OTC 17299 Launching

download OTC 17299 Launching

of 12

Transcript of OTC 17299 Launching

  • 8/4/2019 OTC 17299 Launching

    1/12

    Copyright 2005, Offshore Technology Conference

    This paper was prepared for presentation at the 2005 Offshore Technology Conference held inHouston, TX, U.S.A., 25 May 2005.

    This paper was selected for presentation by an OTC Program Committee following review ofinformation contained in a proposal submitted by the author(s). Contents of the paper, aspresented, have not been reviewed by the Offshore Technology Conference and are subject tocorrection by the author(s). The material, as presented, does not necessarily reflect anyposition of the Offshore Technology Conference, its officers, or members. Papers presented atOTC are subject to publication review by Sponsor Society Committees of the OffshoreTechnology Conference. Electronic reproduction, distribution, or storage of any part of thispaper for commercial purposes without the written consent of the Offshore TechnologyConference is prohibited. Permission to reproduce in print is restricted to a proposal of not

    more than 300 words; illustrations may not be copied. The proposal must contain conspicuousacknowledgment of where and by whom the paper was presented. Write Librarian, OTC, P.O.Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.

    AbstractThe Holstein truss spar hull, the largest ever built, was

    fabricated in two sections in Finland and the U.S. The Truss

    section with the soft tank was fabricated in the U.S. and

    required transferring from land to water at the fabrication yard

    before it could be mated with the hard tank section. The

    challenges due to the size, schedule and government

    regulations resulted in selecting a unique controlled launch

    submergence method to offload the truss section into the

    water. The offloading operation involved inclining the H-627

    launch barge to unusually high angles while ballast operatorswere onboard the vessel, moving the truss down the barge in a

    controlled fashion with winches rigged to skid shoes and

    finally submerging the barge to create separation. The truss

    section was loaded on the barge from the bow and launched

    over the tilt beam at the stern. Discontinuous removable skid

    shoes were used instead of traditional continuous permanent

    launch cradles.

    The truss section travel over the barge, and speed control

    during launch was achieved by employing two sets of

    winches, Pull Winches and Hold Back Winches, located on

    the Barge Deck. Structural modifications had to be made to

    the barge, skid beams and soft tank structure to make theoperation feasible. Additional barge marine systems had to be

    added for the unusual ballasting and floating configuration

    required for the operation. An active mooring system along

    with the winch line tensions was used to control the barge and

    the truss during the operation.

    IntroductionThe Holstein truss spar hull (Ref. 1) due to its large diameter

    of 45.5 m (about 150 ft.) and 227.38 m (746 ft.) length, and

    weight could not be carried as a single piece, from the

    fabrication yard in Finland to the offloading site in Gulf of

    Mexico, on the largest heavy lift vessel available at the time o

    fabrication. As a result, the Spar hull was fabricated in two

    pieces and in two different fabrication yards. The truss and

    the soft tank (referred to only as truss structure from here on)

    were fabricated on land as one-piece in Technips GMF yard

    in South Texas. The hard tank of the hull was built in

    Technips TOF yard in Finland and transported to the Gulf ofMexico on a heavy lift vessel and offloaded in sheltered water

    near the truss fabrication yard. The two floating sections were

    joined (mated) and welded together in the water next to the

    fabrication yard (Ref. 2).

    The truss structure had to be offloaded into the water next

    to the fabrication yard for mating with the hard tank. The

    truss structure with the skid shoes weighed approximately

    11,600 short tons. Various options were investigated to

    offload the truss and soft tank. Some of the options

    investigated are as follows:

    Submersible barge.

    Dry Dock - either by bringing the dry dock next to thefabrication yard or loadout of the structure on a barge

    transport to a dry dock, offload the truss and wet tow the

    structure back to the yard for wet mating with the hard

    tank.

    Lift Loadout the structure on a barge and use land basedcranes or crane barges to lift and lower into water.

    Use a combination of submersible barges and liftingequipment.

    VersaTruss system.

    Launch barge and controlled launch.

    Fabricate truss and soft tank sections separately and jointhem over water.

    Due to the size, weight and floating draft of the structure

    most of these options were not feasible using the existing

    facilities in the U.S. New build or modification of existing

    vessels in the U.S. was also investigated and ruled out because

    of cost and project schedule. Submersible barges available to

    perform truss offload operation were not employed due to

    various legal considerations. The option selected, about seven

    months before the execution of the offload operation, was to

    OTC 17299

    Controlled Launch Offloading of Holstein Spar Truss Section

    A. Sablok, J. Gebara, and T. DeMerchant,Technip Offshore, Inc.; S. Piter,EdMar Engineering, Inc.;S. Perryman,BP America Inc.

  • 8/4/2019 OTC 17299 Launching

    2/12

    2 OTC-17299

    use a launch barge and controlled launch the structure in the

    waters next to the truss structure fabrication yard (GMF) in

    South Texas. The launch barge selected for this operation was

    Heeremas H-627. There were restrictions regarding the

    offloading configuration and procedure in order to satisfy the

    Jones Act. The barge could not be moved but only yawed

    about its center to offload after the truss structure was loaded

    on the barge. Furthermore, the barge geometric center and thetruss geometric center were to coincide at the time of rotating

    the barge for the yaw operation not to be considered a

    transport of the truss. This requirement resulted in performing

    a bow loadout and offloading the truss over the stern where

    the tilt beam is located. The offloading operation involved

    inclining the H-627 launch barge to an unusually high angle,

    moving the truss down the barge in a controlled fashion with

    winches rigged to the skid shoes and finally submerging the

    barge to create separation. Figures 1 and 2 shows the initial

    and final configuration of the offloading operation

    respectively. This paper describes: the challenges faced, the

    offloading system, the barge modifications required, other fit-

    for-purpose structures used for this operation, the offload

    analysis and the offload procedure.

    Description of Truss StructureThe truss structure positioned on the H-627 barge is shown in

    Figure 1. The truss structure included three Truss bays with

    three heave plates and a soft tank at the bottom of the Truss.

    The overall dimension and the weight of the truss structure are

    as follows:

    Length, overall 130.62 m (428.5 ft.)

    Breadth 45.50 m (~150 ft.)

    Depth 45.50 m (~150 ft.)

    Outfitted Loadout Weight 10,572 mt (11650 s. tons)

    The truss was supported at the three heave plates and under

    the soft tank with discontinuous skid shoes on two sides inside

    the vertical plane of the Truss Legs. The nominal height of

    the skid shoes was 9 ft. including 1 ft. high timber. The

    mating tank (Ref. 2) required for making the truss float during

    offloading and mating operations was also supported on the

    skid shoe under the aft most heave plate. The six skid shoes

    under the heave plates were suspended from the heave plates

    with steel wire and offloaded with the truss. Restraints

    provided on the skid shoes prevented the skid shoes from

    moving longitudinally, laterally and rotating. The skid shoe

    under the soft tank stayed on the barge when the Truss wasoffloaded. The truss structure longitudinal movement during

    the offloading operation was done through the two skid shoes

    under the soft tank as explained below. The mating tank was

    placed on the skid shoes of the aft most heave plate with

    restraint provided on the skid shoes to prevent the mating tank

    from accidentally sliding longitudinally off the skid shoes

    when the barge is pitched down. Laterally, the truss legs were

    supported on the cradle of the mating tank. During loadout, a

    small gap was left between the mating tank cradle and the

    truss legs. This gap closed once the mating tank became

    positively buoyant during the offloading operation. This was

    required to reduce the concentrated loads on the mating tank

    during loadout and offload.

    Figure 1: Truss Structure on H-627 Barge at Start of OffloadOperation

    Figure 2: Configuration at End of Offload Operation

    During the offloading operation, the truss rotated relative to

    the barge about the end of the soft tank. Two hinge structure

    were installed at the bottom of the soft tank in line with the

    skid shoes as shown in Figure 3. The hinge structure wa

    welded to the soft tank with a half tubular at the bottom. The

    half tubular was placed in a cup structure welded on top of the

    skid shoe. During loadout, a small gap was kept between thehalf tubular and the cup to ensure that the loadout loads were

    not passed through the hinge but distributed along the soft

    tank skidshoe. The hinge system was also designed to allow

    the truss structure to yaw relative to the skid shoe due to

    environmental load. Side plates were added toprevent latera

    sliding. The maximum total force that each hinge had to carry

    during the offload operation was 3000 metric tons.

    Skid Shoes

    Soft Tank

    Mating

    Tank

  • 8/4/2019 OTC 17299 Launching

    3/12

    OTC-17299 3

    Figure 3: Hinge Structure at Bottom of Soft Tank

    Barge H-627 DescriptionThe dimensions of the Launch Barge H-627 used for the float-

    off operation are as follows:

    Length, hull 176.78 m (580 ft.)

    Length, overall 192.35 m (631 ft.)

    Breadth 48.77 m (160 ft.)

    Depth 10.97 m (36 ft.)

    Skidway Height 1.54 m (5 ft.)

    The barge has eight rows of tanks along its length and

    generally four compartments per row except at the stern wherethere were five compartments across the width. There is a

    central tunnel compartment where the pumping system and

    machinery are located. There are two pumps that can pump

    simultaneously or individually to all the ballast compartments

    except the compartment located at the stern, aft of the tunnel.

    This compartment, normally not used for launching

    operations, had to be manually ballasted and deballasted with

    external pumps. The system also allows transferring water

    between two compartments. The valves for opening or

    closing the water supply to the compartments had to be

    manually operated. These valves were located next to the

    compartments and therefore personnel had to walk along the

    length of the tunnel to control the valves.

    The barge had two adjustable tilt beams and skidbeams

    running from the stern aft of the tilt beam to short of the bow.

    Figure 4 shows the top view of the barge before the truss

    structure was loaded out on the barge.

    Offload Analysis

    Three primary analyses were performed for the offload

    operation: Hydrostatic/Structural analysis, Winching analysis

    and Mooring analysis. The Hydrostatic analysis results served

    Figure 4: Barge H-627 before Truss Loadout

    as partial input to the other two analyses. Based on theanalyses, all the systems required to execute the operation

    were designed. The offloading systems and the challenges to

    execute the operation are discussed later in the paper.

    Hydrostatic/Structural Analysis. This analysis helped to

    develop the offload procedure steps with regards to the

    ballasting and skidding operation. The analysis was done

    using a quasi-static approach. Spring compression connector

    were used at the supports. A hinge connector was modeled a

    the bottom of the soft tank. Structural models of the truss and

    the barge were used for the analysis. The stiffness of the

    connectors was based on the stiffness of the barge skid beams

    and the skid shoes. Two different analyses were done. Rigid

    body analysis was performed using the truss section and theH-627 models. This analysis treated the bodies as rigid

    connected by flexible generalized springs. The second

    analysis used the same model of the truss section, but a new

    model was created with a complete structural model of the

    barge. In this analysis, after the equilibrium position wa

    found, a structural analysis was performed considering the

    flexibility of the barge and truss. Flexible connectors were

    also used between the two bodies. Figure 5 shows the analysis

    steps used to develop the offload procedure. Sensitivity

    analyses with weight and C.G. variation of the truss structure

    and barge were also performed. The following

    assumptions/restraints were used for the purpose of

    performing the offload analysis:

    Maximum submergence depth of the barge of 76 ft.

    The maximum loads were not to exceed the strengthdesign of the truss or barge.

    The offload was to be done under favorable weatherconditions.

    Ballast tanks full at 98%.

    Ballast tanks empty at 2.25% for the No. 1 tanks and4.50% for all others.

    Ballasting and Winching are sequential operations, nosimultaneous.

    Bow

    Stern

    Welded to

    SkidShoe

    Welded toBottom ofSoftTank

    Half Tubular

  • 8/4/2019 OTC 17299 Launching

    4/12

    4 OTC-17299

    Separation of the truss and barge of at least one foot wasrequired at the separation point.

    Barge must have at least 1.0 m of metacentric height(GM) during all stages of offload.

    The following limits maintained the truss section and skidshoes within allowable limit states:

    Reactions at the truss section support points not to

    exceed 1.5 x their reaction when the truss issupported with all supports on a level plane.

    Hinge Reactions during and after rotation to be 3000mT or less

    The barge/truss system deflections at the skid shoesupports must not exceed plus or minus 32 mm (1.25

    inches) during skidding.

    Figure 5: Offload Analysis Procedure

    A simplified symmetrical mooring system was included in

    the hydrostatic analysis to help in the process of finding

    equilibrium. The individual mooring line tensions were

    adjusted at each step to 30 kips. The purpose of this system

    was to constrain lateral motions of the H-627 during the

    offload analysis. It had negligible effect on the analysis. The

    detail mooring analysis of the actual mooring configuration

    used is described later. Figure 6 shows the truss and the barge

    model with simplified mooring at one of the final steps of theoffload operation.

    Figure 6: Computer analysis model of Truss, Barge and Mooring

    Figure 7 summarizes the configuration of the barge and the

    position of the truss for the various steps. Results of these

    studies indicated that the truss section could be safely

    offloaded from the H-627. The sensitivity studies showed tha

    there was sufficient reserve in the system to accommodate the

    variances of the base parameters within the boundaries set as

    criteria. An independent study was carried out by Det Norske

    Veritas to verify the offload analysis and found very similarresults.

    Figure 7: Offload Procedure Summary

    Winch Load Analysis. The net loads required to either push

    or hold the truss structure during various steps of the analyses

    above were estimated based on the barge/truss pitch angle and

    net vertical loads on the truss structure including buoyancyloads. The following criteria were used to determine the

    winching requirements and design the rigging required for the

    operation:

    Friction coefficients (Sealed, greased wood on lubricated

    Teflon):

    Static friction = 0.10

    Dynamic friction range = 0.04 - 0.08

    Friction losses within sheaves and blocks were

    considered.

    Step 0

    Step 1

    Step 2

    Step 3

    Step 4

    Step 5

    Step 6

    Step 7

    Step 8

    Step 9

    Step 10

    Step 11

    Step 12

    Step 13

    Step 14

    Step 15

    Step 16

    Step 17

    Step 18

    Step 19

    Step 20

  • 8/4/2019 OTC 17299 Launching

    5/12

    OTC-17299 5

    The fleet angle on winches, blocks and sheaves did not

    exceed 2.5 degrees.

    No skew load was considered owing to the fact that the

    loads in the pulling systems were measured and could be

    adjusted.

    The winch and rigging systems selected based on the analyses

    are described below.

    Offload SystemThe quasi-static launch operation consisted of a combination

    of winching the truss structure along the length of the barge

    and ballasting of the barge. The winching system, shown in

    Figure 8, consisted of a Pull Winch System and Hold-Back

    Winch system.

    The pull system initially was used to overcome the friction

    load and push the truss structure towards the stern of the

    barge. After ballasting the barge and reaching certain pitch

    angles always accounting for the truss structure buoyancy, the

    weight component of the truss parallel to the barge deck

    becomes higher than the friction force between the truss

    structure and the barge skid beams and theoretically no pull

    force is required to move the truss. The truss, therefore,

    would slide without any external load and required restraint

    from launching dynamically. Dynamic launch of the truss

    structure was not a feasible option because of the potential

    damage to the truss and the barge due to limited water depth

    and proximity of the barge to the bulkhead. Any restraint on

    the barge to keep it in place and not move backwards towards

    the bulkhead may result in the truss structure colliding with

    the barge tilt beam as it separated from the barge. The Hold

    Back system was used to control the launch of the structure

    Since the skid shoes on the truss were not continuous, the

    pivoting of the barge tilt beam would have damaged the truss

    while moving the truss and finally separating. Therefore, the

    Tilt Beam was fixed and not allowed to pivot.

    Each of the winching systems consisted of a pair of 200 tonwinches. All four winches were spooled with 6000 ft. of 2

    inch wire rope reeved through a pair of 8-sheave 850 ton

    blocks. A 12-part rigging was used for each of the winches.

    The pull and the hold back loads were applied to the truss

    structure through the skid shoe under the soft tank of the truss

    structure. Due to the limit on the maximum submergence of

    the barge, the offload procedure required that the soft tank

    skid shoe be moved almost to the tip of the Tilt Beam for the

    separation to occur. To make this happen, a deadman for the

    pull system had to be located outside the barge and aft of the

    stern. This was not feasible with the offload procedure

    therefore a skid frame connected to the soft tank skid shoe was

    used to make offload of the truss structure feasible. The skid

    frame is shown in Figure 9. Essentially, the skid frame

    extended the length of the soft tank skid shoe. The Pull and

    the Hold Back systems were connected to the soft sank skid

    shoe through the Skid Frame. The two Pull System deadmen

    were placed at the aft most possible location on the raked end

    of the barge deck. The traveling blocks of the Pull and Hold

    Back systems were connected to the Skid Frame. The Skid

    Frame was designed to stay parallel to the barge deck and was

    sliding on the barge skid beams.

    Figure 8: Offload System, Skid Frame and Winch Lines shown in final position

    Hold back winch

    Hold back linesPulling lines

    Skid frame

    Deadmen

    Blocks in pulling lines

    Blocks in hold back lines

    Blocks in hold back lines Blocks in pulling linesPullin winch

    DeaBow

    Bollard (Typ)

  • 8/4/2019 OTC 17299 Launching

    6/12

    6 OTC-17299

    The Winch control system was designed to synchronize the

    winches or control them individually. The synchronization

    option was to ensure that the load and payout length of wire

    was within acceptable ranges on both sides of the truss. A

    minimum nominal tension was kept in the wires during the

    entire operation to prevent the lines from becoming slack and

    to control the alignment of the truss longitudinal axis with the

    barge longitudinal axis.

    Figure 9: Skid Frame used for Offload Operation

    Mooring SystemMooring control systems were used for the offload of the truss

    section of the Holstein truss spar from the H-627 launch barge.

    They consisted of the following three major sub-systems:

    Barge Mooring System, Truss Mooring System and the

    Onboard Winch System. The Barge Mooring system was

    designed for a directional environment with wind speeds (one

    minute average) up to 26 knots and current speeds up to 1.0

    m/s. The truss section control system was designed for an

    omni-directional environment with maximum wind speeds

    (one minute average) of 18 knots and current speeds of 0.6

    m/s, respectively. The Barge Mooring system was designed

    for a higher speed due to its longer exposure to the

    environment when the barge is prepared for the offload afterthe loadout, and possibly need to wait for a favorable weather

    window for the offload operation. The Truss Mooring system

    was used to control the truss after it separates from the launch

    barge. Waves during the operation were assumed benign and

    were notconsidered in the mooring analysis.

    1) Barge Mooring System: An 8-line barge mooring systemthat was used to maintain the position of H-627 barge

    during the offload operation. The mooring lines were

    double-parted 1-1/2 diameter, 6x41 IWRC EEEIPS wire

    ropes which were connected to land-based winches

    through the sheaves on the mooring dolphin or fairleads

    on land. Spring lines were also included in each line to

    soften and minimize the shock on the offloading system

    in case any mooring line was damaged. The winches o

    moving deadmen were used to adjust the barge position

    and mooring line pretensions. The same mooring system

    was also used for the truss section load-out. The loads in

    each line were monitored by attaching an in-line load cell

    Figure 10 shows the barge mooring configuration. Themooring line pretensions during the offload operation

    tightened up as the barge submerged and had to be

    adjusted by paying out lines at intermediate float-over

    steps. Since the direction of mooring line loads relative to

    the barge change due to submergence of the barge during

    the offload operation, special bollards had to be designed

    and installed on the barge. These bollards helped the

    mooring lines to stay connected to the barge and also take

    high mooring line loads. The existing barge bollards were

    of the open type and not suited for the mooring line loads

    experienced during the operation. Figure 11 shows the

    tubular bollards used for the offload operation.

    Figure 10: Barge Mooring System

    Figure 11: Barge Mooring Bollards

    Connected to

    Pull Lines

    Connected to

    Soft Tank Skid

    Connected to

    Pull Lines

    Connected to

    Hold Back Lines

    Bollard

  • 8/4/2019 OTC 17299 Launching

    7/12

    OTC-17299 7

    2) Truss Mooring System: A 6-line control system on thetruss section that was used to control the position of the

    truss section during and after the offload operation. Each

    line was a single 2 diameter, IWRC EIPS wire rope

    connecting the truss to land-based winches through the

    mooring dolphin and fairleads on land. This system was

    activated when the truss started to rotate upward from thebarge at the hinge on the soft tank. It assisted the

    winching system on the barge in keeping the orientation

    of the truss so that the truss could continuously skid along

    the skid beams before the final separation from the barge.

    Tugs were also deployed to control the position of truss

    section during and after the offload.

    3) Onboard Winching System: An on-board winchingsystem that consisted of two pulling lines and two hold

    back lines. Each line consists of a 2 IWRC EIPS wire

    rope running between two blocks and controlled by an on-

    board winch. It is used to control the movement of the

    truss section as it is skidded off from thebarge.

    Analysis of the winching system was performed for the

    stage at which the truss was partially floating and the soft

    tank end was still supported on the barge. At this stage,

    only the last pair of skid shoes under the soft tank were in

    contact with the barge. Wind and current loads in the

    transverse direction (beam direction) would force the

    truss to rotate (yaw) around the soft tank end of the truss.

    Excessive yaw of the truss would prevent the truss from

    being continuously skidded off along the skid beam. The

    results showed that the winching system alone (without

    the help of the mooring lines on the truss) could maintain

    the truss position during the operation in the design

    environment of 18-knot wind and 1.2-knot current. Themaximum expected relative (to the barge) yaw of the truss

    was 0.16 degrees which would occur in the beam

    environment. To achieve such low yaw motion of the

    truss, the pulling winch lines had to maintain a minimum

    of 200 kips of tension in each line during the operation.

    PlanningThe planning and design for the offload operation started

    about seven months before actual execution of the operation.

    Many tasks had to be completed during the short duration.

    These included performing the analyses, developing the

    procedures, designing and fabricating the different systems

    (Mooring, Pull and Hold Back System) required for theoperation, making modifications to the barge after arrival at

    the fabrication yard, determining the dredging requirements,

    dredging the area, testing various systems and training

    personnel for the operation. The float-off operation was

    among the most challenging of all operations performed on the

    Holstein project. Various risks were identified during risk

    reviews of the procedure and were eliminated or mitigated by

    changing the design, procedure or performing additional

    verification and tests. Following are some of the tasks that

    were performed to mitigate risks:

    1) FMECA analysis of the entire operation performed todetermine the most vulnerable component or

    procedure that may cause failure of the operation.

    2) New wires used with higher than normal margin onsafety factors.

    3) All sheaves and blocks inspected and load tested.4) Soft tank skid shoes tied off with wires to avoid

    lateral motion or to prevent shoes rolling over due tolateral loads.

    5) Multiple redundant systems used to keep the truss in-line with the barge during winching and while truss

    was over hanging beyond the stern of the barge.

    6) Barge inclination test performed to the maximuminclination of the barge without the truss onboard

    The test was performed to ensure that: a) all barge

    systems would operate safely to the required

    inclination angles, b) to train ballasting crew and c)

    to perform a safety drill which ensured that safety

    procedures for retrieving an injured person were

    tested and an evacuation was possible at any stage of

    the offload operation.

    7) Introduced soft lines in the mooring system.8) Third party verification of the analyses.9) Trained personnel before the actual operation.

    The execution of this first-of-a-kind operation was very

    successful and smooth to a large extent, as a result of the steps

    taken to identify and minimize the risks.

    Barge ModificationsSeveral modifications to the launch barge had to be made to

    make the truss structure offload operation possible and safe.

    The major modifications made are listed below:

    1) Bow Extension Beams: The barge was designed toloadout structures and launch them over the tilt beams

    As a result the skid beams are not required for the entire

    length of the barge. For the Holstein truss structure, a

    Bow Loadout had to be done, followed by a controlled

    launch over the stern. Additional skid beams had to be

    added on the forward end to make the skid beams span

    the entire length of the barge and also cantilever over the

    bow for loadout.

    2) Marine System: The barge compartment vents are locatedat the top of each compartment. Figure 2 shows the

    floating configuration of the barge near the end of the

    offload operation with about half the barge deckunderwater. Also, there are other openings for pump

    exhaust, fuel intake and ventilation hatches aft of the

    midships. To avoid water going through the vents and

    other openings, they either had to be closed or routing

    them forward above the final waterline on the bargedeck

    Thevents for all the aft compartments were modified by

    adding vent pipes to the existing vents and routed forward

    to be above water all through the offload operation. The

    vent extensions for some compartments were combined

    taking into consideration the ballast plan for all the

    offload steps. The pump room exhausts were also

    extended and routed forward. The extension pipes were

  • 8/4/2019 OTC 17299 Launching

    8/12

    8 OTC-17299

    run along the sides of the barge and along the longitudinal

    center of the barge away from the winching system and

    mooring lines as shown in Figure 12.

    3) Cattle Chute: It was very critical to maintain thelongitudinal axis of the truss aligned with that of the barge

    while the truss was skidded down the barge. Otherwise

    there was a risk of the truss falling off the skid beams.Guide rails were provided along the skid beams to help

    guide the skid shoes during the winching operation.

    However the risk of the truss going off line was very high

    after the passage of the soft tank skid shoe past the barge

    skid beams and while on the tilt beam. At this point the

    truss structure was supported only on two points on the

    soft tank hinges. As a safeguard, a bumping structure was

    built on top of the tilt beams. The bumping structure,

    fabricated with tubulars and resembling a cattle chute was

    used to guide the skid shoes as it was being skidded. The

    cattle chute structures also helped to guide the skid shoes

    under the heave plates. Figure 13 shows the cattle chute

    structures on top of the Tilt Beams.

    4) Mooring Bollards: As explained in the mooring sectionand shown in Figure 11, new bollards were designed and

    installed for mooring the barge.

    5) Deadmen: As mentioned above in the winching systemsection, one deadman was required for each of the pull

    and hold back lines. The deadmen for the pull lines were

    located on the aft rake of the barge. A sheave was welded

    on top of this deadmen. The deadmen for the Hold Back

    lines were welded on top of the new Bow Extension

    beams. The locations of the Deadmen are shown in

    Figure 8.

    Figure 12: Barge Modifications Vent and Exhaust Lines Extended Forward

    Figure 13: Cattle Chute Structure on Top of Tilt Beam

    Bow

    Vent and Exhaust Lines

    Extended Forward

    S

  • 8/4/2019 OTC 17299 Launching

    9/12

    OTC-17299 9

    Barge Inclination Test. The H-627 barge had never been

    used or designed to perform an operation similar to the

    Holstein truss offload operation. The barge structure and its

    systems were being pushed to their design limits and to

    conditions for which the systems were never tested. The barge

    had never been submerged statically to the depth required for

    the offload operation of 76 ft. or statically pitched to about 9

    degrees. The barge pumping and marine system had neverbeen subjected to the heads required for this operation. The

    worst case for the pumping system was to pump water from

    the aft most compartments to the foremost during the barge re-

    float operation at the end of the offload operation.

    To understand and minimize risks related to the launch barge

    and mooring during the actual offload operation, it was

    decided to perform a barge inclination test by simulating the

    truss offload procedure without the Truss. The barge

    inclination test was performed for the following purposes:

    Test the barge pumping system because of extensivepumping required for ballasting the barge to a high pitch

    angle, submergence and also for barge re-float.

    Verify theoretical predictions related to bargeperformance with actual operation.

    Train the personnel working in the pump room operatingthe barge pumps to familiarize and operate at high barge

    pitch angles.

    Verify no leaks through the manholes or vents includingthe vent extension system added for this operation.

    Test the active mooring system to control the barge.

    Train the land mooring winch personnel with theprocedure to adjust line tensions required for active

    mooring of the barge during actual offload operations

    Run safety evacuation drills with actual conditions duringoffload operations.

    Test the access system to the barge from the land withvarying freeboard of the barge and with boats during

    actual operations.

    Verify the dimensional control procedure and familiarizepersonnel with taking dimensional control measurements

    with changing barge floating configuration.

    Test the communication system between the Pump Room,Barge Deck, Mooring Winch operators and the Control

    Room during the operation.

    Understand any uncertainties and surprises with theoperation.

    The inclination test helped the personnel understand the

    magnitude of the task required to perform the actual operation

    and what to expect as far as the barge and mooring are

    concerned. The inclination test revealed a few important

    issues, mainly with the mooring, and raised confidence among

    the personnel to perform the actual operation with the truss

    loaded on the barge. The important findings or lessons

    learned from the inclination test are as follows:

    Barge pump system is well suited to ballast and de-ballastthe barge.

    Helped understand the ballasting and deballasting timerequired for the actual operation. Personnel developed a

    better understanding regarding different filling rates when

    water is pumped in different compartments

    simultaneously and how to control the barge roll during

    ballasting/de-ballasting.

    Few underwater manhole seals had to be changed thatleaked during the test. One of the welds at the exhaus

    extension line had to be repaired since water leaked into

    the Pump Room. One of the mooring lines broke during adjustment of pre-

    tensions. Mooring Line load cells need to be replaced

    with in-line load cells. The mooring line pre-tension

    adjustment procedure had to be modified and additiona

    mooring personnel were required during the actua

    offload operation.

    It was possible to maintain the barge in position asrequired and there was sufficient clearance between the

    barge and the dredged pit.

    Figure 14 shows the picture of the barge being ballasted

    during the inclination test.

    Figure 14: Barge Inclination Test Photo

    Measurements during Offload OperationIt was very important to understand and maintain the globa

    position of the barge during the entire operation to maintain

    sufficient clearance all around and between the barge and the

    dredged pit, and to ensure conformance with the Jones Ac

    requirements. Also knowing the floating position of the barge

    the truss, and the relative position of the truss on the barge wasimportant to understand and control the operation and to make

    any adjustments in case of any unforeseen events. The loads

    in the mooring lines and the pull/hold back lines were required

    to be measured constantly to monitor and control the

    operation. Generally at least two independent measurement

    were made to determine the floating configuration of the

    barge. Various instruments/tools were used to measure

    different quantities during the operation. These included:

    Optical targets on the barge and truss

    Additional draft measuring sticks at bow and sternbelow keel and above deck respectively (Barge draf

  • 8/4/2019 OTC 17299 Launching

    10/12

    10 OTC-17299

    marks at the bow were above water line and at the

    stern completely underwater during most of the

    operation)

    Barge bubble gage

    Paint marks on barge deck

    Barge compartment soundings

    Mooring line Load Cells

    Load Links in-line with the hold back/pull system, Length of wire on the winch spools.

    The frequency of the measurements depended on the

    operation step.

    The measurements from the optical targets installed on the

    barge, truss and land were used as a primary means of

    understanding the position and configuration of the barge and

    truss. The optical targets provided accurate and high

    resolution readings. The readings from different targets were

    fed to a computer program and corrected for the rotation of the

    barge/truss to provide:

    Position and orientation of barge relative to land andthe dredged pit.

    Barge floating configuration (Draft, Roll, Pitch,Yaw).

    Deflection of the barge.

    Position of the truss on the barge and configurationof the truss (Draft, Roll, Pitch, Yaw).

    Offload ProcedureThis section briefly describes the offload procedure. Only one

    major task such as ballasting, winching or mooring

    adjustment, was done at any given time to understand and

    control the operation at the critical stages of the operation.The offload operation was completed within 24 hours of

    starting the ballasting to separation of the truss from the barge.

    Post Load-out Re-rigging. At the end of load-out operation,

    the truss section was seated at the middle of barge with the

    keel of the soft tank located 23.0 m from the barge bow. After

    the loadout operation, the loadout pulling system was

    disconnected from the barge, loadout compression struts

    removed, cantilevered portion of the extension beam cut and

    the barge rotated approximately 5 deg. about its geometric

    center to line up with the deepest section of the deep pit.

    Following the rotation and mooring adjustment, re-rigging on

    the barge was done. During the re-rigging phase, the Pulling

    Winch system was hooked to the Skid frame connected to the

    soft tank. Figure 15 shows the picture of the truss loaded on

    the barge.

    Winching and Connecting Holdback System. The truss

    section was winched sternward 70.0 m [230 ft]. During the

    winching, the H-627was ballasted at each individual step to

    make the system even keel. At the end of winching, the

    Pulling Winch HPU was transferred from a cargo barge to the

    Deck of the H-627; the Hold Back System (winches, HPU and

    deadmen) was installed on the H-627 and connected to the

    Figure 15: Truss Structure Loaded Out on Barge

    skid frame. The Holdback system was pre-tensioned followed

    by ballasting of two mating tank compartments to correct for

    transverse eccentricity in the truss section and to ensure tha

    the truss and mating tank would float at even roll. The tie-bars

    connecting the skid shoes during loadout were disconnected

    and removed from the barge before the following steps

    Figure 16 shows the location of the truss at the end of this

    procedure.

    Figure 16: Truss Structure Winched for Initial Ballasting

    Initial Ballasting. The H-627 was ballasted until it had a trim

    of approximately 6.6 degrees by the stern. Figure 17 show

    the configuration of the truss at the end of initial ballasting.

    Winching. The truss section was winched sternward 112.78m [370 ft] (until Deck 1 of the soft tank was 182.83 m or 600

    ft. from the barge bow). As the truss section moved, the

    mating tank continued to gain buoyancy and the truss section

    rotated upward with respect to the barge. The winching

    continued until the forward end of the soft tank skidshoes

    were 178.56 m [586 ft] aft of the barge bow. The H-627 then

    had a trim of about 6.25 degrees by the stern and the truss had

    a trim of about 1.50 degrees by the mating tank. The

    winching speed was about 1 ft/min or less. Figure 18 show

    the configuration at the end of the winching operation.

  • 8/4/2019 OTC 17299 Launching

    11/12

    OTC-17299 11

    Survey information was continuously updated at regular

    intervals during the offload. The distance from the H-627 bow

    to the soft tank keel was reported along with barge and truss

    section list, trim and yaw at each interval. This survey

    information was used to verify that the operation was within

    the allowable tolerances.

    Figure 17: Truss Structure at End of Initial Ballasting

    Figure 18: Configuration at End of Winching Operation

    Final Ballasting. The H-627 was then ballasted until the

    truss section floated off from the hinge. The barge had a trim

    of approximately 8.1 degrees by the stern at this point and the

    truss had a trim of approximately 0.43 degree by the soft tank.

    The barge was further ballasted to about 8.5 deg. to provide

    sufficient clearance for the truss to be safely pulled away from

    the barge. At the moment of separation the actual truss draft

    was within 2 inches of the predicted draft. Figure 19 shows

    the pictures of the truss and the barge at the end of finalballasting.

    Post Float-off. The truss section was transferred to thecontrol of the tugs and wires connected to winches on land.

    The mooring lines were slacked and disconnected. The tugs

    then maneuvered the truss section to the mating site where it

    was moored and made ready for mating.

    The execution of this first-of-a-kind offload operation was

    very successful and smooth and worked according to plan.

    The complete operation was coordinated well between the

    ballasting, winching and mooring operations. The operation

    was completely controlled at all times. The detailed design

    planning, preparations and good communications helped to

    successfully execute the operation while mitigating the

    associated risks.

    Figure 19: Barge and Truss at the End of Offload Operation.

  • 8/4/2019 OTC 17299 Launching

    12/12

    12 OTC-17299

    Conclusions1) The truss offload operation, the first-of-a-kind was

    designed and executed over a period of about seven

    months.

    2) The truss structure was loaded out from the bow andoffloaded over the stern of the barge by winching the truss

    and ballasting the barge to cause total separation.

    3) The barge inclination test performed without the trussonboard helped to verify most of the systems used for the

    offloading operation and helped to improve the execution

    procedure.

    4) Various systems were used to address the critical issue ofwinching the truss parallel to the barge longitudinal axis.

    5) Proper planning and detail planning was important insuccessfully executing the challenging operation of

    offloading the truss structure from H-627 barge while

    mitigating the associated risks.

    6) The operation was completed conforming to the Jones Actregulation.

    References[1] Perryman, S., Gebara, J., Botros, F. and Yu, A. (2005),

    Holstein Truss Spar and Top Tension Riser System DesignChallenges and Innovations, OTC Paper No 17292.

    [2] Sablok, A., Liu, C., Gebara, J., Cattell, A. and Perryman, S.(2005), Mating of Holstein Hard Tank and Truss Challenges,Execution, Dimensional Control and Analysis, OTC Paper No

    17297.

    AcknowledgementsThe authors wish to thank BP America Inc., Shell Offshore

    Inc. and Technip Offshore, Inc. for their permission to publish

    this paper. The authors would also like to acknowledge their

    colleagues at the Houston engineering office and at the

    fabrication yard for their contribution to the offload design and

    operation.