OVERVIEW OF ELECTRIC POWER INDUSTRYjaime.addu.edu.ph/wp-content/uploads/2015/06/Atty-Lotillas...BOT...
Transcript of OVERVIEW OF ELECTRIC POWER INDUSTRYjaime.addu.edu.ph/wp-content/uploads/2015/06/Atty-Lotillas...BOT...
OVERVIEW OF ELECTRIC POWER INDUSTRY
PRE-EPIRA
NPC
Generation
+
Transmission &
Sub transmission
Distribution
Utilities
End-users
State
monopoly of
Generation &
Transmission
of electricity
sells b
uys
sells
buys
NPC
IPPs
buys
sells
Private
monopoly
within
franchise
area
No power
to choose
source of
electricity
OWNERSHIPREGULATORY REGIME
(Energy Regulatory Board)
Bundled
Tariff
Regulated
Price
Setting
Bundled
Tariff
Regulated
Price
Setting
Bundled Tariff
E. O. 215
BOT Law
IPPsbuys
sells
Source: PSALM
THE NEW ELECTRIC POWER INDUSTRY
STRUCTURE UNDER EPIRA
•Sale of NPC
generation assets
•Unbundling of electricity tariffs for
transparency
•Opening up of high voltage t- lines for easy access of
distributors & large consumers
•Opening up of distribution lines for competitive consumers
Source: Department of Energy
Firm dates of Open Access implementation is crucial to spur investment and competition
Delays in implementation pushed generators to contract with MERALCO instead of reserving for Open Access
Congress passed EPIRA
Declare initial Implementation of Open Access
1MW & Up 750KW
Implementation of RCOA to EC’s
Gradual decrease in threshold until it reaches the households
1st Declaration of Open Access
Initial Commercial Operations (1MW & up)
Start of Customer Switching
2nd Declaration of Open Access
As stated in the R.A
Actual Timeline of RCOA Implementation
Retail Competition and Open
Access
Congress passed EPIRA.
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
May 26, 20155
EPIRA IS WORKING
2014 Capacity MixLUZON VISAYAS MINDANAO
BASE LOAD
POWER
PLANTS:
67.48%
BASE LOAD
POWER
PLANTS:
75.34%
BASE LOAD
POWER
PLANTS:
51.43%Note:• Baseload Power Plants are the facilities used to meet some or all of a given continuous energy demand, and produce energy at a constant
rate, usually at low cost relative to other facilities available to the system
Source: DOE list of Existing Power Plants, December 2014
Dependable Capacity = 11,622 MW
Dependable Capacity = 2,160 MW
Dependable Capacity = 1,851 MW
BASE LOAD
CAPACITY:
66.91%
BASE LOAD
GENERATION:
85.40%
2014 Dependable Capacity = 15,633 MW 2013 Gross Generation = 75,266 GWh
Capacity and Generation
Self Sufficiency = 56.24 %
PHILIPPINES
Source: DOE list of Existing Power Plants, December 2014DOE Power Statistics 2013
POWER SUPPLY SITUATION
AND OUTLOOK
8
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
11,000
1-J
an
3-J
an
5-J
an
7-J
an
9-J
an
11-J
an
13-J
an
15-J
an
17-J
an
19-J
an
21-J
an
23-J
an
25-J
an
27-J
an
29-J
an
31-J
an
2-F
eb
4-F
eb
6-F
eb
8-F
eb
10-F
eb
12-F
eb
14-F
eb
16-F
eb
18-F
eb
20-F
eb
22-F
eb
24-F
eb
26-F
eb
28-F
eb
2-M
ar
4-M
ar
6-M
ar
8-M
ar
10-M
ar
12-M
ar
14-M
ar
16-M
ar
18-M
ar
20-M
ar
22-M
ar
24-M
ar
26-M
ar
28-M
ar
30-M
ar
1-A
pr
3-A
pr
5-A
pr
7-A
pr
9-A
pr
11-A
pr
13-A
pr
15-A
pr
17-A
pr
19-A
pr
21-A
pr
TOTAL AVAILABLE CAPACITY SYSTEM PEAK DEMAND REQ'D REG. RESEREVE
Luzon Supply-Demand Situation01 January – 21 April 2015
Source: National Grid Corporation of the Philippines (NGCP) Daily Operations Report
Note:
FO – Forced Outage / PO – Planned Outage
B2 fuel – diesel with 2% biodiesel
JAN FEB MAR APR
Max Demand
= 8,727 MW (20 Apr)
Demand = 5,539
MW
Papal Visit
(15-19 Jan 2015)
GNPower U1 (302 MW) on
FO from 26 Oct 2014 - 15
Mar 2015GNPower U2 on PO from
29 Dec 2014 -23 March
2015
Min Demand
= 4,659 MW (01
Jan)
New Year
Ilijan A2 (300 MW) on FO
from 23 Dec 2014 to 24 Feb
2015
QPPL (456 MW) on PO from
17 Jan – 4 Mar 2015
Malampaya
Turnaround
15 Mar – 13 Apr 2015
Ilijan A2 on FO from 14-20
Mar 2015
5,314 MW (3 Apr)
Good Friday
Ilijan A (600 MW) limited at 385 MW running using
B2* fuel; Ilijan B (600 MW) on PMS from 15 Mar-
13Apr 2015 (extended to 15 Apr 2015)
Sual Units 1 and 2 tripped
on 13 Mar 2015
2015Mar: 10 MW Pampanga Solar*
135 MW SLTEC Puting Bato U1*18 MW Pililia Wind P1 18 MW IBEC Bio
Apr: 18 MW Pililia Wind P240 MW Majestic Solar****
May: 18 MW Pililia Wind P3
2018Jun: 460 MW SBPL**
1 MW Bulanao
HEPP***
1 MW Prismc HEPP***
2015Jun: 150 MW SLPGC Coal U1
82 MW Anda Coal100 MW Avion****
Aug: 150 MW SLPGC Coal U2Sep: 13.2 MW Sabangan HEPPOct: 12.5 MW Bataan CogenNov: 150 MW SLTEC Puting Bato Coal U2Dec: 3.2 MW Bicol Biomass
12 MW Green Innov Bio
LUZON SUPPLY-DEMAND OUTLOOK 2014-
2020
Notes
a. Required Reserve Margin (RM) i.e. 4% regulating reserve and contingency and dispatchable reserve requirement
b. 4.2 % peak demand growth rate resulted from observed 0.6 elasticity ratio of demand for electric power with national economic growth
applied to 7 percent GDP growth rate (GR) target for 2014-2015.
c. 4.8 % peak demand growth rate resulted from observed 0.6 elasticity ratio of demand for electric power with national economic growth
applied to 8 percent GDP growth rate (GR) target for 2016-2020.
d. Assumed average forced outage of the total available capacity
Actual
** for Validation
*** TBD – To be determined (target commercial operation)
****: 100 MW Avion and 40 MW Majestics considered as additional
capacity (not in the committed power projects)
* On-going testing and commissioning
2016Jun: 450 MW San Gabriel NGAug: 150 MW Limay Coal U1Dec: 12 MW SCJIPower Bio P2
Newly-Operational150 EDC Burgos P1 and P2
12 MW SJCIPower Bio P1
18.9 MW NWPDC Wind Ph3
81 MW Caparispisan Wind
2017Nov: 420 MW Pagbilao 3
150 MW Limay Coal
U2
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
(%) 1.5 2.0 2.0 6.3 5.6 7.5 7.5 2.8 5.2 6.9 7.2 3.1
MW 167 230 631 712 642 858 856 316 595 779 808 348
10
Name of the Project Project Proponent Mother/ JV Company Location Rated Capacity (MW)Target Testing &
Commissioning
Target
Commercial
Operation
Puting Bato Coal Fired Power
Plant Phase I**
South Luzon Thermal
Energy Corp. (SLTEC)
Trans Asia Oil and
Energy Development
Corporation (TAOil)
Brgy. Puting Bato
West, Calaca,
Batangas
135.0 Oct 2014 Mar 2015
SLPGC Coal-Fired Power Plant
Phase I Unit 1
Southwest Luzon
Power Generation
Corporation (SLPGC)
DMCI Power
Corporation
Brgy. San Rafael,
Calaca, Batangas150.0 Apr 2015 Jun 2015
Anda Power Corporation's 82
MW Ciculating Fluidized Bed
Coal Fired Power Plant
Anda Power
Corporation
Anda Power
Corporation
Brgy. Bundagul,
Mabalacat,
Pampanga
82.0 Jun 2015 Jun 2015
SLPGC Coal-Fired Power Plant
Phase I Unit 2
Southwest Luzon
Power Generation
Corporation (SLPGC)
DMCI Power
Corporation
Brgy. San Rafael,
Calaca, Batangas150.0 Jun 2015 Aug 2015
Puting Bato Coal Fired Power
Plant Phase II
South Luzon Thermal
Energy Corp. (SLTEC)
Trans Asia Oil and
Energy Development
Corporation (TAOil)
Brgy. Puting Bato
West, Calaca,
Batangas
135.0 Aug 2015 Nov 2015
Limay Power Plant Project
Phase I Unit 1
SMC Consolidated
Power Corporation
SMC Consolidated
Power Corporation
Brgy. Lamao,
Limay, Bataan150.0 May 2016 Aug 2016
Limay Power Plant Project
Phase I Unit 2
SMC Consolidated
Power Corporation
SMC Consolidated
Power Corporation
Brgy. Lamao,
Limay, Bataan150.0 Oct 2016 Jan 2017
Pagbilao 3 Coal-Fired Thermal
Power Plant
Pagbilao Energy
Corporation
TeaM Energy / Aboitiz
Power
Pagbilao Power
Station, Nrgy.
Ibabang Polo,
Pagbilao, Quezon
420.0 May 2017 Nov 2017
San Buenaventura Power Ltd.
Co. (SBPL) Project***
San Buenaventura
Power Ltd. Co. (SBPL)QPPL/EGCO Mauban, Quezon 460.0 Mar 2018 Jun 2018
20 MW IBEC Biomass Power
Plant
Isabela Biomass
Energy Corporation
(IBEC)
Isabela Biomass
Energy Corporation
(IBEC)
Isabela 18.0 Mar 2015 Mar 2015
12.5 MW Bataan 2020 Rice
hull-fired Cogen PlantBataan 2020 Inc. Bataan 2020 Inc. Bataan 7.5 Oct 2014 Oct 2015
3.5 MW Bicol Biomass Energy
Corporation
Bicol Biomass Energy
Corporation
Bicol Biomass Energy
CorporationCamarines Sur 3.2 Dec 2015 Dec 2015
COMMITTED POWER PROJECTS
* Excluding Off-grid power projects** On-going testing and commissioning
As of 31 January 2015
Luzon Grid Committed Power Projects, 2,410.7 MW*
*** for validation
11
COMMITTED POWER PROJECTS
Luzon Grid Committed Power Projects, 2,410.7 MW*
As of 31 January 2015
* Excluding Off-grid power
projects
Name of the Project Project Proponent Mother/ JV Company Location
Rated
Capacity
(MW)
Target Testing &
Commissioning
Target
Commercial
Operation
12 MW GITC Biomass Power
Plant Project
Green Innovations for
Tomorrow Corporation
(GITC)
Green Innovations for
Tomorrow Corporation
(GITC)
Nueva Ecija 10.8 Dec-2015 Dec 2015
12 MW SJCiPower Rice Husk-
Fired Biomass power Plant
Project Phase 2
San Jose City I Power
Corporation
San Jose City I Power
Corporation
Brgy. Tulat, San
Jose, Nueva Ecija10.0 Dec 2016 Dec 2016
San Gabriel Plant Phase II First Gas Power Corp.First Gen Power
Corporation
San Gabriel,
Batangas450.0 Mar 2015 Jun 2016
Pampanga Solar Power
Project**Raslag Corporation Raslag Corporation
Brgy. Suclaban,
Mexico, Pampanga10.0 Feb 2015 Mar 2015
Sabangan HEPP Hedcor Sabangan, Inc.Aboitiz Power
CorporationMt. Province 13.2 Jun 2015 Sep 2015
Bulanao HEPPDPJ Engineers and
ConsultantsTabuk, Kalinga 1.0 TBD TBD
Prismc HEPP PNOC-Renewables
CorporationPNOC Rizal, Nueva Ecija 1.0 TBD TBD
Pililla Wind Power Project
Ph1
Alternergy Wind One
CorporationAlternergy
Brgy. Halayhayin,
Pililla, Rizal18.0 Mar 2015 Mar 2015
Pililla Wind Power Project
Ph2
Alternergy Wind One
CorporationAlternergy
Brgy. Halayhayin,
Pililla, Rizal18.0 Apr 2015 Apr 2015
Pililla Wind Power Project
Ph3
Alternergy Wind One
CorporationAlternergy
Brgy. Halayhayin,
Pililla, Rizal18.0 May 2015 May 2015
TOTAL 2,410.7
** On-going testing and commissioning
12
400
600
800
1,000
1,200
1,400
1,600
1,800
2,000
1-J
an
3-J
an
5-J
an
7-J
an
9-J
an
11-J
an
13-J
an
15-J
an
17-J
an
19-J
an
21-J
an
23-J
an
25-J
an
27-J
an
29-J
an
31-J
an
2-F
eb
4-F
eb
6-F
eb
8-F
eb
10-F
eb
12-F
eb
14-F
eb
16-F
eb
18-F
eb
20-F
eb
22-F
eb
24-F
eb
26-F
eb
28-F
eb
2-M
ar
4-M
ar
6-M
ar
8-M
ar
10-M
ar
12-M
ar
14-M
ar
16-M
ar
18-M
ar
20-M
ar
22-M
ar
24-M
ar
26-M
ar
28-M
ar
30-M
ar
1-A
pr
3-A
pr
5-A
pr
7-A
pr
9-A
pr
11-A
pr
13-A
pr
15-A
pr
17-A
pr
19-A
pr
21-A
pr
TOTAL AVAILABLE CAPACITY SYSTEM PEAK DEMAND REQ'D REG. RESEREVE
REQ'D CONT. RESERVE REQ'D DISP. RESERVE
Visayas Supply-Demand Situation01 January – 21 April 2015
Source: National Grid Corporation of the Philippines (NGCP) Daily Operations Report
1,196 MW (17
Jan)
Papal Visit/Sinulog
TPC Thermal (60 MW) on
FO from 20 Jan 2015 to 02
Feb 2015
PEDC U2 (82 MW) on FO
from 20 Jan 2015 to 22 Jan
2015
UMPP U3 (27.1 MW) on
FO from 09 Jan 2015 to 19
Feb 2015
CEDC U3 (82 MW) on
PMS from 14 Jan 2015 to
28 Jan 2015
PEDC U1 (82 MW) on FO
from 10 Feb - 05 Mar 2015
CEDC U3 (82 MW) on
FO from 28 Feb - 8 Mar
2015
CEDC U1 (82 MW) on
PMS from 21 Feb - 7 Mar
2015
19 Feb 2015
Visayas Partial
Blackout
TGPP U2 (35.7 MW) on PO
from 7-26 Mar 2015
CEDC U2 (82 MW) on
FO from 16 -31Mar
2015
Max Demand
= 1,587 MW (20 Apr)
Min Demand
= 1,137MW (03 Apr)
Good Friday
Note:
FO – Forced Outage / PO – Planned Outage
JAN FEB MAR APR
Panay Partial Blackout
on the evening of 20 April
2015 due to tripping of
PEDC Units 1 and 2
Notes
a. Reserve Margin (RM) i.e. 4% regulating reserve and largest online unit for contingency and dispatchable reserve requirement
(100 MW to increase by 135 MW in 2016)
b. 7 % peak demand growth rate resulted from observed 1 elasticity ratio of demand for electric power with national economic
growth applied to 7 percent GDP growth rate (GR) target for 2014-2015.
c. 8 % peak demand growth rate resulted from observed 1 elasticity ratio of demand for electric power with national economic
growth applied to 8 percent GDP growth rate (GR) target for 2016-2020.
d. Assumed 4.35 percent average forced outage of the total available capacity
VISAYAS SUPPLY-DEMAND OUTLOOK 2014-2020
2015Mar: 8 MW Villasiga HEP*
46 MW URC Bio*
12 MW Hpo Bagasse*
82 MW TPC Coal
Expansion*
36 MW Nabas Wind Ph1
Sep: 14 MW Nabas Wind Ph2
135 MW Concepcion
Coal 1
Dec: 20 MW SCBiopower
2016Nov: 135 MW Concepcion Coal
2
2017Jun: 8 MW Cantakoy HEPP
34 MW VMCI Bio (TBD**)
** TBD – To be determined (target commercial operation)
* On-going testing and commissioning
Actual
Newly-Operational54 MW TAREC San Lorenzo
Wind
14
COMMITTED POWER PROJECTS
* Excluding Off-grid power projects
* Ongoing Testing and CommissioningAs of 31 January 2015
Visayas Grid Committed Power Projects, 473.0 MWName of the Project Project Proponent
Mother/ JV
CompanyLocation
Rated Capacity
(MW)
Target Testing &
Commissioning
Target Commercial
Operation
TPC Coal-Fired Power Plant
Expansion Project*
Toledo Power
Company
Global Business
Power CorporationToledo City, Cebu 82.0 Oct 2014 Mar 2015
Concepcion Coal-fired Power Plant
Unit 1
Palm Thermal
Consolidated
Holdings Corp.
AC Energy Holdings,
Inc./ Palm Thermal
Consolidated
Holdings
Corporation/ Jin
Navitas Resource,
Inc.
Brgy. Nipa,
Concepcion, Iloilo135.0 Jun 2015 Sep 2015
Concepcion Coal-fired Power Plant
Unit 2
Palm Thermal
Consolidated
Holdings Corp.
AC Energy Holdings,
Inc./ Palm Thermal
Consolidated
Holdings
Corporation/ Jin
Navitas Resource,
Inc.
Brgy. Nipa,
Concepcion, Iloilo135.0 Sep 2016 Nov 2016
Villasiga HEP
Sunwest Water &
Electric Co., Inc.
(SUWECO)
Sunwest Water &
Electric Co., Inc.
(SUWECO)
Brgy. Igsoro,
Bugasong, Antique8.0 Sep 2014 Mar 2015
Cantakoy HEPQuadriver Energy
Corp.
Quadriver Energy
Corp.Danao, Bohol 8.0 Jun 2017 Jun 2017
8.0 MW HPCo Bagasse
Cogeneration Plant*
Hawaiian Philippines
Company
Hawaiian Philippines
CompanyNegros Occidental 3.0 Nov 2014 Mar 2015
46 MW Universal Robina
Corporation Bagasse Cogeneration
Facility*
Universal Robina
Corporation
JG Summit Holdings
Inc.Negros Occidental 31.0 Dec 2014 Mar 2015
20 MW SCBiopower Bagasse-Fired
Power Generation Project
San Carlos Biopower
Inc.
Bronzeoak
PhilippinesNegros Occidental 18.0 Dec 2015 Dec 2015
34 MW VMCI Bagasse-Fired
Cogeneration Plant
Victorias Milling
Company Inc.
Victorias Milling
Company Inc.Negros Occidental 3.0 TBD TBD
Nabas Wind Power Project Phase 1Petrogreen Energy
Corporation
Petrogreen Energy
Corporation
Brgy. Pawa, Nabas,
Aklan36.0 Jan 2015 Mar 2015
Nabas Wind Power Project Phase 2Petrogreen Energy
Corporation
Petrogreen Energy
Corporation
Brgy. Pawa, Nabas,
Aklan14.0 Sep 2015 Sep 2015
TOTAL 473.0 15
600
800
1,000
1,200
1,400
1,600
1,800
1-J
an
3-J
an
5-J
an
7-J
an
9-J
an
11-J
an
13-J
an
15-J
an
17-J
an
19-J
an
21-J
an
23-J
an
25-J
an
27-J
an
29-J
an
31-J
an
2-F
eb
4-F
eb
6-F
eb
8-F
eb
10-F
eb
12-F
eb
14-F
eb
16-F
eb
18-F
eb
20-F
eb
22-F
eb
24-F
eb
26-F
eb
28-F
eb
2-M
ar
4-M
ar
6-M
ar
8-M
ar
10-M
ar
12-M
ar
14-M
ar
16-M
ar
18-M
ar
20-M
ar
22-M
ar
24-M
ar
26-M
ar
28-M
ar
30-M
ar
1-A
pr
3-A
pr
5-A
pr
7-A
pr
9-A
pr
11-A
pr
13-A
pr
15-A
pr
17-A
pr
19-A
pr
21-A
pr
TOTAL AVAILABLE CAPACITY SYSTEM PEAK DEMAND REQ'D REG. RESEREVE
REQ'D CONT. RESERVE REQ'D DISP. RESERVE
Mindanao Supply-Demand
Situation01 January – 21 April 2015
Source: National Grid Corporation of the Philippines (NGCP) Daily Operations Report
Note:
FO – Forced Outage / PO – Planned Outage
Min Demand
= 1079 MW (01
Jan)
New Year
Max Demand
= 1,405 MW (21
Apr)
STEAG U1 (105 MW) on PO
since 21 Feb 2015 until 16 Mar
2015
STEAG U2 (105 MW)
on PO from 19 Feb-2 Mar 2015
Pulangi4 HEPP U3 (70
MW) on FO since 15 Jan
2015
PUL4 U1 (85 MW) on
FO since 21 Mar
25 Jan 2015
Agus 5 U1 PO (27.5MW)
Agus 6 U3 PO (50MW)
TMI-2 U1 PO (50 MW)
1,107 MW (03 Apr)
Good Friday
5 April 2015
Mindanao Partial
Blackout
TMI 2 U2 (50 MW) on
PMS on 3 April 2015
JAN FEB MAR APR
2016Feb: 150 MW SMC Davao U1
Mar: 25 MW Lake Mainit
Jun: 135 MW FDC Coal U1
Aug: 150 MW SMC Davao U2
Sep: 135 MW FDC Coal U2
Nov: 100 MW SEC Coal 2
Dec: 135 MW FDC Coal U3
10 MW Malaybalay Bio
MINDANAO SUPPLY-DEMAND OUTLOOK 2014-2020
Notes
a. Required Reserve Margin (RM) i.e. 4% regulating reserve and contingency and dispatchable reserve requirement
b. 5.6 % peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for electric power with national economic
growth applied to 7 percent GDP growth rate (GR) target for 2014-2015.
c. 12.8 % peak demand growth rate resulted from observed 1.6 elasticity ratio of demand for electric power with national
economic growth applied to 8 percent GDP growth rate (GR) target for 2016
d. 8 % peak demand growth rate resulted from observed 1 elasticity ratio of demand for electric power with national economic
growth applied to 8 percent GDP growth rate (GR) target for 2017-2020
e. Assumed 3.3 percent average forced outage of the total dependable capacity ** TBD – To be determined (target commercial operation)
* On-going testing and commissioning
Actual
2015Mar: 5.2 MW Peak Power
PSFI*
150 MW Therma South 1
Jun: 150 MW Therma South 2
Oct: 100 MW SEC Coal 1
Dec: 10 MW LPC Bio
2017Feb: 55 MW Minergy Coal 1
Apr: 55 MW Minergy Coal 2
Jun: 55 MW Minergy Coal 3
Jul: 30 MW Puyo HEP
Dec: 540 MW GNPower
Kauswagan
Newly-Operational
21 MW Peak Power PSI
15 MW MEGC DPP
2018Jan: 9 MW Limbatangon HEPP
8 MW Asiga HEPP **
3 MW PTCI Bio **
17
COMMITTED POWER PROJECTS
* Ongoing Testing and Commissioning
** New Entry from Indicative list As of 31 January 2015
Mindanao Grid Committed Power Projects, 2,007.8 MWName of the Project Project Proponent
Mother/ JV
CompanyLocation
Rated Capacity
(MW)
Target Testing &
Commissioning
Target Commercial
Operation
PSFI Bunker-Fired Power Plant*Peak Power San
Francisco (PSFI)
Peak Power Energy
Inc. (subsidiary of A
Brown)
ASELCO Compound,
Brgy. San Isidro,San
Francisco, Agusan del
Sur
5.2 Sep 2014 Mar 2015
2 X 150 MW Coal-Fired Therma
South Energy ProjectTherma South Inc.
Aboitiz Power
Corporation
Brgy. Binugao, Toril,
Davao City and Brgy.
Inawayan, Sta. Cruz,
Davao Del Sur
300.0 Feb 2015U2 – Mar 2015
U1 – June 2015
Southern Mindanao Coal Fired
Power Station Unit 1
Sarangani Energy
Corporation (SEC)
Alsons Power
Corporation
Brgy, Kamanga, Maasim,
Sarangani100.0 Jun 2015 Oct 2015
SMC Davao Power Plant Project
Phase I Unit 1
San Miguel
Consolidated Power
Corporation
San Miguel
Consolidated Power
Corporation
Brgy. Culaman, Malita,
Davao del Sur150.0 Dec 2015 Feb 2016
SMC Davao Power Plant Project
Phase I Unit 2
San Miguel
Consolidated Power
Corporation
San Miguel
Consolidated Power
Corporation
Brgy. Culaman, Malita,
Davao del Sur150.0 May 2016 Aug 2016
3 X 135 MW FDC-Misamis
Circulating Fluidized Bed (CFB)
Coal-Fired Power Plant Project
FDC Utilities, Inc. FDC Utilities, Inc.
Phividec Industrial
Estate, Villanueva,
Misamis Oriental
405.0
U1 – Dec 2015
U2 – Mar 2016
U3 – Jun 2016
U1 – Jun 2016
U2 – Sep 2016
U3 – Dec 2016
Southern Mindanao Coal Fired
Power Station Unit 2
Sarangani Energy
Corporation (SEC)
Alsons Power
Corporation
Brgy, Kamanga, Maasim,
Sarangani100.0 Feb 2015 Nov 2016
3x55 MW Balingasag Thermal
Power Plant (Circulating
Fluidized Bed Combustion
(CFBC) Coal-Fired Power Plant
Plant)**
Minergy Coal
CorporationMinergy
Brgy. Mandangoa,
Balingasag, Misamis
Oriental
165.0
U1 – Feb 2017
U2 – Apr 2017
U3 – Jun 2017
U1 – Feb 2017
U2 – Apr 2017
U3 – Jun 2017
GNPower Kauswagan Ltd.
540MW Clean Coal-Fired Power
Plant
GN Power
KausawaganGN Power Ltd. Co.
Kauswagan, Lanao del
Norte540.0 Feb 2017 Dec 2017
18
COMMITTED POWER PROJECTS
** New Entry from Indicative listAs of 31 January 2015
Mindanao Grid Committed Power Projects, 2,007.8 MW
Name of the Project Project ProponentMother/ JV
CompanyLocation
Rated Capacity
(MW)
Target Testing &
Commissioning
Target Commercial
Operation
Lake MainitAgusan Power
CorporationTranzen Group Inc.
Jabonga, Agusan del
Norte25.0 Mar 2016 Mar 2016
Puyo Hydroelectric Power
Project
First Gen Mindanao
Hydropower Corp.
First Gen Power
Corporation
Jabonga, Agusan del
Norte30.0 Jul 2017 Jul 2017
Limbatangon Hydroelectric
Power Project
Turbines Resource &
Development Corp.
Turbines Resources
and Development
Corp. (TRDC)
Cagayan de Oro City,
Misamis Oriental9.0 Jan 2018 Jan 2018
Asiga HEPP**Asiga Green Energy
Corp.
Santiago, Agusan del
Norte8 TBD TBD
15 MW LPC Biomass Power
Plant Project
Lamsan Power
Corporation
Lamsan Power
CorporationMaguindanao 10.0 Dec 2015 Dec 2015
10 MW Malaybalay Bio-Energy
Corporation Multi Feedstock
Power Generating Facility
Malaybalay
Bioenergy
Corporation
Malaybalay
Bioenergy
Corporation
FIBECO, Anahawan,
maramag, Bukidnon9.0 Dec 2016 Dec 2016
3 MW Biomass Cogeneration
Facility
Philippine Trade
Center, Inc.
Philippine Trade
Center, Inc.Maguindanao 1.6 TBD TBD
TOTAL 2,007.8
19
•III. The Bangsamoro Government shall have
exclusive powers that it exercises within its territorial
iurisdiction, over the following matters:
•14. Establishment of government-owned and
controlled corporations (GOCCs) and financial
institutions - The Bangsamoro Government may
legislate and implement the creation of its own
GOCCs in the pursuit of the common good and
subject to economic viability. The GOCCs shall be
duly registered with the Securities and Exchange
Commission or established under legislative charter
by the Bangsamoro Government;
• 15. The Bangsamoro Government shall have authority
to regulate power generation, transmission, and
distribution operating exclusively in the Bangsamoro. lt
shall promote investments, domestic and international,
in the power sector industry in the Bangsamoro. Power
plants and distribution networks in the Bangsamoro shall
be able to interconnect and sell power over the national
transmission grid to electric consumers. The
Bangsamoro Government may assist electric
cooperatives in accessing funds and technology, to
ensure their financial and operational viability. When
power generation, transmission, and distribution facilities
are connected to the national transmission grid, the
Central Government and the Bangsamoro Government
shall cooperate and coordinate through the
intergovernmental relations mechanism ;
• 16. Public utilities operations in the Bangsamoro - ln case
of inter-regional utilities, there shall be cooperation and
coordination among the relevant government agencies;
• 34. Environment, parks, forest management, wildlife. nature
reserves and conservation - The Bangsamoro Government
shall have the authority to protect and manage the
environment. lt shall have the power to declare nature
reserves and aquatic parks, forests, and watershed
reservations, and other protected areas in the Bangsamoro.
The Bangsamoro Basic Law will provide for the process
that will transfer the management of national reserves and
aquatic parks, forests and watershed reservations, and
other protected areas already defined by and under the
authority of the Central Government;
• 35. Inland waterways for navigation;
• 36. lnland waters;
• 37. Management, regulation and conservation
of all fishery, marine and aquatic resources
within the Bangsamoro territorial jurisdiction;
• 2. Mineral and Energy Resources The Bangsamoro
Government shall have authority and jurisdiction over the
exploration, development, and utilization of mines and
minerals in its prfitory. The applications for financial and
technical assistance 'agreements (FTAAs) shall be
commenced at and recommended by the Bangsamoro
Government to the President. The Bangsamoro Government
and the Central Government shall jointly exercise the
power to grant rights, privileges and concessions over the
exploration, development and utilization of fossil fuels
(petroleum, natural gas, and coal) and uranium in the
Bangsamoro, giving preferential rights to qualified citizens
who are bona fide inhabitants of the Bangsamoro. The
modalities for the exercise of this power shall be provided
in the Bangsamoro Basic Law. lmplementing rules and
regulations for the exercise of this power, including
safeguards against potential unfair business practices, shall
be jointly drawn up.
• Part One. Intergovernmental Relations
• The Central Government and the Bangsamoro
Government shall establish a mechanism at the
highest levels that will coordinate and harmonize
their relationships. For this purpose, a primary
mechanism shall be a Central Government
Bangsamoro Government lntergovernmental Relations
body to resolve issues on intergovernmental
relations. Disputes relating to these
intergovernmental relations shall be resolved through
regular consultations and continuing negotiations in a
non-adversarial manner.