler) on 27/05@14:00Possibility that the new junction gallery could introduce RP risk in the USC55No time to produce simulations before the workshop

JP Corso EN-MEF

[email protected] 23

B

09/06/2010

CMS escape route – Option 3.b

Services difficult to relocate

[email protected] 2409/06/2010

CMS escape route – Option 3.c

CV equipmentTo relocate for

R2E

BRAN GasCan be moved

6.92m

J Bos PH-CMX

[email protected] 25

→Connection of route3 inside the UJ56 allows keeping most of the services in place

09/06/2010

CMS escape route – Option 3.c

J Bos PH-CMX

[email protected] 26

→Remarks:→CMS would like route 3.c to become the baseline→ Impact of CE work on the overall work sequence to be assessed

→Where should the excavation start from?→How to remove the spoil? →How to ventilate the work site?→How to seal off CMS and sensitive equipment in the UJ56?

09/06/2010

CMS escape route

Likely configuration of CMS during the 2012 shut down

[email protected] 2709/06/2010

Relocation in USC55 S4

TYCFL02

DYXF01

YYACS01RYSA01 - 02

CYCIB01

→ Some rack users wish to group their electronics in the USC55 S4

Philippe Orlandi, JC Guillaume, N Dos Santos [EN-EL]

[email protected] 2809/06/2010

Relocation in USC55 S4

S Maridor EN-MEF

Link between Bypass andUSC55 is nearing saturationBut should still be OK

S4 area is part of the USC55AUG network

[email protected] 29

→ In addition to the UJ561 and the USC55S4 area, the UL55 bypass would be used. Because of the existing cable trays, smaller racks would have to be used- Equipment installed there would not be available during operation- Using space for future upgrade projects+ No need for additional CE work+ Work in an area relatively empty

09/06/2010

Relocation scenario A

[email protected] 3009/06/2010

ERD1/56

EOD1/56 - EOD3/56

EBS1/56 - UPS machine

QYC01 - 03

RYSA01- 02

CYTIM01 – CYFRE01

Relocation scenario A

Philippe Orlandi, JC Guillaume, N Dos Santos [EN-EL]

[email protected] 31

→ In addition to the UJ561 and the USC55S4 area, the USC55 control room area would be used

- Need for new metallic structures- Need for 1 service duct (CE work) between UJ561 and USC55- Additional mixing of LHC/CMS networks (already the case in S4)+ Equipment available at all times+ Work on the metallic structures could be done during operation => no

penalty for schedule+ Space in Bypass remains available for future projects such as inner

triplet upgrade+ Synergies with CMS upgrade programs

09/06/2010

Relocation scenario B

[email protected] 3209/06/2010

LHC EL

ROOM

6 LH

C ra

cks

Relocation scenario B

JP Corso EN-MEF

[email protected] 3309/06/2010

[email protected] 3409/06/2010

A second emergency exit has to be foreseen for theEvacuation of personnel in the new control room

[email protected] 3509/06/2010

[email protected] 3609/06/2010

→Whatever scenario is chosen the UJ56 will still host some equipment→Radiation Hard or Radiation Tolerant→The space freed by the relocation will allow the

erection of a shielding wall inside the UJ56, possibly with a roof

→Such a wall might not be needed after all, depending on tests to be performed on EN-EL equipment at CNGS

State of the UJ56 after relocation

[email protected] 3709/06/2010

State of the UJ56 after relocation

Work method to be used to assemble the shielding wall still to be designed

[email protected] 3809/06/2010

ESD2/56ESD3/56

ESD1/56

Commutation et distrib. 48 Vdc

Chargeurs et bat. 48 Vdc

4 racks patch pannel

Tabl. HT 18 kV

Transfo 18/.4 kV

EBD1/56

EBD2/56EAD1/56

Ep. 1 m

State of the UJ56 after relocation

Philippe Orlandi, JC Guillaume, N Dos Santos [EN-EL]

State of the UJ56 after relocation

→During relocation work, essential services would be powered through temporary switchboards installed on the 1st floor of the UJ56

Space left free by relocation of Power Converters

[email protected] 4009/06/2010

State of the UJ56 after relocation

→Should all equipment in the safe room be made radiation tolerant or be relocated, substantial cost saving would be made on both the inner and outer shielding of the UJ56

[email protected] 4109/06/2010

Remaining issues to study

→Installation/construction methods and impact on schedule/cost→Shielding wall→CE work gallery/ducts→CV work (Water cooling and ventilation)→Cable tray capacity

→Impact of work on CMS & LHC (loss of services, dust..)

→Requests of a few racks owners

[email protected] 4209/06/2010

ID Task Name Duration

1 Install cooling pipes in UJ561 (demi and chilled water) 6 wks

2 Prepare removal Power Converters from UJ56 1st floor 30 days

6 Prepare UJ561, UL55 and USC55 for relocation 40 days

12 Move Power Converters to UJ561 10 days

15 Install cables for UPS/ERD/Pcters 20 days

16 Install and connect cables to UPS and Power Converters 4 wks

17 Install and connect cables to control racks (AU, switchboards…) 4 wks

18 Prepare UJ56 for reorganisation 20 days

19 Remove cables linked to Ctrl protection and Survey 4 wks

20 Prepare relocation of EL safe room 30 days

21 Install temporary switchboards in UJ56 1st floor 6 wks

22 Install short cables between switchboards 6 wks

23 Connect temporary switchboards 6 wks

24 Switch on temporary switchboards 6 wks

25 Remove existing equiipment in safe room 6 wks

26 Build shilding wall 6 wks

27 Excavate escape gallery + coring jobs 12 wks

28 Build new UJ56 saferoom 20 days

29 Erect new partit ion walls 2 wks

30 Modify false floor 2 wks

31 Reinstall safe room in UJ56 40 days

32 Install cable trays 8 wks

33 Install new switchboards 8 wks

34 Install cables to new switchboards 8 wks

35 Switch on new switchboards 8 wks

36 Form service ducts 8 wks

37 Install ctrl and DC cables 100 days

38 Install ctrl and DC cables between UJ56 and UJ561, UL55 and USC55 20 wks

39 Install patch panels in UJ56 racks (not relocated) 20 wks

40 Install connectors 20 wks

41 Commiss ion new cables + connectors 20 wks

42 Install cooled cable trays 30 days

43 Install cable supports 6 wks

44 Install cooled cables + test 6 wks

45 Commiss ion full system 6 wks

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug SepQtr 4, 2011 Qtr 1, 2012 Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 2013 Qtr 3, 2013

Very first draft time estimates

Time window for CE and shielding work

Total EN-EL work ~ 14.5 Months CE gallery ~ 3 months

[email protected] 4309/06/2010

Very first draft time estimates

→Once the work methods will have been designed, opportunities to work in parallel could emerge.

→Many pieces of information are still missing. This prevents the design of a reliable schedule.

→It looks reasonable to assume that the work could not take less than 15 months.

[email protected] 4409/06/2010

Very first draft cost estimates

→EN-EL work: ~ CHFM2.3→Not including work to be done by other service groups

contributing to the relocation of EN-EL equipment→GS-SEM work:→Escape gallery: < CHFM1→Service ducts: CHF4,000/m→E.g: 15m link between UJ56 and bypass = CHF60,000

→Costs of fire doors, smoke detection, metallic structures, cooling and ventilation, re-commissioning still not assessed

[email protected] 4509/06/2010

Summary

→The relocation program at point 5 is a major undertaking.

→It will remain a cross department effort→It will be a multimillion CHF project→It will be difficult to fit it into a 1 year shutdown→Many pieces of information are still missing→Defining a baseline scenario is urgently needed to

focus the few resources available on detailed studies

CERN, February 9th Extended R2E Seminar & Workshop PreparationCERN, February 9th Extended R2E Seminar & Workshop Preparation

F. DELSAUX

ENVIRON 18 MHT LIBRE 2600 mm

CHICANE

UJ56

1500

R562

VERS UJ56

VERS UJ57

UJ56 Shielding Option

46

CERN, February 9th Extended R2E Seminar & Workshop PreparationCERN, February 9th Extended R2E Seminar & Workshop Preparation

BLINDAGE UJ56

MUR FIXE ACIERHAUTEUR 2000mm

COMPLEMENTBRIQUETTES ACIERHAUTEUR 600mm

BLINDAGE ACIERDEMONTABLEEP. 400mmHAUTEUR 2000mm

MONORAIL

RAIL DE MANUTENTIONDES BLOCS DE BLINDAGE

300mm

800mm

300mm

400mmxz view

UJ56 Shielding Option

F. DELSAUX

47

Added shilding

CERN, February 9th Extended R2E Seminar & Workshop PreparationCERN, February 9th Extended R2E Seminar & Workshop Preparation

xz view

UJ56 Shielding OptionAssuming 1 year of operation at nominal luminosity (100 fb-1)

Shielding Effectiveness:

- Ground floor: ~10

- First floor: ~2

Upstream weak-point could be improved, so could be the maze … BUT

48

© R. Versaci et al.

CERN, February 9th Extended R2E Seminar & Workshop PreparationCERN, February 9th Extended R2E Seminar & Workshop Preparation

Assuming 1 year of operation at nominal luminosity (100 fb-1)

Shielding Effectiveness:

- Ground floor: ~10

- First floor: ~2

w/o shielding

UJ56 Shielding Option

with shielding

1st Floor-Shielding can hardly be improved

-> First Floor Critical

49

© R. Versaci et al.