This project involves a new 42,223 square foot, single-story,
tilt wall building for use as a K-8 school. The school is being
constructed on 5.25 acres in Denver, North Carolina.
PROJ ECT GOAL S:
1. Ensure the low voltage contractor is providing
the equipment, per RAD specifications
2. Manage the CSUSA –RAD turnover dates
effectively to eliminate delays
3. Closely monitor the amount of exported dirt
from the site.
4. Ensure VCT and base finishes meet RAD
expectations
• Project Size: 42,223 SF
• Project Type: Education
• Project Amenities/Features:
o Fenced Playfield
o Canopy Playground
o Gym/Multi-Purpose Room
o Collaborative Classrooms
o Music, Science and Art labs
Project Description & Goals
Executive Summary – Key Highlights
PROGRESS UPDATE
• Started Site Paving
• Started Ceiling Tile Install
• Started MP Room Lighting
• Continue Plumbing Fixture Install
• Continue Irrigation Install
• Complete Restroom Accessories
Executive Summary – Key Highlights
UPCOMING ACTIVITIES & MILESTONES
• Complete Site Paving
• Complete Striping and Signage
• Complete Plumbing Fixture Install
• Complete Ceiling Tiles
• Complete Interior Paint
• Complete Electrical Install
• Complete Irrigation Install
• Begin Landscape Install
Insert Caption Here – Adjust Box as Needed
Loop Road Asphalt Complete Ceiling Grid and Hallway Lights
Insert Caption Here – Adjust Box as Needed
Exit Lights and Ceiling Grid Ceiling Tile Install Started
Construction Team
Eric OtradovecProject Manager I
Phone: [email protected]
Mike Migliaccio Jr. Superintendent
Phone: [email protected]
Bill BrandSuperintendent
Phone: [email protected]
Scott StenmanVice President of Construction
Phone: [email protected]
Brad HillDirector of Construction
Phone: [email protected]
John BentleyRegional Field Coordinator
Phone: [email protected]
Chantel NitzkorskiSenior Project Coordinator
Phone: [email protected]
Design Team
Richard LoseeProfessional Engineer – LAI Design Associates
Phone: [email protected]
Aaron MaagPrincipal – Jenkins Maag Associates
Phone: [email protected]
Ken PalczykEngineer – Jenkins Maag Associates
Phone: [email protected]
Steve GrinavicDesign Engineer – LAI Design Associates
Phone: [email protected]
Jeff JenkinsAssociate – Jenkins Maag Associates
Phone: [email protected]
Corey Solich
Phone: [email protected]
Chris BosticP.E.
Phone: [email protected]