Oshawa to Bowmanville Expansion Environmental...
Transcript of Oshawa to Bowmanville Expansion Environmental...
Oshawa to Bowmanville ExpansionEnvironmental Assessment
Presentation to City of OshawaOctober 5, 2009
Presentation agenda
• Oshawa to Bowmanville– Study area– Study scope– Ridership– Expansion requirements– Service levels– Design/construction
• East regional bus maintenance & storage facility
Oshawa to BowmanvilleStudy area
Brock Street, Whitbyin the West
Townline R.R. 42 approx. at Hwy 35/115
in the East
Study scopeProject elements
• New rail maintenance facility• Extension of GO rail service into
Bowmanville• Evening layover needed at end-of-line
Study scopeCN vs. CPR line
• 1990s study preferred CPR • Latest feasibility study preferred CPR• Primary reason was municipal support for
CPR alignment, as it was closer to downtown Oshawa and centre of Bowmanville
Ridership
18,0009,5007,000
6,0004,0004,000Whitby
9,0004,0003,000Oshawa (Thornton Road)*
1,000500n/aOshawa (Ritson Road)1,000600n/aCourtice1,000400n/aBowmanville
203120152008AM peak-period boardings
Expansion requirements
Rail Maintenance Facility,
West of Thickson Road
Existing VIA
Thornton Road GO Ritson Road GO
Harmony Road GO (future)
Courtice GO
Bowmanville GO
Rundle Road layover
(preferred)
Providence Road layover
(potential)Hwy. 401 crossing
East of Thickson Rd.
Rail Maintenance Facilitywest of Thickson Road
Coach shop Maintenance shop Daily mtce. bays
Wayside power & fueling
Wash bay
Locomotive washStorage
for up to 18 trains
300-400 employees
Option 1Operate south of CP track
CP track
Hwy. 401 crossing
Two overpasses
Corbett Creek (track widening & waterworks)
Option 2Operate north of CP track
Hwy. 401
crossing
Overpass at Corbett Creek and CP Tracks
CP track
Option 3Extend GO subdivision
Corbett Creek crossing
Thornton Road GO
Hwy. 401
crossing
Underneath Thornton Road
GO sub and CP Belleville sub
connection (west of Stevenson Road)
CP track
GO sub
Track and signal work
Additional two tracks• Existing GO Line to Ritson Road
Single track• Ritson Road to Bowmanville
Optional service levels
• Phase 1– All-day service to Ritson GO – Peak-period service to Bowmanville GO
• 4 trains in AM & PM peaks
• Phase 2 (as demand warrants)– All-day service to Bowmanville GO
Study scheduleTransit Project Assessment Process for EA
Phase 1 • June 2009 – Public Open House #1• Field data (survey, noise baseline, vibration baseline, air quality)• Preliminary analysis• Stakeholder input• Prior to Notice of Commencement – EA 90% complete
Phase 2• November 2009 – Notice of EA Commencement• Mid-November – Public Information Centre #1• March 2010 – Notice of Completion• 30 day public review• MOE review/decision (35 days)
Project milestones
• EA decision – Spring 2010• Design & Construction phase: Rail
Corridor – 3 years• Design & Construction phase:
Maintenance Yard – 4 years• Actual Construction dates dependant upon
budget approval ($500-$600 million) from Province.
East regional bus maintenance & storage facility
• Approx. 330,000 sq ft• Approx. 150 employees• Full-service facility • Storage
– 60 indoor (possible +60)– 12 outdoor
• Silver LEED certification
Study milestones
Class Environmental Assessment Process
2010• Early-February – Notice of Commencement• Mid-February – Public Information Centre #1• April – Notice of Completion• Public review (45 days)