osila bosini
-
Upload
hossein-zohdi-rad -
Category
Documents
-
view
11 -
download
0
description
Transcript of osila bosini
-
DET NORSKE VERITASTM
REPORT NO./DNV REG NO.: 2013-4091 / 17TLT29-3
REV 1, 11.06.2013
APPENDIX D - LEAK
FREQUENCIES ANALYSIS
SKANGASS AS
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page i of i
Table of Contents Page
1 LEAK FREQUENCY ANALYSIS .................................................................................................... 1 1.1 Equipment of LNG bunkering installation ................................................................................... 1 1.2 LNG loading arm failure .............................................................................................................. 1 1.3 Leak Frequency ............................................................................................................................ 3
2 RESULTS DISCUSSION ................................................................................................................... 6
3 REFERENCES .................................................................................................................................... 6
ANNEX 1 P&IDS 1301-1100-100, SHEETS TA01/TB01/TC01 ........................................................... 7
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 1 of 11
1 LEAK FREQUENCY ANALYSIS
The frequency analysis determines the annual release of hazardous materials (flammable) from process
equipment for LNG bunkering of Fjordline at Risavika harbour. The frequency analysis is critical to
the analysis as the frequencies and hole size distribution are the fundamental assumptions which the
consequence and risk estimates are based upon.
The generic failure frequencies for valves, flanges and pipes are based on HCRD 2010 database and
DNV report 2008-1768 rev 4 dated 22nd of December 2010, ref. /1/ . This database is viewed as the
most comprehensive collection of leak frequency data currently available in any industry.
1.1 Equipment of LNG bunkering installation
The frequencies detailed parts count of the system was using the available P&IDs (cf. Annex 1) together with estimates of line lengths from plot plans. The P&IDs used in this assessment are as close as possible to the final version. The frequency have been calculated using the DNV software
LEAK v3.3 to produce release frequencies based on a defined hole size distributions, ref. Table D1.
The LNG bunkering system has been divided into five main sections and subdivided into LNG line
and Vapour Return line:
Equipment for LNG ferry bunkering located inside the LNG plant area (including pump,
flowmeter, LNG line and vapour return line)
Pipeline section under ground between LNG plant and LNG ferry bunkering station (LNG line
and Vapour return line)
LNG ferry bunkering station upstream ESD valve on jetty
LNG ferry bunkering downstream ESD valve on jetty
LNG loading arm
Welded connections have a lower leak frequency than flanges connections. It has been assumed that
the flanges are welded, with the exception of the flanges present in the different P&IDs (cf. Annex 1)
that have been taken into account.
Note that the size of leak large covers two leak size, large and full bore rupture.
Table D1 Hole size distribution
Size of Leak Range [mm]
Small 1 10
Medium 10 50
Large > 50
1.2 LNG loading arm failure
Loading arm leak frequency is calculated separately and based on ACDS data covering both
connection failures and ranging failures (leading to disconnection), ref. /2/. The ACDS data is
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 2 of 11
considered to be the most representative data for liquefied gas loading arms, although it can be
considered a conservative estimate for LNG loading arms.
The generic loading arm frequency applied is 7.6E-05 per visit/transfer for all failure contributors, ref.
Assumption no 3-C in Appendix A. The frequency is per bunkering operation for an LNG tanker.
Assuming a typical LNG tanker bunkering operation will last for minimum 18 hours, whereas the
bunkering of the Fjordline ferries lasts 1 hour (LNG transfer), the frequency is reduced with a factor
1/18.
For ranging/disconnection failure (i.e. mooring and striking by passing ships) 100% of the total
frequency is defined as a large release:
Ranging failures per year = 9E-07 (per visit) * 365 visits * 1/18 * 100% = 1.8E-05
For connection type failures (failure of arm, failure of quick release, failure of ships pipework and operator error) the leak size distribution is defined as 70% small leaks, 25% medium leaks and 5%
large release.
Connection failure, small, per year = 7.5E-05 (per visit) * 365 visits * 1/18 * 70% = 1.1E-03
Connection failure, medium, per year = 7.5E-05 (per visit) * 365 visits * 1/18 * 25% = 3.8E-04
Connection failure, large, per year = 7.5E-05 (per visit) * 365 visits * 1/18 * 5% = 7.6E-05
Based on this a total frequency of 1.5E-03 per year is applied for the loading arm, where 9.4E-5 leaks
are large leaks.
It should be noted that, even with accounting for shorter bunkering time, the generic failure frequency
is assumed to be conservative. The reason for this is twofold:
The ferry terminal has an extremely sheltered location, minimizing the risk of collision with other ships.
The ferry terminal is believed to provide a more reliable mooring system compared to LNG tankers, which ref. /2/ is based on.
The above would give reason to reduce the ranging failure frequency further. This has not been done
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 3 of 11
1.3 Leak Frequency
Table D2 presents the basis for leak frequency calculation in LEAK.
Table D2 Basis for leak frequency model
Ferry bunkering
Pressure (bara): 10
Equipment Line Size (inch) Number Gas/Liquid (%)
New equipment for LNG ferry bunkering inside plant
LNG Pump
Small Bore fittings LNG Line 0.5 7 0/100
Vapour Return Line 0.5 4 95/5
Flanges
LNG Line
1 1 0/100
4 1 0/100
6 7 0/100
10 4 0/100
Vapour Return Line
1 3 95/5
2 2 95/5
4 1 95/5
Actuated valve LNG Line
2 1 0/100
4 1 0/100
6 1 0/100
Vapour Return Line 2 1 95/5
Manual valve
LNG Line
1 15 0/100
2 10 0/100
3 1 0/100
4 3 0/100
6 1 0/100
10 1 0/100
Vapour Return Line 1 7 95/5
2 7 95/5
Pump LNG Line - 1 0/100
Piping
LNG Line
1 25 m 0/100
2 17.5 m 0/100
4 5 m 0/100
6 37.5 m 0/100
10 25 m 0/100
Vapour Return Line
1 12.5 m 95/5
2 17.5 m 95/5
6 37.5 m 95/5
Flowmeter Small Bore fittings
LNG Line 0.5 14 0/100
Vapour Return Line 0.5 1 95/5
Flanges LNG Line 6 6 0/100
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 4 of 11
Ferry bunkering
Pressure (bara): 10
Equipment Line Size (inch) Number Gas/Liquid (%)
8 10 0/100
Vapour Return Line 4 4 95/5
Actuated Valve LNG Line - - -
Vapour Return Line - - -
Manual Valve LNG Line
1 10 0/100
2 4 0/100
6 10 0/100
Vapour Return Line - - -
Piping
LNG Line
1 10 m 0/100
2 10 m 0/100
6 10 m 0/100
Vapour Return Line
1 10 m 95/5
2 10 m 95/5
4 10 m 95/5
Piping between LNG pump
and Flowmeter Piping
LNG Line 8 25 m 0/100
Vapour Return Line 4 25 m 95/5
Pipeline between LNG plant and ferry bunkering station
Underground pipelines
Flange LNG line 8 1 0/100
Piping section LNG Line 8 495m 0/100
Vapour Return Line 4 495 m 95/5
Ferry bunkering station
Upstream up to ESD valve
Small Bore fittings LNG Line - -
Flange LNG Line - - -
Actuated valve LNG Line 6 1 0/100
Manual valve LNG Line
1 5 0/100
2 1 0/100
3 1 0/100
6 1 0/100
Vapour Return Line - - -
Piping section
LNG Line 1 3 m 0/100
6 3 m 0/100
Vapour Return Line 2 3 m 95/5
4 3 m 95/5
Downstream ESD valve
(365 hours per year)
Small Bore fittings LNG Line 0.5 6 0/100
Vapour Return Line - - -
Flange LNG Line 6 2 0/100
Vapour Return Line 4 1 95/5
Actuated valve LNG Line - - -
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 5 of 11
Ferry bunkering
Pressure (bara): 10
Equipment Line Size (inch) Number Gas/Liquid (%)
Vapour Return Line 2 1 95/5
Manual valve
LNG Line 1 5 0/100
2 3 0/100
Vapour Return Line
1 2 95/5
2 3 95/5
6 1 95/5
Piping section
LNG Line 1 4 m 0/100
6 4 m 0/100
Vapour Return Line 2 4 m 95/5
4 4 m 95/5
Even if it has been assessed that the equipment will be used with different durations, the leak
frequencies presented in Table D3 are per year.
The difference in usage duration has been taken into account into the Leak Frequency model as
follows:
- All the equipment on the LNG line up to the ESD valve will be filled with LNG the whole year;
- Meanwhile the equipment on the LNG line downstream the ESD valve will be filled with LNG only during the bunkering operation let assumed 365 hours per year.
- The same assumption is applicable to the vapour return line that is going to be used only for the bunkering operation, let 365 hours per year.
Table D3 Leak frequency by section (per year)
Frequencies (per year) Small Medium Large Total
Equipment for LNG ferry bunkering inside plant
LNG Line 1.3E-02 1.8E-03 6.6E-04 1.6E-02
Vapour Return Line1 2.1E-04 2.1E-05 2.2E-06 2.3E-04
Between plant and ferry bunkering station
LNG Line 5.0E-05 7.7E-06 3.0E-06 6.0E-05
Vapour Return Line1 1.9E-08 9.6E-08 1.6E-08 1.3E-07
Jetty area Upstream ESD valve
LNG Line 5.3E-04 5.3E-05 1.5E-05 5.9E-04
Vapour Return Line1 4.7E-07 3.7E-08 8.1E-09 5.1E-07
Jetty area Downstream ESD valve1
LNG Line1 6.6E-05 8.3E-06 4.1E-07 7.5E-05
Vapour Return Line1 2.3E-05 1.9E-06 8.0E-07 2.5E-05
Loading arms LNG Line 1.1E-03 3.8E-04 9.4E-05 1.6E-03
TOTAL 1.5E-02 2.3E-03 7.7E-04 1.8E-02
1Only in use during 365 hours per year.
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 6 of 11
2 RESULTS DISCUSSION
Since the previous update ref./3/, it has been assessed that the total leak frequency has increased by
42%. It is due to the new design that increased strongly the number of flanges and small bore fittings,
both high contributor of leak frequency. The small leak frequency has increased by 54%, the medium
leak frequency by 22% and the large leak frequency reduced by 34%.
Compared to the previous design used in the previous QRA, the leak frequencies have evolved in the
different sections as follows:
- 108 % increase in the plant area;
- 95 % reduction for the underground pipelines;
- 70 % reduction for the jetty area.
The leak frequencies are not distributed evenly between the different sections of the bunkering
installation. Indeed, 87.5% of the total leak frequency is in the plant perimeter, 0.3 % in the
underground section and the rest, 12.2 % is inside the jetty area. It has been assessed that the
underground LNG pipeline represent a very low contribution to the leak frequency. It is due to the
design retained for the underground pipeline (underground double wall full containment pipe with all
the connections and extension welded) giving a very low probability of failure.
On the other hand, the new design includes a vapour line return running from the jetty area to the
plant. But due to the low pressure and the few hours in operation, the leak probability is low. The
contribution of the vapour return line has been assessed to represent 1 % of the total leak frequency,
meanwhile the LNG line do represent 99 % of the total leak frequency.
3 REFERENCES
/1/ DNV report 2008-1768 rev 4 Offshore QRA Standardised Hydrocarbon Leak Frequencies.; dated December 2010 , Based upon HCRD 10/92 03/10)
/2/
DNV Guideline 16, LNG QRA Guideline, rev 0, 09.11.2011
/3/
QRA for Risavika Ferry Bunkering Station, Skangass AS, Report No./DNV Reg No.:
2012-4049/143MJ79-5; Rev. 0, 18.05.2012
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 7 of 11
ANNEX 1 P&IDS 1301-1100-100, SHEETS TA01/TB01/TC01
These P&IDs served as basis for the counting of equipment. Note based on the request of Skangass
AS, some equipment have been added to the inventory, even if they are not appearing on the drawings:
- For each PSV loop, instead of the diameter redactor a valve has been added to the inventory;
- One valve has been added to the underground LNG line.
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 8 of 11
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 9 of 11
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 10 of 11
-
Det Norske Veritas
Report for Skangass AS
Appendix D - Leak Frequencies Analysis
MANAGING RISK
DNV Reg. No.: 17TLT29-3 Revision No.: 1
Date : 11.06.2013 Page 11 of 11
-
Det Norske Veritas:
DNV is a global provider of knowledge for managing risk. Today, safe and responsible business conduct is both a
license to operate and a competitive advantage. Our core competence is to identify, assess, and advise on risk
management, and so turn risks into rewards for our customers. From our leading position in certification, classification,
verification, and training, we develop and apply standards and best practices. This helps our customers to safely and
responsibly improve their business performance.
Our technology expertise, industry knowledge, and risk management approach, has been used to successfully manage
numerous high-profile projects around the world.
DNV is an independent organisation with dedicated risk professionals in more than 100 countries. Our purpose is to
safeguard life, property and the environment. DNV serves a range of industries, with a special focus on the maritime
and energy sectors. Since 1864, DNV has balanced the needs of business and society based on our independence and
integrity. Today, we have a global presence with a network of 300 offices in 100 countries, with headquarters in Oslo,
Norway.
Global impact for a safe and sustainable future:
Learn more on www.dnv.com