Outline
Mirabella Villas Construction Update
Bella Vista Apartments Construction Update
Riviera Residences Update
La Perla Residences Update
1
3
2
4
5 Kitala Gerenge Road Construction Update
Mirabella Construction Update
September Site Overview
Priority 1
House 1-6 , 20-22
Priority 3
House 7 - 12
Priority 2
House 13 - 19
Mirabella Villa
Progress Fact sheet
Item Details
Type of House Mirabella Residences-4 bedrooms + Maid +2Livingrooms + Laundry area Price: From 330,000$
Construction Period 70 weeks
Weeks Elapsed 47 weeks
Programme of works status Project on schedule
Significant Milestone by end of
August
House 1-6, 20-22 Roof and Ceiling works at 70%, internal plaster is at 70% awaiting plaster finish atdoor and window openings. Clients have chosen their preferred floors
House 13-19 Roof, Ceiling works and internal plaster are at 70%. Clients have chosen theirpreferred floors
House 7-12 Roof is at 20%, internal plaster at 50%. Clients have chosen their preferred floors
Expected Milestone for September
Priority 1 Priority 2 Priority 3
• Proceed with Parapet walling• Commence Screed works• Complete roof, ceiling works and
internal plaster
• Proceed with internal plastering, roof and ceiling works
• Procced with parapet walling
• Commence parapet walling• Proceed with internal plastering• Proceed with roof and ceiling
works
Mirabella Showhouse
• The Mirabella showhouse is under construction and is scheduled for
completion by end of November 2019.
Construction Team
Project Architect Imparqt Associates
Project Quantity Surveyor Integrated YMR Partnership
Project structural Engineer Gumak Associates supervised by Gamma Associates
Project MEP Engineer Emsult supervised by Multi Konsults
Interior Designer Image 360 Designs
Main Contractor Roko Construction Company Limited
Developer Pearl Marina Estates Limited
Bella Vista Apartments Construction Update
September Site Overview – Phase 1a
Bella Vista Apartments
Progress Fact sheet
Item Details
No. of Blocks 14 Price: 1,2 and 3 Bedrooms starting from 39,000$,59,000$ and 68,000$ Respectively.
Construction Period 117 weeks
Weeks Elapsed 22 weeks
Programme of works status On schedule
Significant Milestone by end of
quarter
Block F,G,H,I & J • Commenced and in progress marram back filling works for Block I.• Necessary checks for the steel works for Blocks F + J were concluded last
week. Casting ground beams soon. • Completed 90% of the steel fixing for the ground beams for Block G. Awaiting
for the side shutters for these beams. • Commenced and in progress with the bituminous painting works on the plinth
walls of Block H in 2 coats. Marram filling to commence this week.
Expected Milestone for next
quarter
Block F,G,H,I & J • Complete backfilling in layers + necessary CBR testing + hardcore packing • Must cast the Ground Beams for block H without fail • Complete bituminous plinth wall panting and start marram back filling • Complete the GB steel fixing + fix side shutters + cast the Ground Beams • Must cast the Ground Beams for this block without fail
Bella Vista Showhouse
• The Bella Vista showhouses are also under construction
and are scheduled for completion by end of November 2019.
• These will showcase the layout of the 1 bedroom apartments,
2 bedroom apartments and the 3 bedroom apartments
Construction Team
Project Architect Imparqt Associates
Project Quantity Surveyor Turner & Townsend
Project structural Engineer Gumak Associates supervised by Gamma Associates
Project MEP Engineer Emsult Engineers supervised by Multi Konsults
Interior Designer Image 360 Designs
Main Contractor Roko Construction Company Limited
Developer Pearl Marina Estates Limited
Riviera Residences
Progress Fact sheet
Item Details
Type of House Riviera / Town house Residences-3 bedrooms + Maid + StudyPrice: From 185,000$
Phase 1 18 No.
Phase 2 18 No.
Phase 3 17 No.
Significant Milestone by end of
quarter
Phase 1 • Town council approval got• Finalized finishes and product offerings
Expected Milestone for end of
quarter
Phase 1 • Ground breaking
La Perla Residences - Overview
La Perla Residences
Progress Fact sheet
Item Details
Type of House Bangalows-3bedrooms + MaidPrice: 140,000$
Phase 1 21 No.
Phase 2 38 No.
Significant Milestone by end of
quarter
Phase 1 • Board approval achieved• Completed Detailed designs
Expected Milestone for next
quarter
Phase 1 • Achieve market validation by December
Kitala – Gerenge Road Construction Update
September Overview
Works Progress:
• works on the road commenced and are at25%
• Reserved 95% of right of way/compensation• Tarmac layer installation commenced in
August 2019 upon release of governmentfirst quarter funds.
Tarmac layer commenced 3.2 Km
Road Tarmac Equipment Procured Ongoing road works